Advanced water stop structure for post-cast strip of bottom plate

By using folding water stop strips, expanded water stop balls and gravel layers in the pre-water stop structure of the bottom plate rear pouring belt, the problems of unstable fixation of the rubber water stop belt and insufficient material strength are solved, and the anti-seepage capacity and construction safety are improved sex.

CN222065582UActive Publication Date: 2024-11-26CHONGQING JIGUANSHI CONSTR ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420703683.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-07
Publication Date
2024-11-26
Estimated Expiration
2034-04-07

AI Technical Summary

Technical Problem

In the existing bottom plate rear casting belt ahead of the water stop structure, the rubber water stop belt is not fixed and leads to offset and cracking, and the extruded polystyrene board or wood fiber asphalt board is insufficient to cause water seepage.

Method used

Use folding water stop strips and expansion water stop balls to fill the gravel layer, expand and tighten after encountering water through expansion water stop balls, increase deformation ability, reduce offset and cracking phenomenon, and fix the anti-fall plate through floor piles to enhance the overall Stability and safety.

Benefits of technology

The anti-seepage capacity and construction safety of the leading water stop structure of the bottom plate rear casting belt are improved, offset and cracking are reduced, and the strength and service life of the gravel layer are enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222065582U_ABST
    Figure CN222065582U_ABST
Patent Text Reader

Abstract

The utility model relates to a bottom plate post-cast strip advanced water stop structure, which belongs to the technical field of building construction and comprises a foundation bed, a first reinforcing mesh arranged at the top end of the foundation bed, a foundation bottom plate arranged at the top of the foundation bed, a cleaning groove formed in the foundation bottom plate, and an expansion joint arranged between the cleaning groove and the first reinforcing mesh. A clamping groove is transversely formed in the middle of the expansion joint. Compared with the prior art, the water-stop device has the advantages that water can be sprayed to the expansion water-stop balls which are placed in the circular grooves in advance through the folding water-stop strips and the expansion water-stop balls, the expansion water-stop balls can expand after meeting water, then the expansion water-stop balls can be clamped with the corresponding circular grooves, deviation of the water-expansion water-stop belts in the construction process can be reduced, and the construction efficiency is improved. And meanwhile, the deformation capacity of the whole water-swelling water stop belt can be improved through the folding water stop strips, then the water-swelling water stop belt is not prone to tension fracture, and therefore the water seepage prevention capacity of the whole bottom plate post-cast strip advance water stop structure can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to an advanced water-stopping structure for a post-cast strip of a bottom plate. Background Art

[0002] In recent years, with the development of construction technology, there are more and more high-rise, super-high-rise and large-scale projects, and the application of post-cast strips has appeared frequently. Post-cast strips can generally be divided into expansion post-cast strips and settlement post-cast strips according to their uses. Both expansion post-cast strips and settlement post-cast strips have a longer retention time. When the foundation of the building is below the groundwater level, the traditional post-cast strip retention method is adopted. The post-cast strip must be poured with post-cast strip concrete after the main structure construction is completed. This requires continuous precipitation to ensure that the groundwater level remains below the foundation. Precipitation can only be stopped after the main structure is completed and the post-cast strip concrete is poured.

[0003] After searching, a Chinese patent discloses a foundation slab advanced water-stop post-casting strip (authorization announcement number CN201581510U), wherein an advanced water-stop bottom plate (2) is added below the foundation slab post-casting strip (8); an expansion joint (3) is left in the middle of the advanced water-stop bottom plate (2), and the joint is filled with extruded polystyrene board; a rubber water-stop strip (4) is arranged horizontally in the middle of the expansion joint (3); a sweeping layer (7) is reserved between the foundation slab post-casting strip (8) and the advanced water-stop bottom plate (2); a quick-closing net (9) is used to support the template on the side of the foundation slab post-casting strip (8), and the advanced water-stop bottom plate (2) and the foundation slab (5) are poured with concrete at the same time: the advanced water-stop bottom plate (2) is arranged with double-layer reinforcement (11). Although this patented technology has the advantages of reducing engineering costs, shortening construction period, reducing safety hazards caused by deep foundation pits, greatly reducing precipitation, and effectively protecting water resources.

