Toe board pier structure

By setting up a toe slab pier structure in the concrete panel rock pile dam project, the span of the Bere Bridge was shortened, and the problem of damage to the toe slabs was solved by the Beire Bridge demolition, reducing investment and improving construction quality.

CN222065141UActive Publication Date: 2024-11-26POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420661535.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-01
Publication Date
2024-11-26
Estimated Expiration
2034-04-01

Smart Images

  • Figure CN222065141U_ABST
    Figure CN222065141U_ABST
Patent Text Reader

Abstract

The utility model provides a toe board pier structure, which is characterized in that a dam upstream abutment and an in-dam abutment are respectively arranged on the upstream side and the downstream side of a toe board, a traffic bridge is erected on the dam upstream abutment and the in-dam abutment, and the traffic bridge is communicated with a dam upstream construction road and an in-dam construction road. An excavation foundation is arranged on a toe board below a path of the traffic bridge, a toe board bridge abutment is arranged on the excavation foundation, the traffic bridge comprises an upstream bailey bridge and a downstream bailey bridge, and the upstream bailey bridge and the downstream bailey bridge are connected with an upstream bridge abutment and an in-dam bridge abutment of a dam respectively through the toe board bridge abutment. The toe board bridge abutment is arranged at the toe board and serves as a middle pier of the bailey bridge, the toe board traffic bridge is divided into two sections, the overall span of the bailey bridge is shortened, the structures and shapes of upstream and downstream piers are simplified, a proper space is kept between the pier at the downstream side dam body and the face plate, and the deformation coordination capacity of rockfill materials is utilized, so that the collapse of the toe board traffic bridge is achieved. The problem of panel stress is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of concrete face rockfill dam engineering, in particular to a toe plate pier structure. Background Art

[0002] In the construction of concrete face rockfill dams, it is common to build transportation roads upstream, especially for projects where the material yard is located in the upstream reservoir. In order to reduce the damage caused by transportation to the completed toe plate structure upstream, the following measures are often adopted:

[0003] Abutments are built upstream and downstream of the toe plate, and a Bailey bridge is erected to cross the toe plate. However, the defect of this plan is that the Bailey bridge needs to cross the entire toe plate, and due to the influence of the excavation upstream and downstream of the toe plate, the span of the Bailey bridge is large. In addition, due to the limitation of the single span of the Bailey bridge, the abutments located inside the dam body are relatively close to the toe plate, and the height of the abutments usually exceeds the dam surface, which needs to be removed later. It is not only time-consuming and labor-intensive, but also unable to effectively guarantee the construction quality. The toe plate is easily damaged during the removal process. Utility Model Content

[0004] The utility model aims to provide a toe board pier structure which can reduce the span of a Bailey bridge and avoid the removal of abutments in a dam at a later stage.

[0005] To this end, the utility model adopts the following technical solutions:

[0006] A toe plate pier structure, wherein an upstream abutment and an inner abutment of the dam are respectively arranged on the upstream and downstream sides of the toe plate, and a traffic bridge is constructed on the upstream abutment and the inner abutment of the dam, and the traffic bridge connects the upstream construction road of the dam and the inner construction road of the dam, and an excavation foundation is arranged on the toe plate below the path of the traffic bridge, and a toe plate abutment is arranged on the excavation foundation, and the traffic bridge comprises an upstream Bailey bridge and a downstream Bailey bridge, and the upstream Bailey bridge and the downstream Bailey bridge are respectively connected to the upstream abutment and the inner abutment of the dam through the toe plate abutment, so that the toe plate abutment forms the middle pier of the overall Bailey bridge construction; an approach road is adjacently arranged on the path of the inner construction road opposite to the toe plate abutment, and the inner abutment of the dam is arranged inside the approach road opposite to the toe plate abutment, so that an interval space is arranged between the inner abutment and the dam panel; a culvert is opened inside the toe plate abutment and runs in the same direction along the toe plate, and both ends of the culvert are connected to the toe plates on both sides.

[0007] Furthermore: the access road between the abutment in the dam and the construction road in the dam is a backfilled road section paved by backfilling, so that a fully connected collapsed toe plate path is formed by partially backfilling slag.

[0008] Furthermore: a guardrail is arranged on the top of the toe bridge abutment along the direction of the traffic bridge path, and the guardrail is arranged between the upstream Bailey bridge and the downstream Bailey bridge.

