Road reconstruction and extension medial strip guardrail structure
By cutting off the upper section of the old concrete guardrail in the guardrail of the central partition belt of the bridge and filling the gaps of the new concrete guardrail, adding cover plates and laying pipeline greening, the problems of collision prevention level improvement and pipeline greening are solved, and construction efficiency and guardrail collision resistance are improved. Reduced damage to the bridge deck.
Patent Information
- Application Number
- CN202420037233.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-05
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-01-05
AI Technical Summary
During the highway renovation and expansion, the anti-collision level improvement of the guardrail of the central partition belt of the bridge is restricted by the depth of the planting tendon, and the existing technology fails to fully utilize the existing guardrail, resulting in low construction efficiency and high cost, and pipeline layout and greening problems. Effective solution.
The upper section is cut off by using the old concrete guardrail, the new concrete guardrail is filled with the gap, and a concrete cover is added to the top wall of the old concrete guardrail to form a comprehensive pipeline layer and green belt to improve the collision resistance and utilization rate of the guardrail.
The collision resistance of the new concrete guardrail has been improved, the pipeline layout and greening problems have been solved, construction costs and damage to the bridge deck have been reduced, construction efficiency has been improved, and the impact on the existing bridge structure has been reduced.
Smart Images

Figure CN222100693U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a highway guardrail structure, in particular to a central dividing strip guardrail structure for highway reconstruction and expansion. Background Art
[0002] Since highway reconstruction and expansion is often the main road that affects regional social and economic development, completely closing traffic for construction will have a huge negative impact on the social economy and transportation of the area along the route. Therefore, most of the reconstruction and expansion projects that have been started in China adopt the construction organization method of "construction and opening to traffic" to minimize the impact of highway reconstruction and expansion on the social economy and residents' travel along the route. In order to ensure the normal operation of traffic, ensure the efficiency of road use, and reduce social impact, how to improve the construction efficiency of reconstruction and expansion projects has become a key and difficult issue that needs to be solved urgently.
[0003] As an important part of the highway, the reconstruction and expansion plan of the central median, especially the bridge section, is also an important part of the highway reconstruction and expansion process. At the same time, due to the differences between the old and new standards, the width of the central median, the height of the guardrail, the anti-collision level of the guardrail, the layout of pipelines, and the green belts usually need to be comprehensively considered and improved during the reconstruction and expansion. At present, the general method is to directly use the status quo without reconstruction and improvement; or completely dismantle the old concrete guardrail and then construct a new concrete guardrail, which fails to make full use of the existing guardrail. Not only is the cost high and the construction period long, but the improvement of the anti-collision level of the guardrail is restricted by the depth of the embedded reinforcement, and the pipeline layout and greening problems in the central median are not effectively solved. Therefore, in the reconstruction and expansion of the highway, the reconstruction plan of the guardrail in the central median of the bridge, the improvement of the anti-collision level of the guardrail, the construction efficiency, the subsequent pipeline layout and greening and other technical issues directly affect the utilization rate of the existing structure, the standard level after reconstruction and the cost during the highway reconstruction and expansion process. Summary of the invention
[0004] In order to overcome the shortcomings of the prior art, the purpose of the utility model is to provide a central median guardrail structure for highway reconstruction and expansion, which can make full use of the old concrete guardrail, solve the problem of insufficient reinforcement depth of the new concrete guardrail in the existing bridge superstructure, enhance the collision resistance of the modified concrete guardrail, and at the same time solve the pipeline layout or central median greening.
[0005] The purpose of the utility model is achieved by the following technical solutions:
[0006] A highway reconstruction and expansion central median guardrail structure comprises two old concrete guardrails, wherein the upper sections of the old concrete guardrails are cut off, leaving the root sections, and new concrete guardrails are provided on the outer sides of the two old concrete guardrails, the gap between the root sections of the old concrete guardrails and the new concrete guardrails is filled with concrete, and the top walls of the old concrete guardrails are cast with newly added concrete cover plates, and the reconstructed central median is provided with an integrated pipeline layer and a green belt from bottom to top, and integrated pipelines are laid in the integrated pipeline layer.
[0007] Specifically, the old concrete guardrail is arranged on the bridge.