[0004] However, the above device still has some shortcomings in actual use. The most obvious one is that since the rubber waterstop is not properly fixed, it is easy to shift and crack during concrete pouring construction, and the extruded polystyrene board or wood fiber asphalt board itself is not strong enough, which leads to deformation during construction, which in turn causes water seepage in the base plate post-cast strip ahead of the waterstop structure. Utility Model Content

[0005] In view of the above-mentioned problems existing in the prior art: since the rubber waterstop is not properly fixed, it is easy to deviate and tear during concrete pouring construction, and the extruded polystyrene board or wood fiber asphalt board itself is not strong enough, which leads to deformation during construction, and further causes water seepage in the advance waterstop structure of the base plate post-cast strip. The main purpose of the utility model is to provide an advance waterstop structure for the base plate post-cast strip.

[0006] The technical solution of the utility model is as follows: a base plate post-cast strip advance water-stopping structure, comprising a foundation cushion layer, a first steel mesh is arranged on the top of the foundation cushion layer, a foundation base plate is arranged on the top of the foundation cushion layer, a cleaning groove is opened inside the foundation base plate, an expansion joint is arranged between the cleaning groove and the first steel mesh, a card slot is arranged horizontally in the middle of the expansion joint, the interior of the expansion joint is filled with a gravel layer, a water-swellable waterstop strip is placed inside the card slot, both ends of the water-swellable waterstop strip are fixedly connected with folded waterstop strips, the ends of the two folded waterstop strips that are far away from each other are fixedly connected with expansion waterstop balls, and a circular groove used in conjunction with the expansion waterstop balls is opened inside the base plate.

[0007] By adopting the above-mentioned technical scheme, through the arrangement of foldable waterstop strips and expandable waterstop balls, water can be sprinkled on the expandable waterstop balls placed in the circular grooves in advance. When the expandable waterstop balls come into contact with water, their volume will expand and then they will be clamped with the corresponding circular grooves, thereby reducing the displacement of the water-expandable waterstop strips during construction. At the same time, the foldable waterstop strips can increase the deformation capacity of the entire water-expandable waterstop strips, thereby making the water-expandable waterstop strips less likely to be torn.

[0008] As a preferred embodiment, a second steel mesh is tied to the top of the foundation slab, an anti-fall plate is provided at the top of the foundation slab, ground piles are provided at both ends of the anti-fall plate, and the anti-fall plate and the foundation slab are connected through the ground piles.

[0009] By adopting the above technical solution and using ground piles, the anti-fall plate can be fixedly installed above the foundation bottom plate, thereby preventing workers from stepping on empty space and improving the construction safety factor.

[0010] As a preferred embodiment, a post-cast strip body is provided inside the cleaning trough, and two waterstop steel plates are connected between the first steel mesh and the second steel mesh via a wire mesh, one end of the waterstop steel plate is inserted into the inside of the foundation bottom plate, and the other end of the waterstop steel plate is inserted into the inside of the post-cast strip body.

[0011] By adopting the above technical solution, the overall stability and reliability of the first steel mesh, the waterstop steel plate and the second steel mesh can be increased, thereby avoiding falling during the construction process.

[0012] As a preferred embodiment, a waterproof layer is fixedly connected to the top of the base cushion layer, and the waterproof layer is a polyurethane waterproof coating.

[0013] By adopting the above technical solution, the waterproof effect of the waterproof layer and the base cushion layer can be improved.

[0014] As a preferred implementation, a wear-resistant layer is fixedly connected to the inner wall of the expansion joint, and the wear-resistant layer is made of a nickel-chromium alloy material.

[0015] By adopting the above technical solution, the wear and tear at the expansion joint can be reduced and the service life of the expansion joint can be increased.

[0016] As a preferred embodiment, an inner groove for use with ground piles is provided inside the anti-fall plate.

[0017] By adopting the above technical solution, the ground piles can be hidden.

[0018] Compared with the prior art, the advantages and positive effects of the utility model are:

[0019] In the utility model, by filling crushed stone in the expansion joint, the crushed stone layer can be made stronger than the extruded polystyrene board or wood fiber asphalt board used in the prior art. At the same time, the use of the crushed stone layer can ensure the needs of expansion and contraction and settlement deformation of the foundation base plate. By setting the folding waterstop strip and the expandable waterstop ball, the expandable waterstop ball placed in the circular groove in advance can be sprinkled with water. When the expandable waterstop ball meets water, its volume will expand and then it will be clamped with the corresponding circular groove, thereby reducing the displacement of the water-expandable waterstop strip during construction. At the same time, the folding waterstop strip can increase the deformation capacity of the entire water-expandable waterstop strip, thereby making the water-expandable waterstop strip less likely to be cracked, thereby improving the anti-seepage capacity of the advance waterstop structure of the entire base plate post-casting strip. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 The utility model provides a front view of the advanced water-stopping structure of the post-cast strip of the bottom plate;

[0021] Figure 2 The utility model provides a bottom plate post-casting belt advanced water-stopping structure Figure 1 The enlarged view of point A in the middle;

[0022] Figure 3 The utility model provides a bottom plate post-casting belt advanced water-stopping structure Figure 1 Enlarged view of point B in the middle.

