Anti-blocking cyclone preheater

By linking the receiving and dispersing components, the problem of blockage in the conical part of the cyclone preheater was solved, enabling smooth discharge of cement raw materials and improving production efficiency.

CN222069314UInactive Publication Date: 2024-11-26GUANGDONG QINGYUAN GUANGYING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420576150.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-23
Publication Date
2024-11-26
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing cyclone preheater cannot effectively clear the conical part of the cyclone preheater, resulting in poor material discharge and affecting normal production.

Method used

An anti-clogging cyclone preheater was designed, comprising a receiving component, a dispersing component, and a linkage component. The elasticity of the receiving component drives the connecting rod and rotating rod system to disperse the contents of the cyclone preheater and the discharge pipe, thereby preventing blockage.

Benefits of technology

It effectively prevents cement raw materials from accumulating and clogging inside the cyclone preheater and in the discharge pipe, ensuring smooth discharge and improving production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222069314U_ABST
    Figure CN222069314U_ABST
Patent Text Reader

Abstract

The utility model provides an anti-blocking cyclone preheater, and relates to the technical field of cyclone preheaters, the anti-blocking cyclone preheater comprises a cyclone preheater body, a material receiving assembly and a scattering assembly, the top of the cyclone preheater body is communicated with a feeding hopper, and the bottom of the cyclone preheater body is communicated with a discharging pipe; a linkage assembly is arranged between the material receiving assembly and the scattering assembly; when the cyclone preheater is used, cement raw materials are added into the cyclone preheater body from the feeding hopper, the cement raw materials are preheated, decomposed and fall in the cyclone preheater body, the cement raw materials impact the material receiving piece in the falling process, the material receiving piece drives the connecting rod to repeatedly move up and down under the elastic force action of the spring, and the connecting rod drives the first rotating rod to rotate through the linkage assembly; the first rotating rod drives the first scattering rod to rotate, the first scattering rod scatters the cement raw materials on the lower portion in the cyclone preheater body, the cement raw materials are prevented from being accumulated and blocked on the lower portion in the cyclone preheater body, and smooth discharging is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of cyclone preheaters, and in particular to a blockage-resistant cyclone preheater. Background Art

[0002] In the cement production process, cyclone preheaters are used to preheat cement raw materials, which is helpful for the production and processing of cement; for example, Chinese patent CN202120322529.0 discloses a cyclone preheater for cement product production, and the disclosed technical solution includes: a cyclone preheater shell, the upper end of the cyclone preheater shell is provided with a first feed pipe, and the outer wall of the cyclone preheater shell is provided with a second feed pipe, and the lower end of the cyclone preheater shell is provided with an upper connecting seat, the lower end of the upper connecting seat is provided with an annular fixed sleeve, and the lower end of the fixed sleeve is provided with a lower connecting seat, and the outer wall of the fixed sleeve is installed with a reducer, the outer wall of the reducer is provided with a motor, and the other side of the reducer is provided with a first transmission gear, the outer part of the first transmission gear is engaged with an annular second transmission gear, and the second transmission gear is provided with a rotating ring inside, and the inner side of the rotating ring is provided with a plurality of material toggling rods. The cyclone preheater for cement product production is provided with a dredging structure inside, which can quickly dredge the blocked discharge pipe, reduce the situation where the discharge pipe is blocked, and improve the flow efficiency of the material.

[0003] This prior art has certain drawbacks during use. Although this type of cyclone preheater can clear a blocked discharge pipe, since the top of the discharge pipe is in an inverted cone shape, blockage may occasionally occur. This type of cyclone preheater cannot clear the tapered portion of the cyclone preheater, which may easily cause poor discharge and affect normal production. Summary of the invention

[0004] The purpose of the embodiments of the present application is to provide a cyclone preheater that is anti-clogging, which can solve the technical problem in the prior art that the conical portion of the cyclone preheater cannot be unblocked.