[0008] Specifically, the new concrete guardrail is arranged on the driving lane side of the old concrete guardrail.
[0009] Specifically, the back side of the new concrete guardrail is tightly fitted with the collision surface of the old concrete guardrail, or a concrete filling layer is provided in the gap between the back side of the new concrete guardrail and the old concrete guardrail to ensure a tight fit.
[0010] Specifically, a newly added concrete cover plate is cast on the top wall of the old concrete guardrail, and the newly added concrete cover plate is closely attached to the back side of the new concrete guardrail.
[0011] Specifically, the integrated pipeline is arranged along the length direction of the new concrete guardrail, and is laid out within the range of the back side of the new concrete guardrail and the top surface or bottom surface of the old concrete guardrail after cutting.
[0012] Specifically, the green belt is arranged along the length direction of the new concrete guardrail and is arranged within the range of the back surface of the new concrete guardrail and the top surface of the old concrete guardrail.
[0013] Compared with the prior art, the beneficial effects of the present invention are:
[0014] When dismantling the old concrete guardrail, taking into account the weight of the guardrail after the renovation, pipeline layout and green space in the renovated central dividing strip, the upper half of the old concrete guardrail is cut off, and according to the width of the renovated and expanded central dividing strip, reinforcement is embedded on the bridge deck of the existing bridge superstructure, and a new concrete guardrail is poured. Concrete is filled in the gap between the old concrete guardrail and the new concrete guardrail until it is flush with the top surface of the old concrete guardrail after cutting; a concrete cover plate is added to the top surface of the old concrete guardrail after cutting, and both sides of the cover plate are close to the back of the new concrete guardrail.
[0015] Compared with the traditional bridge central median guardrail reconstruction scheme, the bridge central median guardrail reconstruction method of the utility model technical scheme makes full use of the old concrete guardrail, adds a cover plate after partial cutting, and solves the problem of collision resistance caused by insufficient reinforcement depth of the new concrete guardrail in the existing bridge superstructure; solves the pipeline layout and greening layout in the central median, improves space utilization, and enhances landscape effects; reduces the amount of guardrail removal work, improves construction efficiency, and reduces damage to the bridge deck; controls the load after reconstruction and minimizes the impact on the existing bridge superstructure.
[0016] The technical solution of the utility model makes full use of the old concrete guardrail, which can solve the problem of insufficient embedded reinforcement depth of the new concrete guardrail in the existing bridge superstructure, and improve the anti-collision ability of the new concrete guardrail after the renovation; a new central dividing strip cover is added to facilitate the laying of pipelines and central dividing strip greening facilities, and at the same time the left and right guardrails of the central dividing strip are connected to enhance the anti-collision ability of the concrete guardrail after the renovation; the workload of dismantling the old concrete guardrail is reduced, and the damage to the bridge deck and the workload of durability restoration are reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a schematic cross-section diagram of the old concrete guardrail;
[0018] Figure 2 It is a cross-sectional schematic diagram of the utility model.
[0019] In the figure: 1. Old concrete guardrail; 2. New concrete guardrail; 3. Concrete filling; 4. New concrete cover. DETAILED DESCRIPTION
[0020] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.
[0021] Combination Figure 1 , Figure 2 A highway reconstruction and expansion central median guardrail structure comprises two old concrete guardrails 1, the upper section of the old concrete guardrail 1 is cut off, and the root section remains. New concrete guardrails 2 are arranged on the outer sides of the two old concrete guardrails 1, and the gap between the root section of the old concrete guardrail 1 and the new concrete guardrail 2 is filled with concrete 3. A newly added concrete cover plate 4 is cast on the top wall of the old concrete guardrail 1, and the central median after reconstruction is provided with an integrated pipeline layer and a green belt from bottom to top, and integrated pipelines are laid in the integrated pipeline layer.
[0022] In this solution, the old concrete guardrail 1 is arranged on the bridge.
[0023] In this solution, the new concrete guardrail 2 is arranged on the driving lane side of the old concrete guardrail 1 .
[0024] In this solution, the back side of the new concrete guardrail 2 is tightly fitted with the collision surface of the old concrete guardrail 1, or the gap between the back side of the new concrete guardrail 2 and the old concrete guardrail 1 is filled with concrete to ensure a tight fit.
