Novel pre-stress reinforced composite floor slab capable of preventing slurry leakage

By designing multiple waterproofing measures and prestressed reinforcement structures in prefabricated laminated plates, the problems of easy leakage of slurry and poor stress performance at the joints are solved, and higher integrity and structural safety are achieved.

CN222044656UActive Publication Date: 2024-11-22SHANDONG YOUDA CONSTR ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323657616.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-22
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

In existing prefabricated buildings, prefabricated laminates are prone to leakage during splicing, and the stress performance at the joints is poor, which affects the integrity and bearing capacity of the floor slabs.

Method used

The new type of prestressed reinforcement of the overlapping floor slab design is adopted, including the base plate, steel truss, corrugated pipe, grouting hole, water leakage pipe, steel bar, cover plate, positioning groove, positioning block, upper notch and lower notch. The design of embedded corrugated pipes, grouting holes and water-exposed pipes, combined with polyurethane-type water-expanded material coating, realizes multiple waterproof measures and enhances the stress and waterproof performance at the joints.

Benefits of technology

Effectively prevent slurry leakage, improve the integrity and structural safety of the floor slabs, enhance the stress performance at the joints, ensure that the floor slabs are not prone to cracking during construction and use, and improve the stability and safety of the building structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044656U_ABST
    Figure CN222044656U_ABST
Patent Text Reader

Abstract

The utility model provides a novel prestressed reinforced composite floor slab capable of preventing slurry leakage. The novel prestressed reinforced composite floor slab comprises a bottom plate, a steel truss, a corrugated pipe, a grouting hole, a bleeding pipe, a steel bar, a corrugated pipe connector, a cover plate, a positioning groove, a positioning block, an upper notch, a lower notch and the like. A corrugated pipe is pre-buried in the bottom plate, a water bleeding pipe and a grouting hole are arranged, and a corrugated pipe connector is subjected to coating treatment and sleeved with rubber, so that the leakage-proof effect is achieved. During construction, the positioning blocks are connected with the grooves, the steel bars are inserted, the cover plates are laid, and the post-pouring layer concrete is poured. And after the strength of the post-cast layer meets the requirement, prestress is applied, grouting is conducted through the grouting holes, and the bottom plate grouting holes exhaust air and bleed water. And the steel core is coated with rubber and is coated with a polyurethane type water-swelling material before connection, so that the leakage-proof performance is improved. The floor has the advantages of prestress reinforcement, simplicity and convenience in construction, corrosion prevention, multi-layer leakage-proof design, environmental protection and the like, and is suitable for improving the safety and the construction efficiency of a building structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of assembled building structures, in particular to a novel prestressed reinforced composite floor slab for preventing slurry leakage. Background Art

[0002] In prefabricated assembled concrete composite slabs, the size is limited due to transportation, lifting and handling. Prefabricated composite slabs with larger sizes need to be split into two pieces. In order to facilitate mold making and installation, the composite prefabricated slab without reinforcement technology is often adopted. The joints are generally only connected by steel mesh, which has low strength and is prone to leakage. In particular, when the composite slab is connected to the cast-in-place reinforced concrete as a whole, concrete needs to be poured, and the gap between the two composite slabs is very prone to leakage.

[0003] At present, during the installation process of existing floor slabs on the market, the floor slabs are pasted together in pairs and installed using cement concrete. The floor slabs are only fixed with concrete, which makes the installation and fixation between the floor slabs unstable. The ability to withstand shear stress between the two is poor, which reduces the bearing capacity between the floor slabs. In addition, in subsequent use, since the prefabricated panels are made in advance, they are only simply spliced ​​when used in construction. It is inevitable that there will be some gaps between the two prefabricated panels, which will cause cracks and make the integrity of the floor slab poor. Utility Model Content

[0004] The utility model provides a new type of prestressed reinforced composite floor slab with anti-leakage slurry, and its purpose is to solve the problem of poor stress performance and easy leakage of slurry when two prefabricated composite slabs are spliced ​​in the prior art. Therefore, a new type of composite floor slab is proposed to enhance the integrity of the composite floor slab, strengthen the stress performance of the joints, and prevent the floor slab from leaking slurry during construction and subsequent use.

