Composite flue gas purification system with self-cleaning function

By designing a self-cleaning composite flue gas purification system, and utilizing pipeline switching and dilute acid spray backwashing technology, the problem of equipment blockage in the smelting flue gas acid production purification system was solved, realizing online cleaning and automated maintenance, and improving system operating efficiency and safety.

CN222069325UActive Publication Date: 2024-11-26国投金城冶金有限责任公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323632396.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-26
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

In the acid purification system of smelting flue gas, the problems of equipment blockage and poor heat exchange effect, especially the blockage of plate dilute acid heat exchangers and packed towers, lead to increased system operating resistance, increased energy consumption and reduced production capacity. Existing cleaning equipment is time-consuming, labor-intensive and inefficient.

Method used

The design incorporates a self-cleaning composite flue gas purification system. This system achieves online cleaning of the plate-type dilute acid heat exchanger and packed tower through a pipeline switching structure. It utilizes dilute acid spray to backwash the water circulation pipeline. Combined with a backup design for the tank filter, the system automatically detects and controls valve switching to achieve automatic cleaning and maintenance of the equipment.

Benefits of technology

Online cleaning of plate-type dilute acid heat exchangers and packed towers has been achieved, reducing equipment operating resistance and energy consumption, minimizing system downtime and personnel operation difficulty, and improving system start-up rate and production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222069325U_ABST
    Figure CN222069325U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of flue gas treatment or purification equipment, and particularly relates to a composite flue gas purification system with a self-cleaning function. The composite flue gas purification system with the self-cleaning function comprises a packed tower, a first tank type filter and a plate type dilute acid heat exchanger, an air inlet is formed in the lower part of the packed tower; a packing layer, a spraying pipe, a first high-pressure flushing pipe, a mist eliminator and a second high-pressure flushing pipe are sequentially arranged in the packed tower from bottom to top; the bottom end of the packed tower is connected with a first liquid discharge pipe, and a circulating pump is arranged on the first liquid discharge pipe close to the joint of the first liquid discharge pipe and the packed tower. The plate type dilute acid heat exchanger can be cleaned through back flushing of acid or circulating water, the mist eliminator in the packed tower can be flushed, and the phenomenon that a system stops due to the fact that an acid path or a water path in the plate type dilute acid heat exchanger is blocked or equipment is blocked due to accumulation of sundries in the packed tower is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of flue gas treatment or purification equipment, and specifically relates to a composite flue gas purification system with a self-cleaning function. Background Art

[0002] The smelting flue gas acid purification system involves purification towers, drying towers, packed towers and other equipment. Due to the long-term operation of various tower equipment, impurities in the flue gas and circulating water are deposited, causing equipment blockage, which will increase the overall system operation resistance, deteriorate the heat exchange effect, increase energy consumption, reduce production capacity, and restrict the productivity of the enterprise. Therefore, the overall system needs to be shut down regularly.

[0003] In addition, the plate-type dilute acid heat exchanger water circuit uses a cooling tower to cool down, which causes the salt in the water circuit to accumulate over time, and is prone to crystallization and scaling. At the same time, when the plate-type dilute acid heat exchanger is cooled by a cooling tower, the cooling tower adopts a closed cooling method, which causes impurities in the environment to easily enter the water circuit of the plate-type dilute acid heat exchanger, resulting in blockage and scaling of the plates, resulting in poor heat exchange effect. If the plate-type dilute acid heat exchanger is disassembled and cleaned, it will take a long time, and the gasket is difficult to replace during cleaning. If the system has only one plate-type dilute acid heat exchanger, cleaning the plate-type dilute acid heat exchanger is likely to cause the entire system to be shut down, which restricts the productivity of the enterprise and increases energy consumption and labor.

[0004] At the same time, there is no equipment in the prior art that can systematically clean the packed tower and the plate-type dilute acid heat exchanger. If manual cleaning is used, it will be time-consuming, labor-intensive and inefficient.

[0005] To this end, the utility model provides a composite flue gas purification system with a self-cleaning function, which switches the acid circuit and the water circuit in the plate-type dilute acid heat exchanger, and uses a dilute acid spray liquid to flush the scale in the water circulation pipeline, thereby achieving smooth water circulation, and utilizing the high water pressure to flush the acid sludge deposited in the acid circulation pipeline, in order to effectively solve the problems of heat exchanger, nozzle, foam collector, pipeline blockage, etc. without stopping the equipment, thereby reducing pump energy consumption, personnel operation difficulty and operation danger, reducing system shutdown caused by excessively high equipment resistance, and improving the system start-up rate. Utility Model Content

[0006] Based on the technical problems existing in the prior art, the utility model proposes a composite flue gas purification system with a self-cleaning function. By designing a first pipeline switching structure and a second pipeline switching structure, the acid circuit and the water circuit in the plate-type dilute acid heat exchanger can be switched. The plate-type dilute acid heat exchanger can be cleaned by backwashing with acid or circulating water, and the foam collector in the packing tower can also be flushed to avoid system shutdown due to blockage of the acid circuit or the water circuit in the plate-type dilute acid heat exchanger, or blockage of the equipment caused by accumulation of debris in the packing tower.

[0007] Meanwhile, two sets of canister filters are arranged in the utility model, one for backup and the other for use. When the resistance of one canister filter increases, the other one is switched to operate to flush and maintain the original canister filter.

[0008] Based on the above purpose, the utility model adopts the following technical solutions:

[0009] A composite flue gas purification system with a self-cleaning function, comprising a packing tower, a first can filter, and a plate-type dilute acid heat exchanger;

[0010] The packing tower is provided with an air inlet at the bottom and an exhaust port at the top;

[0011] The packed tower is provided with a packing layer, a spray pipe, a first high-pressure flushing pipe, a foam catcher, and a second high-pressure flushing pipe from bottom to top;

[0012] The bottom end of the packing tower is connected to a first liquid discharge pipe, a liquid discharge valve is provided at the connection between the first liquid discharge pipe and the bottom end of the packing tower, and a circulating pump is provided on the first liquid discharge pipe near the connection with the packing tower;

[0013] The bottom end of the first canister filter is an inlet end, and the top end is an outlet end;

[0014] The first liquid discharge pipe is provided with two branches, namely a first branch and a second branch; the first branch is an acid liquid filtering pipeline, and the inlet end of the first tank filter is connected to the first branch through the first liquid inlet pipe;

[0015] The plate-type dilute acid heat exchanger is provided with an acid circulation pipeline and a water circulation pipeline, the acid circulation pipeline and the water circulation pipeline do not intersect, and the acid circulation pipeline and the water circulation pipeline are arranged side by side to achieve heat exchange;

