Freezing receiving ground wall obstacle clearing safety protection door in confined water layer

By adopting the design of the frozen receiving floor wall clearance safety protective door in the pressure-bearing water layer in the shield construction, and using the combined structure of the connecting screw and the pressing plate, the problem of cumbersome installation and removal of the protective door is solved, and the frame body is realized Easy disassembly and efficient construction.

CN222045868UActive Publication Date: 2024-11-22CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420894004.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-25
Publication Date
2024-11-22
Estimated Expiration
2034-04-25

AI Technical Summary

Technical Problem

The installation and removal of protective doors during existing shield construction are complicated, and partial damage to the tunnel walls is required, affecting construction efficiency.

Method used

A safety protection door for freezing and receiving floor wall cleaning in the pressure-bearing water layer is designed, using a mounting frame and a protective door body. The connecting components include a connecting screw and a pressing plate. The connecting screw is used to force the connecting screw to make the pressing plate tighten the inner wall of the tunnel. , realize the frame fixation, facilitate locking or unlocking, and disassembly and assemble by screwing the connecting screw to avoid damage to the tunnel wall.

Benefits of technology

The disassembly and assembly operations of protective doors are simplified, construction efficiency is improved, damage to tunnel walls is reduced, and the frame is conveniently disassembly and assembly and stable fixation is achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222045868U_ABST
    Figure CN222045868U_ABST
Patent Text Reader

Abstract

The utility model discloses a freezing receiving ground wall obstacle clearing safety protection door in a confined water layer, and belongs to the technical field of protection doors, the freezing receiving ground wall obstacle clearing safety protection door comprises a mounting frame body and a protection door body, the mounting frame body is provided with connecting assemblies, the connecting assemblies are arranged around the outer side of the mounting frame body, and each connecting assembly comprises a connecting screw rod and a pressing plate; the connecting screw rod penetrates through the mounting frame body and is in threaded fit with the mounting frame body, the pressing plate is fixedly connected to one end of the connecting screw rod and is located outside the mounting frame body, the protective door body is hinged to the mounting frame body, and the mounting frame body is provided with a locking assembly for locking or unlocking the protective door body. The protective door dismounting device has the effects that dismounting of the protective door is conveniently achieved, and the working efficiency of dismounting of the protective door is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of protective doors, and in particular to a safety protective door for clearing obstacles on a frozen receiving ground wall in a pressurized water layer. Background Art

[0002] Among the current tunnel construction technologies, shield construction has been widely used because it can adapt to complex geological conditions and has high construction safety. In order to effectively avoid damage to the surrounding environment, improve construction speed and quality, shorten construction period, and reduce the impact on road traffic, current shield construction usually adopts the frozen dark excavation method in water-rich layers.

[0003] In the prior art, when the frozen tunneling method is used for tunnel construction, the soil is usually first frozen and reinforced by freezing pipes. After the soil reaches the designed strength, the protective door is installed. After the protective door is installed, the ground-connected wall inside the protective door is gradually chiseled out and the debris is transported through the protective door to achieve obstacle clearance. After the obstacle clearance is completed, the protective door is dismantled and backfilled with foam concrete, and then the shield is advanced to effectively isolate groundwater and ensure the safety of tunnel excavation.

[0004] With regard to the above-mentioned prior art, the protective door needs to be installed and removed during the shield construction process. The frame of the protective door is usually fixed to the tunnel wall by multiple rows of expansion bolts. When the protective door is removed, it is generally necessary to partially destroy the connected tunnel wall before removing it. The operation of disassembling and installing the protective door is cumbersome. Utility Model Content

[0005] In order to facilitate the disassembly and assembly of the protective door and improve the work efficiency of disassembly and assembly of the protective door, the present application provides a safety protective door for clearing obstacles of a frozen receiving ground wall in a pressurized water layer.