[0005] The utility model solves the technical problem by adopting the following technical solution: a novel prestressed reinforced composite floor slab for preventing leakage of slurry, comprising a bottom plate, a steel truss, a corrugated pipe, a grouting hole, a seepage pipe, a steel bar, a cover plate, a positioning groove, a positioning block, an upper notch and a lower notch, a pre-buried corrugated pipe is arranged at the lower part of the bottom plate, a seepage pipe is connected in the middle of the corrugated pipe, the corrugated pipe and the seepage pipe are both rolled by steel strips, a corrugated pipe interface is arranged at one end of the corrugated pipe, the outermost steel plate layer of the corrugated pipe interface is coated with paint, and the outermost steel plate layer is coated with paint. The side is covered with rubber, and the seepage pipe leads to the top of the bottom plate. A steel truss is arranged on the bottom plate, and the steel truss is arranged on the upper part of the embedded corrugated pipe. Upper notches and lower notches are opened on both sides of the bottom plate. The upper notch forms a U-shaped groove for placing the cover plate after the two plates are spliced ​​together. The cover plate includes a steel top plate and a rubber strip. The top plate is a steel plate. The rubber strip is pressed into the U-shaped groove. The lower notch forms a rectangular groove for placing the steel bar after the two plates are spliced ​​together. The steel bar is composed of a steel core and rubber. The steel core is covered with the rubber and coated with paint.

[0006] During construction, two adjacent prefabricated composite slabs are placed in parallel, and the two adjacent prefabricated composite slabs are accurately connected through positioning blocks and positioning grooves, so that the corrugated pipe interface can be accurately connected to another composite floor slab. After the two plates are connected, the steel core is inserted, and the cover plate is laid. Then, the post-cast concrete is poured. After the concrete strength reaches the requirement, prestress is applied to the two plates on site through the post-tensioning method, and cement slurry is poured into the grouting holes on the side of the bottom plate, and the air and water are exhausted through the weeping ports.

[0007] Specifically, a layer of rubber is wrapped outside the steel core, and the function of preventing leakage of slurry is initially realized by squeezing during connection. At the same time, before the two plates are spliced, paint is applied on the connection side to assist in preventing leakage of slurry.

[0008] Specifically, the coating is a polyurethane-type water-swellable material, which expands and deforms when exposed to water, thereby playing a role in sealing and waterproofing.

[0009] The specific beneficial effects of the utility model are:

[0010] The utility model discloses a novel prestressed reinforced composite floor slab with anti-leakage slurry, which ensures the transverse stress performance of the slab by applying prestress on site, improves the influence of the splicing of the composite floor slab on the integrity of the floor slab, thereby ensuring that the floor slab will not be easily cracked and damaged during subsequent use, and maintains good performance. In addition, a steel core and a cover plate are arranged at the connection point, which can further ensure the longitudinal stress performance of the joint, and solve the problem of poor stress performance at the joint due to the lack of reinforcement.

[0011] The utility model arranges multiple waterproof measures to comprehensively perform waterproofing. In order to prevent leakage at the interface of the corrugated pipe, a three-layer corrugated pipe interface is arranged. After the two plates are spliced, the corrugated pipe interface is tightly plugged into the corrugated pipe on the other side. The two defense lines of rubber extrusion and water expansion are used to prevent water leakage at the splicing of the corrugated pipe. A cover plate is arranged to preliminarily prevent water leakage during concrete pouring. In addition, a steel core is also arranged at the lower notch of the lower part to further prevent water leakage. Water leakage during construction is prevented by multiple defense lines, the appearance of the floor slab is avoided from being damaged, and the concrete vibration caused by leakage is prevented from being loose, thereby ensuring the structural strength and improving the safety of the building structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.

