Underground waterproof system

By adopting a hierarchical waterproof structure in the underground waterproof system, combining the outsourcing waterproof material layer and the pre-layed waterproof roll layer, it is difficult to use the pre-layed HDPE polymer self-adhesive film waterproof roll material alone in the prior art. Meet the requirements of the new version of the specifications and achieve better waterproofing and durability.

CN222065576UActive Publication Date: 2024-11-26江苏雨中情防水材料有限责任公司
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323557597.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-26
Publication Date
2024-11-26
Estimated Expiration
2033-12-26

AI Technical Summary

Technical Problem

The existing pre-paved HDPE polymer self-adhesive film waterproof coil is difficult to meet the requirements of first-level fortification in the new version of the general specification for waterproofing of buildings and municipal governments 55030-2022. There are hidden dangers of overlapping seams and puncture damage of post-pouring concrete. This leads to the question of the waterproof effect.

Method used

The underground waterproof system is arranged in a hierarchical manner, including a plain soil layer, a concrete cushion layer, an isolation protective layer, an outsourcing waterproof material layer and a post-pouring waterproof concrete layer. The outsourcing waterproof material layer and a prepaved waterproof coil layer form an integral waterproof System, isolation layer provides additional waterproofing and protection functions to avoid damage to the waterproof layer caused by base layer settlement.

Benefits of technology

It improves the waterproof effect and durability of the underground waterproofing project, meets the waterproof design needs of the new version specifications, enhances the stability and durability of the waterproof system, avoids long-term soaking of waterproof coatings, and improves the overall waterproof performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222065576U_ABST
    Figure CN222065576U_ABST
Patent Text Reader

Abstract

The utility model provides an underground waterproof system, which relates to the field of waterproof material construction engineering, and comprises an underground bottom plate layer waterproof system, the underground bottom plate layer waterproof system comprises a plain soil layer, a concrete cushion layer, a first isolation protection layer, an outer wrapping type waterproof material layer, a pre-paving type waterproof roll layer and a post-pouring waterproof concrete layer which are arranged layer by layer; the lateral foundation pit waterproof system is divided into a vertical foundation pit and a sloping foundation pit, and the lateral foundation pit waterproof system comprises a plain soil layer, a concrete cushion layer, a second isolation protection layer, an outer wrapping type waterproof material layer, a pre-paving type waterproof roll layer and a post-pouring waterproof concrete layer which are arranged layer by layer; the foundation pit upper plane waterproof system comprises a plain soil layer, a concrete cushion layer, a first isolation protection layer, an outer wrapping type waterproof material layer, a pre-paving type waterproof coiled material layer and a post-pouring waterproof concrete layer which are arranged layer by layer. According to the scheme, the waterproof effect of the underground waterproof engineering design is further improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of waterproof material construction engineering, in particular to an underground waterproof system. Background Art

[0002] In waterproofing projects, the products currently used in underground waterproofing projects are mainly pre-laid polymer self-adhesive membrane waterproofing membranes. The pre-laid waterproofing membrane uses HDPE polymer sheets as the main material, and is coated with hot-melt pressure-sensitive adhesive on the upper surface, and then mullite is attached to the upper surface of the hot-melt pressure-sensitive adhesive to prepare it. The pre-laid construction process is adopted during construction. After the bottom plate or side foundation is compacted, a concrete cushion layer is laid on it. After the cushion layer is cured, the pre-laid reverse-adhesive construction HDPE polymer self-adhesive membrane waterproofing membrane is used on it. The lower surface of the membrane is paved with an empty paving method. After the construction is completed, the post-poured waterproof concrete is poured on it. This construction process adopts a pre-laid covering construction mode, which is cast as a whole with the upper concrete structure, which can more effectively avoid the penetration of external water vapor and ensure the waterproof effect of the main body of the building. More importantly, due to Because the waterproof membrane and the main body of the building are cast into a whole through post-poured concrete, there is no structural connection with the underlying base layer. As a result, when the base layer sinks in the future, the waterproof layer will not sink together with the lower base layer or deform due to the settlement of the base layer, causing damage to the waterproof system, thereby affecting the waterproof effect of the waterproof layer. Therefore, in the early construction practice of HDPE polymer self-adhesive waterproof membrane, the pre-laid polymer self-adhesive film waterproof membrane used for underground projects is used as the main recommended design scheme. One layer of HDPE polymer self-adhesive film waterproof membrane can meet the requirements of primary defense in underground waterproofing practice. Compared with other waterproof membranes and waterproof coatings that must be combined with two waterproof systems to meet the requirements of primary defense, it has better waterproof effect and application economy, and is widely recommended for application.

[0003] However, in the process of promoting and applying the corresponding waterproof design scheme in China, the above-mentioned method of using a single layer of pre-laid HDPE polymer self-adhesive membrane waterproofing membrane as the first-level defense has gradually shown certain problems. Due to the differences in quality control of various manufacturers and the differences in construction application effects during the construction process of construction units, simply using a pre-laid polymer waterproofing system may not necessarily guarantee a good waterproofing effect. In addition, the hidden dangers of lap joints in a waterproofing system itself and the puncture damage of pre-laid membranes by post-poured concrete construction are also relatively common. The defense effect of a single layer of polymer pre-laid waterproofing membrane is also increasingly questioned by waterproofing design and construction units.

[0004] On April 1, 2023, the Ministry of Housing and Urban-Rural Development's "General Specification for Building and Municipal Waterproofing-55030-2022" will be officially implemented. The standard puts forward new requirements for the waterproofing of open-cut underground projects. For open-cut underground projects with a level one defense level, the number of waterproofing layers shall not be less than 3 layers, of which post-poured waterproof concrete is one layer and is mandatory, and the remaining two waterproof layers are composed of waterproof membranes, waterproof coatings, and cement-based waterproof coatings, of which one waterproof membrane or waterproof coating must be included; the implementation of this general specification puts forward new requirements for the waterproofing design of underground projects. According to the construction process of the aforementioned pre-laid polymer self-adhesive membrane waterproof membrane, there will be one less waterproof layer, which does not meet the design requirements of the new level one waterproofing standard of the general specification. Based on past design experience, a waterproofing system that can meet the requirements of the new level one waterproofing standard of the general specification is designed to further increase the waterproofing effect of the underground waterproofing project design, which will have good application value. Utility Model Content

[0005] The utility model provides an underground waterproof system, which further increases the waterproof effect of underground waterproof engineering design.