[0005] The embodiment of the present application provides a cyclone preheater with anti-blocking, comprising a cyclone preheater body, a material receiving assembly and a scattering assembly, wherein the top of the cyclone preheater body is connected to a feed hopper, and the bottom of the cyclone preheater body is connected to a discharge pipe;

[0006] The material receiving assembly comprises a mounting block, a spring, a material receiving piece and a connecting rod, wherein the mounting block is fixedly arranged in the body of the cyclone preheater, the material receiving piece is located below the mounting block, the spring is pre-pressed between the mounting block and the material receiving piece, and the connecting rod is fixedly arranged on the material receiving piece;

[0007] The breaking up assembly comprises a first rotating rod and a plurality of first breaking up rods, wherein the first rotating rod is located below the material receiving member, the first breaking up rod is fixedly arranged on the first rotating rod, and the first breaking up rod is located at the lower inner part of the cyclone preheater body;

[0008] A linkage component is arranged between the material receiving component and the scattering component.

[0009] In which, the linkage assembly includes an installation chamber, a installation rod, a rack, a flat gear, a second rotating rod, a first bevel gear and a second bevel gear, the installation chamber is located between the material receiving piece and the first breaking up rod, the installation rod is fixedly arranged between the installation chamber and the cyclone preheater body, the connecting rod slides through the installation chamber, the rack is located in the installation chamber, and the rack is fixedly arranged on the connecting rod, the second rotating rod is rotatably arranged in the installation chamber through a bearing, the flat gear is fixedly sleeved on the second rotating rod, and the flat gear is meshingly connected with the rack, the first bevel gear is fixedly arranged on the second rotating rod, one end of the first rotating rod is rotatably arranged in the installation chamber through a bearing, the other end of the first rotating rod rotates through the installation chamber and extends out of the installation chamber, the second bevel gear is located in the installation chamber, and the second bevel gear is fixedly sleeved on the first rotating rod, and the second bevel gear is meshingly connected with the first bevel gear.

[0010] Wherein, the breaking up assembly also includes a plurality of second breaking up rods, the second breaking up rods are fixedly arranged on the first rotating rod, and the second breaking up rods are located in the discharge pipe.

[0011] Wherein, a scraper rod is fixedly arranged on the first rotating rod, and the scraper rod abuts against the inner wall of the cyclone preheater body.

[0012] Wherein, the mounting block is arranged in a cone shape.

[0013] Wherein, the top of the installation chamber is arranged in a cone shape.

[0014] Wherein, a supporting leg is fixedly provided at the lower end of the cyclone preheater body.

[0015] Beneficial effects of the utility model:

[0016] The utility model provides an anti-blocking cyclone preheater. When in use, cement raw materials are added into the cyclone preheater body from a feed hopper. The cement raw materials are preheated, decomposed and fall in the cyclone preheater body. In the process of falling, the cement raw materials hit a material receiving piece. Under the elastic force of a spring, the material receiving piece drives a connecting rod to move up and down repeatedly. The connecting rod drives a first rotating rod to rotate through a linkage assembly. The first rotating rod drives a first breaking rod to rotate. The first breaking rod breaks up the cement raw materials in the lower part of the cyclone preheater body to prevent the cement raw materials from accumulating and blocking in the lower part of the cyclone preheater body, thereby ensuring smooth discharge. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 This is a schematic diagram of the overall structure of some embodiments of the present application;

[0019] Figure 2 for Figure 1 A schematic diagram of the enlarged structure at point A;

[0020] Figure 3 It is a schematic diagram of the top view of the material receiving member in some embodiments of the present application.