[0016] The plate-type dilute acid heat exchanger is provided with an acid liquid flange inlet A, a circulating water flange outlet B, a circulating water flange inlet C, and an acid liquid flange outlet D; the acid liquid flange inlet A is the inlet end of the acid liquid circulating pipeline in the plate-type dilute acid heat exchanger, and the acid liquid flange outlet D is the outlet end of the acid liquid circulating pipeline in the plate-type dilute acid heat exchanger; the circulating water flange inlet C is the inlet end of the water circulating pipeline in the plate-type dilute acid heat exchanger, and the circulating water flange outlet B is the outlet end of the water circulating pipeline in the plate-type dilute acid heat exchanger;

[0017] The second branch of the first liquid discharge pipe is an acid liquid inlet pipeline, and the second branch is connected to the acid liquid flange inlet A;

[0018] The inlet end of the spray pipe extends out of the packing tower, and the acid liquid flange outlet D is connected to the inlet end of the spray pipe through the acid liquid discharge pipe;

[0019] The outlet end of the first canister filter is connected to the second branch through a second liquid discharge pipe;

[0020] A first pipeline switching structure is provided between the second branch and the circulating water outlet pipe, and a second pipeline switching structure is provided between the acid liquid discharge pipe and the circulating water inlet pipe;

[0021] The first pipeline switching structure and the second pipeline switching structure can realize the circulation switching of the acid circulation pipeline and the water circulation pipeline in the plate-type dilute acid heat exchanger, and backwash the acid circulation pipeline or the water circulation pipeline.

[0022] Furthermore, a first pressure gauge is provided at the exhaust port.

[0023] Furthermore, a plastic filler is provided in the filler layer to increase the contact area between the spray liquid and the smoke.

[0024] Furthermore, the foam collector can adopt the wire mesh foam collector commonly used in the prior art, whose main function is to remove droplets or foam entrained in the gas to ensure mass transfer efficiency, reduce material loss, and improve the working conditions of subsequent equipment. The foam collector described in the utility model has a diameter of DN6800mm and a thickness of 100-3000mm. It can be customized according to the diameter of the packed tower, and can also adopt the commonly used models in the prior art.

[0025] Furthermore, a second pressure gauge is provided on the side wall of the packed tower, and the second pressure gauge is located below the first high-pressure flushing pipe and above the spray pipe, that is, the second high-pressure flushing pipe, the foam catcher, and the first high-pressure flushing pipe are located in the packed tower between the first pressure gauge and the second pressure gauge.

[0026] Furthermore, the bottom of the packed tower is also filled with water for subsequent circulation to form acid liquid (acid liquid can also be used. Since the packed tower is mainly used to adsorb gases such as sulfur dioxide in high-temperature flue gas, the acid liquid can also be sulfuric acid), and the liquid level is lower than the air inlet.

[0027] Furthermore, a first valve is provided on the first liquid inlet pipe, and a third pressure gauge is provided on the first branch near the first liquid inlet pipe.

[0028] Furthermore, the circulating water flange outlet B is connected to the inlet end of the external circulating water storage device through the circulating water outlet pipe; the circulating water flange inlet C is connected to the outlet end of the external circulating water storage device through the circulating water inlet pipe.

[0029] Furthermore, a second valve is provided on the second drain pipe; a first flushing end is also provided at the bottom end of the first tank filter, the first flushing end is connected to a first flushing pipe, and a third valve is provided on the first flushing pipe; when the first tank filter stops running, the first valve and the second valve can be closed, and the third valve can be opened to flush the first tank filter to flush away the acid scale or water scale generated due to long-term operation.

[0030] Furthermore, a fourth valve is provided on the second branch, between the connection between the second liquid discharge pipe and the second branch, and between the connection between the second branch and the first branch.

[0031] Further preferably, in order to facilitate flushing of the first canister filter, the composite flue gas purification system with a self-cleaning function further includes a spare canister filter, the spare canister filter is arranged side by side with the first canister filter, and the spare canister filter has the same structure as the first canister filter, that is, the bottom end of the spare canister filter is the inlet end, and the top end is the outlet end;

[0032] The inlet end of the spare tank filter at the bottom is connected to the first branch through the second liquid inlet pipe, and the outlet end of the spare tank filter at the top is also connected to the second branch through the third liquid discharge pipe;

[0033] The second liquid inlet pipe is provided with a fifth valve, and the third liquid discharge pipe is provided with a sixth valve.

[0034] Furthermore, a second flushing end is provided at the bottom end of the standby tank filter, the second flushing end is connected to a second flushing pipe, and a seventh valve is provided on the second flushing pipe; similarly, when the standby tank filter stops running, the fifth valve and the sixth valve can be closed, and the seventh valve can be opened to flush the inside of the standby tank filter to flush away the acid scale or water scale generated due to long-term operation.

[0035] Further preferably, the first canister filter and the backup canister filter are both provided with a wire mesh inside, which can filter the impurities in the acid path, and the first canister filter and the backup canister filter are used in a standby mode. When the resistance of one canister filter increases, the other one is switched to operate, and the original canister filter is flushed at the same time. The first canister filter and the backup canister filter in the utility model can both be conventional equipment in the art.

[0036] Furthermore, a bypass pipe is provided on the second branch, and the connection between the bypass pipe and the second branch is located between the connection between the third drain pipe and the second branch, and the connection between the second branch and the acid liquid flange inlet A;

[0037] The bypass pipe is provided with two branches, namely the third branch and the fourth branch; the inlet end of the second high-pressure flushing pipe and the inlet end of the first high-pressure flushing pipe both extend out of the packing tower, and the fourth branch is connected to the inlet end of the second high-pressure flushing pipe, and the third branch is connected to the inlet end of the first high-pressure flushing pipe;

[0038] The third branch is provided with an eighth valve, and the fourth branch is provided with a ninth valve.

[0039] Specifically, the first pipeline switching structure includes a first connecting pipe, a second connecting pipe, a fourth pressure gauge arranged on the second branch near the acid liquid flange inlet A, and a fifth pressure gauge arranged on the circulating water outlet pipe at the circulating water flange outlet B;

[0040] The inlet end of the first connecting pipe and the inlet end of the second connecting pipe are both connected to the second branch, and the outlet end of the first connecting pipe and the outlet end of the second connecting pipe are both connected to the circulating water outlet pipe;

[0041] The connection between the inlet end of the second communicating pipe and the second branch is close to the fourth pressure gauge, the connection between the inlet end of the first communicating pipe and the second branch is far from the fourth pressure gauge, and a tenth valve is provided in the pipeline between the connection between the inlet end of the first communicating pipe and the second branch and the connection between the inlet end of the second communicating pipe and the second branch;

[0042] The connection between the outlet end of the first connecting pipe and the circulating water outlet pipe is close to the fifth pressure gauge, the connection between the outlet end of the second connecting pipe and the circulating water outlet pipe is far away from the fifth pressure gauge, and the pipeline between the connection between the outlet end of the first connecting pipe and the circulating water outlet pipe and the connection between the outlet end of the second connecting pipe and the circulating water outlet pipe is provided with an eleventh valve;

[0043] The first connecting pipe is provided with a twelfth valve, and the second connecting pipe is provided with a thirteenth valve.