[0006] In order to solve the above technical problems, the technical solution of the utility model is as follows:

[0007] The embodiment of the utility model provides an underground waterproof system, comprising:

[0008] An underground floor waterproofing system, wherein the underground floor waterproofing system comprises a hierarchically arranged plain soil layer, a concrete cushion layer, a first isolation protection layer, an externally wrapped waterproofing material layer, a pre-laid waterproofing membrane layer, and a post-cast waterproofing concrete layer;

[0009] A lateral foundation pit waterproofing system, wherein the lateral foundation pit is divided into a vertical foundation pit and a slope foundation pit, and the lateral foundation pit waterproofing system comprises a hierarchically arranged plain soil layer, a concrete cushion layer, a second isolation protection layer, an externally wrapped waterproof material layer, a pre-laid waterproof membrane layer, and a post-cast waterproof concrete layer;

[0010] The surface waterproofing system on the foundation pit comprises a hierarchically arranged plain soil layer, a concrete cushion layer, a first isolation protection layer, an externally wrapped waterproof material layer, a pre-laid waterproof membrane layer and a post-poured waterproof concrete layer.

[0011] Furthermore, the first isolation protection layer includes a fine sand isolation layer, a fine sand plus isolation cloth isolation layer, and an isolation cloth isolation layer;

[0012] The fine sand isolation layer is formed by laying and compacting fine sand of two different particle sizes in batches. The particle size of the coarse sand is 0.2-0.4 mm, and the particle size of the fine sand is 0.1-0.2 mm. When in use, the coarse sand is laid first with a thickness of 1.0-3 cm, and then the fine sand is laid on top with a thickness of 0.2-0.5 cm and compacted.

[0013] The isolation layer of the isolation cloth is non-woven fabric or polypropylene fabric with a thickness of 1.0-1.5 mm;

[0014] The fine sand plus isolation cloth isolation layer is prepared by laying non-woven fabric or polypropylene fabric on the top of the fine sand isolation layer, and the thickness of the non-woven fabric or polypropylene fabric is 1.0-1.5 mm.

[0015] Furthermore, the second isolation protective layer is a non-woven fabric or polypropylene fabric isolation layer with a thickness of 1.0-1.5 mm, which is laid on the concrete cushion layer in sequence, with the upper end turned outward to the upper part of the fine sand structure in the first isolation protective layer of the upper plane waterproofing system of the foundation pit and extending 30-50 cm. The back of the overlapping area is fixed with double-sided self-adhesive tape and bonded to the base layer through the double-sided self-adhesive tape.

[0016] Further, when the outer package waterproof material layer is applied to the underground floor layer or the flat waterproof system on the foundation pit, it is composed of one or two of a 1.5-2.0 mm thick polyurethane waterproof coating layer, a 2.0-3.0 mm non-curing rubber asphalt waterproof coating layer, a 1.5-2.0 mm thick polymer cement waterproof coating layer, a 1.5-2.0 mm thick polymer emulsion waterproof coating layer, a 3-mm thick type II SBS modified asphalt waterproofing membrane layer, a 1.5-3.0 mm thick type II self-adhesive waterproofing membrane layer, and a 1.2-1.5 mm thick polymer waterproofing membrane, and the composite form is as follows:

[0017] a: The first isolation protection layer adopts fine sand structure, the upper layer is paved with 3mm thick type II SBS modified asphalt waterproof membrane, and the upper layer is set with 2.0mm thick non-curing rubber asphalt waterproof coating layer.

[0018] b: The first isolation protection layer adopts fine sand plus isolation cloth structure, and the upper layer is constructed with 1.5mm thick single-sided self-adhesive NIIPET self-adhesive waterproof membrane.

[0019] c: The first isolation protection layer adopts a fine sand structure, the upper layer is laid with a 1.5mm thick PVC polymer waterproof board, and the upper layer is set with a 1.5mm thick polyurethane waterproof coating layer.

[0020] d: The first isolation protection layer adopts an isolation cloth isolation layer, the upper layer is laid with a 4.0mm thick SBS modified asphalt waterproof membrane, and the upper layer is set with a 2.0mm thick polymer emulsion waterproof coating.

[0021] Furthermore, when the external waterproof material layer is applied to the foundation pit waterproofing system, its laying form is as follows:

[0022] a: When the outermost side of the outer-wrapped waterproof material layer is a non-self-adhesive coiled material or a non-self-adhesive side surface of a self-adhesive coiled material, it is laid on the inner side of the second isolation protective layer;

[0023] b: When the outermost side of the outer-wrapped waterproof material layer is the self-adhesive surface of the self-adhesive waterproof membrane, it is bonded to the inner side of the second isolation protective layer;

[0024] C: When the outer waterproof material layer is a single layer of waterproof coating, it is applied on the second isolation protective layer.

[0025] Further, the pre-laid waterproofing membrane layer 6 includes a HDPE polymer self-adhesive film waterproofing membrane layer and an asphalt-based pre-laid waterproofing membrane layer 62;

[0026] The thickness of the main material of the HDPE polymer self-adhesive film waterproofing coiled material layer is not less than 1.2 mm;

[0027] The main material thickness of the asphalt-based pre-laid waterproofing membrane layer 62 is 4.0 mm.

[0028] Furthermore, the HDPE polymer self-adhesive film waterproof coiled material layer comprises a HDPE sheet layer, a pressure-sensitive adhesive layer, and a sintered sand layer;

[0029] The asphalt-based pre-paved waterproofing membrane layer 62 includes a base layer, a self-adhesive rubber layer, a PE film layer and a sand surface layer.

[0030] Furthermore, the raw soil layer is prepared by compacting the raw soil of the base layer, and the compaction coefficient is ≥0.96.

[0031] Furthermore, the concrete cushion layer is C10 or above grade concrete, with a thickness ranging from 100 to 150 mm.

[0032] Furthermore, the strength of the post-cast waterproof concrete layer is not less than C25, its minimum water resistance grade is not less than P8, and its thickness is more than 150 mm.