[0021] The reference numerals are:

[0022] 1. Cyclone preheater body; 11. Feed hopper; 12. Discharge pipe; 13. Support legs;

[0023] 2. Material receiving assembly; 21. Mounting block; 22. Spring; 23. Material receiving piece; 24. Connecting rod;

[0024] 3. Scattering assembly; 31. First rotating rod; 32. First scattering rod; 33. Second scattering rod; 34. Scraping rod;

[0025] 4. linkage assembly; 41. mounting chamber; 42. mounting rod; 43. rack; 44. flat gear; 45. second rotating rod; 46. first bevel gear; 47. second bevel gear. DETAILED DESCRIPTION

[0026] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.

[0027] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.

[0028] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0029] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the application is usually placed when in use. They are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as a limitation on the present application. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0030] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0031] In the description of this application, it should also be noted that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0032] like Figure 1 and 3As shown, the embodiment of the present application provides an anti-blocking cyclone preheater, comprising a cyclone preheater body 1, a material receiving assembly 2 and a scattering assembly 3, the top of the cyclone preheater body 1 is connected to a feed hopper 11, and the bottom of the cyclone preheater body 1 is connected to a discharge pipe 12;

[0033] The material receiving assembly 2 comprises a mounting block 21, a spring 22, a material receiving piece 23 and a connecting rod 24. The mounting block 21 is fixedly arranged in the cyclone preheater body 1, the material receiving piece 23 is located below the mounting block 21, the spring 22 is pre-pressed between the mounting block 21 and the material receiving piece 23, and the connecting rod 24 is fixedly arranged on the material receiving piece 23;

[0034] The breaking up assembly 3 includes a first rotating rod 31 and a plurality of first breaking up rods 32. The first rotating rod 31 is located below the material receiving member 23. The first breaking up rods 32 are fixedly arranged on the first rotating rod 31. The first breaking up rods 32 are located at the lower part of the inner part of the cyclone preheater body 1.

[0035] A linkage assembly 4 is provided between the material receiving assembly 2 and the scattering assembly 3 .

[0036] When in use, cement raw materials are added into the cyclone preheater body 1 from the feed hopper 11, and the cement raw materials are preheated, decomposed and fall in the cyclone preheater body 1. In the process of falling, the cement raw materials hit the material receiving piece 23. Under the elastic force of the spring 22, the material receiving piece 23 drives the connecting rod 24 to move up and down repeatedly. The connecting rod 24 drives the first rotating rod 31 to rotate through the linkage assembly 4, and the first rotating rod 31 drives the first breaking rod 32 to rotate. The first breaking rod 32 breaks up the cement raw materials in the lower part of the cyclone preheater body 1 to prevent the cement raw materials from accumulating and clogging in the lower part of the cyclone preheater body 1, thereby ensuring smooth discharge.

[0037] like Figure 1 and 2 As shown, in this embodiment, the linkage assembly 4 includes an installation chamber 41, an installation rod 42, a rack 43, a flat gear 44, a second rotating rod 45, a first bevel gear 46 and a second bevel gear 47. The installation chamber 41 is located between the material receiving member 23 and the first scattering rod 32, the installation rod 42 is fixedly arranged between the installation chamber 41 and the cyclone preheater body 1, the connecting rod 24 slides through the installation chamber 41, the rack 43 is located in the installation chamber 41, and the rack 43 is fixedly arranged on the connecting rod 24, and the second rotating rod 45 is rotatably arranged on the installation chamber 41 through a bearing. In the mounting chamber 41, the flat gear 44 is fixedly sleeved on the second rotating rod 45, and the flat gear 44 is meshed with the rack 43, the first bevel gear 46 is fixedly set on the second rotating rod 45, one end of the first rotating rod 31 is rotatably set in the mounting chamber 41 through a bearing, and the other end of the first rotating rod 31 rotates through the mounting chamber 41 and extends out of the mounting chamber 41, the second bevel gear 47 is located in the mounting chamber 41, and the second bevel gear 47 is fixedly sleeved on the first rotating rod 31, and the second bevel gear 47 is meshed with the first bevel gear 46.

