Roadbed connecting structure based on curing technology
By laying a solidified soil transition layer and setting up drainage blind ditches at the roadbed junction, the problem of uneven settlement of the roadbed was solved, and the roadbed connection was made convenient, environmentally friendly and efficient, thus improving the stability and economy of the road.
Patent Information
- Application Number
- CN202323362775.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-11
AI Technical Summary
The uneven settlement at the roadbed junction caused by existing technologies affects the stability and durability of the road structure, and also results in complicated construction procedures, low material utilization, long construction period, and high project cost.
The original soil treated with solidification technology forms a solidified soil transition layer, which is used to connect the old and new roadbeds. Combined with impermeable geotextile and drainage blind ditches, it forms a stepped structure to improve the integrity and stability.
It improves the integrity and stability of roadbed junctions, reduces construction procedures, saves materials and construction time, lowers project costs, and adapts to the needs of different levels and traffic volumes.
Smart Images

Figure CN222065054U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of new construction and reconstruction of municipal roads or highways, in particular to a roadbed connection structure based on solidification technology. Background Art
[0002] At the intersection of cut-and-fill on newly built roads, and at the intersection of old and new roads on renovated and expanded roads, the inconsistent consolidation time of the roadbed on both sides of the intersection often leads to uneven settlement of the roadbed, affecting the stability and durability of the road structure. Commonly used measures for the connection of cut-and-fill and new and old roadbeds include digging steps, laying geotextiles layer by layer, loading or natural settlement. The main problems are: (1) The quality of the backfill soil required for digging steps is high, and the utilization rate of the original soil in the existing site is low; (2) Laying geotextiles layer by layer is relatively cumbersome, and large-scale machinery is not suitable for rolling on geotextiles, resulting in a long construction period and difficult to control quality; (3) The construction period of roadbed preloading and natural settlement is long.
[0003] In summary, conventional treatment methods require a large amount of earthwork, make little use of the original soil, are not environmentally friendly, require many construction steps, are costly, and have difficulty ensuring quality. Therefore, a new roadbed connection technology needs to be designed to solve the above problems. Summary of the Invention
[0004] The purpose of this utility model is to provide a road subgrade connection structure based on solidification technology in response to the above-mentioned deficiencies in the existing technology. By laying a solidified soil transition layer composed of original soil treated with solidification technology at the new and old junctions of the road subgrade, an organic connection at the new and old junctions of the road subgrade is achieved, thereby improving environmental protection, ease of construction, reliability and economy.
[0005] The purpose of this utility model is achieved by the following technical solutions:
[0006] A road subgrade connection structure based on solidification technology is used for connecting two different road subgrades, wherein the two road subgrades include a first subgrade and a second subgrade, and is characterized in that a stepped structure is arranged between the first subgrade and the second subgrade, and a solidified soil transition layer is arranged on one or more layers of the stepped structure, one end of the solidified soil transition layer is arranged in the first subgrade, and the other end is arranged in the second subgrade, that is, the solidified soil transition layer is arranged at the connection position between the first subgrade and the second subgrade.
[0007] The top surface and / or bottom surface of the solidified soil transition layer is provided with an anti-seepage geotextile.
[0008] A drainage blind ditch is provided in the solidified soil transition layer.
[0009] The connection structure is used for connecting the excavation section roadbed and the filling section roadbed when constructing a new road. The excavation section roadbed is the first roadbed, the filling section roadbed is the second roadbed, and the thickness of the solidified soil transition layer is 0.8-2.0m.
[0010] The connection structure is used for connecting the original roadbed and the widened roadbed when the road is rebuilt or expanded. The original roadbed is the first roadbed, the widened roadbed is the second roadbed, and the thickness of the solidified soil transition layer is 0.8-2.0m.
[0011] The solidified soil transition layer is original soil treated with a solidifying agent.