[0006] The present application provides a safety protection door for clearing obstacles on a frozen receiving wall in a pressurized water layer, which adopts the following technical solution:

[0007] A safety protective door for clearing obstacles on a frozen receiving ground wall in a pressurized water layer comprises a mounting frame and a protective door body, the mounting frame is provided with a connecting assembly, a plurality of connecting assemblies are arranged around the outer side of the mounting frame, the connecting assembly comprises a connecting screw and a pressure plate, the connecting screw is passed through and threadedly engaged with the mounting frame, the pressure plate is fixedly connected to one end of the connecting screw and is located outside the mounting frame, the protective door body is hingedly mounted on the mounting frame, and the mounting frame is provided with a locking assembly for locking or unlocking the protective door body.

[0008] By adopting the above technical scheme, when installing the installation frame, force is applied to rotate the connecting screw so that the connecting screw drives the pressure plate to move in the direction away from the installation frame. When each pressure plate is pressed against the inner wall of the tunnel, the position of the installation frame is fixed, so that it is convenient to transport and clear the debris by locking or unlocking the protective door body. When dismantling the installation frame, the connecting screw is rotated in the opposite direction so that the pressure plate releases the pressure against the inner wall of the tunnel, thereby releasing the fixation between the installation frame and the inner wall of the tunnel, thereby facilitating the disassembly of the installation frame. When disassembling and assembling the installation frame, force is applied to screw the connecting screw, without partially destroying the tunnel wall, so that the overall disassembly and assembly of the protective door is simple, which is conducive to improving the work efficiency of disassembling and assembling the protective door.

[0009] Optionally, a plug-in portion is fixedly connected to a side of the pressure plate away from the connecting screw, and an end of the plug-in portion away from the pressure plate is arranged in a pointed shape.

[0010] By adopting the above technical solution, when the pressure plate is pressed against the inner wall of the tunnel, the plug-in part is simultaneously inserted into the inner wall of the tunnel, thereby further limiting the position of the installation frame, which is beneficial to further ensure the stability of the installation frame when it is fixed.

[0011] Optionally, a wear-resistant pad is fixedly connected to a side of the pressure plate away from the connecting screw, and the plug-in portion is inserted through the wear-resistant pad.

[0012] By adopting the above technical scheme, the setting of the wear-resistant pad, on the one hand, plays a protective role when the pressure plate is pressed and fixed, which is beneficial to ensure the service life of the pressure plate; on the other hand, it further increases the friction between the pressure plate and the inner wall of the tunnel, which is beneficial to further ensure the stability of the installation frame when it is fixed.

[0013] Optionally, an installation arch beam arranged in one-to-one correspondence with the connecting screw is fixedly connected to the outside of the installation frame, the connecting screw is passed through the installation arch beam and cooperates with the installation arch beam thread, the connecting screw is fixedly connected with a rotating handle, and the rotating handle is located in the area enclosed by the installation arch beam and the installation frame.

[0014] By adopting the above technical solution, the installation of the arched beam makes it easy to achieve a longer movement stroke of the connecting screw along its own axis in a smaller space, thereby improving applicability. On the other hand, the rotation force space is divided, making it easy to rotate the connecting screw by applying force through the rotating handle.

[0015] Optionally, the locking assembly includes a locking screw and a locking plate, the locking screw is rotatably connected to the mounting frame, the locking plate is threadedly engaged with the locking screw, and a receiving hole for receiving the locking screw is opened on one side of the protective door body.

[0016] By adopting the above technical solution, the locking screw is rotated so that the locking screw is located in the accommodating hole, and then the locking plate is rotated so that the locking plate is pressed against the protective door body to achieve a firm fixation between the protective door body and the installation frame, which is easy to operate.

[0017] Optionally, the installation frame includes a first frame and a second frame, the first frame is provided with an installation cavity, the second frame is fixedly installed on the cavity wall of the installation cavity, the locking screw is rotatably installed on the second frame, and the second frame is provided with a movable groove corresponding to the accommodating hole on the side facing the first frame, and the locking screw is rotatably set in the movable groove.

[0018] By adopting the above technical solution, the arrangement of the first frame and the second frame facilitates the assembly of the locking screw, and the arrangement of the movable groove plays a further limiting role when the locking screw rotates, thereby facilitating further ensuring the stability of the locking screw when it rotates.

[0019] Optionally, the installation frame is provided with a sealing groove, a groove wall of the sealing groove is fixedly connected with a sealing gasket, the protective door body is fixedly connected with a sealing portion, and when the protective door body is locked with the installation frame, the sealing gasket presses against the sealing portion.

