Gravity dam foundation pit edge reinforcing structure

By setting inner and outer piles on the edge of the foundation pit and connecting them through connecting ribs, a reinforced structure is formed, the problem of the reduction of structural strength of the foundation pit edge gravity dam during the flood season is solved, and the stability of the pit edge is improved to prevent collapse accidents. .

CN222083568UActive Publication Date: 2024-11-29SHANGHAI CONSTRUCTION NO 7 (GROUP) CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420002437.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-02
Publication Date
2024-11-29
Estimated Expiration
2034-01-02

AI Technical Summary

Technical Problem

The existing foundation pit edge gravity dam is affected by rainwater during the flood season, and the structural strength is reduced, making it prone to dangerous accidents such as collapse.

Method used

The inner pile and the outer pile are connected by connecting ribs to form a reinforced structure. The inner pile is a continuous Larsen steel sheet pile, and the outer pile is H-shaped steel with a spacing of 2 meters. The reinforcement ribs are welded on the inner piles to increase the pulling force.

Benefits of technology

It effectively avoids the reduction in structural strength caused by rainwater, improves the stability of the foundation pit edge, and prevents collapse accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083568U_ABST
    Figure CN222083568U_ABST
Patent Text Reader

Abstract

The utility model relates to a gravity dam foundation pit edge reinforcing structure which comprises inner side piles, outer side piles and connecting ribs, the inner side piles are arranged on the excavation face of a gravity dam, the outer side piles are arranged on the outer side of the gravity dam, and the outer side piles are connected with the inner side piles through the connecting ribs. According to the gravity dam foundation pit edge reinforcing structure, the inner side piles and the outer side piles are arranged on the excavation face and the outer side of the gravity dam respectively, the two piles are tied through the connecting ribs, reinforcing of the gravity dam foundation pit edge is achieved, and the situation that the structural strength of the gravity dam foundation pit edge is reduced due to the influence of rainwater is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a gravity dam foundation pit edge reinforcement structure. Background Art

[0002] At present, with the rapid development of urban modernization, deep foundation pit construction can be seen everywhere. The safety of the foundation pit is the top priority in the foundation pit construction process. Once the stability of the foundation pit cannot be guaranteed and safety problems arise, the consequences will be disastrous. At that time, reinforcement measures for the foundation pit edge become particularly important, which can ensure the stability of the foundation pit and enable the underground project to be implemented smoothly.

[0003] Now, the gravity dam beside the foundation pit is affected by rain during the flood season, and its structural strength will be greatly reduced, making it prone to dangerous accidents such as collapse. Utility Model Content

[0004] The utility model aims to solve the problem that the existing gravity dam beside the foundation pit is affected by rainwater during the flood season, its structural strength will be greatly reduced, and dangerous accidents such as collapse will easily occur. The technical scheme adopted is: a gravity dam foundation pit reinforcement structure, including: inner piles, outer piles and connecting bars, the inner piles are arranged at the excavation surface of the gravity dam, the outer piles are arranged outside the gravity dam, and the outer piles are connected to the inner piles through the connecting bars.

[0005] A further improvement is that the inner piles are continuous Larsen steel sheet piles.

[0006] A further improvement is that the outer piles are H-shaped steel.

[0007] A further improvement is that the top end of the outer pile is connected to the top end of the inner pile through the connecting rib.

[0008] A further improvement is that there are multiple outer piles, and the interval between two adjacent outer piles is 2 meters.

[0009] A further improvement is that a reinforcing rib is fixed to the inner side of the inner pile.

[0010] A further improvement is that the reinforcing ribs are double-jointed channel steels.

