Assembly type guardrail mounting structure
By using embedded screws, lifting components and fixing components in the prefabricated guardrail installation structure, the problems of high construction difficulty, high safety risks and intimate connections during the installation of concrete anti-collision guardrails are solved, and efficient and safe installation and Connection effect.
Patent Information
- Application Number
- CN202420523885.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-18
AI Technical Summary
During the installation process, prefabricated concrete collision-proof guardrails have problems such as high construction difficulty, high safety risks, low construction efficiency and uncontrollable quality. The connection between the guardrail and the bridge is not tight enough, and it is easy to move under external impact.
A prefabricated guardrail installation structure is designed, using embedded screws, hoisting components and fixing components. Through the connection between embedded screws and bottom plates, and combining limit grooves and telescopic springs, the guardrail base and bridge base are realized. The tight fixation of steel bars simplifies the installation process and improves connection stability.
It effectively reduces installation difficulty and safety risks, improves construction efficiency and quality control, ensures the close connection between the guardrail and the bridge, and improves the practicality and safety of installation.
Smart Images

Figure CN222100613U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of guardrail installation structures, in particular to an assembled guardrail installation structure. Background Art
[0002] The bridge guardrail adopts a new type of assembled concrete anti-collision guardrail design. Among them, the Wohe River Eight Bridges: the total length of the bridge is 1201.0m (excluding the main bridge and the cross-embankment bridge, the guardrail length is 2724m), the bridge length is 120m (the guardrail length is 480m), the Sifang Lake Diversion Bridge: the bridge length is 210m (the guardrail length is 840m), the assembled concrete anti-collision guardrail is 4044m in total, and the assembled concrete anti-collision guardrail design adopts a new structural design. It is connected as a whole through the concrete base cavity and the bridge deck pre-embedded steel bars installed and grouting. The concrete base and the upper steel structure guardrail columns and beams are connected as a whole through screws. The guardrail consists of an upper steel structure and a lower concrete base. The concrete base adopts a prefabricated assembly form, and the net distance between adjacent bases is 5mm. The upper steel structure is mainly composed of double beams and columns, and the columns and concrete base are connected with pre-embedded screws.
[0003] In this plan, the total length of standard prefabricated concrete anti-collision guardrail is 4044m. At present, the prefabricated concrete anti-collision guardrail has the problems of great difficulty in installation and construction, high safety risk, low construction efficiency and uncontrollable quality. How to ensure safety and high quality while being fast, efficient and economical while meeting the requirements of prefabricated structure development concept, energy conservation and material reduction, green environmental protection, etc., is one of the key points of prefabricated bridge construction. When the prefabricated concrete anti-collision guardrail is installed, it is stuck on the outer wall of the base steel bar, but the connection between the prefabricated concrete guardrail and the bridge body is not tight enough, and it is easy to be displaced by external force, which is not practical. Therefore, an prefabricated guardrail installation structure is needed to improve the above problems. Utility Model Content
[0004] In order to solve the current situation of great construction difficulty, high safety risk, low construction efficiency and uncontrollable quality when installing the guardrail, the utility model provides an assembled guardrail installation structure to solve the above problems.
[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0006] An assembled guardrail installation structure comprises a guardrail base, an outer wall of which is embedded with a pre-buried screw, a hoisting assembly is installed on the outer wall of the guardrail base, a fixing groove is opened on the outer wall of the guardrail base, and a fixing assembly is installed on the inner wall of the fixing groove;
[0007] The hoisting assembly comprises a bottom plate, the bottom plate is mounted on the outer wall of the guardrail base, a vertical plate is mounted on the outer wall of the bottom plate, a mounting groove is provided on one side of the vertical plate and located on the outer wall of the bottom plate, the mounting groove is mounted on the outer wall of the embedded screw, a nut is threadedly connected on one side of the mounting groove and located on the outer wall of the embedded screw, a mounting hole is provided on the outer wall of the vertical plate, a fixing bolt is pluggably connected on the inner wall of the mounting hole, and a shackle is installed on the outer wall of the fixing bolt;
[0008] The fixing assembly includes a fixing block, which is embedded in the inner wall of the fixing groove, a limiting groove is provided on the outer wall of the fixing block, a limiting hole is provided on one side of the limiting groove and located on the inner wall of the fixing block, the limiting block is slidably connected on the inner wall of the limiting hole, a telescopic rod is installed on the outer wall of the limiting block, a telescopic spring is installed on one side of the telescopic rod and located on the outer wall of the limiting block, and one end of the telescopic rod is connected to the inner wall of the fixing block.