[0020] By adopting the above technical solution, the sealing gasket is helpful to ensure the sealing of the protective door body after being locked with the installation frame, thereby helping to ensure the protective performance of the protective door body.

[0021] Optionally, a return spring is fixedly arranged in the sealing groove, and when the protective door body is locked with the installation frame, the return spring has an elastic force to push the sealing part to move in a direction away from the sealing groove.

[0022] By adopting the above technical solution, after the lock between the protective door body and the installation frame is released, the protective door body moves in a direction away from the sealing groove under the elastic force of the reset spring, thereby further facilitating the staff to open and close the protective door body, and the operation is simple.

[0023] Optionally, the mounting frame is fixedly connected with a connecting tube, and the connecting tube has a connecting groove extending through the vertical direction. The protective door body is fixedly connected with a connecting rod plugged into the connecting groove, and one end of the connecting rod is fixedly connected with a fixing part and the other end is threadedly engaged with a locking nut.

[0024] By adopting the above technical solution, the connection between the protective door body and the installation frame can be achieved by inserting the connecting rod into the connecting groove. At the same time, the locking nut is screwed so that the locking nut contacts the connecting rod. The cooperation between the fixing part and the connecting rod plays a limiting role when the protective door body rotates, which is beneficial to further ensure the stability of the protective door body when it rotates.

[0025] In summary, the present application includes at least one of the following beneficial technical effects:

[0026] 1. When the installation frame is disassembled, the connecting screws can be screwed by applying force, without partially destroying the tunnel wall, so that the overall disassembly and assembly of the protective door is simple and convenient, which is conducive to improving the work efficiency of the disassembly and assembly of the protective door.

[0027] 2. The installation of the arched beam makes it easy to achieve a longer movement stroke of the connecting screw along its own axis in a smaller space, thereby improving applicability. On the other hand, the force application space for rotation is separated, making it easier to rotate the connecting screw by applying force through the rotating handle.

[0028] 3. The arrangement of the first frame and the second frame facilitates the assembly of the locking screw, and the arrangement of the movable groove further limits the rotation of the locking screw, thereby facilitating further ensuring the stability of the locking screw during rotation. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.

[0030] Figure 2 It is a schematic diagram of the structure of the installation frame and the protective door body in the embodiment of the present application.

[0031] Figure 3 It is an exploded schematic diagram of the protective door body and the mounting frame in the embodiment of the present application.

[0032] Figure 4 It is a schematic diagram of the structure of the protective door body in the embodiment of the present application.

[0033] Description of reference numerals:

[0034] 1. Installation frame; 101. First frame; 102. Second frame; 2. Protective door body; 3. Installation cavity; 4. Connecting screw; 5. Pressure plate; 6. Installing arch beam; 7. Rotating handle; 8. Plug-in part; 9. Wear-resistant pad; 10. Fixing screw; 11. Reinforcement seat; 12. Connecting port; 13. Connecting cylinder; 14. Connecting groove; 15. Connecting rod; 16. Fixing part; 17. Locking nut; 18. Locking screw; 19. Locking plate; 20. Installation groove; 21. Locking handle; 22. Movable groove; 23. Accommodating hole; 24. Reinforcing rib; 25. Sealing groove; 26. Sealing pad; 27. Sealing part; 28. Ejection groove; 29. ​​Reset spring; 30. Ejection plate; 31. Fixed seat. DETAILED DESCRIPTION

[0035] The following is combined with Figure 1-4 This application is described in further detail.

[0036] An embodiment of the present application discloses a safety protection door for clearing obstacles of a frozen receiving diaphragm wall in a confined aquifer. Refer to Figure 1 , the safety protection door for clearing obstacles of the frozen receiving diaphragm wall in the confined aquifer includes a mounting frame body 1 and a protection door body 2. Among them, the mounting frame body 1 includes a first frame 101 and a second frame 102. In the embodiment of the present application, the first frame 101 is arranged in a U-shape. An installation cavity 3 is formed through the first frame 101, and the installation cavity 3 extends to the bottom of the first frame 101. The second frame 102 is fixedly installed on the cavity wall of the installation cavity 3 by welding, and multiple groups of connection components are arranged on the outside of the first frame body.

