Arc-shaped section top plate concrete pouring formwork of station main body structure
By using a segmented formwork system in the concrete pouring of the arched top slab, the problem of fixing the formwork on the outer side of the arch was solved, and the stress at the arch foot was controlled during pouring, ensuring the density of the concrete and the quality of construction.
Patent Information
- Application Number
- CN202323576644.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-27
AI Technical Summary
In the traditional process of pouring concrete for curved sections, the outer formwork of the arch cannot be fixed, which makes it difficult to control the concrete slump, resulting in insufficient compaction and construction quality problems.
A segmented formwork system is adopted, including a first formwork, a second formwork, and a sealing plate. It is connected to the arc-shaped support rail by fasteners to form a detachable formwork structure. Segmented pouring is used to control the stress at the arch foot and ensure the compactness of the pouring.
By controlling the stress at the arch foot through segmented pouring, the increased stress caused by a single pour was avoided, thus improving the density of the concrete and the construction quality.
Smart Images

Figure CN222066768U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of arc-section top plate casting technology, in particular to an arc-section top plate concrete casting template of a station main structure. Background Art
[0002] In the traditional arc segment concrete pouring process, the arc casting bottom template is supported by a bracket, and the template cannot be fixed on the outside of the arch. Therefore, the existing technology usually completes the pouring from the bottom sections on both sides of the arc casting bottom template upward. During the pouring process, the concrete is easy to collapse, and the poured concrete cannot be vibrated, which directly causes the arch concrete to be not dense after pouring. At the same time, the arc top plate between the arch pressure plate and the side wall is usually poured at one time because there is no conventional fixed template. The slump of the concrete is not easy to control, which is easy to cause construction quality problems. Utility Model Content
[0003] The purpose of the utility model is to provide a concrete pouring template for the arc-shaped top plate of the main structure of the station in accordance with the above-mentioned deficiencies of the prior art. By installing a segmented template for pouring the arc-shaped top plate on the outside of the arch, the force at the arch foot during the pouring process can be controlled, and the force at the arch foot is not increased due to one-time pouring, thereby further ensuring the density of pouring.
[0004] The purpose of this utility model is achieved by the following technical solutions:
[0005] A concrete pouring template for an arc-shaped top slab of a station main structure, comprising:
[0006] A first template, wherein the first template has a first mounting portion;
[0007] At least one second template, the second template having a second mounting portion; wherein
[0008] A sealing plate is detachably and movably arranged between the first mounting portion of the first template and the second mounting portion of the second template, and a reserved hole is formed between the first template and the second template.
[0009] Optionally, it also includes vertical side walls, a middle plate at the bottom, a curved casting bottom formwork supported by a bracket above the middle plate, and a curved support rail located above the curved casting bottom formwork and having a curvature consistent with that of the curved casting bottom formwork, the first formwork and the second formwork are connected to the curved support rail and are close to the arch foot position.
[0010] Optionally, one end of the first template contacts the flattened surface of the arch foot after the pouring is completed or is flush with the flattened surface.
[0011] Optionally, a side wall arch foot casting section is formed between the side wall and the arc-shaped casting bottom template.
[0012] Optionally, an arc-shaped casting section is formed between the arc-shaped casting bottom template and the arc-shaped supporting guide rail.
[0013] Optionally, the top position directly above the arc-shaped casting section is the vault pressure plate casting section.
[0014] Optionally, an isolation net is provided when casting the arch pressure plate casting section.
[0015] Optionally, the first template and the second template are connected to the arc-shaped support rail via a first fastener.
[0016] Optionally, the sealing plate is connected to the first template and the second template via a second fastener.
