Fabricated tunnel construction supporting structure
By designing a prefabricated tunnel construction support structure including base, curved roof and damping spring shock absorber, the problems of complex connections and insufficient impact resistance of existing steel arch frames are solved, and simple assembly and high stability are achieved , improve construction safety.
Patent Information
- Application Number
- CN202420291605.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-17
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-02-17
AI Technical Summary
During tunnel construction, existing steel arch frames have many connecting parts, large on-site assembly workload, insufficient impact resistance, which affects the safety and stability of the support.
A prefabricated tunnel construction support structure is designed, using base, curved roof plate, damping spring shock absorber, rubber pad, fixing ring, locking column, lever, spring, positioning groove and stud components, through elasticity Connection and buffering devices enable simple assembly and high stability.
It realizes simple on-site assembly and convenient disassembly and move, and improves the impact resistance and safety of the support structure.
Smart Images

Figure CN222084541U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of initial support for tunnel construction, in particular to an assembled tunnel construction support structure. Background Art
[0002] Sprayed anchor support is one of the most widely used support forms in current tunnel construction. When the surrounding rock conditions of the tunnel are poor, a steel arch is generally added to the initial support to strengthen the support strength. The steel arch structure mainly uses L, U, I-shaped steel and rails, steel pipes and other steels, processed into the required shape, and reinforced by overall installation or assembly. The support measures for underground projects can quickly provide sufficient support resistance to meet the basic requirements of initial support. However, the main problems of the steel arch are: there are many connecting parts, and the workload of on-site assembly is large; when there is a huge impact force on the top of the tunnel, its impact resistance is insufficient, affecting the safety and stability of the support. Utility Model Content
[0003] The technical problem to be solved by the utility model is to overcome the existing defects and provide an assembled tunnel construction support structure, which is simple to assemble on site, convenient to disassemble and move, and has high stability, and can effectively solve the problems in the background technology.
[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0005] An assembled tunnel construction support structure comprises a base;
[0006] Base: Support rods are provided at the four corners of its upper surface, and an arc-shaped top plate is provided at the upper end between the support rods. The outer arc surface of the arc-shaped top plate is connected to the protective plate through a damping spring shock absorber, and two splicing grooves and matching splicing seats are respectively provided on the front and rear sides of the base.
[0007] Furthermore, a rubber pad is provided on the outer curved surface of the protective plate.
[0008] Furthermore, the upper side of the base is provided with evenly distributed fixing rings, the middle part of the fixing rings is slidably connected with locking columns, a lever is provided between two laterally adjacent locking columns, and the upper side of the splicing seat is provided with evenly distributed docking holes, and the lower ends of the locking columns pass through the base and are plugged into adjacent docking holes.
[0009] Furthermore, a second spring is provided between the fixing ring and the adjacent shifting rod, and the second spring is movably sleeved with the outer side of the locking column.
[0010] Furthermore, a positioning groove is provided on the front side of the arc-shaped top plate, and a positioning seat matching the positioning groove is provided on the rear side.
[0011] Furthermore, studs are threadedly connected at the middle of the left and right ends of the base, a rotating disk is provided at the upper end of the stud, and a conical nail is provided at the lower end of the stud.
[0012] Furthermore, anti-slip patterns are evenly distributed in the middle of the upper surface of the base.
[0013] Compared with the prior art, the beneficial effects of the utility model are:
[0014] According to the tunnel construction situation, a suitable number of support structures are selected for on-site assembly. The two levers on the front side of the support structure are pushed to move it vertically upward, and the second spring is elastically stretched. Then, the splicing seat on the adjacent support structure is inserted into the splicing groove. Then, the pulling force applied to the lever is released, and the locking column is plugged into the docking hole through the stretching elastic force of the second spring, so that the bases of the two adjacent support structures are assembled together. At the same time, a positioning groove is provided on the front side of the arc-shaped top plate, which is plugged into the positioning seat on the adjacent support structure to realize the assembly of the arc-shaped top plate. This structure is convenient for assembly and fixation and disassembly and movement in the construction tunnel, and is easy to use.
