Externally-hung drainage system of residential building
Through the design of external riser and lowered plate structures in the building, the problem of drainage of the different floors of residential buildings is solved, and drainage and rapid replacement of the same floor are achieved. It is suitable for the renovation of old communities and improves the flexibility and convenience of the drainage system.
Patent Information
- Application Number
- CN202420066602.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-11
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-01-11
AI Technical Summary
The drainage system of existing residential buildings has problems with different floor drainage, which leads to great influence on leakage and noise, and is difficult to replace pipes, especially when renovating in old communities.
Design an external drainage system, the riser is suspended in the integrated pipe well module of the building's exterior wall, and is connected to the drainage horizontal pipe through a horizontal interface. The lowering structure forms a concave space to lay the drainage pipeline, realizing drainage and rapid replacement of the same layer, which is suitable for Renovation of existing residential buildings.
It realizes rapid replacement and disassembly of drainage systems, which facilitates transformation, reduces construction difficulty and impact on owners' lives, and is suitable for the renovation of old communities.
Smart Images

Figure CN222083685U_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of building drainage, and specifically relates to an external drainage system for residential buildings, and is particularly suitable for the external drainage system for the renovation of existing residential buildings. Background Art
[0002] Most of the existing residential buildings, especially the toilets of houses, adopt different-layer drainage. When the upper-layer users drain water, the lower-layer residents are greatly affected. Leakage is very common, and drainage noise is easy to cause disputes. Most of the existing residential drainage main pipes are set in the toilet, and many are hidden in the pipe well. On the one hand, it takes up the toilet space; on the other hand, when the pipe needs to be replaced, it is necessary to enter the house for replacement, and the decoration of the house needs to be restored after the replacement, which is difficult. Furthermore, when the residents of a certain floor in the unit do not agree to the replacement or are not allowed to enter the house, it will cause the replacement of the pipes of all the residents connected by the pipes to be impossible. Utility Model Content
[0003] In view of the above analysis, an embodiment of the utility model aims to provide an external drainage system for a residential building to solve the above problems existing in the prior art.
[0004] The purpose of the utility model is achieved in this way:
[0005] An external drainage system for a residential building comprises a vertical pipe and a horizontal drainage pipe; wherein the vertical pipe is located outdoors and is suspended in an integrated pipe well module on the outer wall of the building, a plurality of tees are arranged on the vertical pipe, each tee is arranged at a structural floor position for drainage of a bathroom and / or kitchen, and the tee has a horizontal interface; the horizontal drainage pipe is arranged in a circular hole on the outer wall of the building, one end of the horizontal drainage pipe is connected to the horizontal interface, and the other end is connected to the drainage pipeline of a water-using device.
[0006] Furthermore, it also includes a drop-down structure, which is fixedly arranged in the demolition space of the structural floor, and has a concave space, and the drainage transverse pipe is laid in the concave space.
[0007] Furthermore, it also includes a building cushion layer, which is arranged inside and above the demolition space and is configured to form a horizontal ground layer for the bathroom and the kitchen.
[0008] Furthermore, the drop-down structure includes a floor slab, which is fixed in the demolition space of the structural floor slab by a steel beam assembly, and the floor slab has a drop-down area and a non-drop-down area, and the drop-down area forms a concave space; or, the steel beam assembly includes a steel beam, a node plate and a chemical anchor, and the steel beam is supported by the walls on both sides and is fixed to the node plates on the walls on both sides in a hinged form, and the node plates are fixed to the wall using chemical anchors.
[0009] Furthermore, the floor slab is a precast concrete slab, the top of the non-drop-down area of the precast concrete slab is flush with the top of the structural floor slab, and the precast concrete slab is fixed to the lower flange of the heightened steel beam.
[0010] Furthermore, the floor slab includes one of a 24 mm thick high-strength cement fiber board, a 8-10 mm thick steel plate, and a glass fiber reinforced plastic plate.
