Prefabricated trestle plate for foundation pit supporting
By designing a detachable plate body and bracket structure on the trench, the board body is stable and conveniently disassembled by the accommodating chamber and connecting components, the risks and pollution problems existing in the disassembly of the existing trench are solved, and the construction is improved Efficiency and stability.
Patent Information
- Application Number
- CN202323404166.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2033-12-14
AI Technical Summary
The existing trench panels have great operating risks during the dismantling process, long construction time, environmental pollution, and inconvenient dismantling.
A prefabricated trench plate for foundation pit support is designed, adopting a detachable plate body and bracket structure, and the board body is stable and conveniently disassembled through the accommodating cavity, the first connecting assembly, the second connecting assembly and the locking assembly. , the locking rod, return spring and drive member are used to achieve a removable connection of the plate body.
It improves the stability and construction convenience of the pier, while simplifying the disassembly process and reducing the risk of environmental pollution.
Smart Images

Figure CN222043863U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of piers, and in particular to a prefabricated pier board for foundation pit support. Background Art
[0002] In the support of large deep foundation pits, especially when the surrounding environment is complex and the site is small, support piles and internal supports are often used. In the process of building the support, due to the needs of excavation, material transportation and operation of equipment, trestle boards are usually built to provide transportation equipment for walking.
[0003] At present, trestles are usually constructed by pouring concrete. Specifically, a pallet support is first set up at a predetermined position, and then a casting formwork is installed on the support, steel bars are tied, and concrete is poured. After the concrete is completely solidified, the formwork is removed to complete the construction of the trestles.
[0004] For the above-mentioned related technologies, when the trestle needs to be dismantled, cutting equipment is needed to cut the trestle boards, which has high operation risks, long construction time, and also causes environmental pollution, and is very inconvenient for dismantling. Utility Model Content
[0005] In order to solve the problem that the trestle board is inconvenient to disassemble, the present application provides a prefabricated trestle board for foundation pit support.
[0006] The prefabricated trestle board for foundation pit support provided in this application adopts the following technical solution:
[0007] A prefabricated trestle board for foundation pit support comprises a bracket and a plurality of plate bodies arranged on the bracket, wherein the plate bodies are detachably connected to the bracket, the plurality of plate bodies are grouped into two plate bodies, and a plurality of groups are arranged along the length direction of the bracket, and the plate bodies of the same group are symmetrically arranged along the length direction of the bracket, a plurality of accommodating cavities for accommodating the plate bodies are arranged on the top of the bracket, and one accommodating cavity corresponds to one plate body, a first connecting assembly is arranged between adjacent plate bodies, a second connecting assembly is arranged between the plate body and the side of the bracket, and a locking assembly for locking two adjacent plate bodies is arranged on the bracket.
[0008] By adopting the above technical scheme, when installing the trestle board, a prefabricated board body is used to reduce the construction difficulty; the board body is limited by multiple accommodating cavities to improve the stability of the trestle board; the board body is detachably connected to the bracket through the first connecting component, the second connecting component and the locking component, which improves the stability of the trestle board and facilitates the installation and disassembly of the board body.
[0009] Optionally, the plate body includes an upper plate and a lower plate, the bottom surface of the upper plate abuts against the top surface of the top of the bracket, the upper plates of adjacent plate bodies fit each other, the lower plate is located in the accommodating cavity, and the bottom surface of the lower plate is flush with the bottom surface of the top of the bracket.
[0010] By adopting the above technical solution, when installing the plate body, a step device of the upper plate and the lower plate is used to set up so that the accommodating cavity limits the lower plate, and the upper plates are spliced with each other, thereby improving the flatness of the trestle surface and facilitating driving.
[0011] Optionally, the first connecting assembly includes a first connecting plate and a locking nut, mounting screws are provided around the bottom of the lower plate, the first connecting plate is plugged into adjacent mounting screws on an adjacent lower plate, the locking nut is threadedly connected to the mounting screws, and the first connecting plate is arranged between the lower plate and the locking nut.
[0012] By adopting the above technical solution, when the first connecting component connects adjacent plates, the first connecting plate is plugged into the mounting screws on the adjacent plates, and the first connecting plate is locked by the locking nut, thereby realizing the connection of adjacent plates, and the installation is more convenient.
[0013] Optionally, a positioning plate is provided on one side of the first connecting plate close to the lower plate, a positioning groove is provided on the bottom surface of the top of the bracket, and the positioning plate is plugged into the positioning groove.