[0044] Specifically, the second pipeline switching structure includes a third connecting pipe, a fourth connecting pipe, a sixth pressure gauge arranged on the circulating water inlet pipe near the circulating water flange inlet C, and a seventh pressure gauge arranged on the acid liquid discharge pipe near the acid liquid flange outlet D;

[0045] The inlet end of the third connecting pipe and the inlet end of the fourth connecting pipe are both connected to the circulating water inlet pipe, and the outlet end of the third connecting pipe and the outlet end of the fourth connecting pipe are both connected to the acid liquid discharge pipe;

[0046] The connection between the inlet end of the third connecting pipe and the circulating water inlet pipe is close to the sixth pressure gauge, the connection between the inlet end of the fourth connecting pipe and the circulating water inlet pipe is far away from the sixth pressure gauge, and a fourteenth valve is provided in the pipeline between the connection between the inlet end of the third connecting pipe and the circulating water inlet pipe and the connection between the inlet end of the fourth connecting pipe and the circulating water inlet pipe;

[0047] The connection between the outlet end of the fourth connecting pipe and the acid liquid discharge pipe is close to the seventh pressure gauge, the connection between the outlet end of the third connecting pipe and the acid liquid discharge pipe is far away from the seventh pressure gauge, and a fifteenth valve is provided in the pipeline between the connection between the outlet end of the third connecting pipe and the acid liquid discharge pipe and the connection between the outlet end of the fourth connecting pipe and the acid liquid discharge pipe;

[0048] The third connecting pipe is provided with a sixteenth valve, and the fourth connecting pipe is provided with a seventeenth valve.

[0049] Compared with the prior art, the beneficial effects of the utility model are:

[0050] 1. The cleaning of the plate-type dilute acid heat exchanger in the utility model is online cleaning, and the system does not need to be shut down. The cleaning fluid is the circulating fluid of the plate-type dilute acid heat exchanger itself. The cleaning process does not require the plate-type dilute acid heat exchanger to be disassembled, which not only does not affect the operation of the system, but also reduces the number of times the plate-type dilute acid heat exchanger is disassembled, and at the same time reduces the energy consumption of the circulating pump, as well as the difficulty and danger of personnel operations.

[0051] 2. The utility model can effectively solve the scaling of the water channel in the plate-type dilute acid heat exchanger and the blockage of the acid channel and water channel inlet, reduce the running resistance of the plate-type dilute acid heat exchanger and the energy consumption of the circulation pump, and thus ensure its heat exchange effect.

[0052] 3. The utility model switches the acid circuit and the water circuit in the plate-type dilute acid heat exchanger, and uses dilute acid spraying liquid to flush the scale in the water circulation pipeline, thereby achieving smooth water circulation, and uses the high water pressure to flush the acid sludge deposited in the acid circulation pipeline, effectively solving the blockage problem of the plate-type dilute acid heat exchanger and other packing tower ancillary equipment, avoiding the shutdown of the overall system, as well as the increase of energy consumption and the decrease of production capacity.

[0053] 4. The canister filter provided in the utility model can filter and deposit the acid road sludge to prevent the spraying from being blocked. At the same time, it can be flushed to reduce the resistance increase of the equipment caused by the blockage and the system shutdown.

[0054] 5. The utility model can judge the pipeline pressure and whether it is blocked according to the pressure difference between the pressure gauges. When the pressure difference rises, it means that the water line or the acid line is blocked, and it can be switched and flushed in time according to the production situation; when the pressure difference returns to normal, it will switch back to the original operating state.

[0055] 6. The utility model can effectively solve the clogging problems in the packed tower, the first tank filter, and the plate-type dilute acid heat exchanger, with a high degree of automation. At the same time, it reduces the workload of manual cleaning operations during maintenance, reduces the work intensity of operators, reduces the time for operators to work under acidic liquids, and reduces the risk of safety incidents. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] Figure 1 This is a schematic diagram of the structure of the composite flue gas purification system with self-cleaning function described in Example 1;

[0057] Figure 2 It is a right side view of the plate-type dilute acid heat exchanger;

[0058] Figure 3 is a front view of the plate-type dilute acid heat exchanger;

[0059] Figure 4 A pipeline switching structure flow chart of the first pipeline switching structure;

[0060] Figure 5 A pipeline switching structure flow chart of the second pipeline switching structure;

[0061] Wherein: 1, packing tower, 11, packing layer, 12, spray pipe, 13, first high-pressure flushing pipe, 14, foam catcher, 15, second high-pressure flushing pipe, 16, circulation pump, 17, first branch, 18, second branch, 181, fourth valve, 182, third branch, 183, fourth branch, 184, eighth valve, 185, ninth valve, 186, tenth valve;

[0062] 2. a first tank filter, 21. a first valve, 22. a second valve, 23. a third valve;

[0063] 3. Plate-type dilute acid heat exchanger, 31. Acid discharge pipe, 32. Fifteenth valve;

[0064] 4. Spare canister filter, 41. Fifth valve, 42. Sixth valve, 43. Seventh valve;

[0065] 51. circulating water outlet pipe, 52. circulating water inlet pipe, 53. 11th valve, 54. 14th valve;

[0066] 6. first connecting pipe, 61. twelfth valve;

[0067] 7. Second connecting pipe, 71. Thirteenth valve;

[0068] 8. the third connecting pipe, 81. the sixteenth valve;

[0069] 9. fourth connecting pipe, 91. seventeenth valve;

[0070] 101. a first pressure gauge, 102. a second pressure gauge, 103. a third pressure gauge, 104. a fourth pressure gauge, 105. a fifth pressure gauge, 106. a sixth pressure gauge, 107. a seventh pressure gauge. DETAILED DESCRIPTION

[0071] In order to facilitate the understanding of the present invention, the following will provide a more comprehensive and detailed description of the present invention in conjunction with the accompanying drawings and preferred embodiments of the specification, but the protection scope of the present invention is not limited to the following specific embodiments.

[0072] Unless otherwise defined, all professional terms used below have the same meaning as those generally understood by those skilled in the art. The professional terms used herein are only for the purpose of describing specific embodiments and are not intended to limit the scope of protection of the present utility model.

[0073] Unless otherwise specified, various raw materials, reagents, instruments and equipment used in the present invention can be purchased from the market or prepared by existing methods.