[0011] Furthermore, a steel tube keel is provided between the two steel beams. The steel tube keel is connected to the bottom of the steel beam through angle steel to form a steel secondary beam. The steel secondary beam is perpendicular to the steel beam, and the floor slab is arranged on the steel tube keel.
[0012] Furthermore, two steel beams are fixed below the structural floor slab, and a water drill is used to cut out the area where the recessed space needs to be set, and the floor slab is placed directly on the lower flange of the steel beam.
[0013] Furthermore, the lowering structure includes a finished caisson, which is a U-shaped structure and is fixedly installed in the demolition space of the structural floor.
[0014] Furthermore, the drop-down structure includes a drop-down folded plate, which is a cast-in-place concrete floor slab, and the steel bars of the cast-in-place concrete floor slab are embedded in the walls on both sides; the longitudinal section of the drop-down folded plate is a two-step shape, and a part of the drop-down folded plate descends to form a concave space.
[0015] Compared with the prior art, the external drainage system for residential buildings provided by the utility model realizes the rapid replacement of same-floor drainage and risers in existing residential buildings by hanging the pipe well outside the building. It has good integrity, can be reused, and is more convenient to disassemble and assemble. It is especially suitable for the renovation of existing residential buildings in old communities. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of this specification or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the embodiments of this specification. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.
[0017] Figure 1a A structural schematic diagram 1 of an external drainage system (single riser system) for a residential building provided by the utility model;
[0018] Figure 1b The structure diagram of the external drainage system (single vertical pipe system) of the residential building provided by the utility model Figure 2 ;
[0019] Figure 1cThe structure diagram of the external drainage system (single vertical pipe system) of the residential building provided by the utility model Figure 3 ;
[0020] Figure 2 A schematic diagram of the structure of an external drainage system (double riser system) for a residential building provided by the utility model;
[0021] Figure 3 A schematic cross-sectional structure diagram of an external drainage system (bathroom drainage) for a residential building provided by the utility model;
[0022] Figure 4 A schematic diagram of the cross-section structure of an external drainage system (kitchen drainage) for a residential building provided by the utility model;
[0023] Figure 5 A schematic diagram of the connection structure between the drainage horizontal pipe and the tee provided by the utility model;
[0024] Figure 6 A schematic diagram of the floor plan structure of a residential building after renovation provided by the utility model;
[0025] Figure 7 for Figure 6 Schematic diagram of the AA section structure;
[0026] Figure 8 Schematic diagram of the floor plan structure after the renovation of the residential building provided by the utility model Figure 2 ;
[0027] Fig. 9 for Figure 8 Schematic diagram of the structure of the middle BB section;
[0028] Fig.10 Schematic diagram of the floor plan structure after the renovation of the residential building provided by the utility model Figure 3 ;
[0029] Fig.11 for Fig.10 Schematic diagram of the CC cross-section structure 1;
[0030] Fig.12 for Fig.10 Schematic diagram of the structure of the middle DD section 1;
[0031] Fig.13 for Fig.10 Schematic diagram of the structure of the middle EE section 1;
[0032] Fig.14 for Fig.10 Schematic diagram of the CC cross-section structure Figure 2 ;
[0033] Fig.15 for Fig.10 Schematic diagram of the DD section structure Figure 2 ;
[0034] Fig.16 for Fig.10 EE cross-section structure diagram Figure 2 ;
[0035] Fig.17 Schematic diagram of the floor plan structure after the renovation of the residential building provided by the utility model Figure 4 ;
[0036] Fig.18 for Fig.17 Schematic diagram of the FF cross-section structure;
[0037] Fig.19 for Fig.17 Schematic diagram of the GG section structure;
[0038] Fig. 20 for Fig.17 Schematic diagram of the HH section structure.