[0014] By adopting the above technical solution, when fixing the first connecting plate, the first connecting plate and the mounting screw can be easily aligned by plugging the positioning plate into the positioning groove, which facilitates construction.
[0015] Optionally, the locking assembly includes a locking plate, a driving member and a reset spring, wherein two locking plates are symmetrically arranged, the locking plate is slidably connected to the bracket, and the sliding direction is in the direction of approaching or moving away from the lower plate, a locking groove is provided on the side of the lower plate, the driving member is slidably connected to the bracket, the driving member is used to drive the locking plate to be plugged into the locking groove, one end of the reset spring is connected to the locking plate, and the other end is connected to the bracket, and the reset spring is used to drive the locking plate to reset.
[0016] By adopting the above technical solution, when the locking member locks the adjacent plate bodies, the two symmetrical locking plates are moved closer to the lower plate through the sliding drive member until the locking plates are plugged into the locking grooves, thereby completing the locking of the adjacent plate bodies; when the plate bodies are unlocked, the driving member is slid in the opposite direction, so that the locking plates are disengaged from the locking grooves under the action of the return spring, thereby achieving the unlocking of the plate bodies and facilitating the disassembly of the plate bodies.
[0017] Optionally, the driving member is a positioning plate, the positioning plate is located between two locking plates, a chamfer is provided on the top of the positioning plate, and when the positioning plate is plugged into the positioning groove, the locking plate and the positioning plate are movably abutted.
[0018] By adopting the above technical solution, the positioning plate is used as a driving member, so that when the first connecting component connects adjacent plates, the positioning plate moves close to the locking plate. Under the squeezing of the positioning plate, the locking plate slides close to the lower plate and is plugged into the locking groove and synchronously linked, thereby facilitating construction.
[0019] Optionally, a chamfer is provided at the bottom of the locking plate on one side close to the positioning plate.
[0020] By adopting the above technical solution, a chamfer is set at the bottom of the locking plate, which can reduce the possibility that the positioning plate cannot push the two locking plates apart and increase the error range.
[0021] Optionally, the second connecting assembly includes a second connecting plate and a locking nut, a mounting screw is provided on the bottom surface of the top of the bracket, the mounting screw is provided on both sides of the bracket, the second connecting plate is plugged into the adjacent mounting screws on the bracket and the lower plate, the locking nut is threadedly connected to the mounting screw, and the second connecting plate is provided between the lower plate and the locking nut.
[0022] By adopting the above technical solution, when the second connecting component connects the plate body and the bracket, the second connecting plate is plugged into the adjacent mounting screws on the plate body and the bracket, and then the second connecting plate is locked by the locking nut, thereby achieving the fixation of the second connecting plate and completing the connection between the plate body and the bracket, which is relatively convenient to operate.
[0023] In summary, the present application includes at least one of the following beneficial technical effects:
[0024] 1. By providing a receiving cavity, a first connecting component, a second connecting component and a locking component, when installing the plate body, the receiving cavity limits the lateral position of the plate body, the first connecting component connects two adjacent plate bodies, the second connecting component connects the plate body with the side of the bracket, and the locking component further locks the two adjacent plate bodies, thereby realizing the detachable installation of the plate body, and facilitating the disassembly of the plate body while maintaining the stability of the plate body;
[0025] 2. By setting a locking rod, a return spring and a driving member, when the first connecting assembly connects adjacent plate bodies, the positioning plate serves as a driving member and slides along with the first connecting plate, so that the first connecting plate moves close to the locking plate and pushes the two adjacent locking plates in the opposite direction so that the locking plates are plugged into the locking grooves, thereby connecting the adjacent plate bodies while locking the two adjacent plate bodies on the bracket, which is convenient for construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0027] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;
[0028] Figure 2 is a schematic structural diagram of a bracket according to an embodiment of the present application;
[0029] Figure 3 is a schematic structural diagram of a plate body in an embodiment of the present application;
[0030] Figure 4 It is a structural schematic diagram of the assembly of the top of the rack and the plate body of an embodiment of the present application;
[0031] Figure 5 is a partial bottom view of an embodiment of the present application;
[0032] Figure 6 is a partial cross-sectional view of an embodiment of the present application;
[0033] Figure 7 yes Figure 6 An enlarged schematic diagram of part A.