[0013] Figure 1 The utility model provides a novel anti-leakage slurry prestressed reinforced composite floor slab of a preferred embodiment of the overall structure schematic diagram.

[0014] Figure 2 This is a cross-sectional view of the joints of a new type of prestressed reinforced composite floor slab with anti-leakage slurry.

[0015] Figure 3 It is a partial enlarged schematic diagram of the side of a new type of prestressed reinforced composite floor slab with anti-leakage slurry.

[0016] Figure 4 for Figure 3 AA section view in.

[0017] In the figure: 1, bottom plate, 2, steel truss, 3, corrugated pipe, 4, grouting hole, 5, seepage pipe, 6, steel bar, 61, steel core, 62, rubber, 7, corrugated pipe interface, 8, cover plate, 81, steel top plate, 82, rubber strip, 9, positioning groove, 10, positioning block, 11, upper notch, 12, lower notch, 13, coating. DETAILED DESCRIPTION

[0018] It should be noted that the following detailed descriptions are illustrative and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.

[0019] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0020] For the convenience of description, if the words "up", "down", "left" and "right" appear in the present invention, they only indicate that they are consistent with the up, down, left and right directions of the drawings themselves, and do not limit the structure. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or component must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0021] Compared with other prefabricated floor components, this new type of anti-leakage prestressed reinforced composite floor can effectively improve the stress performance and aesthetics of the composite floor joints, while preventing leakage and ensuring the structural safety of the cast-in-place layer. The utility model adopts on-site prestressing and connects two composite floor slabs in series by post-tensioning. The application of prestressing makes the two plates have higher integrity and more reliable stress performance at the joints. At the same time, multiple lines of defense such as cover plates and steel bars are set to prevent leakage at the joints. It can not only ensure that the cast-in-place layer will not be reduced in strength and the safety of the floor will not be reduced due to leakage, but also ensure the beauty of the floor after the construction is completed.

[0022] In a typical implementation of the present invention, Figure 1 Shown is a preferred embodiment type.

[0023] The present embodiment discloses a novel prestressed reinforced composite floor slab for preventing leakage of grout, which mainly includes a base plate 1, a steel truss 2, a corrugated pipe 3, a grouting hole 4, a seepage pipe 5, a steel bar 6, a corrugated pipe interface 7, a cover plate 8, a positioning groove 9, a positioning block 10, an upper notch 11, a lower notch 12, etc. A pre-buried bellows 3 is provided at the lower part of the bottom plate 1, and a seepage pipe is connected in the middle of the bellows 3. The bellows 3 and the seepage pipe 5 are both made of rolled steel strips. A bellows interface 7 is provided at one end of the bellows 3. The innermost bellows 3 is coated with paint 13, and the outermost side is covered with rubber 62. The seepage pipe 5 leads to the top of the bottom plate 1. A steel truss 2 is provided on the bottom plate 1. The steel truss 2 is arranged on the upper part of the pre-buried bellows 3. Upper notches 11 and lower notches 12 are provided on both sides of the bottom plate 1. The upper notch 11 forms a U-shaped groove for placing the cover plate 8 after the two plates are spliced ​​together. The cover plate 8 includes a steel top plate 81 and a rubber strip 82. The rubber strip 82 is pressed into the U-shaped groove. The lower notch 12 forms a rectangular groove for placing the steel bar 6 after the two plates are spliced ​​together. The steel bar 6 consists of a steel core 61 and rubber 62. The steel core 61 is covered with rubber 62 and coated with paint 13.

[0024] During construction, two adjacent prefabricated composite panels are placed in parallel, and the two adjacent prefabricated composite panels are accurately connected through the positioning blocks 10 and the positioning grooves 9, so that the corrugated pipe interface 7 can be accurately connected to another composite floor. After the two panels are connected, the steel bars 6 are inserted, and the cover plate 8 is laid. Then, the post-cast concrete is poured. After the concrete strength reaches the requirement, prestress is applied to the two panels on site through the post-tensioning method, and cement slurry is poured into the grouting holes 4 on the side of the bottom plate 1, and the gas and water are discharged through the seepage pipe 5.