[0039] Reference numerals:
[0040] 1. Integrated pipe well module; 1-1. Pipe well exterior wall; 1-2. Pipe well interior wall; 1-3. Aluminum alloy ears; 1-4. Opening fan; 1-5. Buckle; 1-6. Insulation in pipe well; 2. Building exterior wall; 2-1. Exterior wall insulation; 3. Vertical pipe; 3-1. Tee; 3-11. Horizontal interface; 3-2. Vertical pipe interface; 3-3. H pipe fitting; 3-4. Ventilation vertical pipe; 3-5. Pipe inspection port; 4. Structural floor; 5. Drainage horizontal pipe; 6. Drop plate structure; 6-1. Finished caisson; 6-2. Drop plate folding plate; 6-3. Floor paving; 7-1. Pipe clamp; 7-2. Steel bar; 7-3. Nut cover; 7-4. Flexible joint; 7-5. Screw nut; 8. Pipe clamp fixings; 9. Steel beam; 10. Steel secondary beam; 11. Building cushion. DETAILED DESCRIPTION
[0041] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described in combination with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all of the embodiments. It should be noted that, in the absence of conflict, the embodiments in the present disclosure and the features in the embodiments can be combined, separated, interchanged and / or rearranged with each other. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0042] In the accompanying drawings, the size and relative size of components may be exaggerated for clarity and / or descriptive purposes. When the exemplary embodiments may be implemented differently, a specific process sequence may be performed in a different order than described. For example, two successively described processes may be performed substantially simultaneously or in an order opposite to the order described. In addition, the same reference numerals represent the same components.
[0043] The terms used here are for the purpose of describing specific embodiments, and are not intended to be restrictive. As used here, unless the context clearly indicates otherwise, the singular forms "one (kind, person)" and "said (the)" are also intended to include plural forms. In addition, when the terms "comprise" and / or "include" and their variations are used in this specification, it is explained that there are stated features, integral bodies, steps, operations, parts, assemblies and / or their groups, but it is not excluded that there are or add one or more other features, integral bodies, steps, operations, parts, assemblies and / or their groups. It should also be noted that, as used here, the terms "substantially", "approximately" and other similar terms are used as approximate terms and not as degree terms, so that they are used to explain the inherent deviations of the measured values, calculated values and / or the values provided that will be recognized by those of ordinary skill in the art.
[0044] Example 1
[0045] A specific embodiment of the utility model discloses an external drainage system for a residential building, such as Figure 1a , 1b , 1c and Figures 2 to 4 As shown, it includes a vertical pipe 3 and a drainage horizontal pipe 5; wherein the vertical pipe 3 is located outdoors and is suspended in an integrated pipe well module 1 of the building outer wall 2, and a plurality of tees 3-1 are arranged on the vertical pipe 3, each tee 3-1 is arranged corresponding to the position of the structural floor 4 of the bathroom and / or kitchen, and the tee 3-1 has a horizontal interface 3-11; the drainage horizontal pipe 5 is arranged in a circular hole in the building outer wall 2, one end of the drainage horizontal pipe 5 is connected to the horizontal interface 3-11, and the other end is connected to the drainage pipeline of the water-using equipment in the bathroom and / or kitchen, that is, it is connected to the water outlet of the bathroom and / or kitchen.
[0046] It should be noted that the external drainage system for residential buildings provided in this embodiment is not only applicable to the renovation of existing residential buildings, but also to new buildings.
[0047] In this embodiment, the external drainage system of the residential building also includes a drop plate structure 6, which is arranged in the demolished space of the structural floor 4. The drop plate structure 6 has a concave space, and the drainage horizontal pipe 5 is laid in the concave space.
[0048] In this embodiment, the demolition range of the structural floor 4 is determined according to the original floor structure of the existing residential building. That is, the demolition space is formed by demolishing at least a part of the original structural floor 4 of the bathroom or kitchen of the existing residential building, and the building exterior wall 2 constitutes an inner wall of the demolition space.
[0049] When renovating the drainage system of an existing residential building: first remove the existing drainage transverse pipes on different floors, and at the same time remove the vertical pipes and pipe wells (if any), remove the floor slabs where the bathroom / kitchen is located, and replace them with a descending plate structure 6 with a concave space. The height of the concave space can be determined according to the size of the bathroom and the layout of the sanitary ware. When replacing the new drainage system, lay the drainage transverse pipe inside the concave space, open a hole in the outer wall close to the bottom of the concave space, extend the drainage transverse pipe to the outdoors, and connect it to the vertical pipes in the integrated pipe well module to complete the replacement of the existing residential indoor drainage system. Only one entry is required. When replacing the drainage vertical pipe in the future, you can directly replace the external integrated pipe well module. It can be replaced in layers or in the entire building.