[0037] Continue to refer to Figure 1 , specifically, the number of connection components is set to three groups, and the three groups of connection components are respectively arranged on the three side walls of the first frame 101 away from the bottom of the tunnel. The connection component includes a connection screw 4 and a pressing plate 5. Further, an installation arched beam 6 is fixedly connected to each of the three side walls of the first frame 101 away from the bottom of the tunnel. The connection screws 4 of the two groups of connection components located on both sides of the first frame 101 in the horizontal direction are respectively arranged through the installation arched beams 6 on both sides of the first frame 101 in the horizontal direction, and the connection screw 4 of the connection component located at the top of the first frame 101 is arranged through the installation arched beam 6 at the top of the first frame 101 in the vertical direction. One end of each connection screw 4 close to the first frame 101 is fixedly connected with a rotating handle 7, and each rotating handle 7 is respectively located in the area surrounded by each installation arched beam 6 and the installation frame body 1, so as to facilitate the staff to apply force to rotate the connection screw 4.

[0038] Refer to Figure 1 and Figure 2 , the pressing plates 5 of each group of connection components are respectively fixedly connected to one end of each connection screw 4 away from the rotating handle 7, and each connection screw 4 is respectively located outside each installation arched beam 6, so that when the connection screw 4 rotates, each connection screw 4 drives each pressing plate 5 to move away from the first frame 101, that is, the installation frame body 1. When each pressing plate 5 abuts tightly against the inner wall of the tunnel, the fixation of the position where the installation frame body 1 is located is realized.

[0039] Continue to refer to Figure 1 and Figure 2In order to further ensure the stability of the position of the first frame 101, i.e., the installation frame 1, when it is fixed, a plug-in portion 8 is fixedly connected to the side of the pressure plate 5 away from the connecting screw 4, and the end of the plug-in portion 8 away from the pressure plate 5 is set to be pointed, so that the plug-in portion 8 can be inserted into the inner wall of the tunnel. A wear-resistant pad 9 is fixedly connected to the side of each pressure plate 5 away from the connecting screw 4. The material of the wear-resistant pad 9 is selected as rubber in the embodiment of the present application. Each plug-in portion 8 is respectively penetrated by each wear-resistant pad 9 to play a protective role when the pressure plate 5 is pressed and fixed, to ensure the service life of the pressure plate 5, and at the same time, to further increase the friction between the pressure plate 5 and the inner wall of the tunnel, thereby further ensuring the stability of the installation frame when it is fixed.

[0040] Continue to refer to Figure 1 and Figure 2 The first frame 101 is fixedly provided with fixed seats 31 at the two corners away from the bottom of the tunnel. The two fixed seats 31 are threadedly matched with fixing screws 10. The ends of the two fixing screws 10 away from the fixed seats 31 are fixedly connected with reinforcement seats 11, so that the reinforcement seats 11 can be pressed against the inner wall of the tunnel by rotating the fixing screws 10, which is conducive to further limiting the position of the frame.

[0041] Reference Figure 2 and Figure 3 In the embodiment of the present application, the second frame 102 is rectangular, and a connecting port 12 is provided in the second frame 102, and the protective door body 2 is hingedly mounted on the second frame 102 and is used to open and close the connecting port 12. Specifically, the free end of the second frame 102 close to one side of its horizontal direction is fixedly connected with two connecting cylinders 13 distributed in the vertical direction, and the connecting cylinder 13 has a connecting groove 14 that is provided in the vertical direction. The protective door body 2 is fixedly connected with a connecting rod 15 that is plugged into the connecting groove 14 and is provided corresponding to the two connecting cylinders 13. One end of the top of the connecting rod 15 is fixedly connected with a fixing portion 16, and the other end is threadedly matched with a locking nut 17, so that the fixing portion 16 and the connecting rod 15 cooperate to limit the rotation of the protective door body 2, thereby further ensuring the stability of the protective door body 2 during rotation.