[0009] Furthermore: anchor bars, foundation consolidation grouting and curtain grouting are arranged at the bottom of the toe abutment.

[0010] Furthermore: a waterstop structure is arranged between the toe abutment and its surrounding structure, the waterstop structure comprises a first waterstop portion connecting the toe abutment and the toe board, and a second waterstop portion connecting the toe abutment and the panel, and the downstream end of the first waterstop portion is connected to the second waterstop portion.

[0011] Furthermore: the first water stop portion is respectively provided with a first plastic water stop and a first water stop copper sheet on the surface and inside of the connection area between the toe abutment and the toe board, an anchor pit is provided at the bottom of the connection area between the toe abutment and the toe board, and the upstream end of the first water stop copper sheet is anchored in the anchor pit.

[0012] Furthermore: the second water stop portion is provided with a second plastic water stop and a second water stop copper sheet on the surface and bottom of the connection area between the toe board abutment and the panel respectively.

[0013] Furthermore: the distance between the abutment inside the dam and the dam panel is not less than 4m, and the height of the abutment inside the dam is less than 1 / 2 of the distance.

[0014] Compared with the prior art, the utility model has the following beneficial effects:

[0015] The utility model arranges a toe board abutment at the toe board, and the toe board abutment serves as the middle pier of the Bailey bridge, so as to divide the collapsed toe board traffic bridge into two sections, shorten the overall span of the Bailey bridge, simplify the structure and size of the upstream and downstream piers, and maintain a proper space between the piers at the downstream dam body and the panel, and solves the panel stress problem by utilizing the deformation coordination ability of the rockfill material itself, thereby solving the problem of damage to the toe board caused by the removal of the downstream abutment of the collapsed toe board traffic bridge, reducing investment and simplifying construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the plane layout of the utility model;

[0017] Figure 2 It is a schematic cross-sectional view of the utility model along the center of the traffic bridge route;

[0018] Figure 3 It is a cross-sectional schematic diagram of the toe board abutment of the utility model along the toe board direction.

[0019] The markings in the attached figure are: 1-construction road upstream of the dam; 2-bridge abutment upstream of the dam; 3-toe abutment; 4-upstream Bailey bridge; 5-protective railings; 6-downstream Bailey bridge; 7-construction road inside the dam; 8-bridge abutment inside the dam; 9-backfill section; 10-toe board; 11-backfill concrete; 12-anchor reinforcement; 13-first waterstop copper sheet; 14-second waterstop copper sheet; 15-panel; 16-first plastic waterstop; 17-second plastic waterstop; 18-anchor pit; 19-culvert. DETAILED DESCRIPTION

[0020] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.

[0021] like Figure 1-3 As shown, a toe bridge pier structure, the toe bridge traffic structure includes an upstream construction road 1 and an inner dam construction road 7, an upstream dam abutment 2 and an inner dam abutment 8 are respectively arranged at the end positions of the area between the roads on both sides, and a traffic bridge is erected on the upstream dam abutment 2 and the inner dam abutment 8, so as to connect the upstream dam construction road 1 and the inner dam construction road 7 through the traffic bridge; the traffic bridge is provided with an excavation foundation on the toe board 10 below its path, the excavation foundation is partially deep excavated according to the traffic load requirements, and the excavation foundation depth is greater than the excavation depth of the toe board 10 foundation, and a toe board abutment 3 is arranged on the excavation foundation, and the lower part of the toe board abutment 3 is the toe board part The upper part is the abutment part, which is an integral reinforced concrete structure; the traffic bridge includes an upstream Bailey bridge 4 and a downstream Bailey bridge 6, which are respectively connected to the upstream abutment 2 and the inner abutment 8 of the dam through the toe abutment 3, so that the toe abutment 3 forms the middle pier of the integral Bailey bridge. The span of the downstream Bailey bridge 6 can be shortened by the toe abutment 3, and the structure and size of the upstream and downstream piers are simplified; an access road is set adjacent to the path of the inner dam construction road 7 on the side of the toe abutment 3, and the inner dam abutment 8 is set on the side of the access road opposite to the toe abutment 3, so that a spacing space is provided between the inner dam abutment 8 and the dam panel 15.

[0022] Among them, a culvert 19 is opened inside the abutment part of the toe abutment 3 and runs in the same direction as the toe board 10. Both ends of the culvert 19 are connected with the toe boards 10 on both sides, serving as a passage for permanent operation and maintenance and water-stopping construction.