[0050] In this embodiment, the external drainage system of the residential building further includes a building cushion layer 11, which is disposed inside and above the demolished space and is configured to form a horizontal ground layer for the bathroom and the kitchen.
[0051] In this embodiment, the external drainage system of the residential building further includes an integrated pipe well module 1, which is arranged outside the building exterior wall 2, and the riser 3 is arranged inside the integrated pipe well module 1. Figure 1a to Figure 1c As shown, the integrated pipe well module 1 is a rectangular tubular structure made of metal composite insulation material, which can be prefabricated in the factory and then transported to the site for installation. The integrated pipe well module 1 has a parallel arranged pipe well outer wall 1-1 and a pipe well inner wall 1-2, and the pipe well inner wall 1-2 is fixedly connected to the structural main body of the building outer wall 2; the riser 3 is vertically arranged in the internal space of the integrated pipe well module 1, and is fixedly connected to the inner wall of the integrated pipe well module through the pipe clamp fixing member 8, and the space between the inner wall of the integrated pipe well module and the pipe wall of the riser can be filled with insulation material in the factory to form the pipe well internal insulation 1-6; the insulation layer between the external integrated pipe well module and the wall is implemented after the external integrated pipe well module is connected to the wall.
[0052] In one optional embodiment, the integrated manhole module 1 outside the room is a composite thermal insulation material pasted on the inner side of an aluminum alloy panel, and the aluminum alloy panel is provided with outward-turned aluminum alloy ears 1-3 at regular intervals in the longitudinal direction, and the aluminum alloy ears 1-3 are fixed to the building outer wall 2 by expansion bolts. This structure facilitates the disassembly and assembly of the integrated manhole module.
[0053] In one of the optional embodiments, an openable and closable inspection door is provided on the outer wall of the pipe well at each floor position, so that it is convenient to dismantle the corresponding pipe well when replacing or inspecting the pipeline. For example, an opening fan 1-4 that can be opened outward is reserved on the outer wall of the pipe well corresponding to the pipe inspection port 3-5. The opening fan 1-4 is usually closed as a hidden door and opened during inspection. A hinge is provided on one side of the opening fan shaft, and a buckle 1-5 is provided on the other side. In this way, the opening fan can be opened when inspecting the pipeline, and can be closed again after the inspection is completed.
[0054] In this embodiment, the aluminum alloy panel of the integrated pipe well module can be made into corresponding colors and effects according to the requirements of the building facade. The integrated pipe well module 1 can form a complete energy-saving system together with the exterior wall insulation 2-1, or it can be hung on the building exterior wall 2 alone. The vertical pipe is arranged inside the integrated pipe well module and is fixedly connected to the metal part of the pipe well through the pipe clamp fixing piece 8.
[0055] In this embodiment, pipes such as the vertical pipe 3 and the drainage horizontal pipe 5 are all made of hard polyvinyl chloride hollow wall silencer pipes.
[0056] In this embodiment, the riser 3 is a single riser system; or, the riser 3 is a double riser system; or, the riser 3 is a triple riser system.
[0057] For example, the drainage riser of a single-riser system has a diameter of DN100; the drainage riser of a double-riser (sewage + ventilation) system has a diameter of DN100, and the diameter of ventilation risers 3-4 is DN100; the double-riser system (sewage + wastewater) has a diameter of DN100 for the sewage riser, and a diameter of DN100 for the wastewater riser; the triple-riser system (sewage + ventilation + wastewater) has a diameter of DN100 for the sewage riser, a diameter of DN100 for the wastewater riser, and a diameter of DN100 for the ventilation risers 3-4.