[0074] Example 1

[0075] like Figure 1-5 As shown, a composite flue gas purification system with a self-cleaning function comprises a packing tower 1, a first canister filter 2, and a plate-type dilute acid heat exchanger 3;

[0076] The packed tower 1 is provided with an air inlet at the bottom and an exhaust port at the top, and a first pressure gauge 101 is provided at the exhaust port;

[0077] The packing tower 1 is provided with a packing layer 11, a spray pipe 12, a first high-pressure flushing pipe 13, a foam catcher 14, and a second high-pressure flushing pipe 15 from bottom to top. The packing layer 11 is provided with a plastic packing for increasing the contact area between the spray liquid and the flue gas.

[0078] The foam catcher 14 can adopt the wire mesh foam catcher commonly used in the prior art, and its main function is to remove the droplets or foam entrained in the gas to ensure mass transfer efficiency, reduce material loss, and improve the working conditions of subsequent equipment. The foam catcher 14 described in the utility model has a diameter of DN6800mm and a thickness of 100-3000mm, which can be customized according to the diameter of the packed tower 1, and can also adopt the commonly used models in the prior art, and its structure is not the invention point of the utility model, so it is not repeated;

[0079] The side wall of the packed tower 1 is also provided with a second pressure gauge 102, which is located below the first high-pressure flushing pipe 13 and above the spray pipe 12, that is, the second high-pressure flushing pipe 15, the foam catcher 14, and the first high-pressure flushing pipe 13 are located in the packed tower 1 between the first pressure gauge 101 and the second pressure gauge 102;

[0080] The bottom of the packed tower 1 is also filled with water for subsequent circulation to form acid liquid (acid liquid can also be used. Since the packed tower 1 is mainly used to adsorb gases such as sulfur dioxide in high-temperature flue gas, the acid liquid can also be sulfuric acid), and the liquid level is lower than the air inlet.

[0081] The bottom end of the packed tower 1 is connected to a first liquid discharge pipe, a liquid discharge valve is provided at the connection between the first liquid discharge pipe and the bottom end of the packed tower 1, and a circulating pump 16 is provided on the first liquid discharge pipe near the connection with the packed tower 1;

[0082] The bottom end of the first canister filter 2 is an inlet end, and the top end is an outlet end;

[0083] The first liquid discharge pipe is provided with two branches, namely a first branch 17 and a second branch 18; the first branch 17 is an acid filtering pipeline, the inlet end of the first tank filter 2 is connected to the first branch 17 through a first liquid inlet pipe, a first valve 21 is provided on the first liquid inlet pipe, and a third pressure gauge 103 is provided on the first branch 17 near the first liquid inlet pipe.

[0084] The plate-type dilute acid heat exchanger 3 is provided with an acid circulation pipeline and a water circulation pipeline, the acid circulation pipeline and the water circulation pipeline do not intersect, and the acid circulation pipeline and the water circulation pipeline are arranged side by side to achieve heat exchange, that is, the circulating water in the water circulation pipeline can exchange heat with the acid in the acid circulation pipeline, so as to cool the acid in the acid circulation pipeline;

[0085] Specifically, the plate-type dilute acid heat exchanger 3 described in the utility model is a conventional device. The utility model mainly describes the pipe connection relationship between the plate-type dilute acid heat exchanger 3 and the packing tower 1 and the first tank filter 2. The structure and model thereof can adopt conventional technical means in the art, and are not the inventive point of the utility model, so they will not be described in detail.

[0086] like Figure 3 The figure is a schematic diagram of the main working surface of the plate-type dilute acid heat exchanger 3 of the utility model, wherein the main working surface of the plate-type dilute acid heat exchanger 3 is provided with an acid liquid flange inlet A, a circulating water flange outlet B, a circulating water flange inlet C, and an acid liquid flange outlet D; the acid liquid flange inlet A is the inlet end of the acid liquid circulation pipeline in the plate-type dilute acid heat exchanger 3, and the acid liquid flange outlet D is the outlet end of the acid liquid circulation pipeline in the plate-type dilute acid heat exchanger 3; the circulating water flange inlet C is the inlet end of the water circulation pipeline in the plate-type dilute acid heat exchanger 3, and the circulating water flange outlet B is the outlet end of the water circulation pipeline in the plate-type dilute acid heat exchanger 3;

[0087] The second branch 18 of the first liquid discharge pipe is an acid liquid inlet pipeline, and the second branch 18 is connected to the acid liquid flange inlet A.

[0088] like Figure 4 , 5 As shown, the circulating water flange outlet B is connected to the inlet end of the external circulating water storage device through the circulating water outlet pipe 51; the circulating water flange inlet C is connected to the outlet end of the external circulating water storage device through the circulating water inlet pipe 52;

[0089] The inlet end of the spray pipe 12 extends out of the packing tower 1, and the acid liquid flange outlet D is connected to the inlet end of the spray pipe 12 through the acid liquid discharge pipe 31;

[0090] The outlet end of the first tank filter 2 is connected to the second branch 18 through a second drain pipe, and a second valve 22 is provided on the second drain pipe; the bottom end of the first tank filter 2 is also provided with a first flushing end, the first flushing end is connected to a first flushing pipe, and a third valve 23 is provided on the first flushing pipe; when the first tank filter 2 stops running, the first valve 21 and the second valve 22 can be closed, and the third valve 23 can be opened to flush the first tank filter 2 to flush away the acid scale or scale generated therein due to long-term operation;

[0091] A fourth valve 181 is provided on the second branch 18 , between the connection between the second liquid discharge pipe and the second branch 18 , and between the connection between the second branch 18 and the first branch 17 .

[0092] Further preferably, in order to facilitate flushing of the first canister filter 2, the utility model further includes a spare canister filter 4, which is arranged side by side with the first canister filter 2, and the spare canister filter 4 has the same structure as the first canister filter 2, that is, the bottom end of the spare canister filter 4 is the inlet end, and the top end is the outlet end;

[0093] The inlet end of the bottom end of the spare tank filter 4 is connected to the first branch 17 through the second liquid inlet pipe, and the outlet end of the top end of the spare tank filter 4 is also connected to the second branch 18 through the third liquid discharge pipe;

[0094] A fifth valve 41 is provided on the second liquid inlet pipe, and a sixth valve 42 is provided on the third liquid outlet pipe;

[0095] The bottom end of the standby tank filter 4 is also provided with a second flushing end, the second flushing end is connected to a second flushing pipe, and the second flushing pipe is provided with a seventh valve 43; similarly, when the standby tank filter 4 stops running, the fifth valve 41 and the sixth valve 42 can be closed, and the seventh valve 43 can be opened to flush the inside of the standby tank filter 4 to flush away the acid scale or water scale generated due to long-term operation.

