T-beam transverse moving device used under high-intensity seismic zone condition
By designing the cross-moving device and adjusting the construction process of anti-falling beam stops in the high-intensity seismic zone, the problem of obstruction of anti-falling beam stops during the cross-moving of the T-beam is solved, and the rapid and safe installation of the T-beam is achieved and the simplification of the simplification of the T-beam is achieved. The construction process is improved and the installation efficiency and safety are improved.
Patent Information
- Application Number
- CN202420672808.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-04-03
AI Technical Summary
In high-intensity seismic zones, it is difficult to quickly and safely complete the installation of T-beams due to the existence of anti-fall beam stops during the transverse movement of T-beams, especially in the interchange bridges and small-radius ramp sections. question.
A horizontal movement device consisting of a horizontal movement track, a reaction frame, a T-beam bracket, a horizontal movement jack, and a vertical jack was designed. The steel bars of anti-falling beam stops were embedded and concrete poured after the T-beam was installed. , the installation process is simplified by the multi-movable reaction frame and bolt connection, ensuring that the edge beam does not overturn, and the rapid installation of the T-beam is achieved through transversely moving jacks and vertical jacks.
The problem of anti-fall beam stop block hindering the transverse movement of the T-beam is solved, the construction process is simplified, the installation efficiency and safety are improved, and the structure installation and disassembly are easier through bolt connections.
Smart Images

Figure CN222043946U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of bridge engineering, in particular to a T-beam transverse displacement device used in high-intensity earthquake zones. Background Art
[0002] As the expressway network extends to the western mountainous areas, the requirements for route design linearity continue to increase, the proportion of bridges and tunnels on the lines increases, and some lines cross earthquake fault zones, which places increasingly high demands on the safety and durability of bridge structures. In areas with high-intensity earthquake zones, in order to enhance the safety of bridge structures, transverse seismic blocks are added to the cap beams during bridge design to enhance the seismic resistance of the bridges. However, due to the addition of seismic blocks, the T-beam erection of the widening section and small-radius ramp section of the interchange bridge has the problem of the lateral movement path being blocked. How to quickly and safely complete the lateral movement of the T-beam has become an urgent problem to be solved. Utility Model Content
[0003] The purpose of this application is to provide a T-beam transverse displacement device for use in high-intensity earthquake zones. By improving the transverse displacement device and adjusting the construction process of the anti-falling beam block, the transverse displacement and installation of the T-beam can be completed.
[0004] The utility model is implemented in this way, providing a T-beam transverse movement device for use in high-intensity earthquake zones, characterized in that the transverse movement device consists of a transverse movement track, a reaction frame, a T-beam bracket, sleepers, a transverse movement jack, and a vertical jack. The transverse movement track is made of steel plates, and a plurality of bolt holes are arranged on both sides. The reaction frame is fixed to the transverse movement track by bolts, sleepers are arranged at the suspended portion of the bottom of the transverse movement track for support, and the T-beam side beam to be erected is placed on the T-beam bracket.
[0005] Furthermore, the T-beam side beam is placed on the T-beam bracket of the transverse movement device, and the placement position is as close as possible to the installation position of the side beam, which can reduce the transverse movement stroke and complete the installation faster. At the same time, the hoisting wire rope of the bridge erection machine remains in the hoisting state to ensure that the side beam does not overturn during the transverse movement.
[0006] Furthermore, bolt connection holes are provided corresponding to the transverse track and the reaction frame, so that the two can be quickly connected and disassembled by bolts.
[0007] Furthermore, the transverse jack is located between the reaction frame and the T-beam bracket. When pushing, the T-beam bracket is pushed instead of the beam body directly to prevent the beam body from being damaged.
[0008] Furthermore, the vertical jack is installed at the edge of the cap beam 1 and below the installation position of the T-beam side beam. During the construction of the cap beam, this position needs to be locally reinforced.
[0009] The implementation process of this patent is:
[0010] Step 1: Disposal of anti-fall beam block
[0011] During the construction of the cap beam, the steel bars for the anti-falling beam stopper blocks are embedded in advance, but they are not fully installed. Only the steel bars at the connection between the stopper and the cap beam are installed.
[0012] Step 2: Conventional T-beam erection
[0013] A bridge-erecting machine is used to erect the T-beam of the middle span, leaving only the side beams and secondary side beams unerected.
[0014] Step 3: Install the traverse device
[0015] Install the transverse device on the cap beam and the secondary side beam pad. The transverse device consists of a transverse track, a reaction frame, a T-beam bracket, a transverse jack, and a vertical jack. The transverse track is made of steel plates, with multiple bolt holes on both sides. The reaction frame can be fixed to the transverse track by bolts. Sleepers are set at the suspended part of the bottom of the transverse track for support. The T-beam bracket is placed on the T-beam side beam to be erected.