[0017] The advantages of the utility model are:
[0018] The utility model installs a segmented template for pouring the arc-shaped top plate on the outer side of the arch, so that the force at the arch foot during the pouring process can be controlled, and the force at the arch foot is not increased due to one-time pouring, thereby further ensuring the density of pouring. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the assembly position of the arc-shaped top plate concrete pouring template of the utility model in the main structure of the station;
[0020] Figure 2 It is a schematic diagram of the installation of the arc-shaped top plate concrete pouring template of the utility model;
[0021] Figure 3 It is a schematic diagram of the concrete pouring route of the remaining arc section after the arch top pressure plate and the arc top plate are poured in the utility model. DETAILED DESCRIPTION
[0022] The marks in the figure are: 1. first formwork, 2. second formwork, 3. closing plate, 4. side wall, 5. middle plate, 6. bracket, 7. arc-shaped casting bottom formwork, 8. arc-shaped support rail, 9. isolation net, 10. arch pressure plate, 11. first fastener, 20. arc-shaped top plate, 30. remaining arc segments, 31. second fastener, 32. reserved hole.
[0023] Example: See Figure 1 and Figure 2As shown, an embodiment of an arc-shaped section top plate concrete casting formwork of a station main structure is shown, wherein the first formwork 1 has a first mounting portion; at least one second formwork 2, the second formwork 2 has a second mounting portion; wherein a sealing plate 3 is detachably and movably arranged between the first mounting portion of the first formwork 1 and the second mounting portion of the second formwork 2, and a reserved hole 32 is formed between the first formwork 1 and the second formwork 2.
[0024] In this embodiment, it also includes a vertical side wall 4, a middle plate 5 located at the bottom, a curved casting bottom template 7 supported above the middle plate 5 by a bracket 6, and a curved support guide rail 8 located above the curved casting bottom template 7 and having a curvature consistent with the curved casting bottom template 7. The first template 1 and the second template 2 are connected to the curved support guide rail 8 and are close to the arch foot position. One end of the first template 1 contacts the surface of the arch foot that is flattened after casting is completed or is flush with the flattened surface.
[0025] In this embodiment, a side wall arch foot casting section is formed between the side wall 4 and the arc-shaped casting bottom formwork 7, an arc-shaped casting section is formed between the arc-shaped casting bottom formwork 7 and the arc-shaped support guide rail 8, and the arch top pressure plate 10 casting section is located at the top position directly above the arc-shaped casting section.
[0026] In this embodiment, when casting the casting section of the arch pressure plate 10, an isolation net 9 is provided, the first template 1 and the second template 2 are connected to the arc support rail 8 through the first fastener 11, and the sealing plate 3 is connected to the first template 1 and the second template 2 through the second fastener 31.
[0027] The characteristics and functions of the present invention can be further understood through the following description.
[0028] This embodiment also discloses a casting process for the main structure of a station, comprising the following steps:
[0029] Step 1: In addition to the main structure concrete construction technical requirements, the arc section concrete pouring process should also be constructed in accordance with the following technical requirements.
[0030] Step 2: See Figure 1 and Figure 2 As shown, the pouring surface is below the arc section and is poured according to the side wall 4 scheme. The vertical height of each pouring shall not exceed 600mm (such as Figure 1 The first and second times are shown in the figure), the pouring height of the arc section shall not exceed 500mm each time (such as Figure 1 The third and fourth displays in the figure).
[0031] Step 3: Two templates need to be added at the arch foot, namely the first template 1 and the second template 2.
[0032] Step 4, after the side wall 4 is poured to the arc section, that is, after the fourth pouring is completed, start pouring the concrete of the arch platen 10. The concrete of the arch platen 10 is 6m wide in total. Isolation nets 9 are fixed on both sides to block the flow of concrete (the slump of the concrete of the arch platen 10 should be appropriately reduced). Pour 150mm each time, and pour to 600mm in four times, corresponding to the fifth to eighth pouring of the arch foot. After the arch foot is flattened, the concrete of the arch platen 10 is poured to 600mm thick, and the remaining 200mm is used for finishing.