[0058] Exemplarily, the center of the riser in a single-riser system is 120 mm away from the inner wall of the pipe well, and the net size of the external pipe well is 240 mm×240 mm; the center of the riser in a double-riser (sewage + ventilation) system is 120 mm away from the inner wall of the pipe well, the pipe spacing between the drainage riser and the ventilation riser 3-4 is 180 mm, and the net size of the external pipe well is 420 mm×240 mm; the center of the riser in a double-riser (sewage + wastewater) system is 120 mm away from the inner wall of the pipe well, the pipe spacing between the sewage riser and the wastewater riser is 340 mm, and the net size of the external pipe well is 580 mm×240 mm; the center of the riser in a three-riser system (sewage + ventilation + wastewater) is 120 mm away from the inner wall of the pipe well, the pipe spacing between the drainage riser and the ventilation riser 3-4 is 180 mm, and the net size of the external pipe well is 600 mm×240 mm.
[0059] For example, in a single-riser system, a tee is reserved at the bottom of the recessed space of the drop-down plate structure 6 for the bathroom drainage transverse pipe, and a DN150 circular hole is reserved on the building's exterior wall; a tee is reserved at a distance of 0.2m (center) from the finished surface of the building on this floor for the kitchen drainage riser in the single-riser system, and a DN80 circular hole is reserved on the building's exterior wall; a tee is reserved at the bottom of the recessed space of the drop-down plate structure 6 for the drainage transverse pipe in the double-riser (sewage + ventilation) system, and a DN160 circular hole is reserved on the building's exterior wall; a tee is reserved at the bottom of the caisson for the drainage transverse pipe in the double-riser (sewage + kitchen wastewater) system, and a DN150 circular hole is reserved on the building's exterior wall, and a tee is reserved at a distance of 0.2m (center) from the finished surface of the building on this floor for the wastewater riser, and a DN80 circular hole is reserved on the building's exterior wall.
[0060] In terms of system pipe connection, the vertical riser of the entire building is composed of multiple sections of risers connected vertically. The two adjacent sections of risers are connected by socket connection. Rubber rings are placed at the interfaces to ensure the sealing of the interfaces, and the fastening is enhanced by screwing the upper pipe threaded cover with the lower pipe threaded cover.
[0061] In the technical solution of the double riser system, the pipe inspection port 3-5 of the double riser (sewage + ventilation) system pipeline is 1m away from the finished surface of the building on this floor, and the ventilation riser 3-4 and the sewage riser are connected by an H pipe fitting 3-3 at a distance of 0.5m from the finished surface of the building on this floor.
[0062] In this embodiment, the horizontal interface 3-11 of the tee 3-1 is connected to the drainage horizontal pipe 5 through a connecting pipe, thereby realizing the rapid installation and removal of the external plastic vertical pipe and the drainage horizontal pipe. Figure 5 As shown, the connecting pipe includes a pipe clamp 7-1, a steel bar 7-2 and a nut cover 7-3. The first end of the steel bar 7-2 is connected to the pipe clamp 7-1, and the second end of the steel bar 7-2 is connected to the nut cover 7-3. The pipe clamp 7-1 is fixed on the vertical pipe 3 and is located below the tee 3-1. The angle between the steel bar 7-2 and the axis of the vertical pipe 3 is 45°. The nut cover 7-3 is installed on the drainage horizontal pipe 5. The locking connection between the drainage horizontal pipe 5 and the horizontal interface 3-11 of the tee 3-1 is achieved by screwing the nut cover 7-3. After the indoor drainage horizontal pipe is installed, it can be directly connected to the external vertical pipe to complete the installation of the drainage system. When replacing the vertical pipe, remove the connecting pipe to separate the drainage horizontal pipe from the tee, and the external vertical pipe can be directly replaced.
[0063] Furthermore, an active joint is provided on the nut cover 7-3, and the second end of the steel bar 7-2 is connected to the nut cover 7-3 through a flexible joint 7-4. This structural arrangement is convenient for disassembly and assembly. The nut cover 7-3 is a round plastic nut cover; the pipe clamp 7-1 is a round steel pipe clamp, and the pipe clamp 7-1 is fixed to the vertical pipe 3 through a screw nut 7-5. In order to improve the sealing of the connection, the connecting pipe also includes a rubber ring, which is provided at the connection between the horizontal interface 3-11 of the tee 3-1 and the drainage horizontal pipe 5.