[0096] The first tank filter 2 and the backup tank filter 4 are both provided with a wire mesh inside, which can filter the impurities in the acid path, and the first tank filter 2 and the backup tank filter 4 are used in a backup mode. When the resistance of one tank filter increases, the other tank filter is switched to operate, and the original tank filter is flushed at the same time. The first tank filter 2 and the backup tank filter 4 in the utility model can be conventional equipment in the art, and their structure is not the inventive point of the utility model, so it is not described in detail.

[0097] Furthermore, a bypass pipe is provided on the second branch 18, and the connection between the bypass pipe and the second branch 18 is located between the connection between the third drain pipe and the second branch 18, and the connection between the second branch 18 and the acid liquid flange inlet A;

[0098] The bypass pipe is provided with two branches, namely the third branch 182 and the fourth branch 183; the inlet end of the second high-pressure flushing pipe 15 and the inlet end of the first high-pressure flushing pipe 13 both extend out of the packed tower 1, and the fourth branch 183 is connected to the inlet end of the second high-pressure flushing pipe 15, and the third branch 182 is connected to the inlet end of the first high-pressure flushing pipe 13;

[0099] An eighth valve 184 is provided on the third branch 182 , and a ninth valve 185 is provided on the fourth branch 183 .

[0100] like Figure 4 , 5 As shown, a first pipeline switching structure is provided between the second branch 18 and the circulating water outlet pipe 51, and a second pipeline switching structure is provided between the acid liquid discharge pipe 31 and the circulating water inlet pipe 52;

[0101] Specifically, the first pipeline switching structure includes a first connecting pipe 6, a second connecting pipe 7, a fourth pressure gauge 104 arranged on the second branch 18 near the acid liquid flange inlet A, and a fifth pressure gauge 105 arranged on the circulating water outlet pipe 51 at the circulating water flange outlet B;

[0102] The inlet end of the first connecting pipe 6 and the inlet end of the second connecting pipe 7 are both connected to the second branch 18, and the outlet end of the first connecting pipe 6 and the outlet end of the second connecting pipe 7 are both connected to the circulating water outlet pipe 51;

[0103] The connection between the inlet end of the second connecting pipe 7 and the second branch 18 is close to the fourth pressure gauge 104, the connection between the inlet end of the first connecting pipe 6 and the second branch 18 is far away from the fourth pressure gauge 104, and the pipeline between the connection between the inlet end of the first connecting pipe 6 and the second branch 18 and the connection between the inlet end of the second connecting pipe 7 and the second branch 18 is provided with a tenth valve 186;

[0104] The connection between the outlet end of the first connecting pipe 6 and the circulating water outlet pipe 51 is close to the fifth pressure gauge 105, and the connection between the outlet end of the second connecting pipe 7 and the circulating water outlet pipe 51 is far away from the fifth pressure gauge 105, and the pipeline between the connection between the outlet end of the first connecting pipe 6 and the circulating water outlet pipe 51 and the connection between the outlet end of the second connecting pipe 7 and the circulating water outlet pipe 51 is provided with an eleventh valve 53;

[0105] The first connecting pipe 6 is provided with a twelfth valve 61 , and the second connecting pipe 7 is provided with a thirteenth valve 71 .

[0106] Specifically, the second pipeline switching structure includes a third connecting pipe 8, a fourth connecting pipe 9, a sixth pressure gauge 106 disposed on the circulating water inlet pipe 52 near the circulating water flange inlet C, and a seventh pressure gauge 107 disposed on the acid liquid discharge pipe 31 near the acid liquid flange outlet D;

[0107] The inlet end of the third connecting pipe 8 and the inlet end of the fourth connecting pipe 9 are both connected to the circulating water inlet pipe 52, and the outlet end of the third connecting pipe 8 and the outlet end of the fourth connecting pipe 9 are both connected to the acid liquid discharge pipe 31;

[0108] The connection between the inlet end of the third connecting pipe 8 and the circulating water inlet pipe 52 is close to the sixth pressure gauge 106, and the connection between the inlet end of the fourth connecting pipe 9 and the circulating water inlet pipe 52 is far away from the sixth pressure gauge 106, and the pipeline between the connection between the inlet end of the third connecting pipe 8 and the circulating water inlet pipe 52 and the connection between the inlet end of the fourth connecting pipe 9 and the circulating water inlet pipe 52 is provided with a fourteenth valve 54;

[0109] The connection between the outlet end of the fourth connecting pipe 9 and the acid liquid discharge pipe 31 is close to the seventh pressure gauge 107, the connection between the outlet end of the third connecting pipe 8 and the acid liquid discharge pipe 31 is far away from the seventh pressure gauge 107, and the pipeline between the connection between the outlet end of the third connecting pipe 8 and the acid liquid discharge pipe 31 and the connection between the outlet end of the fourth connecting pipe 9 and the acid liquid discharge pipe 31 is provided with a fifteenth valve 32;

[0110] The third connecting pipe 8 is provided with a sixteenth valve 81 , and the fourth connecting pipe 9 is provided with a seventeenth valve 91 .

[0111] The operating principle of the utility model:

[0112] 1. Flue gas purification process: In this process, the high-temperature acid-containing flue gas first enters from the air inlet of the packing tower 1 and then flows upward. At this time, the drain valve and the circulation pump 16 are opened, and the water (or acid liquid) at the bottom of the packing tower 1 is discharged from the first drain pipe for use as a spray liquid. At this time, the fourth valve 181, the third valve 23, the fifth valve 41, the sixth valve 42, the seventh valve 43, the eighth valve 184, the ninth valve 185, the twelfth valve 61, the thirteenth valve 71, the sixteenth valve 81, and the seventeenth valve 91 are closed;

[0113] Open the first valve 21, the second valve 22, the tenth valve 186, the eleventh valve 53, the fourteenth valve 54, and the fifteenth valve 32;

[0114] The spray liquid first enters from the inlet end of the lower end of the first tank filter 2 and is discharged from the outlet end of the top end, passing through the first tank filter 2. The first tank filter 2 is provided with a wire mesh inside, which can filter the impurities of the spray liquid. The filtered spray liquid passes through the second branch 18 from the acid flange inlet A to the acid circulation pipeline in the plate-type dilute acid heat exchanger 3. At this time, the cooling circulating water from the external circulating water storage device enters from the circulating water flange inlet C to the water circulation pipeline in the plate-type dilute acid heat exchanger 3 through the circulating water inlet pipe 52, and the spray liquid in the acid circulation pipeline is heat exchanged and cooled by the cooling circulating water;

[0115] The spray liquid after cooling is discharged from the acid liquid flange outlet D, and enters the spray pipe 12 through the acid liquid discharge pipe 31, and then sprays from the spray pipe 12. The spray liquid enters the packing layer 11 and contacts with the rising high-temperature acid-containing flue gas, and adsorbs sulfur dioxide and other gases therein to purify the gas. The purified gas continues to rise. When passing through the foam catcher 14, the foam catcher 14 can adsorb the acid foam entrained in the flue gas when passing through the packing layer 11, so as to prevent the flue gas from entraining acid foam. Finally, the flue gas after purification and adsorption is discharged from the exhaust port in compliance with the standards;

[0116] At the same time, the cooling circulating water after heat exchange is discharged from the circulating water flange outlet B, and enters the external circulating water storage device again through the circulating water outlet pipe 51 for recycling.