[0015] 2. During the use of the support structure, if there is an impact force on the top of the construction tunnel, it will hit the rubber pad, and the first stage of support impact protection will be achieved through the buffering of the rubber pad. Then the impact force will be transmitted to the protective plate, and the second stage of protection will be achieved through the buffering and shock absorption of the damping spring shock absorber between the arc-shaped top plate and the protective plate, which effectively improves the stability of the support structure and improves the safety of use. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the structure of the utility model;
[0017] Figure 2 It is a schematic diagram of the enlarged structure of point A of the utility model.
[0018] In the figure: 1 base, 2 anti-slip groove, 3 support rod, 4 arc-shaped top plate, 5 damping spring shock absorber, 6 rotating plate, 7 protective plate, 8 rubber pad, 9 splicing groove, 10 locking column, 11 lever, 12 spring two, 13 fixing ring, 14 splicing seat, 15 docking hole, 16 positioning groove, 17 positioning seat, 18 stud, 19 conical nail. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model. Example 1
[0020] See also Figure 1-2 ,This embodiment provides a technical solution: an assembled tunnel construction support structure, comprising a base 1;
[0021] Base 1: Support rods 3 are provided at the four corners of its upper surface, and an arc-shaped top plate 4 is provided at the upper end between the support rods 3. The outer arc surface of the arc-shaped top plate 4 is connected to the protective plate 7 through four evenly distributed damping spring shock absorbers 5, wherein the top and bottom ends of the damping spring shock absorber 5 are respectively fixed on the protective plate and the arc-shaped top plate; the outer arc surface of the protective plate 7 is provided with a rubber pad 8.
[0022] If the supporting structure is hit during use, the impact force reaches the rubber pad 8, and the first stage of impact protection is achieved through the rubber pad 8. The impact force is then transmitted to the protective plate 7, and the damping spring shock absorber 5 between the protective plate 7 and the arc-shaped top plate 4 is used to absorb and buffer the impact force, thereby improving the stability of the supporting structure.
[0023] The front and rear sides of the base 1 are provided with splicing grooves 9 and splicing seats 14 matched therewith, the upper side of the base 1 is provided with evenly distributed fixing rings 13, the middle part of the fixing rings 13 is slidably connected with locking columns 10, a lever 11 is provided between two adjacent locking columns 10 in the horizontal direction, evenly distributed docking holes 15 are provided on the upper side of the splicing seats 14, the lower ends of the locking columns 10 pass through the base 1 and are plugged into the adjacent docking holes 15, a spring 2 12 is provided between the fixing ring 13 and the adjacent lever 11, and the spring 2 12 is movably sleeved with the outer side of the locking column 10. A positioning groove 16 is provided on the front side of the arc-shaped top plate 4, and a positioning seat 17 matching and plugging with the positioning groove 16 is provided on the rear side. When the utility model needs to be assembled, the front lever 11 is pushed to move it vertically to the outside of the corresponding splicing groove 9, the spring 2 12 is elastically stretched, and then the splicing seat 14 on the adjacent supporting structure is inserted into the corresponding splicing groove 9 so that the lower end of the locking column 10 is vertically aligned with the adjacent docking hole 15, and then the tension applied to the lever 11 is released, and the locking column 10 is plugged into the vertically adjacent docking hole 15 through the stretching elastic force of the spring 2 12; at the same time, the positioning grooves 16 and the positioning seats 17 on the arc-shaped top plates 4 of the two adjacent supporting structures are just plugged in, so that the assembly of the two adjacent supporting structures is realized, and the assembly method is simple, the stability is high, and the disassembly and assembly are convenient.