[0023] Legend: 1. Foundation cushion; 2. Waterproof layer; 3. First steel mesh; 4. Foundation bottom plate; 5. Cleaning trough; 6. Post-cast strip body; 7. Waterstop steel plate; 8. Anti-fall plate; 9. Second steel mesh; 10. Ground piles; 11. Expansion joint; 12. Wear-resistant layer; 13. Water-swelling waterstop; 14. Slot; 15. Folding waterstop strip; 16. Circular groove; 17. Expandable waterstop ball; 18. Gravel layer; 19. Inner groove. DETAILED DESCRIPTION

[0024] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.

[0025] Reference Figure 1-3 A base plate post-casting strip advance water-stopping structure comprises a foundation cushion layer 1, a first steel mesh 3 is arranged on the top of the foundation cushion layer 1, a foundation base plate 4 is arranged on the top of the foundation cushion layer 1, a cleaning groove 5 is opened inside the foundation base plate 4, an expansion joint 11 is arranged between the cleaning groove 5 and the first steel mesh 3, a card slot 14 is arranged horizontally in the middle of the expansion joint 11, the expansion joint 11 is filled with a gravel layer 18, a water-expandable waterstop strip 13 is placed inside the card slot 14, both ends of the water-expandable waterstop strip 13 are fixedly connected with folded waterstop strips 15, the ends of the two folded waterstop strips 15 that are far away from each other are fixedly connected with expansion waterstop balls 17, and a circular groove 16 used in conjunction with the expansion waterstop ball 17 is opened inside the base base plate 4.

[0026] When in use, by filling gravel in the expansion joint 11, the gravel layer 18 will be stronger than the extruded polystyrene board or wood fiber asphalt board used in the prior art. At the same time, the use of the gravel layer 18 can ensure the needs of expansion and contraction and settlement deformation of the foundation slab 4, and through the arrangement of the folding waterstop strip 15 and the expandable waterstop ball 17, the expandable waterstop ball 17 placed in the circular groove 16 in advance can be sprinkled with water. When the expandable waterstop ball 17 meets water, its volume will expand and then it will be clamped with the corresponding circular groove 16, thereby reducing the displacement of the water-expandable waterstop strip 13 during construction. At the same time, the folding waterstop strip 15 can increase the deformation capacity of the entire water-expandable waterstop strip 13, thereby making the water-expandable waterstop strip 13 less likely to crack, thereby improving the anti-seepage ability of the advance water-stop structure of the entire slab post-cast strip.

[0027] Reference Figure 1 A second steel mesh 9 is tied to the top of the foundation bottom plate 4, and an anti-fall plate 8 is arranged on the top of the foundation bottom plate 4. Ground piles 10 are arranged at both ends of the anti-fall plate 8. The anti-fall plate 8 is connected to the foundation bottom plate 4 through the ground piles 10. By using the ground piles 10, the anti-fall plate 8 can be fixedly installed above the foundation bottom plate 4, thereby preventing the staff from stepping on empty space, thereby improving the construction safety factor.

[0028] Reference Figure 1A post-cast strip body 6 is provided inside the cleaning trough 5, and two water-stop steel plates 7 are connected between the first steel mesh 3 and the second steel mesh 9 through a wire mesh. One end of the water-stop steel plate 7 is inserted into the inside of the foundation bottom plate 4, and the other end of the water-stop steel plate 7 is inserted into the inside of the post-cast strip body 6. By adopting the above structure, the overall stability and reliability of the first steel mesh 3, the water-stop steel plate 7 and the second steel mesh 9 can be increased, thereby avoiding falling during the construction process.

[0029] Reference Figure 2 The top of the base cushion layer 1 is fixedly connected with a waterproof layer 2, and the waterproof layer 2 is a polyurethane waterproof coating, which can improve the waterproof effect of the waterproof layer 2 and the base cushion layer 1.