[0033] The above solution of the utility model includes at least the following beneficial effects:

[0034] The underground waterproof system described in the utility model aims at the situation that the existing construction technology does not meet the actual use conditions of existing engineering waterproofing and the latest requirements of "General Specification for Waterproofing of Buildings and Municipal Engineering 55030-2022" for building waterproofing. Aiming at the shortcomings of the existing construction technology, a waterproof system is proposed in which a layer of outer-packaged waterproof material layer is arranged on the outside of the pre-laid waterproof membrane during the construction of underground projects. The outer-packaged waterproof material can be fully bonded with the internal pre-laid waterproof system to form a uniform and integrated waterproof system, or the pre-laid waterproof membrane can be arranged on the inner side of the outer-packaged waterproof coating in the form of empty paving, and the inner pre-laid waterproof membrane is combined with the main body of the building by post-pouring waterproof concrete. The application advantage of pre-laid wrapped waterproofing is that the waterproof material on the outside is initially set on the isolation layer and is not fixed to the base layer below. The outer package waterproof material layer is used as an independent waterproof system or is combined with the internal pre-laid waterproof membrane layer, and is bonded together with the upper waterproof membrane to form an integral waterproof layer, or the upper membrane is laid in an empty position as a separate waterproof layer. The waterproof layer will not be torn and damaged by the settlement of the base layer. At the same time, the lower isolation layer has a certain gap, which can allow part of the water gathered on the lower side of the isolation layer to seep in, avoiding the long-term immersion of the waterproof coating in the underground water seepage area, so that the outer package material layer has better durability and waterproof effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a schematic diagram of an open-cut vertical foundation pit underground waterproofing system of the utility model;

[0036] Figure 2 It is a schematic diagram of an underground waterproof system of an open-cut sloped foundation pit of the utility model;

[0037] Figure 3 It is a schematic diagram of the structure of the HDPE polymer self-adhesive film waterproofing coiled material layer of the underground waterproofing system of the utility model.

[0038] Figure 4 This is a schematic diagram of the structure of the asphalt-based pre-paved waterproofing membrane layer 62 of the underground waterproofing system of the utility model.

[0039] Figure 5 The utility model is a schematic diagram of the short-side overlap structure of the overlapping side of the waterproofing membrane constructed by the pre-laying method of the underground waterproofing system.

[0040] Description of reference numerals:

[0041] 1. Bare soil layer; 2. Concrete cushion layer; 3. First isolation protection layer; 4. Second isolation protection layer; 5. Outsourced waterproof material layer; 6. Pre-laid waterproof membrane layer; 7. Post-cast waterproof concrete layer; 61. HDPE polymer self-adhesive film waterproof membrane layer; 62. Asphalt-based pre-laid waterproof membrane layer 62; 611. HDPE sheet layer; 612. Pressure-sensitive adhesive layer; 613. Sintered sand layer; 621. Tire base layer; 622. Self-adhesive layer; 623. PE film layer; 624. Sand surface layer. DETAILED DESCRIPTION

[0042] The exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.

[0043] like Figure 1 As shown, an embodiment of the utility model provides an underground waterproof system, comprising:

[0044] An underground floor waterproofing system, wherein the underground floor waterproofing system comprises a hierarchically arranged plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally wrapped waterproof material layer 5, a pre-laid waterproofing membrane layer 6 and a post-cast waterproofing concrete layer 7;

[0045] A lateral foundation pit waterproofing system, wherein the lateral foundation pit is divided into a vertical foundation pit and a slope foundation pit, and the lateral foundation pit waterproofing system comprises a hierarchically arranged plain soil layer 1, a concrete cushion layer 2, a second isolation protection layer 4, an externally wrapped waterproof material layer 5, a pre-laid waterproof roll material layer 6 and a post-cast waterproof concrete layer 7;

[0046] The flat waterproofing system on the foundation pit includes a hierarchically arranged plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproofing material layer 5, a pre-laid waterproofing membrane layer 6 and a post-cast waterproofing concrete layer 7.

[0047] In the embodiment of the utility model, the plain soil layer 1 of the underground floor waterproofing system provides basic support and drainage functions; the concrete cushion layer 2 levels the surface of the underground floor to increase strength and stability; the first isolation protection layer 3 blocks groundwater infiltration and protects the concrete cushion layer; the outer package waterproof material layer 5 provides the main waterproof layer to prevent groundwater infiltration; the pre-laid waterproof membrane layer 6 enhances the waterproof performance and provides higher durability and reliability; the post-cast waterproof concrete layer 7 increases the thickness and strength of the waterproof layer to further protect the system from groundwater erosion; the plain soil layer 1 of the side foundation pit waterproofing system provides support and drainage functions for the foundation pit; the concrete cushion layer 2 levels the surface of the side wall of the foundation pit to enhance The second isolation protection layer 4 blocks groundwater penetration and protects the concrete cushion layer; the external waterproof material layer 5 provides the main waterproof layer to prevent groundwater penetration; the pre-laid waterproof membrane layer 6 enhances the waterproof performance and provides higher durability and reliability; the post-cast waterproof concrete layer 7 increases the thickness and strength of the waterproof layer to further protect the foundation pit from groundwater erosion; the plain soil layer 1 of the upper plane waterproof system of the foundation pit provides support and drainage functions for the foundation pit plane; the concrete cushion layer 2 levels the surface of the foundation pit plane to increase strength and stability; the first isolation protection layer 3 blocks groundwater penetration and protects the concrete cushion layer; the external waterproof material layer 5 provides the main waterproof layer, Prevent groundwater infiltration; the pre-laid waterproof membrane layer 6 enhances the waterproof performance and provides higher durability and reliability; the post-cast waterproof concrete layer 7 increases the thickness and strength of the waterproof layer, further protecting the foundation pit plane from groundwater erosion; a layer of externally wrapped waterproof material is arranged on the outside of the pre-laid waterproof membrane 6, and the externally wrapped waterproof material can be fully bonded with the internal pre-laid waterproof system to form a uniform and integrated waterproof system, or the pre-laid waterproof membrane can be arranged on the inside of the externally wrapped waterproof coating in the form of empty paving, and the inner pre-laid waterproof membrane is combined with the main body of the building through the post-cast waterproof concrete layer 7, which has the application advantages of pre-laid encapsulated waterproofing The waterproof material on the outside is initially set on the isolation layer and is not fixed to the base layer below. The external waterproof material layer is used as an independent waterproof system or is combined with the internal pre-laid waterproof membrane layer, and is bonded together with the upper waterproof membrane to form an integral waterproof layer, or the upper membrane is laid empty as a separate waterproof layer. The waterproof layer will not be torn and damaged as the base layer settles. At the same time, the lower isolation layer has a certain gap, which allows part of the water gathered on the lower side of the isolation layer to seep in, avoiding the long-term immersion of the waterproof coating in the underground water seepage area, so that the external material layer has better durability and waterproof effect.

