Embedded steel plate structure at bottom of plate girder
By using a hinged upper steel plate and wedge plate structure, the problem of leveling the bottom surface of the slab beam was solved, the construction progress was improved, and the delay caused by the wedge steel plate was avoided.
Patent Information
- Application Number
- CN202420189549.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-01-25
AI Technical Summary
In bridge design, due to the presence of longitudinal and transverse slopes, it is difficult to keep the bottom surface of the slab girder level. This necessitates the pre-customization of wedge-shaped steel plates during the installation of precast slab girders, and the inability of suppliers to deliver them on time affects the construction progress.
The structure uses a pre-embedded steel plate that is hinged and spliced with an upper steel plate and a wedge plate. The wedge plate is pre-embedded by screwing it out, and after casting, it is screwed in to form the required slope, thus avoiding the need for additional wedge plates.
This allows the required slope to form naturally after the slab beam is poured, improving construction efficiency and avoiding construction progress problems caused by delays due to wedge-shaped steel plates.
Smart Images

Figure CN222083321U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of plate beam bottom leveling construction, in particular to a plate beam bottom pre-buried steel plate structure. Background Art
[0002] The bearing is an important part of the bridge structure. It is a force transmission and connection device for the upper and lower structures of the bridge. The bearing reliably transmits the force of the upper load of the bridge to the bridge pier. The bridge bearing is horizontal, so it is required that the bottom surface of the slab beam is also horizontal when the prefabricated slab beam is installed. However, due to the existence of longitudinal slope and transverse slope in the bridge design, the bottom surface of the slab beam is often not horizontal. Therefore, when installing the prefabricated slab beam, certain technical measures need to be taken to perform local leveling on the bottom surface of the beam slab above the bearing to ensure close contact between the beam slab and the bearing and uniform pressure on the bearing.
[0003] The commonly used method is to add a wedge-shaped steel plate that matches the slope of the bridge between the embedded steel plate at the bottom of the beam and the steel plate on the top of the support. This solution requires that the wedge-shaped steel plate that matches the slope of the bridge be customized in advance, and the wedge-shaped steel plate be installed between the embedded steel plate and the steel plate on the top of the support before hoisting. If the wedge-shaped steel plate produced by the supplier cannot be delivered to the construction site on time, the next hoisting process cannot be carried out, affecting the overall construction progress.
[0004] To this end, the present application specifically proposes a pre-embedded steel plate structure at the bottom of a plate beam to solve the above technical problems. Utility Model Content
[0005] The main purpose of the utility model is to solve the above-mentioned shortcomings and provide a pre-embedded steel plate structure at the bottom of a slab beam. The pre-embedded steel plate is formed by hingedly splicing an upper steel plate and a wedge-shaped plate. When pre-embedding, the wedge-shaped plate is screwed out of the upper steel plate and then pre-embedded. After the slab beam is cast, the wedge-shaped plate is screwed into the upper steel plate to naturally form the required inclined surface without the need to install an additional wedge-shaped steel plate.
[0006] In order to solve the above technical problems, the utility model adopts the following technical solutions:
[0007] A pre-buried steel plate structure at the bottom of a plate beam comprises: a pre-buried steel plate, which is formed by hingedly splicing an upper steel plate and a wedge-shaped plate; and knob pins, which are symmetrically arranged on both sides of the wedge-shaped plate and are used to adjust and fix the relative positions of the upper steel plate and the wedge-shaped plate.
[0008] Furthermore, a wedge-shaped groove for installing the wedge plate is provided at the bottom of the upper steel plate, and the end with a smaller cross-section of the wedge plate is hinged to the upper steel plate. When the wedge plate is completely screwed into the upper steel plate around the hinge axis, the bottom surface of the wedge plate is flush with the bottom surface of the upper steel plate.
[0009] Furthermore, a first installation groove is provided in the wedge-shaped groove, a sealing strip is provided in the first installation groove, and the sealing strip and the wedge-shaped plate are fitted in an interference fit.
