Efficient operation rack for tunnel

By designing a tunnel efficient operation bench with adjustable height, the construction progress problems caused by traditional operation benches are solved, the working efficiency of railway tunnel construction is improved, and it is suitable for drilling and blasting construction of different levels of surrounding rocks.

CN222066746UInactive Publication Date: 2024-11-26CHINA RAILWAY SEVENTH BUREAU GRP XIAN RAILWAY ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323274268.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-01
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During railway tunnel construction, traditional operation benches cause long drilling time for the blast hole, which affects the construction progress. Especially when drilling holes in different levels of surrounding rocks, it is necessary to frequently adjust the distance between the blast holes, resulting in workers working at high places for a long time, affecting efficiency. .

Method used

An efficient tunnel operation bench was designed, including working platform plates, protective lantern rods, holed steel frames, mobile small support and steel mesh platform, allowing workers to adjust the operation height according to on-site needs and improve work efficiency.

Benefits of technology

Through the adjustable height working bench, the working efficiency is significantly improved, the progress bottleneck of tunnel construction is solved, the progress needs of the owners are met, and it is suitable for various tunnel drilling and blasting construction methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222066746U_ABST
    Figure CN222066746U_ABST
Patent Text Reader

Abstract

The utility model provides a tunnel efficient operation rack which comprises an operation rack body, an operation platform plate is arranged at the upper end of the operation rack body, protective flange rods are arranged on the two sides of the operation platform plate, a top operation platform is arranged in the middle of the operation platform plate, and a bottom operation platform is arranged in the middle of the top operation platform. Hole steel frames are arranged on the two sides of the lower portion of the operation platform plate, a steel frame is arranged in the middle of the operation platform plate, and a middle operation platform and a base operation platform are arranged on the hole steel frames. Blasthole drilling is carried out at the required height on site, the working efficiency is greatly improved, the problems that the tunnel working face is small and the progress is not easy to promote are solved, the progress requirements of owners are guaranteed, and popularization is convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel construction equipment requiring a drilling and blasting method, in particular to a tunnel high-efficiency operation platform. Background Art

[0002] During the construction of railway tunnels, the surrounding rock levels are mostly III, IV, and V, and the basic quality index BQ values ​​of the surrounding rock are 350-450, 250-350, and <250, respectively. Drilling of railway tunnels in surrounding rocks of different levels mostly adopts the drilling and blasting method, and peripheral holes, auxiliary holes, and slot holes need to be drilled in advance on the face. In order to better control over-excavation and under-excavation and reduce disturbance to the surrounding rock, the spacing between blastholes will be reduced, and the minimum resistance will be reduced, resulting in more blastholes and a long drilling time. At this time, whether the blastholes can be drilled quickly and simultaneously has become a constraint on the progress of the railway tunnel. The traditional method of use is to place an operating platform made of I-beams welded on the face, and workers stand on the operating platform to drill blastholes at the same time. After a long period of technical accumulation, the time required has been basically fixed. Utility Model Content

[0003] The technical problem solved by the utility model is to provide a tunnel efficient operation platform to solve the problems raised in the above background technology.

[0004] The technical problem solved by the utility model is achieved by adopting the following technical scheme: a tunnel efficient working platform, including a working platform body, a working platform plate is arranged on the upper end of the working platform body, protective blue rods are arranged on both sides of the working platform plate, a top working platform is arranged in the middle of the working platform plate, perforated steel frames are arranged on both sides of the lower side of the working platform plate, a steel frame is arranged in the middle of the working platform plate, and a middle working platform and a base working platform are arranged on the perforated steel frame.

[0005] Furthermore, a ladder is connected between the middle working platform and the base working platform.

[0006] Furthermore, there are two perforated steel frames, which are symmetrically arranged on both sides below the working platform plate. Holes are opened on the perforated steel frames, and the spacing between the holes is 400 mm.

[0007] Furthermore, two small movable supports are inserted on the perforated steel frame.

[0008] Furthermore, a steel mesh moving platform is placed on the small moving support.

[0009] Furthermore, a diagonal brace is provided in the movable small support.

[0010] Furthermore, the steel frames are provided in 6 rows, and the 6 steel frames are equidistantly provided on both sides below the working platform plate.