[0012] The advantages of the utility model are:
[0013] (1) Solidified soil technology is used in the roadbed at the junction to form a transition layer structure similar to a "slab", which is more conducive to ensuring the integrity and stability of both sides of the junction and effectively reducing uneven settlement;
[0014] (2) The main materials of the transition layer are existing soil, curing agent, etc., with fewer types of materials, convenient local materials, environmental protection and cost saving;
[0015] (3) The main machinery is basically the same as the roadbed treatment machinery, with mature technology and convenient construction;
[0016] (4) Reduce the laying of geotextiles, reduce the number of processes, and save construction time;
[0017] (5) For roads of different grades and different traffic demands, the length and thickness of the transition layer can be adjusted to meet the connection requirements, and the design and construction are more flexible. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 This is a cross-sectional diagram of the application of the utility model to the roadbed treatment at the intersection of fill and cut of a newly built road (the connection between the longitudinal (parallel to the driving direction) and transverse (perpendicular to the driving direction) fill and cut intersection of the newly built road (the thickness of the transition layer ∈ [0.8m, 1.0m]);
[0019] Figure 2 This is a cross-sectional diagram of the application of the utility model to the roadbed treatment at the intersection of fill and cut of a newly built road (the connection between the longitudinal (parallel to the driving direction) and transverse (perpendicular to the driving direction) fill and cut intersection of the newly built road (the thickness of the transition layer ∈ [1.2m, 2.0m]);
[0020] Figure 3 This is a cross-sectional view of the utility model applied to the roadbed treatment at the junction of the old and new roads in the reconstruction (the reconstruction and expansion road is connected horizontally (perpendicular to the driving direction) (the thickness of the transition layer ∈ [0.8m, 1.0m]);
[0021] Figure 4This is a cross-sectional diagram of the application of the utility model to the roadbed treatment at the junction of the new and old roads (the connection at the transverse (perpendicular to the driving direction) of the expanded and reconstructed road (the thickness of the transition layer ∈ [1.2m, 2.0m]). DETAILED DESCRIPTION
[0022] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by those skilled in the art:
[0023] like Figure 1-4 As shown, the symbols in the figure respectively represent: solidified soil transition layer 1, fill roadbed 2, drainage blind ditch 3, anti-seepage geotextile 4, anti-seepage geotextile 5, solidified soil transition layer 6, solidified soil transition layer 7, fill roadbed 8, drainage blind ditch 9, anti-seepage geotextile 10, anti-seepage geotextile 11;
[0024] Solidified soil transition layer 12, fill roadbed 13, drainage blind ditch 14, anti-seepage geotextile 15, anti-seepage geotextile 16, solidified soil transition layer 17, solidified soil transition layer 18, fill roadbed 19, drainage blind ditch 20, anti-seepage geotextile 21, anti-seepage geotextile 22;
[0025] Ground line 23, pavement structure 24, original pavement structure 25, widened pavement structure 26, original road slope 27; excavation section A, fill section B, original road C, widened road D.
[0026] Example 1: Figure 1 and Figure 2 As shown, the roadbed connection structure based on solidification technology in this embodiment is used to connect the roadbed at the intersection of cut and fill on a newly built road, specifically the connection between cut section A and fill section B. A ground line 23 is located at the location of cut section A, and a pavement structure 24 is laid on the newly built roadbed.
[0027] like Figure 1 or Figure 2 As shown, a staggered stepped structure is interlaced between the excavation section A and the fill section B to enhance the integrity of the two sections. In this embodiment, the stepped structure overlaps from the fill section B to the excavation section A. That is, the fill roadbed 2 within the fill section B overlaps the steps constructed in the excavation section A. This ensures that the traffic load above is primarily borne by the newly constructed fill roadbed 2 of the fill section B. Furthermore, this embodiment provides two connection methods at the intersection of the excavation and fill of the newly constructed road, tailored to different design requirements:
[0028] 1) If Figure 1As shown, this method is suitable for connecting the longitudinal (parallel to the driving direction) and transverse (perpendicular to the driving direction) fill-cut junctions of newly constructed roads, primarily targeting low-grade or lightly trafficked roads. In this case, a solidified soil transition layer 1 is installed on the roadbed of fill section B, corresponding to the first step from top to bottom. This solidified soil transition layer 1 acts as a "shortcut," and its thickness covers the entire roadbed working area. This means that the load at the junction is primarily borne by the solidified soil transition layer. Generally speaking, the thickness of the solidified soil transition layer 1 matches the thickness of a single step in the stepped structure to ensure that the load borne by the solidified soil transition layer 1 is evenly transferred downward.
[0029] An impermeable geotextile 5 is laid on top of the solidified soil transition layer 1 to create an impermeable pavement structure in areas with high rainfall. Furthermore, drainage blind ditches 3 or blind pipes are installed within the solidified soil transition layer 1, and an impermeable geotextile 4 is laid beneath the solidified soil transition layer 1 to accommodate use in areas with high groundwater levels. In this case, the fill roadbed 2 can also be constructed using a material with high water permeability.
[0030] In this embodiment, a solidified soil transition layer 1 is paved together for the excavation section A and the filling section B after over-excavation. The thickness of the solidified soil transition layer 1 is not less than 0.8m and not more than 1.0m. The longitudinal transition layer length is preferably 10m, and the transverse transition layer length is preferably 3m.
[0031] 2) If Figure 2 As shown, it is suitable for the connection between the longitudinal (parallel to the driving direction) and transverse (perpendicular to the driving direction) fill-cut junction of newly built roads and is mainly for high-grade roads or roads with large traffic volume. Compared with low-grade roads or roads with small traffic volume, the difference is that two separate layers of solidified soil transition layers are set at the connection between the excavation section A and the fill section B, including solidified soil transition layer 6 and solidified soil transition layer 7. This transition layer increases the overall thickness of the solidified soil transition layer in the depth direction, but Figure 2 In the cross-sectional direction shown, the solidified soil transition layer 6 and the solidified soil transition layer 7 still match the stepped staggered structure set between the excavation section A and the fill roadbed 8 of the fill section B, that is, the solidified soil transition layer 6 and the solidified soil transition layer 7 are also in the shape of a plank, and the solidified soil transition layer 6 is deeper into the range of the excavation section A than the solidified soil transition layer 7, so as to completely cover the working area and ensure the bearing capacity of the connection position between the new and old roadbeds.