[0010] Furthermore, a plurality of positioning holes for cooperating with the plug of the knob pin are symmetrically provided on both side walls of the wedge-shaped groove.
[0011] Furthermore, a second mounting groove is symmetrically provided at the bottom of the wedge-shaped plate near the end with a larger cross section, and a knob latch is provided in the second mounting groove.
[0012] Furthermore, a third mounting groove is provided at the bottom of the wedge-shaped plate near the end with a larger cross section, and a handle is provided in the third mounting groove.
[0013] Furthermore, a first cover plate is hinged at the notch of the second mounting slot, and a second cover plate is hinged at the notch of the third mounting slot. When the first cover plate and the second cover plate are in a flipped closed state, their bottom surfaces are flush with the bottom surface of the wedge plate.
[0014] Furthermore, the end of the wedge-shaped plate with a larger cross section is an arc surface with the center line of the hinge shaft as the axis.
[0015] The beneficial effects of the utility model are embodied in:
[0016] The utility model provides an upper steel plate, a wedge plate and knob pins arranged on both sides of the wedge plate, which are hingedly assembled. The wedge plate is rotated out of the upper steel plate to a required angle and fixed by the knob pins before pre-embedded casting, and then the bottom surface of the wedge plate is put into the bottom surface of the plate beam casting mold with the bottom surface of the wedge plate as the contact surface. After the casting is completed, due to the blocking effect of the part of the wedge plate rotated out of the upper steel plate, there is no cement filling in this part. After the wedge plate is screwed into the upper steel plate again by the knob pin, a wedge-shaped groove is naturally formed. The bottom surface of the wedge plate is the required installation leveling inclined surface, and there is no need to install the wedge steel plate when the plate beam is hoisted, which saves time and labor and ensures the progress of the project. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The drawings constituting part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:
[0018] Figure 1 This is a schematic diagram of the overall appearance of an embodiment of the utility model;
[0019] Figure 2 A schematic diagram of a wedge-shaped plate being rotated out according to an embodiment of the utility model;
[0020] Figure 3 This is a schematic diagram of the cooperation between the upper steel plate and the wedge-shaped plate in one embodiment of the utility model;
[0021] Figure 4 This is a schematic diagram of the upper steel plate structure of an embodiment of the utility model;
[0022] Figure 5 This is a schematic diagram of the installation slot structure of an embodiment of the utility model;
[0023] Figure 6 This is a schematic diagram of the wedge plate structure of an embodiment of the utility model;
[0024] Figure 7 This is a schematic diagram of the wedge plate structure of an embodiment of the utility model;
[0025] Figure 8 This is a schematic diagram of positioning the upper steel plate and the wedge-shaped plate in one embodiment of the utility model;
[0026] Fig. 9 For an embodiment of the utility model Figure 8 A magnified image of point A;
[0027] Fig.10 This is a schematic diagram of the pre-embedded method of the original pre-embedded steel plate;
[0028] Fig.11 This is a schematic diagram of pre-embedded steel plates according to an embodiment of the utility model;
[0029] Fig.12 For an embodiment of the utility model Fig.11 Enlarged view of point B.
[0030] In the figure:
[0031] 1. Embedded steel plate; 101. Upper steel plate; 102. Wedge-shaped plate; 2. Threaded column; 3. Wedge-shaped groove; 4. Positioning hole; 5. First installation groove; 6. Sealing strip; 7. Second installation groove; 8. Third installation groove; 9. Knob latch; 10. Handle; 11. First cover plate; 12. Second cover plate. DETAILED DESCRIPTION
[0032] The following will be combined with the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. In the absence of conflict, the embodiments in this application and the features in the embodiments can be combined with each other. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0033] like Figure 1-12 As shown, the utility model provides a pre-buried steel plate structure at the bottom of a plate beam, comprising:
[0034] The embedded steel plate 1 is formed by hingedly joining an upper steel plate 101 and a wedge-shaped plate 102;
[0035] The knob latches 9 are symmetrically arranged on both sides of the wedge plate 102 and are used to adjust and fix the relative positions of the upper steel plate 101 and the wedge plate 102 .