[0011] The beneficial effects of the utility model are:

[0012] The utility model provides a gravity dam foundation pit edge reinforcement structure, in which inner piles and outer piles are respectively arranged on the excavation surface and the outer side of the gravity dam, and the two piles are tied together by connecting bars, thereby realizing the reinforcement of the gravity dam foundation pit edge and avoiding the reduction of the structural strength due to the influence of rainwater. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0014] Figure 1 It is a structural schematic diagram of a gravity dam foundation pit edge reinforcement structure of the utility model. DETAILED DESCRIPTION

[0015] Now the utility model is further described in detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the utility model in a schematic manner, and therefore only show the components related to the utility model.

[0016] In the description of the utility model, it is necessary to understand that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the utility model.

[0017] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0018] In the utility model, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the utility model can be understood according to the specific circumstances.

[0019] like Figure 1As shown, in order to ensure the overall stability of the gravity dam foundation pit when affected by rainwater, the utility model provides a gravity dam foundation pit edge reinforcement structure, including: inner piles 1, outer piles 2 and connecting ribs 4. A row of inner piles 1 are fully driven at the excavation surface of the gravity dam 100, and the outer piles 2 are driven on the outside of the gravity dam 100. The outer piles 2 are connected to the inner piles 1 through the connecting ribs 4. Specifically, the two ends of the connecting ribs 4 are respectively fixedly connected to the outer piles and the inner piles by welding. After all are completed, the dam body is densely backfilled.

[0020] The utility model provides a gravity dam foundation pit edge reinforcement structure, in which inner piles and outer piles are respectively arranged on the excavation surface and the outer side of the gravity dam, and the two piles are tied together by connecting bars, thereby realizing the reinforcement of the gravity dam foundation pit edge and avoiding the reduction of the structural strength due to the influence of rainwater.

[0021] A further improvement is that the inner piles 1 are made of continuously constructed Larsen steel sheet piles.

[0022] A further improvement is that the outer pile 2 is an H-shaped steel, which can provide a stable tensioning force for the inner pile.

[0023] A further improvement is that the top end of the outer pile 2 is connected to the top end of the inner pile 1 through the connecting rib 4 .

[0024] In order to reduce the construction workload while ensuring that stable and reliable tensioning force can be provided for all the inner piles 1, a further improvement of the technical solution is that there are multiple outer piles 2, and the construction is arranged according to the shape of the gravity dam, and the interval between two adjacent outer piles 2 is 2 meters.

[0025] In order to make all the inner piles more integrated and improve the pulling effect on the inner piles, the technical solution is further improved as follows: a reinforcing rib 3 is welded and fixed to the inner side of the inner pile 1, and a connecting rib 4 is connected to the outer pile 2 at one end and to the reinforcing rib 3 at the other end.

[0026] A further improvement is that the reinforcing rib 3 is a double-jointed channel steel, which not only has high structural strength and is not easy to deform, but also is easy to obtain.

[0027] Based on the above ideal embodiments of the utility model, the relevant staff can make various changes and modifications without deviating from the technical concept of the utility model through the above description. The technical scope of the utility model is not limited to the content of the specification, and its technical scope must be determined according to the scope of the claims.

Claims

1. A gravity dam foundation pit reinforcement structure, characterized in that: include: Inner piles, outer piles and connecting ribs, the inner piles are arranged at the excavation surface of the gravity dam, the outer piles are arranged outside the gravity dam, and the outer piles are connected to the inner piles through the connecting ribs.

2. The gravity dam foundation pit reinforcement structure according to claim 1, characterized in that: The inner piles are continuous Larsen steel sheet piles.

3. The gravity dam foundation pit reinforcement structure according to claim 1, characterized in that: The outer piles are H-shaped steel.

4. The gravity dam foundation pit reinforcement structure according to claim 1, characterized in that: The top end of the outer pile is connected to the top end of the inner pile through the connecting rib.

5. The gravity dam foundation pit reinforcement structure according to claim 1, characterized in that: There are multiple outer piles, and the interval between two adjacent outer piles is 2 meters.

6. The gravity dam foundation pit reinforcement structure according to claim 1, characterized in that: A reinforcing rib is fixed on the inner side of the inner pile.