[0032] In this embodiment, a drainage blind ditch 9 is also provided at the solidified soil transition layer 6, and an anti-seepage geotextile 11 and an anti-seepage geotextile 10 are respectively provided on the top and bottom surfaces thereof.
[0033] In this embodiment, the overall thickness of the solidified soil transition layer is not less than 1.2 m and not more than 2.0 m. The longitudinal transition layer length is preferably 10 m, and the transverse transition layer length is preferably 3 m.
[0034] Example 2: Figure 3 and Figure 4 As shown, this embodiment differs from Example 1 in that it is used for the connection of roadbeds at the junction of a new and an old road, specifically the connection between an existing road C and a widened road D. The surface of the existing road C is paved with an existing pavement structure 25, while the surface of the widened road D is paved with a widened pavement structure 26, which connects with the existing pavement structure 25. The existing road C has an existing roadside slope 27, and the stepped structure between the fill roadbed 13 (or fill roadbed 19) of the widened road D and the existing road C intrudes into the inside of the existing roadside slope 27.
[0035] Similarly, this embodiment provides two connection methods at the intersection of fill and cut of the new road according to different design requirements, as follows:
[0036] 1) If Figure 3 As shown, this method is suitable for connecting roads transversely (perpendicular to the direction of travel) during road expansion and reconstruction, primarily targeting low-grade roads or roads with low traffic volume. A solidified soil transition layer 12 is installed at the roadbed connecting the existing road C and the widened road D. This solidified soil transition layer 12 includes a drainage blind ditch 14, an impermeable geotextile 15, and an impermeable geotextile 16. The thickness of the solidified soil transition layer 12 is not less than 0.8m and not more than 1.0m, and its length is preferably 3m.
[0037] 2) If Figure 4 As shown, it is suitable for connecting the transverse (perpendicular to the direction of travel) connection of roads during renovation and expansion, and is primarily targeted at high-grade roads or roads with high traffic volume. It includes a solidified soil transition layer 17 and a solidified soil transition layer 18. Solidified soil transition layer 17 is provided with a drainage blind ditch 20, an anti-seepage geotextile 21, and an anti-seepage geotextile 22. The overall thickness of the solidified soil transition layer is not less than 1.2m and not more than 2.0m, and the length is preferably 3m.
[0038] In the above embodiment, the primary materials for the solidified soil transition layer are undisturbed soil and a solidifying agent. The organic matter content of the usable undisturbed soil or treated undisturbed soil should not exceed 10%, and the moisture content and other parameters must meet the requirements of the selected solidifying agent. The solidified soil transition layer exhibits greater integrity and stability than conventional roadbeds. L1-L10 represent the parameters for setting the length of the solidified soil transition layer.
[0039] Each solidified soil transition layer can be constructed by layered backfilling and compaction, with the thickness of each layer not exceeding 0.3m to ensure the density of the solidified soil transition layer itself and the corresponding structural performance.
[0040] In some cases, when the thickness of the solidified soil transition layer exceeds 1m, the steps are constructed according to the fill-excavation boundary line, the step height shall not exceed 1m, and the step length shall be 1m.
[0041] Although the above embodiments have described the concepts and embodiments of the present invention in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the present invention without departing from the scope of the claims, so they are not described here one by one.
Claims
1. A road subgrade connection structure based on solidification technology, used for connecting two different road subgrades, the two road subgrades comprising a first subgrade and a second subgrade, Features: A staggered step-like structure is arranged between the first roadbed and the second roadbed, and a solidified soil transition layer is arranged on one or more layers of the stair-like structure, one end of the solidified soil transition layer is arranged in the first roadbed, and the other end is arranged in the second roadbed, that is, the solidified soil transition layer is arranged at the connecting position between the first roadbed and the second roadbed.
2. A road subgrade connection structure based on solidification technology according to claim 1, Features: The top surface and / or bottom surface of the solidified soil transition layer is provided with an anti-seepage geotextile.
3. A road subgrade connection structure based on solidification technology according to claim 1, Features: A drainage blind ditch is arranged in the solidified soil transition layer.
4. A road subgrade connection structure based on solidification technology according to claim 1, Features: The connection structure is used for connecting the excavation section roadbed and the filling section roadbed when a new road is constructed. The excavation section roadbed is the first roadbed, the filling section roadbed is the second roadbed, and the thickness of the solidified soil transition layer is 0.8-2.0m.
5. A road subgrade connection structure based on solidification technology according to claim 1, Features: The connection structure is used for connecting the original roadbed and the widened roadbed when the road is rebuilt or expanded. The original roadbed is the first roadbed, the widened roadbed is the second roadbed, and the thickness of the solidified soil transition layer is 0.8-2.0m.
6. A road subgrade connection structure based on solidification technology according to claim 1, Features: The solidified soil transition layer is original soil treated with a solidifying agent.