[0024] The middle part of the left and right ends of the base 1 are both threadedly connected with studs 18, the upper end of the stud 18 is provided with a rotating disk 6, and the lower end of the stud 18 is provided with a conical nail 19. The base 1 is placed on the bottom wall inside the tunnel, and then the rotating disk 6 is rotated to drive the stud 18 to rotate. The stud 18 is threadedly connected with the base 1, thereby driving the conical nail 19 to enter the bottom wall of the construction tunnel, thereby fixing the utility model in the tunnel.
[0025] The middle part of the upper surface of the base 1 is provided with evenly distributed anti-skid patterns 2 to provide anti-skid protection for construction workers.
[0026] The utility model provides an assembled tunnel construction support structure, and its working principle is as follows: according to the construction situation, a suitable number of support structures are selected for installation and assembly, and the base of the support structure is first installed and fixed. The specific method is to rotate the rotating disk 6 to drive the stud 18 to rotate, and the stud 18 is threadedly connected with the base 1 to drive the conical nail 19 to enter the bottom wall of the construction tunnel, thereby realizing the fixation of the first support structure. Then, the lever 11 on the front side of the support structure is moved vertically to the outside of the splicing groove 9, and the spring 2 12 is elastically stretched. Then, the splicing seat 14 of the adjacent support structure is inserted into the corresponding splicing groove 9 so that the lower end of the locking column 10 is vertically aligned with the adjacent docking hole 15, and then the tension applied to the lever 11 is released. The locking column 10 is plugged into the vertically adjacent docking hole 15 through the stretching elastic force of the spring 2 12; at the same time, the positioning grooves 16 and the positioning seats 17 on the arc-shaped top plates 4 of the two adjacent support structures are just plugged in correspondingly, so as to realize the stable assembly of the two adjacent support structures. In the next step, the base of the adjacent support structure is further fixed in the tunnel by the conical nails 19 until the fixed assembly is completed. This assembly method is simple, convenient for disassembly and movement, firmly fixed, and has high stability.
[0027] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. An assembled tunnel construction support structure, characterized in that: comprising a base (1); Base (1): Support rods (3) are provided at the four corners of the upper surface thereof, an arc-shaped top plate (4) is provided at the upper ends between the support rods (3), the outer arc surface of the arc-shaped top plate (4) is connected to the protective plate (7) via a damping spring shock absorber (5), and two splicing grooves (9) and splicing seats (14) matching therewith are respectively provided on the front and rear sides of the base (1).
2. The assembled tunnel construction support structure according to claim 1, characterized in that: The outer arc surface of the protection plate (7) is provided with a rubber pad (8).
3. The assembled tunnel construction support structure according to claim 1, characterized in that: The upper side of the base (1) is provided with evenly distributed fixing rings (13), the middle part of the fixing rings (13) is slidably connected with a locking column (10), a lever (11) is provided between two laterally adjacent locking columns (10), the upper side of the splicing seat (14) is provided with evenly distributed docking holes (15), and the lower ends of the locking columns (10) pass through the base (1) and are plugged into adjacent docking holes (15).
4. The assembled tunnel construction support structure according to claim 3 is characterized in that: A second spring (12) is provided between the fixing ring (13) and the adjacent shifting rod (11), and the second spring (12) is movably sleeved with the outer side of the locking column (10).
5. The assembled tunnel construction support structure according to claim 1, characterized in that: The front side of the arc-shaped top plate (4) is provided with a positioning groove (16), and the rear side is provided with a positioning seat (17) matching the positioning groove (16).
6. The assembled tunnel construction support structure according to claim 1, characterized in that: The middle parts of the left and right ends of the base (1) are both threadedly connected with studs (18), the upper end of the studs (18) is provided with a rotating disk (6), and the lower end is provided with a conical nail (19).
7. The assembled tunnel construction support structure according to claim 1, characterized in that: Anti-slip patterns (2) are evenly distributed in the middle of the upper surface of the base (1).