[0038] When in use, the material receiving piece 23 drives the connecting rod 24 to move up and down repeatedly, the connecting rod 24 drives the rack 43 to move, the rack 43 drives the flat gear 44 to rotate, the flat gear 44 drives the second rotating rod 45 to rotate, the second rotating rod 45 drives the first bevel gear 46 to rotate, the first bevel gear 46 drives the second bevel gear 47 to rotate, the second bevel gear 47 drives the first rotating rod 31 to rotate, the first rotating rod 31 drives the first breaking rod 32 to rotate, the first breaking rod 32 breaks up the cement raw materials in the lower part of the cyclone preheater body 1 to prevent the cement raw materials from accumulating and clogging in the lower part of the cyclone preheater body 1, and ensure smooth discharge.

[0039] like Figure 1 As shown, in this embodiment, the breaking up assembly 3 also includes a plurality of second breaking up rods 33, the second breaking up rods 33 are fixedly arranged on the first rotating rod 31, and the second breaking up rods 33 are located in the discharge pipe 12; when in use, when the first rotating rod 31 drives the first breaking up rod 32 to rotate, the first rotating rod 31 simultaneously drives the second breaking up rod 33 to rotate, and the first breaking up rod 32 breaks up the cement raw materials in the discharge pipe 12 to prevent the cement raw materials from accumulating and clogging in the discharge pipe 12, thereby further ensuring smooth discharge.

[0040] like Figure 1 As shown, in this embodiment, a scraper rod 34 is fixedly provided on the first rotating rod 31, and the scraper rod 34 abuts against the inner wall of the cyclone preheater body 1; when the first rotating rod 31 drives the first breaking rod 32 to rotate, the first rotating rod 31 simultaneously drives the scraper rod 34 to rotate, and the scraper rod 34 scrapes off the cement raw materials attached to the inner wall of the cyclone preheater body 1, thereby preventing the cement raw materials from adhering to and clogging the inner wall of the cyclone preheater body 1, and further ensuring smooth discharge.

[0041] like Figure 1 As shown, in this embodiment, the mounting block 21 is arranged in a conical shape; the conical mounting block 21 is conducive to reducing the accumulation of materials on the upper end of the mounting block 21.

[0042] like Figure 2 As shown, in this embodiment, the top of the installation chamber 41 is set in a cone shape; the cone-shaped top of the installation chamber 41 is conducive to reducing the accumulation of materials at the upper end of the installation chamber 41.

[0043] like Figure 1 As shown, in this embodiment, a support leg 13 is fixedly provided at the lower end of the cyclone preheater body 1; the support leg 13 supports and protects the cyclone preheater body 1, thereby improving the stability in use.

[0044] Working principle: When the anti-blocking cyclone preheater provided by the present application is in use, cement raw materials are added from the feed hopper 11 into the cyclone preheater body 1, the cement raw materials are preheated and decomposed in the cyclone preheater body 1 and fall, and the cement raw materials hit the material receiving piece 23 during the falling process, and under the elastic force of the spring 22, the material receiving piece 23 drives the connecting rod 24 to move up and down repeatedly, the connecting rod 24 drives the rack 43 to move, the rack 43 drives the flat gear 44 to rotate, the flat gear 44 drives the second rotating rod 45 to rotate, the second rotating rod 45 drives the first bevel gear 46 to rotate, the first bevel gear 46 drives the second bevel gear 47 to rotate, the second bevel gear 47 drives the first rotating rod 31 to rotate, and the first rotating rod 31 drives The first breaking rod 32 is driven to rotate, and the first breaking rod 32 breaks up the cement raw materials in the lower part of the cyclone preheater body 1 to prevent the cement raw materials from accumulating and clogging in the lower part of the cyclone preheater body 1; when the first rotating rod 31 drives the first breaking rod 32 to rotate, the first rotating rod 31 synchronously drives the second breaking rod 33 to rotate, and the first breaking rod 32 breaks up the cement raw materials in the discharge pipe 12 to prevent the cement raw materials from accumulating and clogging in the discharge pipe 12; when the first rotating rod 31 drives the first breaking rod 32 to rotate, the first rotating rod 31 synchronously drives the scraper rod 34 to rotate, and the scraper rod 34 scrapes off the cement raw materials attached to the inner wall of the cyclone preheater body 1 to prevent the cement raw materials from attaching and clogging on the inner wall of the cyclone preheater body 1.