[0048] like Figures 1 to 5 As shown, the first isolation protection layer 3 includes a fine sand isolation layer, a fine sand plus isolation cloth isolation layer and an isolation cloth isolation layer;

[0049] The fine sand isolation layer is formed by laying and compacting fine sand of two different particle sizes in batches. The particle size of the coarse sand is 0.2-0.4 mm, and the particle size of the fine sand is 0.1-0.2 mm. When in use, the coarse sand is laid first with a thickness of 1.0-3 cm, and then the fine sand is laid on top with a thickness of 0.2-0.5 cm and compacted.

[0050] The isolation layer of the isolation cloth is non-woven fabric or polypropylene fabric with a thickness of 1.0-1.5 mm;

[0051] The fine sand plus isolation cloth isolation layer is prepared by laying non-woven fabric or polypropylene fabric on the top of the fine sand isolation layer, and the thickness of the non-woven fabric or polypropylene fabric is 1.0-1.5 mm.

[0052] In the embodiment of the utility model, the fine sand isolation layer of the first isolation protection layer 3 is formed by laying and compacting fine sand of two different particle sizes in batches. The different particle sizes of coarse sand and fine sand can form a relatively tight drainage structure. The fine sand isolation layer can effectively drain groundwater and prevent moisture from penetrating into the waterproof layer below. The fine sand isolation layer can fill the uneven surface of the underground floor or foundation pit to ensure the flatness and tightness of the waterproof layer. The fine sand isolation layer can disperse the load and reduce the pressure and deformation on the waterproof layer; the isolation cloth isolation layer adopts non-woven fabric or polypropylene fabric. The isolation cloth can effectively isolate the rough material on the surface of the underground floor or foundation pit and the waterproof layer to prevent direct contact, thereby protecting the integrity and performance of the waterproof layer; the isolation cloth is used as a waterproof system. The first isolation protective layer 3 comprises a first isolation layer, a second isolation layer, and a second isolation layer. ... layer

[0053] like Figures 1 to 5 As shown, the second isolation protective layer 4 is a non-woven fabric or polypropylene fabric isolation layer with a thickness of 1.0-1.5 mm. It is laid on the concrete cushion layer 2 in sequence, and the upper end is turned outward to the upper part of the fine sand structure in the first isolation protective layer 3 of the upper plane waterproofing system of the foundation pit and extends 30-50 cm. The back of the overlapping area is fixed with double-sided self-adhesive tape and bonded to the base layer through the double-sided self-adhesive tape.

[0054] In an embodiment of the utility model, the second isolation protective layer 4 adopts non-woven fabric or polypropylene fabric as the isolation layer. The second isolation protective layer 4 can effectively isolate the concrete cushion layer and the upper waterproof layer to prevent direct contact between the concrete cushion layer and the upper waterproof layer, and can prevent the alkaline substances, moisture or other chemicals in the concrete cushion layer from corroding the waterproof layer, thereby protecting the integrity and performance of the waterproof layer; the upper end of the second isolation protective layer 4 is turned outward to the upper part of the fine sand structure in the first isolation protective layer of the upper plane waterproof system of the foundation pit and extends 30-50cm, forming an overlapping and connected structure, which strengthens the connection between the concrete cushion layer and the upper waterproof layer, and ensures the tightness and integrity between the two; the back of the overlap area is fixed with double-sided self-adhesive tape, and is bonded to the base layer with the double-sided self-adhesive tape. This fixing and bonding method can effectively fix the second isolation protective layer and provide additional sealing to prevent moisture penetration. At the same time, the double-sided self-adhesive tape can also increase the overall stability and durability of the waterproof system.

[0055] like Figures 1 to 5 As shown, when the outer package waterproof material layer 5 is applied to the underground floor layer or the flat waterproof system on the foundation pit, it is composed of one or two of a 1.5-2.0 mm thick polyurethane waterproof coating layer, a 2.0-3.0 mm non-curing rubber asphalt waterproof coating layer, a 1.5-2.0 mm thick polymer cement waterproof coating layer, a 1.5-2.0 mm thick polymer emulsion waterproof coating layer, a 3-mm thick type II SBS modified asphalt waterproofing membrane layer, a 1.5-3.0 mm thick type II self-adhesive waterproofing membrane layer, and a 1.2-1.5 mm thick polymer waterproofing membrane, and the composite form is as follows:

[0056] a: The first isolation protection layer 3 adopts fine sand structure, with 3mm thick type II SBS modified asphalt waterproofing membrane laid on the upper layer, and 2.0mm thick non-curing rubber asphalt waterproof coating layer set on the upper layer.

[0057] b: The first isolation protection layer 3 is made of fine sand and isolation cloth structure, and the upper layer is constructed with 1.5mm thick single-sided self-adhesive NIIPET self-adhesive waterproof membrane.

[0058] c: The first isolation protection layer 3 adopts a fine sand structure, with a 1.5 mm thick PVC polymer waterproof board laid on the upper layer, and a 1.5 mm thick polyurethane waterproof coating layer set on the upper layer.

[0059] d: The first isolation protection layer 3 adopts an isolation cloth isolation layer, a 4.0 mm thick SBS modified asphalt waterproofing membrane is laid on the upper layer, and a 2.0 mm thick polymer emulsion waterproofing coating is set on the upper layer.