[0042] Continue to refer to Figure 2 and Figure 3The second frame 102 is provided with a locking assembly for locking or unlocking the protective door body 2. The locking assembly is located on the side of the second frame 102 away from the connecting tube 13 and has two groups distributed in the vertical direction. Specifically, the locking assembly includes a locking screw 18 and a locking plate 19. The first frame 101 is provided with a mounting groove 20 in a closed shape near the cavity wall of the mounting cavity 3. One end of the locking screw 18 is rotatably connected to the groove wall of the mounting groove 20. The locking plate 19 is threadedly engaged with the locking screw 18. The locking plate 19 is fixedly connected with a locking handle 21. The locking screw 18 is penetrated through the locking handle 21 and threadedly engaged with the locking handle 21, so that the staff can apply force to realize the rotation of the locking plate 19.

[0043] Reference Figure 3 The second frame 102 is provided with two movable grooves 22 respectively corresponding to the two locking screws 18 on one side facing the first frame 101. The two locking screws 18 are respectively rotated and matched in the two movable grooves 22, so as to facilitate the installation of the locking screws 18 and ensure the stability of the locking screws 18 when they rotate. The protective door body 2 is provided with a receiving hole 23 corresponding to the movable groove 22 on one side facing the locking screws 18. When the protective door body 2 closes the communication port 12, the receiving hole 23 is connected with the movable groove 22, so as to accommodate the locking screws 18 when the locking screws 18 rotate, and then the protective door body 2 and the second frame 102, i.e., the installation frame 1, are firmly fixed by screwing the locking plate 19.

[0044] Reference Figure 3 and Figure 4 A plurality of reinforcing ribs 24 are fixedly connected to the side of the protective door body 2 away from the second frame 102 to ensure the structural strength of the protective door body 2. To ensure the sealing performance of the protective door body 2 when the communication port 12 is closed, a circle of sealing grooves 25 arranged in an annular shape is provided on the side of the second frame 102 facing the protective door body 2. A circle of sealing gaskets 26 in a closed shape are fixedly connected to the side groove wall of the sealing groove 25. A sealing portion 27 is fixedly connected to the protective door body 2. The sealing portion 27 is plugged into and matched with the sealing groove 25. When the protective door body 2 closes the communication port 12, each sealing gasket 26 presses against the sealing portion 27.

[0045] Reference Figure 3A plurality of ejection grooves 28 are provided on the groove wall of the sealing groove 25 away from its own groove opening, that is, the bottom groove wall of the sealing groove 25. A return spring 29 is fixedly connected to the groove wall of each ejection groove 28 away from its own groove opening. An ejection plate 30 is fixedly connected to one end of each return spring 29 facing the groove opening of the ejection groove 28. When the protective door body 2 closes the connecting port 12 and is locked with the second frame 102, that is, the installation frame 1, the ejection plate 30 has an elastic force to push the sealing portion 27 to move away from the sealing groove 25 under the elastic force of the return spring 29, so that after the protective door body 2 is unlocked from the second frame 102, that is, the installation frame 1, the protective door body 2 is pushed by the ejection plate 30, that is, moves in the direction away from the sealing groove 25 under the elastic force of the return spring 29, thereby facilitating the opening of the protective door body 2.

[0046] The implementation principle of the safety protection door for clearing obstacles on the frozen receiving ground wall in the pressurized water layer in the embodiment of the present application is as follows: when installing the installation frame 1, force is applied to rotate the connecting screw 4 so that the connecting screw 4 drives the pressure plate 5 to move in the direction away from the installation frame 1. When each plug-in part 8 is inserted into the inner wall of the tunnel and each pressure plate 5 is pressed against the inner wall of the tunnel, the position of the installation frame 1 is fixed, thereby facilitating the transportation and clearing of debris by locking or unlocking the protection door body 2. When dismantling the installation frame 1, the connecting screw 4 is rotated in the opposite direction so that the connecting part 8 is separated from the inner wall of the tunnel and the pressure plate 5 is released from the tight contact with the inner wall of the tunnel, so as to release the fixation between the installation frame 1 and the inner wall of the tunnel, thereby facilitating the disassembly of the installation frame 1. When disassembling and assembling the installation frame 1, force is applied to screw the connecting screw 4, without partially destroying the tunnel wall, so that the overall disassembly and assembly operation of the protection door is simple, which is conducive to improving the work efficiency of disassembling and assembling the protection door.