[0117] 2. Backwashing process of plate-type dilute acid heat exchanger 3: After the system has been running for a period of time, scale or other impurities in the cooling circulating water will remain in the water circulation pipeline of the plate-type dilute acid heat exchanger 3, causing the pipeline to be blocked. At the same time, the acid circulation pipeline may also be blocked due to impurities in the spray liquid (acid). At this time, by adjusting the first pipeline switching structure and the second pipeline switching structure, the scale in the water circulation pipeline is flushed with dilute acid spray liquid, thereby achieving smooth water circulation; the specific adjustment is:

[0118] When the pressure difference displayed by the fifth pressure gauge 105 and the sixth pressure gauge 106 rises too much, or the pressure difference displayed by the fourth pressure gauge 104 and the seventh pressure gauge 107 rises too much, it indicates that a blockage has occurred in the water circulation pipeline or the acid circulation pipeline of the plate-type dilute acid heat exchanger 3. At this time, the fourth valve 181, the third valve 23, the eighth valve 184, the ninth valve 185, the fifth valve 41, the sixth valve 42, the seventh valve 43, the tenth valve 186, the eleventh valve 53, the fourteenth valve 54, and the fifteenth valve 32 are closed;

[0119] At the same time, open the drain valve, the circulation pump 16, the first valve 21, the second valve 22, the twelfth valve 61, the thirteenth valve 71, the sixteenth valve 81, and the seventeenth valve 91;

[0120] At this time, if Figure 4 , 5 As shown, the spray liquid entering the second branch 18 enters from the inlet end of the first connecting pipe 6, then flows into the circulating water outlet pipe 51, and reversely enters the water circulation pipeline of the plate-type dilute acid heat exchanger 3 from the circulating water flange outlet B, and then reversely flows out from the circulating water flange inlet C, using the corrosiveness of the acid to achieve backwashing of the water circulation pipeline and corrode away the scale;

[0121] After the spray liquid flows out from the circulating water flange inlet C, it enters the acid liquid discharge pipe 31 through the third connecting pipe 8, and then enters the spray pipe 12, sprays out from the spray pipe 12, and is collected at the bottom of the packed tower 1;

[0122] At the same time, the cooling circulating water flows from the external circulating water storage device, sequentially passes through the circulating water inlet pipe 52, the fourth connecting pipe 9, the acid liquid discharge pipe 31, and reversely flows from the acid liquid flange outlet D into the acid liquid circulating pipeline of the plate-type dilute acid heat exchanger 3, and the blockage in the acid liquid circulating pipeline is backwashed out by the cooling circulating water, and then flows out from the acid liquid flange inlet A in reverse direction;

[0123] After the cooling circulating water flows out from the acid liquid flange inlet A, it enters the circulating water outlet pipe 51 through the second connecting pipe 7, and then enters the external circulating water storage device again through the circulating water outlet pipe 51 for recycling.

[0124] When the pressure difference displayed by the fifth pressure gauge 105 and the sixth pressure gauge 106, or the pressure difference displayed by the fourth pressure gauge 104 and the seventh pressure gauge 107 returns to the original pressure difference, it means that the impurities and scale have been flushed and the original valve operation mode can be switched back to carry out the above-mentioned flue gas purification process.

[0125] 3. Maintenance and cleaning process of the first tank filter 2: After the system has been running for a period of time, due to the presence of some impurities in the spray liquid (acid solution), flow resistance appears in the first tank filter 2. By switching the pipelines between the packing tower 1, the first tank filter 2, the spare tank filter 4, and the plate-type dilute acid heat exchanger 3, the first tank filter 2 is cleaned and maintained; the specific operations are as follows:

[0126] When the pressure difference displayed by the fourth pressure gauge 104 and the third pressure gauge 103 rises too much, it indicates that the first tank filter 2 is clogged. At this time, the first valve 21, the second valve 22, the third valve 23, the eighth valve 184, the ninth valve 185, the fifth valve 41, the sixth valve 42, and the seventh valve 43 are closed;

[0127] Open the drain valve, the circulation pump 16, the fourth valve 181, the tenth valve 186, the eleventh valve 53, the fourteenth valve 54, and the fifteenth valve 32;

[0128] The spray liquid passes through the second branch 18 and the acid liquid flange inlet A in sequence and enters the plate-type dilute acid heat exchanger 3 to undergo the aforementioned normal flue gas purification process.

[0129] In addition, when the pressure difference displayed by the fourth pressure gauge 104 and the third pressure gauge 103 rises too large, the drain valve, the circulation pump 16, the fifth valve 41, the sixth valve 42, the tenth valve 186, the eleventh valve 53, the fourteenth valve 54, and the fifteenth valve 32 may also be opened;

[0130] Close the fourth valve 181, the first valve 21, the second valve 22, the third valve 23, and the seventh valve 43, and use the spare tank filter 4 to replace the first tank filter 2 to remove impurities from the spray liquid (acid liquid), and at the same time maintain and clean the first tank filter 2.

[0131] 4. Cleaning process of the foam catcher 14: When the flue gas rises to the foam catcher 14, a small amount of impurities may remain in the flue gas. After the system has been running for a period of time, excessive impurities may cause the foam catcher 14 to be blocked. At this time, the pressure difference between the first pressure gauge 101 and the second pressure gauge 102 is detected 13 and the exhaust port of the packing tower 1. When the pressure difference displayed by the first pressure gauge 101 and the second pressure gauge 102 rises too much, the foam catcher 14 is blocked. At this time, the drain valve, the circulation pump 16, the first valve 21, the second valve 22, the eighth valve 184, and the ninth valve 185 are opened;

[0132] Close the tenth valve 186, the third valve 23, the fifth valve 41, the sixth valve 42 and the seventh valve 43; at this time, the spray liquid passes through the second branch 18, the third branch 182, the fourth branch 183 in sequence, and is sprayed out from the first high-pressure flushing pipe 13 and the second high-pressure flushing pipe 15 to flush the foam catcher 14.

[0133] All valves in the utility model use acid-resistant material valves to prevent equipment corrosion. In addition, in order to improve the degree of automation of the overall system, all valves in the utility model can also use electric acid-resistant valves, and can also use the DCS system for interlocking control. The specific electric control method is not the invention point of the utility model, so it will not be repeated.