[0034] Figure numerals: 1. bracket; 11. top of the rack; 111. accommodating chamber; 112. positioning groove; 12. supporting leg; 13. guardrail; 2. plate body; 21. upper plate; 22. lower plate; 221. mounting screw; 222. locking groove; 3. first connecting assembly; 31. first connecting plate; 32. locking nut; 33. positioning plate; 4. second connecting assembly; 41. second connecting plate; 5. locking assembly; 51. locking plate; 52. return spring. DETAILED DESCRIPTION
[0035] The following is combined with Figure 1-7 This application is described in further detail.
[0036] The present application embodiment discloses a prefabricated trestle board for foundation pit support. Figure 1 The prefabricated trestle board for foundation pit support includes a bracket 1 and a plurality of plate bodies 2. The plate bodies 2 are rectangular as a whole. The plurality of plate bodies 2 are grouped in two. The two plate bodies 2 are symmetrically arranged along the length direction of the bracket 1. The bracket 1 is provided with a plurality of groups of plate bodies 2 along its own length direction. In this embodiment, the length of the plate body 2 is 6 meters and the width is 4 meters. The plate body 2 is detachably connected to the bracket 1. The bridge deck layer of the trestle is formed by splicing a plurality of plate bodies 2, thereby facilitating the movement of vehicles.
[0037] Reference Figure 2 The bracket 1 includes a frame top 11, support legs 12 and guardrails 13, and the frame top 11, support legs 12 and guardrails 13 are all made of square steel. There are multiple support legs 12 and they are fixed at equal intervals at the bottom of the foundation pit. The frame top 11 is welded to the tops of the multiple support legs 12. There are two guardrails 13 and they are welded to the two sides of the frame top 11 respectively. There are multiple accommodating cavities 111 on the frame top 11. The accommodating cavities 111 are rectangular cavities, and one accommodating cavity 111 corresponds to one plate body 2. Before installing the plate body 2, the bracket 1 is first fixed at a preset position in the foundation pit, so as to facilitate the hoisting of the prefabricated plate body 2 onto the bracket 1 for installation.
[0038] Reference Figure 3 The plate body 2 includes an upper plate 21 and a lower plate 22. The area of the upper plate 21 is slightly larger than that of the lower plate 22. The upper plate 21 and the lower plate 22 are cast in a production plant by casting a formwork and prefabricated steel bars, and the upper plate 21 and the lower plate 22 are integrally formed. A plurality of mounting screws 221 are welded to the bottom of the lower plate 22. The mounting screws 221 are arranged vertically. In this embodiment, four mounting screws 221 are arranged at the bottom of the lower plate 22, and are respectively located near the midpoints of the four edges of the lower plate 22. The other three sides of the lower plate 22 away from the side of the frame top 11 are provided with locking grooves 222.
[0039] Reference Figure 4 The size of the accommodating cavity 111 is the same as that of the lower plate 22. When the plate body 2 is installed, the lower plate 22 is completely embedded in the accommodating cavity 111, and the bottom surface of the upper plate 21 abuts against the top surface of the frame top 11, thereby limiting the lateral position of the plate body 2. At this time, the bottom surface of the lower plate 22 is flush with the bottom surface of the frame top 11, so that the plate body 2 is easily fixed.
[0040] Reference Figure 5 A first connecting component 3 is provided between adjacent plate bodies 2, and a second connecting component 4 is provided between the plate body 2 and the side of the rack top 11. Through the first connecting component 3 and the second connecting component 4, the plate body 2 is fixed on the rack top 11, which facilitates the installation and disassembly of the plate body 2 and improves the stability of the plate body 2.
[0041] Specifically, refer to Figure 6 and Figure 7 The first connecting component 3 includes a first connecting plate 31 and a locking nut 32. The first connecting plate 31 is a rectangular plate. Two through holes are provided on the first connecting plate 31. The first connecting plate 31 is plugged into two adjacent mounting screws 221 on the adjacent plate body 2, that is, the locking screw 221 passes through the through hole on the first connecting plate 31, and the locking nut 32 is threadedly connected to the mounting screw 221.
[0042] When connecting two adjacent plate bodies 2 through the first connecting assembly 3, the first connecting plate 31 is plugged into two adjacent mounting screws 221 on the two adjacent plate bodies 2, and the locking nuts 32 are threadedly connected to the two mounting screws 221 until the first connecting plate 31 is tightly pressed against the bottom of the lower plate 22 and the bottom of the frame top 11, thereby achieving the connection of the two adjacent plate bodies 2. Two locking nuts 32 are provided on each mounting screw 221 to increase the stability of the first connecting assembly 3.