[0025] Specifically, the steel bar 6 preliminarily realizes the function of preventing slurry leakage by squeezing the rubber 62 when the two plates are connected. At the same time, before the two plates are spliced, the coating 13 is applied on the connection side to assist in preventing slurry leakage.

[0026] Specifically, the coating 13 is a polyurethane-type water-swellable material, which expands and deforms when exposed to water, thereby playing a role in sealing and waterproofing.

[0027] Through the design of pre-buried corrugated pipes, grouting holes, and seepage pipes, a multi-level leak-proof design is achieved, which improves the safety and reliability of the overall structure and effectively prevents the possibility of water leakage. The corrugated pipes and seepage pipes are rolled with steel belts, and through the layers of rubber and paint, a strong waterproof barrier is formed, which improves the leak-proof performance of the floor.

[0028] The use of steel trusses and prestressed construction methods has significantly enhanced the load-bearing capacity and seismic performance of the floor slab, improving the stability and safety of the overall structure. The design of positioning blocks and positioning grooves has achieved accurate connection of prefabricated composite panels, simplifying the construction process. The prestressed construction method can also be quickly implemented on site, improving the efficiency of engineering construction.

[0029] The combination of steel core, coating and rubber effectively improves the corrosion resistance of the floor and prolongs its service life, making it particularly suitable for construction projects in harsh environments. The use of polyurethane water-expandable material as coating is environmentally friendly and can not only achieve effective sealing and waterproofing effects, but also expands in volume when exposed to water, thus better enhancing the waterproofing performance.

Claims

1. A new type of prestressed reinforced composite floor slab with anti-leakage slurry, characterized in that: It includes a base plate, a steel truss, a corrugated pipe, a grouting hole, a seepage pipe, a steel bar, a corrugated pipe interface, a cover plate, a positioning groove, a positioning block, an upper notch and a lower notch. A pre-buried corrugated pipe is arranged at the lower part of the base plate, a steel truss is arranged on the upper part of the pre-buried corrugated pipe, a seepage pipe is connected in the middle of the corrugated pipe, and a seepage pipe is arranged on one side of the corrugated pipe.

2. The novel prestressed reinforced composite floor slab with anti-leakage slurry as claimed in claim 1 is characterized in that: The bellows and the seepage pipe are both rolled from steel strips. A bellows interface is provided at one end of the bellows. The innermost bellows is coated with paint, the outermost layer is covered with rubber, and upper and lower notches are provided on both sides of the bottom plate.

3. The novel prestressed reinforced composite floor slab with anti-leakage slurry as claimed in claim 1 is characterized in that: The upper groove forms a U-shaped groove for placing the cover plate after the two plates are spliced ​​together. The cover plate includes a steel top plate and a rubber strip. The rubber strip is pressed into the U-shaped groove. The lower groove forms a rectangular groove for placing the steel bar after the two plates are spliced ​​together. The steel bar consists of a steel core and rubber. The steel core is covered with rubber and coated with paint.

4. The novel prestressed reinforced composite floor slab with anti-leakage slurry as claimed in claim 1 is characterized in that: The steel bar initially realizes the function of preventing slurry leakage by squeezing rubber when the two plates are connected. At the same time, before the two plates are spliced, paint is applied on the connection side to assist in preventing slurry leakage.

5. The novel prestressed reinforced composite floor slab with anti-leakage slurry as claimed in claim 4 is characterized in that: The coating is a polyurethane-type water-swellable material, which expands and deforms when in contact with water, thereby playing a role of sealing and waterproofing.

6. The novel prestressed reinforced composite floor slab with anti-leakage slurry as claimed in claim 1 is characterized in that: Through the design of pre-buried corrugated pipes, grouting holes and seepage pipes, a multi-level leak-proof design is achieved, which improves the safety and reliability of the overall structure and effectively prevents the possibility of water leakage.

Citation Information

Cited By

  • Environment-friendly energy-saving heat preservation type composite floor slab

    CN121802981A