[0064] In this embodiment, the lowering plate structure 6 has four structural schemes:
[0065] Option 1: If Figure 6 to Figure 7 As shown, the lowering plate structure 6 includes a finished caisson 6-1, which is a U-shaped structure, such as a glass fiber reinforced plastic product, a stainless steel product, etc. The U-shaped space of the finished caisson is the concave space of the lowering plate structure, and the finished caisson 6-1 is fixedly installed in the demolition space of the structural floor 4. During implementation, a narrow strip of floor slab close to the building exterior wall is cut out using a water drill, and the narrow strip plate hole formed by the cut-out is the concave space. For example, the size of the cut-out floor slab is: 300mm wide and 1000mm long, and the specific size is determined according to the specific situation; then a U-shaped glass fiber reinforced plastic, stainless steel or other finished caisson 6-1 is used, and the finished caisson 6-1 is placed in the range of the cut narrow strip plate hole, and the caisson is fixed to the floor slab and the building exterior wall with bolts, etc., so as to achieve the purpose of drainage on the same floor within the lowering plate range. The characteristics of this scheme are: low construction difficulty, short construction period, low cost, and little impact on the normal life of the owner.
[0066] Option 2: If Figures 8 to 9 As shown, the lowering plate structure 6 includes a lowering plate folding plate 6-2, which is a cast-in-place concrete floor slab, and the steel bars of the cast-in-place concrete floor slab are embedded in the walls on both sides; the longitudinal section of the lowering plate folding plate 6-2 is a two-step ladder, and a part of the lowering plate folding plate 6-2 is lowered to form a concave space. During implementation, a water drill is used to remove the entire prefabricated plate involved in the bathroom area (because the original floor slab system is a one-way slab system, only one prefabricated plate is removed, which does not affect the stress of other plates or walls and beams); then the bathroom area is made into a lowering plate folding plate using the method of cast-in-place floor slabs; the steel bars of the cast-in-place slab are embedded in the walls on both sides, the formwork is supported, and C30 concrete is poured. It can be used after the concrete strength reaches 70%. Advantages of this solution: low construction difficulty, low cost, the net height will not be reduced due to the renovation, and the cast-in-place concrete floor slab has good sound insulation and high strength.
[0067] Scheme 3 and Scheme 4: The lowering structure 6 includes a floor slab 6-3, which is fixed in the demolition space of the structural floor slab 4 by a steel beam assembly. The floor slab 6-3 has a lowering area and a non-lowering area, and a concave space is formed in the lowering area.
[0068] In one optional embodiment, the steel beam assembly includes a steel beam 9, a node plate and a chemical anchor. The steel beam 9 is supported by the walls on both sides and is fixed to the node plates on the walls on both sides in a hinged manner. The node plate is fixed to the wall using chemical anchors.
[0069] When implementing scheme three, a water drill is used to remove the entire prefabricated slab involved in the bathroom area (because the original floor system is a one-way slab system, only one prefabricated slab is removed, which does not affect the stress of other slabs or walls and beams); two I-beams, channel steels or steel pipes are set as steel beams on both sides of the removed slab. The steel beams are supported by the walls on both sides and are fixed to the node plates on the walls on both sides in a hinged form. The node plates are fixed to the wall with chemical anchor bolts; the structure and setting method of laying the floor slab include two schemes: scheme three a and scheme three b:
[0070] Option 3a: If Figures 10 to 13 As shown, the floor slab 6-3 is a precast concrete slab. The top of the non-dropping area of the precast concrete slab is flush with the top of the structural floor slab 4, and the precast concrete slab is fixed to the lower flange of the heightened steel beam 9. During implementation, the precast concrete slab prefabricated off-site, with the same thickness as the original floor slab, or 10 to 20 mm thinner than the original floor slab, is placed on the lower flange of the steel beam so that the floor slab is placed within the height range of the steel beam, which can save the net height. In the non-dropping area, the top of the slab is flush with the top of the original slab; in the drop-off area, a section of steel beam is welded under the steel beam to raise the height of the steel beam, and the precast concrete slab is placed on the lower flange of the heightened steel beam to form a drop-off effect. Advantages of this solution: Due to the use of steel structure and precast slabs, the construction period is short, the construction difficulty is low, the impact on the normal life of the owner is small, and the net height is almost unchanged.