[0043] Reference Figure 6 The second connecting component 4 includes a second connecting plate 41 and a locking nut 32. A plurality of mounting screws 221 are welded to the bottom of both sides of the rack top 11. The second connecting plate 41 is plugged into the mounting screws 221 on the rack top 11 and the mounting screws 221 on the lower plate 22 close to the side of the rack top 11, and the second connecting plate 41 is locked with the locking nut 32. The specific installation method is the same as that of the first connecting plate 31.
[0044] One side of the plate body 2 close to the side of the rack top 11 is fixedly connected to the rack top 11 through the second connecting component 4, and the other three sides are fixedly connected to the rack top 11 through the first connecting component 3, so that the four sides of the plate body 2 are fixed, thereby improving the stability of the plate body 2.
[0045] Reference Figure 7 A positioning plate 33 is welded on the top of the first connecting plate 31, and the positioning plate 33 is arranged vertically. A plurality of positioning grooves 112 are provided at the bottom of the frame top 11, and the number of the positioning grooves 112 is consistent with the number of the first connecting assembly 3, and the first connecting plate 31 is plugged into the positioning grooves 112. When installing the first connecting plate 31, the positioning plate 33 is first plugged into the positioning grooves 112, and then the first connecting plate 31 is plugged into the mounting screw 221, so that the through hole on the first connecting plate 31 is easily aligned with the mounting screw 221, reducing the difficulty of construction.
[0046] Reference Figure 7, a plurality of locking components 5 are arranged inside the rack top 11, and the number of the locking components 5 is the same as that of the first connecting components 3, and one locking component 5 corresponds to one first connecting component 3. The locking component 5 includes a locking plate 51, a driving member and a reset spring 52. Two locking plates 51 are provided, and the two locking plates 51 are symmetrically arranged along the length direction of the first connecting plate 31. The locking plates 51 are slidably connected to the rack top 11, and the sliding direction is along the width direction of the first connecting plate 31. The locking plates 51 are T-shaped as a whole, that is, the locking plates 51 include a plate body 511 and a plate head 512, and the height of the plate head 512 is greater than the height of the plate body 511. When the locking component 5 is in a locked state, one end of the plate body 511 is located inside the rack top 11, and the other end protrudes from the rack top 11 and is plugged into the locking groove 222. The plate head 512 is located inside the rack top 11 and abuts against the upper and lower surfaces inside the rack top 11. The bottom of the plate head 512 close to the adjacent plate head 512 is chamfered. The driving member is a positioning plate 33, which is located between two adjacent locking plates 51. The top of the positioning plate 33 is chamfered. As shown in the figure, the top of the positioning plate 33 is in a triangular cone shape, so as to facilitate driving the two locking plates 51 to plug into the locking grooves 222. The return spring 52 is located between the plate head 512 and the frame top 11. One end of the return spring 52 is welded to the plate head 512, and the other end is welded to the frame top 11.
[0047] Before the first connection assembly 3 is installed, the plate heads 512 of the two locking plates 51 are in contact with each other under the action of the return spring 52; during the installation of the first connection assembly 3, as the first connection plate 31 moves closer to the rack top 11, the positioning plate 33 gradually approaches the locking plate 51, causing the two locking plates 51 to slide away from each other until the locking plate 51 is plugged into the locking groove 222, thereby locking the side of the plate body 2 with the rack top 11. The chamfers on the positioning plate 33 and the plate heads 512 increase the error range of the relative position of the positioning plate 33 and the locking plate 51.
[0048] When the plate body 2 is disassembled, the locking nut 32 is rotated to release the first connecting plate 31 and the second connecting plate 41, so that the positioning plate 33 is disengaged from the positioning groove 112, and the locking plate 51 is disengaged from the locking groove 222 under the action of the return spring 52, thereby unlocking the plate body 2, making it easy to take the plate body 2 out of the accommodating cavity 111 and recycle it.
[0049] In this embodiment, a steel bar reserved piece is reserved on the upper plate 21 of the plate body 2, and two steel bar reserved pieces are provided on each plate body 2, and are respectively located at two corners of the plate body 2 near the side of the frame top 11, which are not shown in the figure. By providing the steel bar reserved piece, it is convenient to hoist the plate body 2.
[0050] The implementation principle of the prefabricated trestle board used for foundation pit support in the embodiment of the present application is as follows: by setting a plurality of accommodating cavities 111 on the bracket 1, the board body 2 is laterally limited, a first connecting component 3 and a second connecting component 4 are set to fix the board body 2 on the bracket 1, and a locking component 5 is set to lock the peripheral side of the board body 2, thereby further reinforcing the board body 2 to improve the stability of the trestle board and facilitate the disassembly of the trestle board; through the linkage between the first connecting component 3 and the locking component 5, the convenience of installation is improved and the construction is facilitated.