[0045] The above are only preferred embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A cyclone preheater with anti-blocking function, characterized in that: The invention comprises a cyclone preheater body (1), a material receiving assembly (2) and a dispersing assembly (3); the top of the cyclone preheater body (1) is connected to a material feed hopper (11), and the bottom of the cyclone preheater body (1) is connected to a material discharge pipe (12); The material receiving assembly (2) comprises a mounting block (21), a spring (22), a material receiving piece (23) and a connecting rod (24); the mounting block (21) is fixedly arranged in the cyclone preheater body (1); the material receiving piece (23) is located below the mounting block (21); the spring (22) is pre-pressed between the mounting block (21) and the material receiving piece (23); and the connecting rod (24) is fixedly arranged on the material receiving piece (23); The scattering assembly (3) comprises a first rotating rod (31) and a plurality of first scattering rods (32), wherein the first rotating rod (31) is located below the material receiving member (23), the first scattering rods (32) are fixedly arranged on the first rotating rod (31), and the first scattering rods (32) are located at the lower inner part of the cyclone preheater body (1); A linkage component (4) is provided between the material receiving component (2) and the scattering component (3).

2. The anti-blocking cyclone preheater according to claim 1, characterized in that: The linkage assembly (4) comprises a mounting chamber (41), a mounting rod (42), a rack (43), a flat gear (44), a second rotating rod (45), a first bevel gear (46) and a second bevel gear (47); the mounting chamber (41) is located between the material receiving member (23) and the first scattering rod (32); the mounting rod (42) is fixedly arranged between the mounting chamber (41) and the cyclone preheater body (1); the connecting rod (24) slides through the mounting chamber (41); the rack (43) is located in the mounting chamber (41), and the rack (43) is fixedly arranged on the connecting rod (24); the second rotating rod (45) is rotatably arranged in the mounting chamber (41) through a bearing. 1), the flat gear (44) is fixedly sleeved on the second rotating rod (45), and the flat gear (44) is meshingly connected with the rack (43), the first bevel gear (46) is fixedly arranged on the second rotating rod (45), one end of the first rotating rod (31) is rotatably arranged in the installation chamber (41) through a bearing, the other end of the first rotating rod (31) rotates through the installation chamber (41) and extends out of the installation chamber (41), the second bevel gear (47) is located in the installation chamber (41), and the second bevel gear (47) is fixedly sleeved on the first rotating rod (31), and the second bevel gear (47) is meshingly connected with the first bevel gear (46).

3. The anti-blocking cyclone preheater according to claim 1, characterized in that: The breaking up assembly (3) further comprises a plurality of second breaking up rods (33), wherein the second breaking up rods (33) are fixedly arranged on the first rotating rod (31), and the second breaking up rods (33) are located in the discharge pipe (12).

4. The anti-blocking cyclone preheater according to claim 1, characterized in that: A scraper rod (34) is fixedly arranged on the first rotating rod (31), and the scraper rod (34) abuts against the inner wall of the cyclone preheater body (1).

5. The anti-blocking cyclone preheater according to claim 1, characterized in that: The mounting block (21) is arranged in a conical shape.

6. The anti-blocking cyclone preheater according to claim 2, characterized in that: The top of the installation chamber (41) is arranged in a conical shape.

7. The anti-clogging cyclone preheater according to claim 1, characterized in that: A supporting leg (13) is fixedly provided at the lower end of the cyclone preheater body (1).