[0009] As a preferred solution of the utility model, the embedded screws are provided in multiple groups and are respectively located on the outer wall of the guardrail base, and the hoisting assembly is located on one side of the fixing groove.
[0010] As a preferred solution of the utility model, the fixing components are provided in multiple groups and are respectively located on the inner wall of the fixing groove, the vertical plate and the bottom plate are vertical structures, and the cross section of the bottom plate is an E-shaped structure.
[0011] As a preferred solution of the utility model, the installation grooves are provided in two groups and are respectively located on the outer wall of the bottom plate, and the nuts are provided in multiple groups and are respectively located on the outer wall of the embedded screw.
[0012] As a preferred solution of the utility model, the fixing bolt is located on one side of the embedded screw rod, and the fixing blocks are provided in multiple groups and are respectively located on the inner wall of the fixing groove.
[0013] As a preferred solution of the utility model, the cross section of the limiting groove is a funnel structure, and the limiting holes are provided in multiple groups and are respectively located on the inner wall of the fixing block.
[0014] As a preferred solution of the utility model, the limit block is a triangular structure, and the limit block is located in the inner cavity of the limit groove.
[0015] As a preferred solution of the utility model, the telescopic spring is located on the inner wall of the limiting hole and is connected in a sliding manner, and one end of the telescopic spring is connected to the inner wall of the fixing block.
[0016] Compared with the prior art, the utility model arranges a lifting component in the assembled guardrail installation structure, which can use embedded screws to fix the 2 cm thick base plate and the vertical plate connecting parts, and then fix the buckle to the inner wall of the mounting hole of the vertical plate with a fixing bolt, and then use a forklift to lift it up with the help of the buckle for installation. The installation process is relatively simple, thereby solving the current problems of assembled concrete anti-collision guardrails, such as difficult installation and construction, high safety risks, low construction efficiency, and uncontrollable quality.
[0017] By inserting the fixing groove of the guardrail base into the base steel bar of the bridge body, the base steel bar slides upward on the inner wall of the limiting groove of the funnel-shaped structure, so that the base steel bar contacts the outer wall of the triangular limiting block, so that the limiting block is squeezed by the base steel bar, and then the limiting block slides inward on the inner wall of the limiting hole, so that the telescopic spring is compressed. Then, when the base steel bar moves to one side of the limiting block, the compressed telescopic spring loses the extrusion force, so that the telescopic spring pushes the limiting block to slide reversely on the inner wall of the limiting hole, so that the limiting block is completely moved to the inner cavity of the limiting groove, so that the base steel bar is fixed in the inner cavity of the fixing block, which is convenient for fixation and the connection between the two is tighter, thereby solving the problem that the assembled concrete anti-collision guardrail is stuck on the outer wall of the base steel bar during installation, but the connection between the assembled concrete guardrail and the bridge body is not tight enough, it is easy to be displaced by external force impact, and the practicality is not good. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0019] Figure 2 This is a schematic diagram of the structure of the guardrail base of the utility model;
[0020] Figure 3 This is a schematic diagram of the structure of the fixing assembly of the utility model;
[0021] Figure 4 It is a schematic diagram of the structure of the hoisting assembly of the utility model.
[0022] In the figure: 1. guardrail base; 2. embedded screw; 3. lifting assembly; 301. bottom plate; 302. vertical plate; 303. mounting slot; 304. nut; 305. mounting hole; 306. fixing bolt; 307. shackle; 4. fixing slot; 5. fixing assembly; 501. fixing block; 502. limiting slot; 503. limiting hole; 504. limiting block; 505. telescopic rod; 506. telescopic spring. DETAILED DESCRIPTION
[0023] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0024] Example: See Figure 1-4 An assembled guardrail installation structure shown includes a guardrail base 1, an embedded screw 2 is installed on the outer wall of the guardrail base 1, a hoisting assembly 3 is installed on the outer wall of the guardrail base 1, a fixing groove 4 is opened on the outer wall of the guardrail base 1, and a fixing assembly 5 is installed on the inner wall of the fixing groove 4;
[0025] In this embodiment, specific reference Figure 1 and Figure 4 The hoisting assembly 3 includes a bottom plate 301, which is mounted on the outer wall of the guardrail base 1. A vertical plate 302 is mounted on the outer wall of the bottom plate 301. The vertical plate 302 and the bottom plate 301 are vertical structures. The cross section of the bottom plate 301 is an E-shaped structure. A mounting groove 303 is provided on one side of the vertical plate 302 and located on the outer wall of the bottom plate 301. The mounting groove 303 is provided with two groups and is respectively located on the outer wall of the bottom plate 301. The mounting groove 303 is installed on the outer wall of the embedded screw 2. A nut 304 is threadedly connected on one side of the mounting groove 303 and located on the outer wall of the embedded screw 2. The nut 304 is provided with multiple groups and is respectively located on the outer wall of the embedded screw 2. A mounting hole 305 is provided on the outer wall of the vertical plate 302. A fixing bolt 306 is plugged and connected on the inner wall of the mounting hole 305. The fixing bolt 306 is located on one side of the embedded screw 2. A shackle 307 is installed on the outer wall of the fixing bolt 306.