[0030] Reference Figure 2 The inner wall of the expansion joint 11 is fixedly connected with a wear-resistant layer 12, which is made of a nickel-chromium alloy material, thereby reducing the occurrence of grinding at the expansion joint 11 and increasing the service life of the expansion joint 11.

[0031] Reference Figure 1 The anti-fall plate 8 has an inner groove 19 for use with the ground pile 10, so that the ground pile 10 can be hidden to prevent the exposed ground pile 10 from affecting the construction workers.

[0032] Working principle: By filling the expansion joint 11 with gravel, the gravel layer 18 will be stronger than the extruded polystyrene board or wood fiber asphalt board used in the prior art. At the same time, the use of the gravel layer 18 can ensure the needs of expansion and contraction and settlement deformation of the foundation slab 4. By setting the folding waterstop strip 15 and the expandable waterstop ball 17, the expandable waterstop ball 17 placed in the circular groove 16 in advance can be sprinkled with water. When the expandable waterstop ball 17 meets water, its volume will expand and then it will be clamped with the corresponding circular groove 16, thereby reducing the displacement of the water-expandable waterstop strip 13 during construction. At the same time, the folding waterstop strip 15 can increase the deformation capacity of the entire water-expandable waterstop strip 13, thereby making the water-expandable waterstop strip 13 less likely to be torn, thereby improving the anti-seepage capacity of the advance water-stop structure of the entire slab post-casting strip, and by using the ground piles 10, the anti-fall plate 8 can be fixedly installed above the foundation slab 4, thereby avoiding the occurrence of workers stepping on air, thereby improving the construction safety factor.

[0033] The above are only preferred embodiments of the present application and are not intended to limit the present application. Although the present application has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application.

Claims

1. A base plate post-cast strip advance water-stopping structure, comprising a foundation cushion layer (1), characterized in that: A first steel mesh (3) is arranged at the top of the foundation cushion layer (1), a foundation base plate (4) is arranged at the top of the foundation cushion layer (1), a cleaning groove (5) is arranged inside the foundation base plate (4), an expansion joint (11) is arranged between the cleaning groove (5) and the first steel mesh (3), a retaining groove (14) is arranged transversely in the middle of the expansion joint (11), the expansion joint (11) is filled with a gravel layer (18), a water-expandable waterstop strip (13) is placed inside the retaining groove (14), both ends of the water-expandable waterstop strip (13) are fixedly connected to foldable waterstop strips (15), and the ends of the two foldable waterstop strips (15) that are far away from each other are fixedly connected to expansion waterstop balls (17), and a circular groove (16) used in conjunction with the expansion waterstop ball (17) is arranged inside the foundation base plate (4).

2. The advanced water-stopping structure of the post-cast strip of the bottom plate according to claim 1 is characterized in that: A second steel mesh (9) is tied to the top of the foundation bottom plate (4), an anti-fall plate (8) is provided at the top of the foundation bottom plate (4), ground piles (10) are provided at both ends of the anti-fall plate (8), and the anti-fall plate (8) and the foundation bottom plate (4) are connected via the ground piles (10).

3. The advanced water-stopping structure of the post-cast strip of the bottom plate according to claim 1 is characterized in that: A post-cast strip body (6) is provided inside the cleaning trough (5), and two water-stop steel plates (7) are connected between the first steel mesh (3) and the second steel mesh (9) via a steel mesh, one end of the water-stop steel plate (7) is inserted into the inside of the foundation bottom plate (4), and the other end of the water-stop steel plate (7) is inserted into the inside of the post-cast strip body (6).

4. The advanced water-stopping structure of the post-cast strip of the bottom plate according to claim 1 is characterized in that: The top of the base cushion layer (1) is fixedly connected to a waterproof layer (2), and the waterproof layer (2) is a polyurethane waterproof coating.

5. The advanced water-stopping structure of the post-cast strip of the bottom plate according to claim 1 is characterized in that: A wear-resistant layer (12) is fixedly connected to the inner wall of the expansion joint (11), and the wear-resistant layer (12) is made of a nickel-chromium alloy material.

6. The advanced water-stopping structure of the post-cast strip of the bottom plate according to claim 2 is characterized in that: An inner groove (19) for use with the ground pile (10) is provided inside the anti-fall plate (8).