[0060] In the embodiment of the utility model, the outer package waterproof material layer 5 in the underground floor layer or the foundation pit upper plane waterproof system includes a polyurethane waterproof coating layer, a non-curing rubber asphalt waterproof coating layer, a polymer cement waterproof coating layer, a polymer emulsion waterproof coating layer, an SBS modified asphalt waterproof roll layer, a self-adhesive waterproof roll layer and a polymer waterproof roll layer, etc., which can be in different composite forms;

[0061] a. The first isolation protection layer 3 adopts a fine sand structure, with a 3mm thick Type II SBS modified asphalt waterproofing membrane on the upper layer, and a 2.0mm thick non-curing rubber asphalt waterproofing coating layer on the upper layer: the first isolation protection layer 3 with a fine sand structure can isolate the underground floor and the upper waterproofing layer to prevent direct contact between the underground floor and the upper waterproofing layer; the Type II SBS modified asphalt waterproofing membrane and the non-curing rubber asphalt waterproofing coating layer provide the main waterproof layer to prevent groundwater penetration;

[0062] b. The first isolation protection layer 3 is made of fine sand and isolation cloth structure, and the upper layer is constructed with 1.5mm thick single-sided self-adhesive NIIPET self-adhesive waterproof membrane: the first isolation protection layer 3 of fine sand and isolation cloth structure can isolate the underground floor and the upper waterproof layer; the single-sided self-adhesive NIIPET self-adhesive waterproof membrane provides the main waterproof layer to prevent groundwater penetration;

[0063] c. The first isolation protection layer 3 adopts a fine sand structure, with a 1.5mm thick PVC polymer waterproof board laid on the upper layer, and a 1.5mm thick polyurethane waterproof coating layer set on the upper layer: the first isolation protection layer of the fine sand structure can isolate the underground floor and the upper waterproof layer; the PVC polymer waterproof board and the polyurethane waterproof coating layer provide the main waterproof layer to prevent groundwater penetration;

[0064] d. The first isolation protection layer 3 adopts an isolation cloth isolation layer, a 4.0 mm thick SBS modified asphalt waterproof membrane is laid on the upper layer, and a 2.0 mm thick polymer emulsion waterproof coating is set on the upper layer: the isolation cloth isolation layer can isolate the underground floor and the upper waterproof layer; the SBS modified asphalt waterproof membrane and the polymer emulsion waterproof coating provide the main waterproof layer to prevent groundwater penetration.

[0065] The outer-wrapped waterproof material layer 5 adopts different composite forms, which can provide isolation, waterproofing and protection functions, effectively prevent groundwater penetration and protect the integrity of the underground structure.

[0066] like Figures 1 to 5 As shown, the pre-laid waterproofing membrane layer 66 includes a HDPE polymer self-adhesive film waterproofing membrane layer 61 and an asphalt-based pre-laid waterproofing membrane layer 6262;

[0067] The main material thickness of the HDPE polymer self-adhesive film waterproof coiled material layer 61 is not less than 1.2 mm;

[0068] The main material thickness of the asphalt-based pre-laid waterproof membrane layer 6262 is 4.0 mm.

[0069] In the embodiment of the utility model, the pre-laid waterproofing membrane layer 66 includes a HDPE polymer self-adhesive film waterproofing membrane layer 61 and an asphalt-based pre-laid waterproofing membrane layer 6262; the HDPE polymer self-adhesive film of the HDPE polymer self-adhesive film waterproofing membrane 61 has excellent waterproof performance, which can effectively prevent water penetration and protect underground structures and equipment from water erosion; the membrane layer is self-adhesive and can be easily pasted on the underground floor or foundation pit surface to improve construction efficiency; the HDPE polymer material has good chemical resistance, aging resistance and temperature resistance, and can maintain the stability and reliability of the waterproof layer under different environmental conditions; the asphalt-based pre-laid waterproofing membrane layer 6262 is made of asphalt-based material , has excellent waterproof performance and can effectively prevent water penetration; asphalt-based materials can provide strength and stability, increase the durability and reliability of the pre-laid waterproof membrane layer 6; asphalt-based materials can provide physical protection for underground structures and equipment to prevent damage to them by external factors; the asphalt-based pre-laid waterproof membrane layer 62 can be pre-fabricated in the factory, which is convenient for on-site construction and improves construction efficiency; the HDPE polymer self-adhesive film waterproof membrane layer and the asphalt-based pre-laid waterproof membrane layer 62 have excellent waterproof performance and durability, can effectively prevent water penetration and erosion, and protect the integrity and stability of underground structures and equipment. At the same time, the construction is convenient and can improve construction efficiency and quality.

[0070] like Figures 1 to 5 As shown, the HDPE polymer self-adhesive film waterproof coiled material layer 61 includes a HDPE sheet layer 611, a pressure-sensitive adhesive layer 612, and a sintered sand layer 613;

[0071] The asphalt-based pre-paved waterproof membrane layer 6262 includes a tread base layer 621 , a self-adhesive rubber layer 622 , a PE film layer 623 and a sand surface layer 624 .

[0072] In the embodiment of the utility model, the HDPE sheet layer 611 of the HDPE polymer self-adhesive film waterproofing coiled material layer 61 is used as the main material, which has excellent waterproof performance and durability, can effectively prevent water penetration, and protect underground structures and equipment from water erosion; the pressure-sensitive adhesive layer 612 provides self-adhesion, which can be conveniently pasted on the underground floor or foundation pit surface to improve construction efficiency; the HDPE sheet layer 611 and the sintered sand layer 613 provide strength and stability, and increase the durability and reliability of the waterproof layer;

[0073] The asphalt-based pre-paved waterproof membrane layer 6262 is made of asphalt-based materials, has excellent waterproof performance, and can effectively prevent moisture penetration; the self-adhesive rubber layer 622 provides self-adhesion, which can be easily pasted on the underground floor or foundation pit surface to improve construction efficiency; the tread layer 621 and the PE film layer 623 provide strength and stability, increase the durability, reliability and anti-seepage performance of the waterproof layer; the sand surface layer 624 can increase the wear resistance and protection of the waterproof layer, and prevent external factors from damaging the waterproof layer.

[0074] like Figures 1 to 5 As shown, when the external waterproof material layer 5 is applied to the foundation pit waterproof system, its laying form is as follows:

[0075] a: When the outermost side of the outer-wrapped waterproof material layer 5 is a non-self-adhesive coil or a non-self-adhesive layer of a self-adhesive coil, it is laid on the inner side of the second isolation protective layer 4;

[0076] b: When the outermost side of the outer-wrapped waterproof material layer 5 is the self-adhesive surface of the self-adhesive waterproof membrane, it is bonded to the inner side of the second isolation protective layer 4;

[0077] C: When the outer-wrapped waterproof material layer 5 is a single-layer waterproof coating, it is applied on the second isolation protection layer 4 .