[0011] Compared with the prior art, the beneficial effects of the utility model are as follows: the utility model is suitable for various tunnels constructed by the drilling and blasting method, has strong adaptability, and the small mobile support can adjust the height arbitrarily, and blasthole drilling can be carried out at the required height on site, which greatly improves work efficiency, solves the problem of small tunnel working surface and difficulty in improving progress, guarantees the progress requirements of the owner, and is easy to promote. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a structural schematic diagram of the utility model.

[0013] Figure 2 It is a front view structural schematic diagram of the utility model.

[0014] Figure 3 It is a left-side structural schematic diagram of the utility model.

[0015] Figure 4 It is a schematic diagram of the top structure of the utility model.

[0016] Figure 5 This is a schematic diagram of the mobile small support structure of the utility model

[0017] In the figure: 1-guardrail; 2-ladder; 3-top working platform; 4-middle working platform; 5-bottom working platform; 6-steel frame; 7-steel frame with holes; 8-small movable support. DETAILED DESCRIPTION

[0018] In order to make the technical means for realizing the utility model, creative features, objectives and effects easy to understand, the utility model is further explained below in conjunction with specific diagrams. In the description of the utility model, it should be noted that, unless otherwise clearly stipulated and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense. For example, it can be a fixed connection or a detachable connection, or an integral connection can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal connection of two components.

[0019] like Figures 1 to 4 As shown, a high-efficiency tunnel work platform includes a work platform body, a work platform plate 9 is arranged on the upper end of the work platform body, protective blue rods 1 are arranged on both sides of the work platform plate 9, a top work platform 3 is arranged in the middle of the work platform plate 9, and perforated steel frames 7 are arranged on both sides of the lower side of the work platform plate 9. A steel frame 6 is arranged in the middle of the work platform plate 9, and a middle work platform 4 and a base work platform 5 are arranged on the perforated steel frame 7.

[0020] Furthermore, a ladder 2 is connected between the middle working platform 4 and the base working platform 5 .

[0021] Furthermore, two perforated steel frames 7 are provided, and the two perforated steel frames 7 are symmetrically arranged on both sides below the working platform plate 9. Holes are opened on the perforated steel frames 7, and the spacing between the holes is 400 mm.

[0022] Furthermore, two small movable supports 8 are inserted on the perforated steel frame 7 .

[0023] Furthermore, a steel mesh mobile platform is placed on the mobile small support 8, so that workers can stand and use it when working, so as to meet the demand of adjusting the height of the working platform at any time according to the needs of the site.

[0024] Furthermore, a diagonal brace is provided in the small movable support 8 to enhance the overall stability.

[0025] Furthermore, the steel frames 6 are provided in six rows, and the six steel frames 6 are equidistantly provided on both sides below the working platform plate 9 .

[0026] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection of the utility model is defined by the attached claims and their equivalents.

Claims

1. A tunnel high-efficiency operation platform, comprising an operation platform body, characterized in that: A working platform plate (9) is arranged at the upper end of the working platform body, protective blue rods (1) are arranged on both sides of the working platform plate (9), a top working platform (3) is arranged in the middle of the working platform plate (9), perforated steel frames (7) are arranged on both sides below the working platform plate (9), a steel frame (6) is arranged in the middle of the working platform plate (9), and a middle working platform (4) and a base working platform (5) are arranged on the perforated steel frame (7).

2. A tunnel high-efficiency operation platform as claimed in claim 1, characterized in that: A ladder (2) is connected between the middle working platform (4) and the base working platform (5).

3. The high-efficiency tunnel operation platform according to claim 1, characterized in that: The perforated steel frames (7) are provided with two frames, and the two perforated steel frames (7) are symmetrically arranged on both sides below the working platform plate (9). The perforated steel frames (7) are provided with holes, and the spacing between the holes is 400 mm.

4. The tunnel high-efficiency operation platform according to claim 1, characterized in that: Two small movable supports (8) are inserted on the perforated steel frame (7).

5. The high-efficiency tunnel operation platform according to claim 4, characterized in that: A steel mesh moving platform is placed on the small moving support (8).

6. A tunnel high-efficiency operation platform as claimed in claim 5, characterized in that: The movable small support (8) is provided with an oblique support.

7. The high-efficiency tunnel operation platform according to claim 1, characterized in that: The steel frames (6) are arranged in six rows, and the six steel frames (6) are arranged equidistantly on both sides below the working platform plate (9).