[0023] Specifically, the access road between the abutment 8 and the construction road 7 in the dam is a backfill section 9 backfilled with slag, so that a fully connected collapsed toe plate path is formed by partially backfilling slag.

[0024] Specifically, a guardrail 5 is arranged on the top of the toe bridge pier 3 along the direction of the traffic bridge path, and the guardrail 5 is arranged between the upstream Bailey bridge 4 and the downstream Bailey bridge 6 .

[0025] In this embodiment, anchor bars 12 and foundation consolidation grouting and curtain grouting (not shown in the figure) are arranged at the bottom of the toe abutment 3. Correspondingly, the toe abutment 3 performs supplementary grouting on the shallow layer after the transportation function is completed; if the grouting work is arranged to be carried out after the transportation function is completed, no supplementary grouting is required.

[0026] Meanwhile, the toe plate 10 connected to the toe plate abutment 3 is designed according to the design requirements of the conventional panel rockfill dam structure, and is also provided with anchor reinforcement and foundation consolidation grouting and curtain grouting.

[0027] In this embodiment, a waterstop structure is provided between the toe abutment 3 and its surrounding structure, and the waterstop structure includes a first waterstop portion connecting the toe abutment 3 and the toe board 10 , and a second waterstop portion connecting the toe abutment 3 and the panel 15 .

[0028] Specifically, the first water stop portion is provided with a first plastic water stop 16 and a first water stop copper sheet 13 on the surface and inside of the connection area between the toe abutment 3 and the toe board 10, respectively. Therefore, the first water stop copper sheet 13 is arranged on both sides of the toe abutment 3 along the direction of the toe board 10, and an anchor pit 18 is provided at the bottom of the connection area between the toe abutment 3 and the toe board 10. The upstream end of the first water stop copper sheet 13 is anchored in the anchor pit 18. Among them, the anchor pit 18 of the copper sheet water stop 13 is made of micro-expansion concrete or backfilled with pre-shrinkage mortar.

[0029] Specifically, the connection between the downstream side of the toe abutment 3 and the dam panel 15 is designed as a peripheral seam, so the second water stop portion is provided with a second plastic water stop 17 and a second water stop copper sheet 14 on the surface and bottom of the connection area between the toe abutment 3 and the panel 15, respectively.

[0030] The downstream end of the first plastic water stop 16 is connected to the second plastic water stop 17 , and the downstream end of the first water stop copper sheet 13 is connected to the second water stop copper sheet 14 , so as to ensure the safety and durability of the overall structure.

[0031] Furthermore, the first water-stop copper sheet 13 and the second water-stop copper sheet 14 are embedded in the concrete when the toe bridge abutment 3 is poured, and the first plastic water-stop 16 and the second plastic water-stop 17 are constructed after the dam is filled and the panel 15 is poured.

[0032] In this embodiment, the distance between the abutment 8 in the dam and the dam panel 15 is not less than 5m, and the height of the abutment 8 in the dam is less than 1 / 2 of the distance, that is, the abutment 8 in the dam does not encroach on the cushion material and transition material of the concrete panel rockfill dam, and the impact range does not affect the force safety of the panel 15. Therefore, the span of the downstream Bailey bridge 6 erected in the dam body on the downstream side of the toe abutment 3 needs to be as large as possible to ensure that there is a sufficient distance between the abutment 8 in the dam and the panel 15 after pouring.

[0033] See also Figure 1-3When constructing the toe-slab traffic structure, the specific steps are as follows:

[0034] S1: Excavation of the foundation of the toe abutment 3: According to the construction road plan, the position of the toe abutment 3 is determined, and the part outside the toe abutment 3 is excavated according to the excavation requirements of the toe 10 foundation. The excavation depth of the toe abutment 3 is appropriately deepened according to the traffic load to form the seating foundation of the toe abutment 3;

[0035] S2: According to the structural requirements, anchor bars 12 are arranged, and the toe abutment 3 is cast with them. The space between the toe abutment 3 and the deep excavated foundation pit is backfilled with backfill concrete 11 to be flush with the designed excavation line of the toe 10. While casting the toe abutment 3, a first water-stop copper sheet 13 is buried on both sides of the toe abutment 3 and a second water-stop copper sheet 14 is buried on the downstream side of the toe abutment 3;