[0134] The utility model respectively arranges a second high-pressure flushing pipe 15 and a first high-pressure flushing pipe 13 at the upper part of the packed tower 1 and above and below the foam catcher 14, so that when the resistance of the foam catcher 14 increases, the foam catcher 14 in the packed tower 1 can be reversely flushed regularly to reduce equipment blockage caused by accumulation of debris.

[0135] A circulation pump 16 is provided on the first liquid discharge pipe of the packed tower 1, which can pump out the spray liquid (acid liquid) in the packed tower 1 and enter the first tank filter 2. When flow resistance appears in the first tank filter 2, the pipelines among the packed tower 1, the first tank filter 2, the spare tank filter 4 and the plate-type dilute acid heat exchanger 3 are switched to switch to the spare tank filter 4 for operation, and the first tank filter 2 is cleaned and maintained at the same time.

[0136] When the water circulation pipeline or the acid circulation pipeline in the plate-type dilute acid heat exchanger 3 has increased resistance, the first pipeline switching structure and the second pipeline switching structure can be directly adjusted and the valve can be switched to switch the water circulation pipeline and the acid circulation pipeline, and the original water circuit can be changed to the acid circuit, and the original acid circuit can be changed to the water circuit. The scale in the water circulation pipeline is flushed with dilute acid spray liquid, so as to achieve smooth water circulation, and the acid sludge deposited in the acid circulation pipeline is flushed by utilizing the high water pressure. At the same time, the original inlet is changed to the outlet, and the original outlet is changed to the inlet, and the original inlet of the plate-type dilute acid heat exchanger 3 is backwashed.

[0137] The utility model also adds pressure gauges above and below the foam catcher 14, at the inlet and outlet of the water circulation pipeline or the acid circulation pipeline of the plate-type dilute acid heat exchanger 3, and at the inlet and outlet of the first tank filter 2. By detecting the pressure difference change, the blockage situation in each device can be judged in time, which is convenient for guiding the valve switching time and ensuring the normal operation of the equipment.

[0138] In addition, during the backwashing process of the plate-type dilute acid heat exchanger 3, an external, relatively clean acid solution can also be used to improve the flushing effect. At this time, no excess water is added to the system to achieve system water balance.

[0139] The composite flue gas purification system with self-cleaning function described in the utility model aims to solve the problem of clogging of the plate-type dilute acid heat exchanger 3 pipeline due to dilute acid or circulating water heat exchange, or clogging of the tower body or scaling of the packing in the packed tower 1 due to acid spraying in the smelting flue gas acid purification system used in the smelting flue gas treatment process.

[0140] The utility model adopts pressure detection, pipeline switching, flushing and other technical means to a certain extent solve the problems of scaling and blockage of the acid circuit or water circuit of the plate-type dilute acid heat exchanger 3, blockage of the spray equipment, blockage of the foam collector and the like in the existing production process; it avoids the problems of increased operation resistance and poor heat exchange effect caused by equipment blockage, which in turn causes difficulties in personnel operation, increased production energy consumption, and restricted productivity. At the same time, it can reduce the number of disassembly times of the plate-type dilute acid heat exchanger 3, as well as the equipment downtime and shutdown maintenance time.

[0141] The system of the utility model can monitor the pressure difference between the inlet and outlet of the equipment in real time. The material of the pipeline in the whole system is connected by acid-resistant material to prevent corrosion. At the same time, the pressure gauge and other detection components can be detected online and displayed on the spot. The utility model can realize the online cleaning of the packing tower 1 and its auxiliary equipment without affecting the normal operation of the whole system.

[0142] The system of the utility model has a simple structure and is easy to operate, and can be applied to the cleaning and maintenance of various smelting fume systems.

[0143] Application Example 1

[0144] Taking a copper smelting production enterprise as an example, the flue gas generated by the copper smelting furnace is cooled by the waste heat boiler, and then enters the acid production section after the electrostatic precipitator and bag filter collect dust. After the flue gas is cooled and dusted by the first-level dynamic wave cooling and dust removal, it enters the packed tower 1 for further cooling and dust removal, and then enters the second-level dynamic cooling and dust removal. At this time, the heat is accumulated in the packed tower 1, and the heat needs to be taken out by the circulating water through the plate-type dilute acid heat exchanger 3;

[0145] The original design of the plate-type dilute acid heat exchanger 3 was to have two units in operation and one in standby. After the heat exchange effect deteriorated, three units were changed to be started at the same time. The foam collector 14 was blocked and the system needed to be stopped for flushing. In addition, due to the accumulation of impurities, the nozzle of the spray system was blocked and the packing layer 11 was compacted. When the heat exchange effect of the plate-type dilute acid heat exchanger 3 deteriorated, the system needed to be disconnected for disassembly and cleaning. However, as time went by, the operating frequency of the circulating water pump 16 increased, the energy consumption increased, and acid sludge was deposited at the bottom of the tower body, requiring the system to be stopped for inspection, cleaning, and maintenance.

[0146] After the transformation, the composite flue gas purification system with self-cleaning function described in the utility model is adopted, the plate-type dilute acid heat exchanger 3 is restored to the original design of two-on and one-standby state, the smear collector 14 can be cleaned online, and the system operation time is extended, the number of maintenance times is reduced, the start-up rate is increased, and at the same time the pump energy consumption is reduced, the cost is reduced, and the operation is stable.

[0147] In the description of the present invention, it should be noted that directional words, such as the terms "center", "lateral", "longitudinal", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", etc., indicating directions and positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of narrating the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and cannot be understood as limiting the specific protection scope of the present invention.

[0148] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged in appropriate circumstances, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, the process, method, system, product or equipment comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or equipment.

[0149] Finally, it should be noted that the above are only preferred embodiments and application technical principles of the utility model. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described here, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the utility model. Therefore, although the utility model is described in more detail through the above embodiments, the utility model is not limited to the specific embodiments described here, and may include more other effective embodiments without departing from the concept of the utility model, and the scope of the utility model is determined by the scope of the attached claims.