[0051] Unless otherwise defined, the technical terms or scientific terms used in this application should be understood by people with ordinary skills in the field to which this application belongs. The words "first", "second", "third" and similar words used in the specification and claims of this application do not indicate any order, quantity or importance, but are only used to distinguish different components. "One" or "one" and similar words do not indicate a quantitative limit, but indicate that there is at least one. "Include" or "comprise" and similar words mean that the elements or objects appearing before "include" or "comprise" include the elements or objects listed after "include" or "comprise" and their equivalents, and do not exclude other elements or objects. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0052] The above are all optional embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A prefabricated trestle board for foundation pit support, characterized in that: The invention comprises a bracket (1) and a plurality of plates (2) arranged on the bracket (1), wherein the plates (2) are detachably connected to the bracket (1), the plurality of plates (2) are grouped into two plates (2), and a plurality of groups are arranged along the length direction of the bracket (1), and the plates (2) of the same group are symmetrically arranged along the length direction of the bracket (1), the top of the bracket (1) is provided with a plurality of accommodating cavities (111) for accommodating the plates (2), one accommodating cavity (111) corresponding to one plate (2), a first connecting component (3) is arranged between adjacent plates (2), a second connecting component (4) is arranged between the plate (2) and the side of the bracket (1), and a locking component (5) for locking two adjacent plates (2) is provided on the bracket (1).
2. The prefabricated trestle board for foundation pit support according to claim 1, characterized in that: The plate body (2) comprises an upper plate (21) and a lower plate (22); the bottom surface of the upper plate (21) abuts against the top surface of the top of the bracket (1); the upper plates (21) of adjacent plate bodies (2) fit together; the lower plate (22) is located in the accommodating cavity (111); the bottom surface of the lower plate (22) is flush with the bottom surface of the top of the bracket (1).
3. The prefabricated trestle board for foundation pit support according to claim 2, characterized in that: The first connection assembly (3) comprises a first connection plate (31) and a locking nut (32); mounting screws (221) are provided around the bottom of the lower plate (22); the first connection plate (31) is plugged into an adjacent mounting screw (221) on an adjacent lower plate (22); the locking nut (32) is threadedly connected to the mounting screw (221); and the first connection plate (31) is provided between the lower plate (22) and the locking nut (32).
4. The prefabricated trestle board for foundation pit support according to claim 3, characterized in that: A positioning plate (33) is provided on one side of the first connecting plate (31) close to the lower plate (22), a positioning groove (112) is provided on the bottom surface of the top of the bracket (1), and the positioning plate (33) is plugged into the positioning groove (112).
5. The prefabricated trestle board for foundation pit support according to claim 4, characterized in that: The locking assembly (5) comprises a locking plate (51), a driving member and a reset spring (52); two locking plates (51) are symmetrically provided; the locking plates (51) are slidably connected to the bracket (1); the sliding direction is in a direction approaching or moving away from the lower plate (22); a locking groove (222) is provided on the side of the lower plate (22); the driving member is slidably connected to the bracket (1); the driving member is used to drive the locking plate (51) to be plugged into the locking groove (222); one end of the reset spring (52) is connected to the locking plate (51) and the other end is connected to the bracket (1); the reset spring (52) is used to drive the locking plate (51) to reset.
6. The prefabricated trestle board for foundation pit support according to claim 5, characterized in that: The driving member is a positioning plate (33), the positioning plate (33) is located between two locking plates (51), a chamfer is provided on the top of the positioning plate (33), and when the positioning plate (33) is plugged into the positioning groove (112), the locking plate (51) and the positioning plate (33) are movably abutted against each other.
7. The prefabricated trestle board for foundation pit support according to claim 6, characterized in that: A chamfer is provided at the bottom of the locking plate (51) on a side close to the positioning plate (33).
8. The prefabricated trestle board for foundation pit support according to claim 1, characterized in that: The second connection assembly (4) comprises a second connection plate (41) and a locking nut (32); a mounting screw (221) is provided on the bottom surface of the top of the bracket (1); the mounting screw (221) is provided on both sides of the bracket (1); the second connection plate (41) is plugged into adjacent mounting screws (221) on the bracket (1) and the lower plate (22); the locking nut (32) is threadedly connected to the mounting screw (221); and the second connection plate (41) is provided between the lower plate (22) and the locking nut (32).