[0016] Step 4: Side beam placement
[0017] The T-beam side beam is placed on the T-beam bracket of the transverse device by the bridge erection machine. The placement position is as close as possible to the installation position of the side beam, which can reduce the transverse travel and complete the installation faster. At the same time, the hoisting wire rope of the bridge erection machine remains in the hoisting state to ensure that the side beam does not overturn during the transverse movement.
[0018] Step 5: Horizontal push
[0019] Start the oil supply of the lateral jack and push the side beam to the installation position. Pay attention to whether the embedded steel bars of the anti-falling beam block block block the T beam. If necessary, cut off some of the embedded steel bars. When the lateral jack reaches the maximum stroke, return the oil of the lateral jack, remove the reaction frame bolts, move the reaction frame forward, reinstall the lateral jack, and push the side beam to the installation position for the second time until it is pushed to the installation position.
[0020] Step 6: T-beam vertical placement
[0021] Start the vertical jack located at the edge of the cap beam and under the T-beam, lift up the T-beam, remove the transverse movement device, install the T-beam support, retract the vertical jack, drop the T-beam onto the support, and complete the transverse movement installation of the T-beam.
[0022] Step 7: Construction of anti-falling beam block
[0023] After all T-beams are installed, the reinforcement binding and concrete pouring of the anti-fall beam blocks are carried out.
[0024] As described above, the utility model provides a T-beam transverse displacement device for use in high-intensity earthquake zones, which has the following advantages:
[0025] 1. The problem of anti-falling beam blocks hindering the lateral movement of T-beams was solved by pre-embedding steel bars in the anti-falling beam blocks and adjusting the construction process to pour concrete after all T-beams were installed.
[0026] 2. By setting a reaction frame that can be moved multiple times on the transverse movement device, the problem of insufficient single stroke of the transverse movement jack is solved. At the same time, the structure is connected by bolts, which makes installation and disassembly relatively simple. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is the construction structure drawing corresponding to the horizontal displacement of the T-beam.
[0028] Among them: 1- cap beam; 2- support pad stone; 3- anti-fall beam block; 4- cap beam block; 5- transverse track; 6- reaction frame; 7- T beam bracket; 8- sleeper; 9- transverse jack; 10 vertical jack; 11- T beam side beam. DETAILED DESCRIPTION
[0029] The following will be combined with the attached Figure 1 The device is described in detail, and the technical scheme in the embodiment of the device is described clearly and completely. Obviously, the described embodiment is only a part of the embodiment of this patent, not all of the embodiments. Based on the embodiments in this utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this patent.
[0030] The utility model provides a counterweight block device for realizing the crossing of a general bridge erecting machine; that is, a T-beam transverse displacement device used in high-intensity earthquake zones. By improving the transverse displacement device and adjusting the construction process of the anti-falling beam stopper, the transverse displacement and installation of the T-beam can be completed more simply and quickly.
[0031] like Figure 1 As shown, the present application provides a T-beam transverse movement device for use in high-intensity earthquake zones, wherein the transverse movement device consists of a transverse movement track 5, a reaction frame 6, a T-beam bracket 7, sleepers 8, a transverse movement jack 9, and a vertical jack 10. The transverse movement track 5 is made of steel plates, and a plurality of bolt holes are arranged on both sides. The reaction frame 6 is fixed to the transverse movement track 5 by bolts, and sleepers 8 are arranged at the suspended part at the bottom of the transverse movement track 5 for support, and the T-beam bracket 7 is placed with a T-beam side beam 11 to be erected.
[0032] In this application, the T-beam side beam 11 is placed on the T-beam bracket 7 of the transverse movement device, and the placement position is as close as possible to the installation position of the side beam, which can reduce the transverse movement stroke and complete the installation faster. At the same time, the hoisting wire rope of the bridge erection machine remains in the hoisting state to ensure that the side beam does not overturn during the transverse movement.
[0033] In the present application, bolt connection holes are provided correspondingly between the transverse track 5 and the reaction frame 6 so that the two can be quickly connected and disassembled by bolts.
[0034] In the present application, the transverse jack 9 is located between the reaction frame and the T-beam bracket. When pushing, the T-beam bracket is pushed instead of the beam body directly to prevent the beam body from being damaged.
[0035] In the present application, the vertical jack 10 is installed at the edge of the cap beam 1 and below the installation position of the T-beam side beam 11. During the construction of the cap beam, this position needs to be locally reinforced.