[0078] In the embodiment of the utility model, in the foundation pit waterproofing system, the outer package waterproof material layer 5 includes a polyurethane waterproof coating layer, a non-curing rubber asphalt waterproof coating layer, a polymer cement waterproof coating layer, a polymer emulsion waterproof coating layer, an SBS modified asphalt waterproofing coiled material layer, a self-adhesive waterproofing coiled material layer and a polymer waterproofing coiled material layer, etc., and its laying forms are:

[0079] a. When the outermost side of the outer-wrapped waterproof material layer 5 is a non-self-adhesive coil or a non-self-adhesive side of a self-adhesive coil, it is laid on the inner side of the second isolation protective layer 4; the second isolation protective layer 4 can isolate the outer-wrapped waterproof material layer from the underground floor or foundation pit surface to prevent the outer-wrapped waterproof material layer from directly contacting the underground floor or foundation pit surface; the non-self-adhesive side of the outer-wrapped waterproof material layer can provide the main waterproof layer to prevent groundwater penetration;

[0080] b. When the outermost side of the outer-wrapped waterproof material layer 5 is the self-adhesive surface of the self-adhesive waterproof membrane, it is bonded to the inner side of the second isolation protective layer 4; the second isolation protective layer 4 can isolate the outer-wrapped waterproof material layer from the underground floor or foundation pit surface to prevent the outer-wrapped waterproof material layer from directly contacting the underground floor or foundation pit surface; the self-adhesive surface of the self-adhesive waterproof membrane can provide the main waterproof layer to prevent groundwater penetration;

[0081] c. When the outer-wrapped waterproof material layer 5 is a single-layer waterproof coating, it is applied on the second isolation protective layer 4; the second isolation protective layer can isolate the outer-wrapped waterproof material layer from the underground floor or foundation pit surface to prevent the outer-wrapped waterproof material layer from directly contacting the underground floor or foundation pit surface; the waterproof coating can provide the main waterproof layer to prevent groundwater penetration;

[0082] Regardless of whether the external waterproof material layer 5 is laid on the inner side of the second isolation protection layer 4, or is bonded or painted on the second isolation protection layer 4, it can isolate the direct contact between the underground floor or foundation pit surface and the external waterproof material layer and provide a waterproof function.

[0083] like Figures 1 to 5 As shown, the preparation method of the bare soil layer 1 is to compact the base bare soil, and the compaction coefficient is ≥0.96.

[0084] In the embodiment of the utility model, the preparation method of the soil layer 1 is to compact the base soil, and the compaction coefficient reaches or exceeds 0.96; compacting the base soil can effectively increase the density and stability of the soil. Through compaction, the gaps between the soil particles will be filled, and the friction between the soil particles will increase, thereby improving the density of the soil; compacting the base soil can provide a stable foundation for the upper structure, and by increasing the soil density, it can reduce the settlement and deformation of the soil, and improve the bearing capacity and stability of the foundation; compacting the base soil can reduce the pores and microcracks in the soil, thereby reducing The permeability of the soil can effectively prevent groundwater or other liquids from penetrating into the underground structure and protect the integrity of the underground structure; compacting the base soil can improve the drainage performance of the soil, and the dense soil structure can provide channels for water to be quickly discharged, reducing water accumulation in the soil and keeping the underground structure dry; compacting the base soil can improve the frost resistance of the soil, and the dense soil structure can reduce the pores and voids in the soil, reduce the infiltration of water, and thus reduce the damage to the soil caused by freeze-thaw cycles; it helps to protect the stability and integrity of the underground structure and improve the bearing capacity and service life of the foundation.

[0085] like Figures 1 to 5 As shown, the concrete cushion layer 2 is C10 or above grade concrete, with a thickness ranging from 100 to 150 mm.

[0086] In the embodiment of the utility model, the concrete cushion layer 2 can provide a uniform bearing layer, disperse and transfer the load of the superstructure, and protect the stability of the underground structure; by increasing the thickness of the cushion layer and using high-strength concrete, the bearing capacity of the foundation can be improved to adapt to the load requirements of the superstructure; the concrete cushion layer can provide a flat surface to facilitate the construction and installation of the superstructure.

[0087] like Figures 1 to 5As shown, the strength of the post-cast waterproof concrete layer 7 is not less than C25, its minimum water-resistance grade is not less than P8, and its thickness is more than 150 mm.

[0088] In the embodiment of the utility model, the post-cast waterproof concrete layer 7 has excellent waterproof performance, can effectively prevent the penetration of water, and its minimum water resistance grade is not lower than P8 grade, which can provide a reliable waterproof layer to prevent groundwater from penetrating into the underground structure; the post-cast waterproof concrete layer 7 has C25 grade strength, can provide sufficient strength and stability to withstand the load of the superstructure and maintain the integrity of the structure; the post-cast waterproof concrete layer 7 has high durability, can maintain waterproof performance for a long time, and protect the underground structure under different environmental conditions.

[0089] Example 1

[0090] An underground waterproof system, the underground waterproof system is composed of an underground floor layer, a side foundation pit, and a plane above the foundation pit; wherein the underground floor layer is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top; the side foundation pit of the waterproof system is divided into a vertical foundation pit and a slope foundation pit; the foundation pit structure is composed of a plain soil layer 1, a concrete cushion layer 2, a second isolation protection layer 4, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from outside to inside; the waterproof system of the plane above the foundation pit is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top;

[0091] The preparation method of the plain soil layer 1 is to compact the plain soil of the base layer, and the compaction coefficient is ≥ 0.96;

[0092] The concrete cushion layer 2 is C10 or above grade concrete with a thickness of 150 mm;

[0093] The first isolation protection layer 3 is a fine sand isolation layer, which is formed by laying and compacting fine sand of two different particle sizes in batches. The particle size of the coarse sand is 0.2-0.4mm, and the particle size of the fine sand is 0.1-0.2mm. When in use, the coarse sand is first laid with a thickness of 1.0cm, and then fine sand is laid on it with a thickness of 0.3cm and compacted, so as to obtain the fine sand isolation layer;

[0094] The second isolation protection layer 4 is a non-woven isolation layer with a thickness of 1.0 mm. It is arranged in a mesh-hanging manner and laid vertically on the base layer in sequence. The upper end is turned outward to the upper part of the fine sand structure in the isolation protection layer of the flat waterproof system on the foundation pit and extends 50 cm. The back of the overlap area is fixed by a double-sided self-adhesive tape and bonded to the base layer by the double-sided self-adhesive tape.