Claims

1. A composite flue gas purification system with self-cleaning function, It is characterized in that It includes a packed tower, a first tank filter, and a plate-type dilute acid heat exchanger; The packing tower is provided with an air inlet at the bottom and an exhaust port at the top; The packed tower is provided with a packing layer, a spray pipe, a first high-pressure flushing pipe, a foam catcher, and a second high-pressure flushing pipe from bottom to top; The bottom end of the packing tower is connected to a first liquid discharge pipe, a liquid discharge valve is provided at the connection between the first liquid discharge pipe and the bottom end of the packing tower, and a circulating pump is provided on the first liquid discharge pipe near the connection with the packing tower; The bottom end of the first canister filter is an inlet end, and the top end is an outlet end; The first liquid discharge pipe is provided with two branches, namely a first branch and a second branch; the first branch is an acid liquid filtering pipeline, and the inlet end of the first tank filter is connected to the first branch through the first liquid inlet pipe; The plate-type dilute acid heat exchanger is provided with an acid circulation pipeline and a water circulation pipeline, the acid circulation pipeline and the water circulation pipeline do not intersect, and the acid circulation pipeline and the water circulation pipeline are arranged side by side to achieve heat exchange; The plate-type dilute acid heat exchanger is provided with an acid liquid flange inlet A, a circulating water flange outlet B, a circulating water flange inlet C, and an acid liquid flange outlet D; the acid liquid flange inlet A is the inlet end of the acid liquid circulating pipeline in the plate-type dilute acid heat exchanger, and the acid liquid flange outlet D is the outlet end of the acid liquid circulating pipeline in the plate-type dilute acid heat exchanger; the circulating water flange inlet C is the inlet end of the water circulating pipeline in the plate-type dilute acid heat exchanger, and the circulating water flange outlet B is the outlet end of the water circulating pipeline in the plate-type dilute acid heat exchanger; The second branch of the first liquid discharge pipe is an acid liquid inlet pipeline, and the second branch is connected to the acid liquid flange inlet A; The inlet end of the spray pipe extends out of the packing tower, and the acid liquid flange outlet D is connected to the inlet end of the spray pipe through the acid liquid discharge pipe; The outlet end of the first canister filter is connected to the second branch through a second liquid discharge pipe; A first pipeline switching structure is provided between the second branch and the circulating water outlet pipe, and a second pipeline switching structure is provided between the acid liquid discharge pipe and the circulating water inlet pipe; The first pipeline switching structure and the second pipeline switching structure can realize the circulation switching of the acid circulation pipeline and the water circulation pipeline in the plate-type dilute acid heat exchanger, and backwash the acid circulation pipeline or the water circulation pipeline.

2. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that A first pressure gauge is provided at the exhaust port; a second pressure gauge is also provided on the side wall of the packing tower, and the second pressure gauge is located below the first high-pressure flushing pipe and above the spray pipe.

3. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that The first liquid inlet pipe is provided with a first valve, and the first branch road is provided with a third pressure gauge at a position close to the first liquid inlet pipe.

4. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that A second valve is arranged on the second liquid discharge pipe; a first flushing end is also arranged at the bottom end of the first tank filter, the first flushing end is connected to a first flushing pipe, and a third valve is arranged on the first flushing pipe.

5. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that A fourth valve is provided on the second branch, between the connection between the second liquid discharge pipe and the second branch, and between the connection between the second branch and the first branch.

6. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that It also includes a spare canister filter, which is arranged side by side with the first canister filter, the bottom end of the spare canister filter is an inlet end, and the top end is an outlet end; The inlet end of the spare tank filter at the bottom is connected to the first branch through the second liquid inlet pipe, and the outlet end of the spare tank filter at the top is also connected to the second branch through the third liquid discharge pipe; The second liquid inlet pipe is provided with a fifth valve, and the third liquid discharge pipe is provided with a sixth valve.

7. The composite flue gas purification system with self-cleaning function according to claim 6, It is characterized in that The bottom end of the standby tank filter is also provided with a second flushing end, the second flushing end is connected with a second flushing pipe, and the second flushing pipe is provided with a seventh valve.

8. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that The second branch is also provided with a bypass pipe, and the connection between the bypass pipe and the second branch is located between the connection between the third drain pipe and the second branch, and the connection between the second branch and the acid liquid flange inlet A; The bypass pipe is provided with two branches, namely the third branch and the fourth branch; the inlet end of the second high-pressure flushing pipe and the inlet end of the first high-pressure flushing pipe both extend out of the packing tower, and the fourth branch is connected to the inlet end of the second high-pressure flushing pipe, and the third branch is connected to the inlet end of the first high-pressure flushing pipe; The third branch is provided with an eighth valve, and the fourth branch is provided with a ninth valve.

9. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that The first pipeline switching structure includes a first connecting pipe, a second connecting pipe, a fourth pressure gauge arranged on the second branch near the acid liquid flange inlet A, and a fifth pressure gauge arranged on the circulating water outlet pipe at the circulating water flange outlet B; The inlet end of the first connecting pipe and the inlet end of the second connecting pipe are both connected to the second branch, and the outlet end of the first connecting pipe and the outlet end of the second connecting pipe are both connected to the circulating water outlet pipe; The connection between the inlet end of the second connecting pipe and the second branch is close to the fourth pressure gauge, the connection between the inlet end of the first connecting pipe and the second branch is far away from the fourth pressure gauge, and the pipeline between the connection between the inlet end of the first connecting pipe and the second branch and the connection between the inlet end of the second connecting pipe and the second branch is provided with a tenth valve; The connection between the outlet end of the first connecting pipe and the circulating water outlet pipe is close to the fifth pressure gauge, the connection between the outlet end of the second connecting pipe and the circulating water outlet pipe is far away from the fifth pressure gauge, and the pipeline between the connection between the outlet end of the first connecting pipe and the circulating water outlet pipe and the connection between the outlet end of the second connecting pipe and the circulating water outlet pipe is provided with an eleventh valve; The first connecting pipe is provided with a twelfth valve, and the second connecting pipe is provided with a thirteenth valve.

10. The composite flue gas purification system with self-cleaning function according to claim 1, It is characterized in that The second pipeline switching structure includes a third connecting pipe, a fourth connecting pipe, a sixth pressure gauge arranged on the circulating water inlet pipe near the circulating water flange inlet C, and a seventh pressure gauge arranged on the acid liquid discharge pipe near the acid liquid flange outlet D; The inlet end of the third connecting pipe and the inlet end of the fourth connecting pipe are both connected to the circulating water inlet pipe, and the outlet end of the third connecting pipe and the outlet end of the fourth connecting pipe are both connected to the acid liquid discharge pipe; The connection between the inlet end of the third connecting pipe and the circulating water inlet pipe is close to the sixth pressure gauge, the connection between the inlet end of the fourth connecting pipe and the circulating water inlet pipe is far away from the sixth pressure gauge, and a fourteenth valve is provided in the pipeline between the connection between the inlet end of the third connecting pipe and the circulating water inlet pipe and the connection between the inlet end of the fourth connecting pipe and the circulating water inlet pipe; The connection between the outlet end of the fourth connecting pipe and the acid liquid discharge pipe is close to the seventh pressure gauge, the connection between the outlet end of the third connecting pipe and the acid liquid discharge pipe is far away from the seventh pressure gauge, and a fifteenth valve is provided in the pipeline between the connection between the outlet end of the third connecting pipe and the acid liquid discharge pipe and the connection between the outlet end of the fourth connecting pipe and the acid liquid discharge pipe; The third connecting pipe is provided with a sixteenth valve, and the fourth connecting pipe is provided with a seventeenth valve.