[0036] The following is combined with Figure 1 Further explain the specific implementation method of this patent:
[0037] Step 1: Construction of anti-falling beam block
[0038] During the construction of the cap beam, 3 steel bars of the anti-falling beam stopper are embedded in advance, but the anti-falling beam stopper 3 steel bars are not fully installed. Only the steel bars at the connection between the stopper and the cap beam are installed.
[0039] Step 2: Conventional T-beam erection
[0040] A bridge-erecting machine is used to erect the T-beam of the middle span, leaving only the side beams and secondary side beams unerected.
[0041] Step 3: Install the traverse device
[0042] A transverse device is installed on the cap beam and the secondary side beam pad. The transverse device consists of a transverse track 5, a reaction frame 6, a T beam bracket 7, sleepers 8, a transverse jack 9, and a vertical jack 10. The transverse track 5 is made of a steel plate, and multiple bolt holes are set on both sides. The reaction frame 6 can be fixed to the transverse track 5 by bolts. Sleepers 8 are set at the suspended part of the bottom of the transverse track 5 for support. The T beam bracket 7 is placed with the T beam side beam 11 to be erected.
[0043] Step 4: Side beam placement
[0044] The T-beam side beam 11 is placed on the T-beam bracket 7 of the transverse movement device by the bridge erection machine. The placement position is as close as possible to the installation position of the side beam, which can reduce the transverse movement stroke and complete the installation faster. At the same time, the bridge erection machine hoisting wire rope remains in the hoisting state to ensure that the side beam does not overturn during the transverse movement.
[0045] Step 5: Horizontal push
[0046] Start the oil supply of the lateral jack 9 and push the side beam to the installation position. Here, pay attention to whether the embedded steel bars of the anti-falling beam block 3 block the T beam. If necessary, some embedded steel bars can be cut off. When the lateral jack 9 reaches the maximum stroke, the oil of the lateral jack 9 is returned, the bolts of the reaction frame 6 are removed, the reaction frame 6 is moved forward, and the lateral jack 9 is reinstalled. The second lateral push is performed and the push is repeated until it is pushed to the installation position.
[0047] Step 6: T-beam vertical placement
[0048] Start the vertical jack 10 located at the edge of the cap beam 1 and below the T beam 11, lift up the T beam 11, remove the transverse movement device, install the T beam support, retract the vertical jack 10, drop the T beam 11 onto the support, and complete the transverse movement installation of the T beam.
[0049] Step 7: Construction of anti-falling beam block
[0050] After all T-beams are installed, the reinforcement binding and concrete pouring of the anti-falling beam block 3 are carried out.
[0051] The advantages of the utility model are:
[0052] 1. The problem of anti-falling beam blocks hindering the lateral movement of T-beams was solved by pre-embedding steel bars in the anti-falling beam blocks and adjusting the construction process to pour concrete after all T-beams were installed.
[0053] 2. By setting a reaction frame that can be moved multiple times on the transverse movement device, the problem of insufficient single stroke of the transverse movement jack is solved. At the same time, the structure is connected by bolts, which makes installation and disassembly relatively simple.
Claims
1. A T-beam lateral displacement device for use in high-intensity earthquake zones, characterized in that; The transverse movement device is composed of a transverse movement track (5), a reaction frame (6), a T-beam bracket (7), a sleeper (8), a transverse movement jack (9), and a vertical jack (10). The transverse movement track (5) is made of a steel plate and has a plurality of bolt holes on both sides. The reaction frame (6) is fixed to the transverse movement track (5) by bolts. A sleeper (8) is provided at the suspended portion of the bottom of the transverse movement track (5) for support. The T-beam bracket (7) is provided with a T-beam side beam (11) to be erected.
2. A T-beam lateral displacement device for use in high-intensity earthquake zones according to claim 1, characterized in that; The T-beam side beam (11) is placed on the T-beam bracket (7) of the transverse movement device, and is placed close to the side beam installation position.
3. A T-beam lateral displacement device for use in high-intensity earthquake zones according to claim 1, characterized in that; The transverse track (5) and the reaction frame (6) are provided with bolt connection holes correspondingly, so that the two can be quickly connected and disassembled by means of bolts.
4. A T-beam lateral displacement device for use in high-intensity earthquake zones according to claim 1, characterized in that; The transverse jack (9) is located between the reaction frame and the T-beam bracket.
5. The T-beam lateral displacement device for use in high-intensity earthquake zones according to claim 1, characterized in that; The vertical jack (10) is installed at the edge of the cap beam (1) and below the installation position of the T-beam side beam (11).