[0036] S3: Install the guardrail 5 on the upper part of the toe bridge abutment 3;

[0037] S4: Build the construction road 1 upstream of the dam, the construction road 7 inside the dam, the bridge abutment 2 upstream of the dam, and the bridge abutment 8 inside the dam, so as to erect the upstream Bailey bridge 4 and the downstream Bailey bridge 6, and make the whole traffic bridge connected through the top section of the toe bridge abutment 3 for traffic;

[0038] S5: After the passage requirement is completed, the upstream Bailey Bridge 4 and the downstream Bailey Bridge 6 will be dismantled;

[0039] S6: The dam body filling and the pouring of the panel 15 are completed, and the first plastic water stop 16 and the second plastic water stop 17 are arranged on the surface of the toe abutment 3, the toe plate 10 and the panel 15 to ensure the water stopping effect.

[0040] The above embodiment is only a preferred technical solution of the present invention. Those skilled in the art should understand that the technical solutions or parameters in the embodiments can be modified or replaced without departing from the principle and essence of the present invention, and all should be included in the protection scope of the present invention.

Claims

1. A toe bridge pier structure, wherein an upstream abutment (2) and an inner abutment (8) of a dam are respectively arranged on the upstream and downstream sides of a toe bridge (10), a traffic bridge is erected on the upstream abutment (2) and the inner abutment (8), and the traffic bridge connects an upstream construction road (1) of the dam and an inner construction road (7), characterized in that: The traffic bridge is provided with an excavated foundation on the toe plate (10) below the path thereof, and a toe plate abutment (3) is provided on the excavated foundation. The traffic bridge comprises an upstream Bailey bridge (4) and a downstream Bailey bridge (6), and the upstream Bailey bridge (4) and the downstream Bailey bridge (6) are respectively connected to the upstream abutment (2) and the abutment (8) inside the dam through the toe plate abutment (3); an approach road is provided adjacent to the path of the construction road (7) inside the dam on the side opposite to the toe plate abutment (3), and the abutment (8) inside the dam is provided on the side opposite to the toe plate abutment (3) of the approach road; A culvert (19) is provided inside the toe board abutment (3) and is opened along the toe board (10) and runs in the same direction. Both ends of the culvert (19) are connected to the toe boards (10) on both sides.

2. The toe bridge pier structure according to claim 1, characterized in that: The access road between the abutment (8) and the construction road (7) in the dam is a backfilled road section (9) paved by backfilling, so that a fully connected collapsed toe plate path is formed by partially backfilling slag.

3. The toe bridge pier structure according to claim 1, characterized in that: A guardrail (5) is arranged on the top of the toe bridge abutment (3) along the direction of the traffic bridge path, and the guardrail (5) is arranged between the upstream Bailey bridge (4) and the downstream Bailey bridge (6).

4. The toe bridge pier structure according to claim 1, characterized in that: Anchor bars (12) and foundation consolidation grouting and curtain grouting are arranged at the bottom of the toe bridge abutment (3).

5. The toe bridge pier structure according to claim 1, characterized in that: A water-stop structure is arranged between the toe abutment (3) and its surrounding structure, and the water-stop structure comprises a first water-stop portion connecting the toe abutment (3) and the toe board (10), and a second water-stop portion connecting the toe abutment (3) and the panel (15), wherein the downstream end of the first water-stop portion is connected to the second water-stop portion.

6. The toe bridge pier structure according to claim 5, characterized in that: The first water stop portion is provided with a first plastic water stop (16) and a first water stop copper sheet (13) on the surface and inside of the connection area between the toe board abutment (3) and the toe board (10), respectively; an anchor pit (18) is provided at the bottom of the connection area between the toe board abutment (3) and the toe board (10); and the upstream end of the first water stop copper sheet (13) is anchored in the anchor pit (18).

7. The toe bridge pier structure according to claim 5, characterized in that: The second water stop portion is provided with a second plastic water stop (17) and a second water stop copper sheet (14) on the surface and bottom of the connection area between the toe bridge abutment (3) and the panel (15), respectively.

8. The toe bridge pier structure according to claim 1, characterized in that: The distance between the abutment (8) and the panel (15) in the dam is not less than 4 m, and the height of the abutment (8) in the dam is less than 1 / 2 of the distance.

Citation Information

Cited By

  • Toe-crossing board traffic structure and construction method thereof

    CN118110083A