[0071] Option 3b: If Fig.10 , Figures 14 to 16 As shown, the floor slab 6-3 adopts a thin floor slab, and the floor slab 6-3 includes one of a 24mm thick high-strength cement fiber board, an 8-10mm thick steel plate, and a glass fiber reinforced plastic plate with performance that meets the requirements. A steel pipe keel is provided between the two steel beams 9, and the steel pipe keel is connected to the bottom of the steel beam 9 through an angle steel to form a steel secondary beam 10. The steel secondary beam 10 is perpendicular to the steel beam 9, and the floor slab 6-3 is arranged on the steel pipe keel. During implementation, angle steel and steel pipe keels with a certain spacing are provided between the two steel beams to form a steel secondary beam 10, and the floor slab is placed on the steel pipe keel; in the range of the lowering plate, the steel pipe keel is sunk, and the thin floor slab is sunk accordingly, forming a lowering plate effect. Advantages of this solution: Because of the use of steel structure and thin material floor slabs, the load is small, the impact on the original structure is small, and the construction period is short, the construction difficulty is low, the impact on the normal life of the owner is small, and the net height is almost unchanged.
[0072] Option 4: If Figures 17 to 20As shown, the floor slab 6-3 is a thin and light floor slab, and the floor slab 6-3 includes one of a 24mm thick high-strength cement fiber board, an 8-10mm thick steel plate, and a glass fiber reinforced plastic plate with performance that meets the requirements; two steel beams 9 are fixed below the structural floor slab 4, and a water drill is used to cut off the part where the concave space needs to be set, and the floor slab 6-3 is directly placed on the lower flange of the steel beam 9. During implementation, firstly, a full-length I-beam, channel steel and other steel beams are set at the edges of both sides of a whole prefabricated board involved in the bathroom range. The steel beam is supported by the walls on both sides and is fixed to the node plates on the walls on both sides in a hinged form. The node plates are fixed to the wall with chemical anchor bolts; after the steel beam is installed, a water drill is used to cut off the part of the bathroom where the floor needs to be lowered, and then the floor slab of the thin material is placed on the lower flange of the steel beam to form a lowering effect. Advantages of this solution: a steel beam is set below the structural floor slab 4, and there is no need to remove the floor slab outside the bathroom, the construction is faster, and the normal life of the owner is less affected.
[0073] Compared with the prior art, the external drainage system for residential buildings provided in this embodiment has the following beneficial effects:
[0074] 1. By hanging the riser on the outside of the building's exterior wall and reserving various drainage holes on the building's exterior wall, the bathroom near the exterior wall can be connected to the drainage riser through the drainage holes. Different from the traditional installation method, the indoor installation can be carried out separately with a high degree of freedom. The integrated module is hung on the building wall to complete the drainage construction. The buried pipes are reserved, and the riser is directly connected to the reserved pipes to complete the installation.
[0075] 2. All or part of the bathroom or kitchen structure floor of the existing residential building will be demolished and replaced with a drop-down structure with a concave space. The bathroom drainage pipeline will be laid in the concave space of the drop-down area. After the vertical pipe is installed outdoors, it is directly connected to the drainage horizontal pipe to complete the installation of the drainage system. In this way, same-floor drainage is achieved, overcoming the defects caused by different-floor drainage. When the vertical pipe needs to be replaced, the vertical pipe hanging outside at the corresponding position can be directly removed, realizing the transformation of different-floor drainage in existing residential buildings into same-floor drainage and the rapid installation and disassembly of the vertical pipe.