[0033] Step 5: See Figure 3 As shown, after the arch foot is cast, the arc top plate 20 is cast from the reserved holes 32 of the first template 1 and the second template 2, the first template 1 is filled, and the reserved holes 32 are blocked at the same time. After the blocking is completed, the second template 2 is cast until the casting of the two templates is completed, and the remaining arc segments 30 are cast.
[0034] Step 6: The remaining arc segments 30 should be poured from the upper side of the isolation net 9 and the concrete of the arch plate 10, and poured by the fluidity of the concrete (such as Figure 3 As shown in A in the figure), the pouring has reached the finishing stage and the slump of concrete is appropriately reduced.
[0035] Step 7. After the surface of the top plate is cured, smooth it with a wooden trowel to remove excess moisture. After the concrete has finally set and people can step on it without sinking, smooth it with an iron trowel and cover it with a film or geotextile for maintenance.
[0036] It is worth noting that pouring needs to be done symmetrically on both sides at the same time, and pouring from one end to the other. Biased pressure is strictly prohibited, and the whole slab is poured. When pouring the part of the arch foot with the external mold, the slump of concrete should be appropriately increased to ensure that the part with the external mold is poured densely. The slump of concrete needs to be adjusted in time with the pouring progress. The on-duty personnel and the pouring team should establish a good communication channel to ensure the workability of the concrete. The arch foot part is the part with the greatest force, and the pouring height must be strictly controlled during pouring.
[0037] In summary, the utility model installs a segmented formwork for casting the arc-shaped top plate on the outside of the arch, so that the force at the arch foot during the casting process can be controlled, and the force at the arch foot is not increased due to one-time casting, thereby further ensuring the density of casting.
[0038] The above are only preferred embodiments of the present invention, and do not limit the implementation mode and protection scope of the present invention. Those skilled in the art should be aware that all solutions obtained by equivalent substitutions and obvious changes made using the description and illustrations of the present invention should be included in the protection scope of the present invention.
Claims
1. A concrete pouring template for the arc-shaped top slab of a station main structure, characterized in that: include: A first template, wherein the first template has a first mounting portion; at least one second template, the second template having a second mounting portion; in A sealing plate is detachably and movably arranged between the first mounting portion of the first template and the second mounting portion of the second template, and a reserved hole is formed between the first template and the second template.
2. The arc-shaped top slab concrete pouring template of the station main structure according to claim 1 is characterized in that: It also includes vertical side walls, a middle plate at the bottom, a curved casting bottom template supported by a bracket above the middle plate, and a curved support rail located above the curved casting bottom template and having a curvature consistent with that of the curved casting bottom template. The first template and the second template are connected to the curved support rail and are close to the arch foot.
3. The arc-shaped top slab concrete pouring template of the station main structure according to claim 2 is characterized in that: One end of the first template contacts the flattened surface of the arch foot after the pouring is completed or is flush with the flattened surface.
4. The arc-shaped top slab concrete pouring template of the station main structure according to claim 2 is characterized in that: A side wall arch foot casting section is formed between the side wall and the arc-shaped casting bottom template.
5. The arc-shaped top slab concrete pouring template of the station main structure according to claim 2 is characterized in that: An arc-shaped casting section is formed between the arc-shaped casting bottom template and the arc-shaped supporting guide rail.
6. The arc-shaped top slab concrete pouring template of the station main structure according to claim 5 is characterized in that: The top position directly above the arc-shaped casting section is the arch pressure plate casting section.
7. The arc-shaped top slab concrete pouring template of the station main structure according to claim 6 is characterized in that: When pouring the vault pressure plate casting section, an isolation net is installed.
8. The arc-shaped top slab concrete pouring template of the station main structure according to claim 2 is characterized in that: The first template and the second template are connected to the arc-shaped support rail through a first fastener.
9. The arc-shaped top slab concrete pouring template of the station main structure according to claim 1, characterized in that: The sealing plate is connected to the first template and the second template via a second fastener.