[0095] In the waterproof system of the underground floor layer and the upper plane of the foundation pit, the outer package waterproof material layer 5 is a 2.0 mm non-curing rubber asphalt waterproof coating layer;

[0096] In the foundation pit waterproofing system, the outer package waterproof material layer 5 is a type N II double-sided self-adhesive waterproofing membrane with a thickness of 1.5 mm, which is bonded to the second isolation protection layer 4, and the pre-laid waterproofing membrane is bonded and laid on it;

[0097] The pre-laid waterproofing membrane layer 6 is an asphalt-based pre-laid waterproofing membrane layer 62 with a thickness of 4.0 mm;

[0098] The post-cast waterproof concrete 7 has a strength of C25, a low impermeability grade of P8, and a thickness of 150 mm.

[0099] Example 2

[0100] An underground waterproof system, the underground waterproof system is composed of an underground floor layer, a side foundation pit, and a plane above the foundation pit; wherein the underground floor layer is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top; the side foundation pit of the waterproof system is divided into a vertical foundation pit and a slope foundation pit; the foundation pit structure is composed of a plain soil layer 1, a concrete cushion layer 2, a second isolation protection layer 4, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from outside to inside; the waterproof system of the plane above the foundation pit is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top;

[0101] The preparation method of the plain soil layer 1 is to compact the plain soil of the base layer, and the compaction coefficient is ≥ 0.96;

[0102] The concrete cushion layer 2 is C10 or above grade concrete with a thickness of 150 mm;

[0103] The first isolation protection layer 3 is a polypropylene cloth isolation layer with a thickness of 1.0 mm;

[0104] The second isolation protection layer 4 is a polypropylene cloth isolation layer with a thickness of 1.0 mm. It is arranged in a mesh-hanging manner and laid vertically on the base layer in sequence. The upper end is turned outward to the upper part of the fine sand structure in the isolation protection layer of the flat waterproof system on the foundation pit and extends 50 cm. The back of the overlap area is fixed by a double-sided self-adhesive tape and bonded to the base layer by the double-sided self-adhesive tape.

[0105] In the waterproof system of the underground floor layer and the upper surface of the foundation pit, the outer waterproof material layer 5 is a type N II self-adhesive waterproof membrane with a thickness of 1.5 mm;

[0106] In the foundation pit waterproofing system, the outer package waterproof material layer 5 is a type N II double-sided self-adhesive waterproofing membrane with a thickness of 1.5 mm, which is bonded to the second isolation protection layer 4, and the pre-laid waterproofing membrane is bonded and laid on it;

[0107] The pre-laid waterproofing coiled material layer 6 is a HDPE polymer self-adhesive film waterproofing coiled material layer, and the main material thickness is 1.5 mm;

[0108] Preferably, the post-cast waterproof concrete layer 7 has a strength of C25, a low impermeability grade of P10, and a thickness of 180 mm.

[0109] Example 3

[0110] An underground waterproof system, the underground waterproof system is composed of an underground floor layer, a side foundation pit, and a plane above the foundation pit; wherein the underground floor layer is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top; the side foundation pit of the waterproof system is divided into a vertical foundation pit and a slope foundation pit; the foundation pit structure is composed of a plain soil layer 1, a concrete cushion layer 2, a second isolation protection layer 4, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from outside to inside; the waterproof system of the plane above the foundation pit is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top;

[0111] The preparation method of the plain soil layer 1 is to compact the plain soil of the base layer, and the compaction coefficient is ≥ 0.96;

[0112] The concrete cushion layer 2 is C10 or above grade concrete with a thickness of 180 mm;

[0113] The first isolation protection layer 3 is a fine sand isolation layer, which is formed by laying and compacting fine sand of two different particle sizes in batches. The particle size of the coarse sand is 0.2-0.4mm, and the particle size of the fine sand is 0.1-0.2mm. When in use, the coarse sand is first laid with a thickness of 1.2cm, and then fine sand is laid on it with a thickness of 0.3cm after compaction, and then non-woven fabric is laid on it with a thickness of 1.2mm;

[0114] Preferably, the second isolation protection layer 4 is a non-woven isolation layer with a thickness of 1.2 mm, which is arranged in a mesh-hanging manner and laid vertically on the base layer in sequence, with the upper end turned outward to the upper part of the fine sand structure in the isolation protection layer of the upper plane waterproof system of the foundation pit and extending 40 cm, and the back of the overlapped area is fixed by a double-sided self-adhesive tape, and is bonded to the base layer by the double-sided self-adhesive tape;

[0115] In the waterproof system of the underground floor layer and the upper surface of the foundation pit, the outer-wrapped waterproof material layer 5 is a 3mm thick type II SBS modified asphalt waterproofing membrane, and a 2.0mm thick non-curing rubber asphalt waterproofing coating layer is set on the upper layer;

[0116] In the foundation pit waterproofing system, the outer package waterproofing material layer 5 is a 3mm thick type II SBS modified asphalt waterproofing membrane, which is laid on the second isolation protection layer 4, and the pre-laid waterproofing membrane is laid on top;

[0117] The pre-laid waterproofing coiled material layer 6 is a HDPE polymer self-adhesive film waterproofing coiled material layer, and the main material thickness is 1.5 mm;

[0118] Preferably, the post-cast waterproof concrete layer 7 has a strength of C25, a low impermeability grade of P10, and a thickness of 180 mm.