[0026] In this embodiment, specific reference Figure 2 and Figure 3The fixing assembly 5 includes a fixing block 501, which is embedded in the inner wall of the fixing groove 4. The fixing block 501 is provided with multiple groups and respectively located on the inner wall of the fixing groove 4. A limiting groove 502 is provided on the outer wall of the fixing block 501. The cross section of the limiting groove 502 is a funnel structure. A limiting hole 503 is provided on one side of the limiting groove 502 and located on the inner wall of the fixing block 501. The limiting hole 503 is provided with multiple groups and respectively located on the inner wall of the fixing block 501. The inner wall of the limiting hole 503 is connected to the sliding A limit block 504 is connected, and the limit block 504 is a triangular structure. The limit block 504 is located in the inner cavity of the limit groove 502. A telescopic rod 505 is installed on the outer wall of the limit block 504. A telescopic spring 506 is installed on one side of the telescopic rod 505 and located on the outer wall of the limit block 504. The telescopic spring 506 is located on the inner wall of the limit hole 503 and is connected in a sliding manner. One end of the telescopic spring 506 is connected to the inner wall of the fixed block 501, and one end of the telescopic rod 505 is connected to the inner wall of the fixed block 501.
[0027] Among them, the embedded screw rods 2 are provided in multiple groups and are respectively located on the outer wall of the guardrail base 1, the lifting components 3 are located on one side of the fixing groove 4, and the fixing components 5 are provided in multiple groups and are respectively located on the inner wall of the fixing groove 4. The structural dimensions of the embedded screw rods 2 are used for the installation of lifting fixtures. According to the diameter of the embedded screw rods 2 of this project, φ24mm, the slot size of the lifting fixture is set to 26mm, and the lifting fixture is welded with 2cm thick steel plates.
[0028] When working, the assembled guardrail installation structure of this scheme is installed on the outer wall of the embedded screw 2 through the installation groove 303. A nut 304 is threadedly connected on one side of the installation groove 303 and located on the outer wall of the embedded screw 2. A mounting hole 305 is opened on the outer wall of the vertical plate 302. A fixing bolt 306 is plugged in and connected to the inner wall of the mounting hole 305. A shackle 307 is installed on the outer wall of the fixing bolt 306. It is only necessary to use a 2 cm thick base plate 301 and a connecting piece of the vertical plate 302 according to the embedded screw 2, and then fix the shackle 307 on the inner wall of the mounting hole 305 of the vertical plate 302 with the fixing bolt 306. Then, use a forklift to lift it up with the shackle 307 for installation. The installation process is relatively simple, thereby solving the current problems of assembled concrete anti-collision guardrails, such as difficult installation and construction, high safety risks, low construction efficiency, and uncontrollable quality.