[0036] Before casting the slab beam, first unscrew the knob pin 9 and rotate the wedge plate 102 out of the upper steel plate 101 to the required angle, then screw in the knob pin 9 to fix the relative position of the wedge plate 102 and the upper steel plate 101, and then put the adjusted embedded steel plate 1 into the bottom surface of the slab beam casting mold with the bottom surface of the wedge plate 102 as the contact surface, with the side provided with the threaded column 2 facing upward. After the casting is completed, due to the blocking effect of the wedge plate 102 being screwed out of the upper steel plate 101, this part is not filled with cement. When the slab beam is transported to the construction site for hoisting, unscrew the knob pin 9 and screw the wedge plate 102 into the upper steel plate 101, a wedge-shaped groove is naturally formed, and the bottom surface of the wedge plate 102 after being screwed into the upper steel plate 101 is the required installation leveling slope.
[0037] In one embodiment, a wedge-shaped groove 3 for installing a wedge-shaped plate 102 is provided at the bottom of the upper steel plate 101. The end of the wedge-shaped plate 102 with a smaller cross section is hinged to the upper steel plate 101. When the wedge-shaped plate 102 is completely screwed into the upper steel plate 101 around the hinge axis, the bottom surface of the wedge-shaped plate 102 is flush with the bottom surface of the upper steel plate 101. With this design, when the pouring is completed, the bottom surface of the embedded steel plate 1 formed after the wedge-shaped plate 102 is screwed into the upper steel plate 101 is flat, which is convenient for the subsequent installation of the support.
[0038] In one embodiment, a first installation groove 5 is provided in the wedge-shaped groove 3, and a sealing strip 6 is provided in the first installation groove 5, and the sealing strip 6 is interference fit with the wedge-shaped plate 102. With this design, when the wedge-shaped plate 102 is screwed out of the upper steel plate 101 for pre-embedded casting, a seal is formed by the interference fit between the wedge-shaped plate 102 and the sealing strip 6, thereby avoiding the problem that cement is poured into the cavity between the wedge-shaped plate 102 and the upper steel plate 101, resulting in the wedge-shaped plate 102 being unable to be screwed into the upper steel plate 101 after casting is completed.
[0039] In one embodiment, a plurality of positioning holes 4 for cooperating with the plug of the knob plug 9 are symmetrically opened on both side walls of the wedge-shaped groove 3. With this design, the wedge-shaped plate 102 can be rotated out of the upper steel plate 101 by cooperating with the knob plug 9 with different positioning holes 4, so that it can be set to a variety of rotation angles, and has a wider range of applications.
[0040] In one embodiment, the bottom of the wedge plate 102 is symmetrically provided with a second installation groove 7 near the end with a larger cross section, and a knob pin 9 is arranged in the second installation groove 7. With this design, by installing the knob pin 9 in the second installation groove 7, the bottom surface of the wedge plate 102 is made flat, ensuring that the bottom surface of the wedge plate 102 can fully contact the bottom surface of the casting mold during casting, reducing cement overflow between the bottom surface of the wedge plate 102 and the bottom surface of the casting mold, and ensuring the accuracy of the final installation leveling slope.
[0041] In one embodiment, a third mounting groove 8 is provided at the bottom of the wedge-shaped plate 102 near the end with a larger cross section, and a handle 10 is provided in the third mounting groove 8. With this design, the wedge-shaped plate 102 can be screwed in and out easily through the handle 10, and the handle 10 is arranged in the third mounting groove 8 to make the bottom surface of the wedge-shaped plate 102 flat, thereby ensuring the accuracy of the finally formed installation leveling slope.