[0119] Example 4

[0120] An underground waterproof system, the underground waterproof system is composed of an underground floor layer, a side foundation pit, and a plane above the foundation pit; wherein the underground floor layer is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top; the side foundation pit of the waterproof system is divided into a vertical foundation pit and a slope foundation pit; the foundation pit structure is composed of a plain soil layer 1, a concrete cushion layer 2, a second isolation protection layer 4, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from outside to inside; the waterproof system of the plane above the foundation pit is mainly composed of a plain soil layer 1, a concrete cushion layer 2, a first isolation protection layer 3, an externally packaged waterproof material layer 5, a pre-laid waterproof roll material layer 6, and a post-cast waterproof concrete layer 7 from bottom to top;

[0121] The preparation method of the plain soil layer 1 is to compact the plain soil of the base layer, and the compaction coefficient is ≥ 0.96;

[0122] The concrete cushion layer 2 is C10 or above grade concrete with a thickness of 180 mm;

[0123] Preferably, the first isolation protective layer 3 is an isolation cloth isolation layer, which is paved with non-woven fabric, and the thickness of the non-woven fabric is 1.2 mm;

[0124] Preferably, the second isolation protection layer 4 is a non-woven isolation layer with a thickness of 1.2 mm, which is arranged in a mesh-hanging manner and laid vertically on the base layer in sequence, with the upper end turned outward to the upper part of the fine sand structure in the isolation protection layer of the upper plane waterproof system of the foundation pit and extending 40 cm, and the back of the overlapped area is fixed by a double-sided self-adhesive tape, and is bonded to the base layer by the double-sided self-adhesive tape;

[0125] In the waterproof system of the underground floor layer and the upper surface of the foundation pit, the outer package waterproof material layer 5 is a 2.0 mm thick polyurethane waterproof coating, and after it is cured, the pre-laid waterproof membrane is laid on it;

[0126] In the foundation pit waterproofing system, the outer waterproof material layer 5 is a 2.0 mm thick polyurethane waterproof coating, which is applied on the isolation protective layer and then paved with the pre-laid waterproof membrane after it is cured;

[0127] The pre-laid waterproofing membrane layer 6 is an asphalt-based pre-laid waterproofing membrane with a thickness of 4.0 mm;

[0128] The post-cast waterproof concrete layer 7 has a strength of C25, a low impermeability grade of P10, and a thickness of 180 mm.

[0129] The above is a preferred embodiment of the present invention. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the protection scope of the present invention.

Claims

1. An underground waterproof system, characterized in that: include: An underground floor waterproofing system, the underground floor waterproofing system comprising a hierarchically arranged plain soil layer (1), a concrete cushion layer (2), a first isolation protection layer (3), an externally wrapped waterproofing material layer (5), a pre-laid waterproofing membrane layer (6) and a post-cast waterproofing concrete layer (7); A lateral foundation pit waterproofing system, wherein the lateral foundation pit is divided into a vertical foundation pit and a slope foundation pit, and the lateral foundation pit waterproofing system comprises a hierarchically arranged plain soil layer (1), a concrete cushion layer (2), a second isolation protection layer (4), an externally wrapped waterproof material layer (5), a pre-laid waterproof roll material layer (6) and a post-cast waterproof concrete layer (7); A foundation pit upper plane waterproofing system, the foundation pit upper plane waterproofing system comprising a hierarchically arranged plain soil layer (1), a concrete cushion layer (2), a first isolation protection layer (3), an externally wrapped waterproof material layer (5), a pre-laid waterproofing coiled material layer (6) and a post-cast waterproofing concrete layer (7).

2. The underground waterproofing system according to claim 1, characterized in that: The first isolation protection layer (3) comprises a fine sand isolation layer, a fine sand plus isolation cloth isolation layer and an isolation cloth isolation layer; The fine sand isolation layer is formed by laying and compacting fine sand of two different particle sizes in batches, wherein the particle size of the coarse sand is 0.2-0.4 mm, and the particle size of the fine sand is 0.1-0.2 mm; The isolation layer of the isolation cloth is non-woven fabric or polypropylene fabric with a thickness of 1.0-1.5 mm; The fine sand plus isolation cloth isolation layer is prepared by laying non-woven fabric or polypropylene fabric on the top of the fine sand isolation layer, and the thickness of the non-woven fabric or polypropylene fabric is 1.0-1.5 mm.

3. The underground waterproofing system according to claim 2, characterized in that: The second isolation protection layer (4) is a non-woven fabric or polypropylene fabric isolation layer with a thickness of 1.0-1.5 mm, which is laid on the concrete cushion layer (2) in sequence, with the upper end turned outward to the upper part of the fine sand structure in the first isolation protection layer (3) of the upper flat waterproof system of the foundation pit and extending 30-50 cm.

4. The underground waterproofing system according to claim 3, characterized in that: When the outer-wrapped waterproof material layer (5) is applied to the underground floor layer or the flat waterproof system on the foundation pit, it is composed of one or two of a 1.5-2.0 mm thick polyurethane waterproof coating layer, a 2.0-3.0 mm non-curing rubber asphalt waterproof coating layer, a 1.5-2.0 mm thick polymer cement waterproof coating layer, a 1.5-2.0 mm thick polymer emulsion waterproof coating layer, a 3-mm thick type II SBS modified asphalt waterproof roll layer, a 1.5-3.0 mm thick type II self-adhesive waterproof roll layer, and a 1.2-1.5 mm thick polymer waterproof roll.

5. The underground waterproofing system according to claim 4, characterized in that: The pre-laid waterproofing roll material layer (6) comprises a HDPE polymer self-adhesive film waterproofing roll material layer (61) and an asphalt-based pre-laid waterproofing roll material layer (62); The thickness of the HDPE polymer self-adhesive film waterproofing coiled material layer (61) is ≥1.2 mm; the thickness of the asphalt-based pre-laid waterproofing coiled material layer (62) is 4.0 mm.

6. The underground waterproofing system according to claim 5, characterized in that: The HDPE polymer self-adhesive film waterproof coiled material layer (61) comprises a HDPE sheet layer (611), a pressure-sensitive adhesive layer (612), and a sintered sand layer (613); The asphalt-based pre-paved waterproof coiled material layer (62) comprises a base layer (621), a self-adhesive rubber layer (622), a PE film layer (623) and a sand surface layer (624).

7. The underground waterproofing system according to claim 6, characterized in that: The thickness of the concrete cushion layer (2) is in the range of 100-150 mm.

8. The underground waterproofing system according to claim 7, characterized in that: The thickness of the post-cast waterproof concrete layer (7) is ≥150 mm.

Citation Information

Cited By

  • Roof waterproof repairing system based on material compatibility and construction method

    CN120867561A