[0047] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A safety protection door for clearing obstacles on the freezing receiving ground wall in a pressurized water layer. Features: The invention comprises an installation frame (1) and a protective door body (2), wherein the installation frame (1) is provided with a connection assembly, wherein a plurality of connection assemblies are arranged around the outer side of the installation frame (1), wherein the connection assembly comprises a connection screw (4) and a pressure plate (5), wherein the connection screw (4) is passed through and threadedly engaged with the installation frame (1), wherein the pressure plate (5) is fixedly connected to one end of the connection screw (4) and is located outside the installation frame (1), wherein the protective door body (2) is hingedly mounted on the installation frame (1), and wherein the installation frame (1) is provided with a locking assembly for locking or unlocking the protective door body (2).

2. A safety protection door for clearing obstacles on a frozen receiving ground wall in a pressurized water layer according to claim 1, Features: A plug-in portion (8) is fixedly connected to the side of the pressure plate (5) away from the connecting screw rod (4), and the end of the plug-in portion (8) away from the pressure plate (5) is arranged in a pointed shape.

3. A safety protection door for clearing obstacles of frozen receiving ground walls in a pressurized water layer according to claim 2, Features: A wear-resistant pad (9) is fixedly connected to the side of the pressure plate (5) away from the connecting screw (4), and the plug-in portion (8) is inserted through the wear-resistant pad (9).

4. A safety protection door for clearing obstacles on a frozen receiving wall in a pressurized water layer according to any one of claims 1 to 3, Features: The outside of the installation frame (1) is fixedly connected with an installation arch beam (6) which is arranged in a one-to-one correspondence with the connection screw (4); the connection screw (4) is inserted into the installation arch beam (6) and threadedly cooperates with the installation arch beam (6); the connection screw (4) is fixedly connected with a rotating handle (7); and the rotating handle (7) is located in an area enclosed by the installation arch beam (6) and the installation frame (1).

5. A safety protection door for clearing obstacles of frozen receiving ground walls in a pressurized water layer according to claim 1, Features: The locking assembly comprises a locking screw (18) and a locking plate (19); the locking screw (18) is rotatably connected to the mounting frame (1); the locking plate (19) is threadedly engaged with the locking screw (18); and a receiving hole (23) for receiving the locking screw (18) is provided on one side of the protective door body (2).

6. A safety protection door for clearing obstacles on a frozen receiving ground wall in a pressurized water layer according to claim 5, Features: The installation frame (1) comprises a first frame (101) and a second frame (102); the first frame (101) is provided with an installation cavity (3); the second frame (102) is fixedly installed on the cavity wall of the installation cavity (3); the locking screw (18) is rotatably installed on the second frame (102); the second frame (102) is provided with a movable groove (22) corresponding to the accommodating hole (23) on a side facing the first frame (101); and the locking screw (18) is rotatably installed in the movable groove (22).

7. A safety protection door for clearing obstacles on a frozen receiving wall in a pressurized water layer according to claim 5, Features: The installation frame (1) is provided with a sealing groove (25), a groove wall of the sealing groove (25) is fixedly connected with a sealing gasket (26), the protective door body (2) is fixedly connected with a sealing portion (27), and when the protective door body (2) and the installation frame (1) are locked, the sealing gasket (26) presses against the sealing portion (27).

8. A safety protection door for clearing obstacles on a frozen receiving ground wall in a pressurized water layer according to claim 7, Features: A return spring (29) is fixedly arranged in the sealing groove (25); when the protective door body (2) and the mounting frame (1) are locked, the return spring (29) has an elastic force that pushes the sealing portion (27) to move in a direction away from the sealing groove (25).

9. A safety protection door for clearing obstacles on a frozen receiving ground wall in a pressurized water layer according to claim 7, Features: The installation frame (1) is fixedly connected to a connection tube (13), the connection tube (13) having a connection groove (14) extending through the connection tube in a vertical direction, the protective door body (2) is fixedly connected to a connection rod (15) plug-fitted with the connection groove (14), one end of the connection rod (15) is fixedly connected to a fixing portion (16), and the other end is threadedly fitted with a locking nut (17).