[0076] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the present application in detail. It should be understood that the above description is only the specific implementation method of the present application and is not intended to limit the scope of protection of the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the scope of protection of the present application.
Claims
1. An external drainage system for residential buildings. It is characterized in that The invention comprises a vertical pipe (3) and a horizontal drainage pipe (5); wherein the vertical pipe (3) is located outdoors and is suspended in an integrated pipe well module (1) on the outer wall (2) of a building; a plurality of tees (3-1) are arranged on the vertical pipe (3); each of the tees (3-1) is arranged at a structural floor (4) for drainage of a toilet and / or kitchen; the tee (3-1) has a horizontal interface (3-11); the horizontal drainage pipe (5) is arranged in a circular hole in the outer wall (2) of the building; one end of the horizontal drainage pipe (5) is connected to the horizontal interface (3-11), and the other end is connected to the drainage pipeline of a water-using device.
2. The external drainage system for residential buildings according to claim 1, It is characterized in that It also comprises a lowering plate structure (6), wherein the lowering plate structure (6) is fixedly arranged in the demolition space of the structural floor (4), the lowering plate structure (6) has a concave space, and the drainage transverse pipe (5) is laid in the concave space.
3. The external drainage system for residential buildings according to claim 2, It is characterized in that It also includes a building pad (11), which is arranged inside and above the demolition space and is configured to form a horizontal ground layer for the bathroom and the kitchen.
4. The external drainage system for residential buildings according to claim 2, It is characterized in that The floor lowering structure (6) comprises a floor slab (6-3), wherein the floor slab (6-3) is fixed in the demolition space via a steel beam assembly, and the floor slab (6-3) has a floor lowering area and a non-floor lowering area, wherein the floor lowering area forms the concave space.
5. The external drainage system for residential buildings according to claim 4, It is characterized in that The steel beam assembly comprises a steel beam (9), a node plate and a chemical anchor bolt. The steel beam (9) is supported by walls on both sides and is fixed to the node plates on the walls on both sides in a hinged manner. The node plates are fixed to the walls using chemical anchor bolts.
6. The external drainage system for residential buildings according to claim 5, It is characterized in that The floor slab (6-3) is a precast concrete slab, the top of the non-drop-down area of the precast concrete slab is flush with the top of the structural floor slab (4), and the precast concrete slab is fixed to the lower flange of the heightened steel beam (9); or, The floor slab (6-3) comprises one of a 24 mm thick high-strength cement fiber board, a 8-10 mm thick steel plate, and a glass fiber reinforced plastic plate.
7. The external drainage system for residential buildings according to any one of claims 4 to 6, It is characterized in that A steel pipe keel is provided between the two steel beams (9), and the steel pipe keel is connected to the bottom of the steel beam (9) through angle steel to form a steel secondary beam (10). The steel secondary beam (10) is perpendicular to the steel beam (9), and the floor slab (6-3) is arranged on the steel pipe keel.
8. The external drainage system for residential buildings according to claim 4, It is characterized in that Two steel beams (9) are fixed below the structural floor (4), and a water drill is used to cut out the part where the concave space needs to be set, and the floor slab (6-3) is directly placed on the lower flange of the steel beam (9).
9. The external drainage system for residential buildings according to claim 2, It is characterized in that The plate lowering structure (6) comprises a finished caisson (6-1), the finished caisson (6-1) is a U-shaped structure, and the finished caisson (6-1) is fixedly installed in the demolition space.
10. The external drainage system for residential buildings according to claim 2, It is characterized in that The drop-down structure (6) comprises a drop-down folded plate (6-2), wherein the drop-down folded plate (6-2) is a cast-in-place concrete floor slab, and the steel bars of the cast-in-place concrete floor slab are embedded in the walls on both sides; The longitudinal cross section of the lowering plate folding plate (6-2) is in a two-stepped shape, and a portion of the lowering plate folding plate (6-2) is lowered to form the concave space.
Citation Information
Cited By
Drainage system suitable for transformation of existing residential building
CN117947965A