[0042] In one embodiment, the first cover plate 11 is hinged at the notch of the second installation groove 7, and the second cover plate 12 is hinged at the notch of the third installation groove 8. When the first cover plate 11 and the second cover plate 12 are in the flipped closed state, their bottom surfaces are flush with the bottom surface of the wedge plate 102. In this design, the knob latch 9 and the handle 10 can be protected by the first cover plate 11 and the second cover plate 12 during the pouring of the plate beam to prevent cement from entering the second installation groove 7 and the third installation groove 8. At the same time, the bottom surfaces of the first cover plate 11 and the second cover plate 12 are flush with the bottom surface of the wedge plate 102 when they are in the closed state in order to ensure the flatness of the bottom surface of the wedge plate 102, which is convenient for subsequent installation operations.
[0043] In one embodiment, the end with the larger cross section of the wedge plate 102 is an arc surface with the center line of the hinge shaft as the axis. This design makes the wedge plate 102 fit more closely with the upper steel plate 101 during the rotation process, avoiding cement from entering during the pouring process due to the existence of gaps, which affects the normal use of the device.
[0044] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or basic features of the present invention. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention.
[0045] It should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back...), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components in a certain specific posture. If the specific posture changes, the directional indications will also change accordingly.
[0046] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the utility model, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or schemes that satisfy both A and B. In addition, "multiple" refers to more than two. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in this field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the utility model.
Claims
1. A pre-buried steel plate structure at the bottom of a plate beam, characterized in that: include: The embedded steel plate (1) is formed by hingedly joining an upper steel plate (101) and a wedge-shaped plate (102); The knob pins (9) are symmetrically arranged on both sides of the wedge-shaped plate (102) and are used to adjust and fix the relative position of the upper steel plate (101) and the wedge-shaped plate (102).
2. The pre-buried steel plate structure at the bottom of a plate beam as claimed in claim 1, characterized in that: A wedge-shaped groove (3) for mounting the wedge-shaped plate (102) is provided at the bottom of the upper steel plate (101); the end of the wedge-shaped plate (102) with a smaller cross-section is hinged to the upper steel plate (101); when the wedge-shaped plate (102) is completely screwed into the upper steel plate (101) around the hinge axis, the bottom surface of the wedge-shaped plate (102) is flush with the bottom surface of the upper steel plate (101).
3. The pre-buried steel plate structure at the bottom of a plate beam as claimed in claim 2, characterized in that: A first installation groove (5) is provided in the wedge-shaped groove (3), a sealing strip (6) is provided in the first installation groove (5), and the sealing strip (6) and the wedge-shaped plate (102) are fitted in an interference fit.
4. The pre-buried steel plate structure at the bottom of a plate beam as claimed in claim 2, characterized in that: A plurality of positioning holes (4) for cooperating with the plug of the knob latch (9) are symmetrically provided on the two side walls of the wedge-shaped groove (3).
5. The pre-buried steel plate structure at the bottom of a plate beam as claimed in claim 1, characterized in that: A second installation groove (7) is symmetrically provided at the bottom of the wedge-shaped plate (102) near the end with a larger cross section, and a knob latch (9) is arranged in the second installation groove (7).
6. The pre-buried steel plate structure at the bottom of a plate beam as claimed in claim 5, characterized in that: A third installation groove (8) is provided at the bottom of the wedge-shaped plate (102) near the end with a larger cross section, and a handle (10) is provided in the third installation groove (8).
7. The pre-buried steel plate structure at the bottom of a plate beam as claimed in claim 6, characterized in that: A first cover plate (11) is hingedly connected to the notch of the second mounting groove (7), and a second cover plate (12) is hingedly connected to the notch of the third mounting groove (8); when the first cover plate (11) and the second cover plate (12) are in a flipped closed state, their bottom surfaces are flush with the bottom surface of the wedge plate (102).
8. The pre-buried steel plate structure at the bottom of a plate beam as claimed in claim 1, characterized in that: The end of the wedge-shaped plate (102) with a larger cross section is an arc surface with the center line of the hinge shaft as the axis.