[0029] Under the action of the fixing groove 4 provided on the outer wall of the guardrail base 1, the fixing groove 4 of the guardrail base 1 is inserted into the base steel bar of the bridge body, and the limiting block 504 is slidably connected on the inner wall of the limiting hole 503. A telescopic rod 505 is installed on the outer wall of the limiting block 504, and a telescopic spring 506 is installed on one side of the telescopic rod 505 and on the outer wall of the limiting block 504. One end of the telescopic rod 505 is connected to the inner wall of the fixing block 501. Under the action of the funnel structure of the cross section of the limiting groove 502, the base steel bar slides upward on the inner wall of the limiting groove 502 of the funnel-shaped structure, so that the base steel bar contacts the outer wall of the triangular limiting block 504, so that the limiting block 504 is squeezed by the base steel bar, and then the limiting block 504 slides inward on the inner wall of the limiting hole 503, so that the telescopic spring 506 is compressed. Then, when the base steel bar moves to one side of the limiting block 504, the compressed telescopic spring 506 loses the extrusion force, so that the telescopic spring 506 pushes the limiting block 504 to slide in the opposite direction on the inner wall of the limiting hole 503, so that the limiting block 504 is completely moved into the inner cavity of the limiting groove 502, so that the base steel bar is fixed in the inner cavity of the fixing block 501, which is convenient for fixation and the connection between the two is tighter, thereby solving the problem that the assembled concrete anti-collision guardrail is stuck on the outer wall of the base steel bar during installation, but the connection between the assembled concrete guardrail and the bridge body is not tight enough, and it is easy to be displaced by external force, which is not practical.
[0030] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An assembled guardrail installation structure, comprising a guardrail base (1), characterized in that: An embedded screw rod (2) is installed on the outer wall of the guardrail base (1), a hoisting assembly (3) is installed on the outer wall of the guardrail base (1), a fixing groove (4) is opened on the outer wall of the guardrail base (1), and a fixing assembly (5) is installed on the inner wall of the fixing groove (4); The hoisting assembly (3) comprises a base plate (301), the base plate (301) being mounted on the outer wall of the guardrail base (1), a vertical plate (302) being mounted on the outer wall of the base plate (301), a mounting groove (303) being provided on one side of the vertical plate (302) and located on the outer wall of the base plate (301), the mounting groove (303) being mounted on the outer wall of the embedded screw rod (2), a nut (304) being threadedly connected on one side of the mounting groove (303) and located on the outer wall of the embedded screw rod (2), a mounting hole (305) being provided on the outer wall of the vertical plate (302), a fixing bolt (306) being pluggably connected to the inner wall of the fixing hole (305), and a shackle (307) being mounted on the outer wall of the fixing bolt (306); The fixing assembly (5) comprises a fixing block (501), the fixing block (501) being embedded and installed on the inner wall of the fixing groove (4), a limiting groove (502) being provided on the outer wall of the fixing block (501), a limiting hole (503) being provided on one side of the limiting groove (502) and located on the inner wall of the fixing block (501), a limiting block (504) being slidably connected on the inner wall of the limiting hole (503), a telescopic rod (505) being installed on the outer wall of the limiting block (504), a telescopic spring (506) being installed on one side of the telescopic rod (505) and located on the outer wall of the limiting block (504), and one end of the telescopic rod (505) being connected to the inner wall of the fixing block (501).
2. The assembled guardrail installation structure according to claim 1 is characterized in that: The embedded screw rods (2) are provided in multiple groups and are respectively located on the outer wall of the guardrail base (1), and the hoisting assembly (3) is located on one side of the fixing groove (4).
3. The assembled guardrail installation structure according to claim 1 is characterized in that: The fixing components (5) are provided in multiple groups and are respectively located on the inner wall of the fixing groove (4); the vertical plate (302) and the bottom plate (301) are vertical structures; and the cross section of the bottom plate (301) is an E-shaped structure.
4. The assembled guardrail installation structure according to claim 1 is characterized in that: The installation grooves (303) are provided in two groups and are respectively located on the outer wall of the bottom plate (301); the nuts (304) are provided in multiple groups and are respectively located on the outer wall of the embedded screw rod (2).
5. The assembled guardrail installation structure according to claim 1 is characterized in that: The fixing bolt (306) is located on one side of the embedded screw rod (2), and a plurality of fixing blocks (501) are provided and are respectively located on the inner wall of the fixing groove (4).
6. The assembled guardrail installation structure according to claim 1, characterized in that: The cross section of the limiting groove (502) is a funnel structure, and the limiting holes (503) are provided in multiple groups and are respectively located on the inner wall of the fixing block (501).
7. The assembled guardrail installation structure according to claim 1, characterized in that: The limiting block (504) is a triangular structure, and the limiting block (504) is located in the inner cavity of the limiting groove (502).
8. The assembled guardrail installation structure according to claim 1, characterized in that: The telescopic spring (506) is located on the inner wall of the limiting hole (503) and is connected in a sliding manner. One end of the telescopic spring (506) is connected to the inner wall of the fixing block (501).