[0025] In this solution, a newly added concrete cover plate 4 is cast on the top wall of the old concrete guardrail 1 , and the newly added concrete cover plate 4 is in close contact with the back of the new concrete guardrail 2 .
[0026] In this solution, the integrated pipeline is set along the length direction of the new concrete guardrail and is laid out within the range of the back side of the new concrete guardrail and the top surface of the old concrete guardrail.
[0027] In this solution, the green belt is set along the length direction of the new concrete guardrail and is arranged within the range of the back side of the new concrete guardrail and the top surface or bottom surface of the old concrete guardrail after removal.
[0028] The technical effects of the utility model are:
[0029] When the old concrete guardrail 1 is demolished, the upper half of the old concrete guardrail 1 is cut off in combination with the weight of the guardrail after the reconstruction, pipeline layout and green space of the central dividing strip after the reconstruction, and reinforcement is embedded on the bridge deck of the existing bridge superstructure according to the width of the central dividing strip after the reconstruction and expansion, and the new concrete guardrail 2 is poured. Concrete is filled in the gap between the old concrete guardrail 1 and the new concrete guardrail 2 until it is flush with the top surface of the old concrete guardrail 1 after cutting; a concrete cover plate is added to the top surface of the old concrete guardrail 1 after cutting, and both sides of the cover plate are close to the back of the new concrete guardrail 2.
[0030] Compared with the traditional bridge central median guardrail reconstruction scheme, this bridge central median guardrail reconstruction method makes full use of the old concrete guardrail, adds a cover plate after partial cutting, and solves the problem of collision resistance caused by insufficient reinforcement depth of the new concrete guardrail 2 in the existing bridge superstructure; solves the pipeline layout and greening layout in the central median, improves space utilization, and enhances landscape effects; reduces the amount of guardrail removal work, improves construction efficiency, and reduces damage to the bridge deck; controls the load after reconstruction and minimizes the impact on the existing bridge superstructure.
[0031] This method makes full use of the old concrete guardrail 1, can solve the problem of insufficient reinforcement depth of the new concrete guardrail 2 in the existing bridge superstructure, and improve the anti-collision ability of the new concrete guardrail 2 after the renovation; a new central dividing strip cover is added to facilitate the laying of pipelines and central dividing strip greening facilities, and at the same time the left and right guardrails of the central dividing strip are connected to enhance the anti-collision ability of the concrete guardrail after the renovation; the workload of dismantling the old concrete guardrail 1 is reduced, and the damage to the bridge deck and the workload of durability restoration are reduced.
[0032] The above-mentioned implementation modes are only preferred implementation modes of the present invention, and cannot be used to limit the protection scope of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.
Claims
1. A central dividing strip guardrail structure for highway reconstruction and expansion, characterized in that: It comprises two old concrete guardrails, the upper half of which is cut off, leaving only the root section; a new concrete guardrail is provided on the outer side of each of the two old concrete guardrails; the gap between the root section of the old concrete guardrail and the new concrete guardrail is filled with concrete; a newly added concrete cover plate is cast on the top wall of the old concrete guardrail; after the renovation, the central dividing zone is provided with an integrated pipeline layer and a green belt from bottom to top, and integrated pipelines are laid in the integrated pipeline layer.
2. The central dividing strip guardrail structure for highway reconstruction and expansion according to claim 1 is characterized by: The old concrete guardrail is arranged on the bridge.
3. The central dividing strip guardrail structure for highway reconstruction and expansion according to claim 1 is characterized by: The new concrete guardrail is arranged on the carriageway side of the old concrete guardrail.
4. The central dividing strip guardrail structure for highway reconstruction and expansion according to claim 1 is characterized by: The back side of the new concrete guardrail is tightly fitted with the collision surface of the old concrete guardrail, or a concrete filling layer is provided in the gap between the back side of the new concrete guardrail and the old concrete guardrail to ensure a tight fit.
5. The central dividing strip guardrail structure for highway reconstruction and expansion according to claim 1 is characterized by: A newly added concrete cover plate is cast on the top wall of the old concrete guardrail, and the newly added concrete cover plate is closely attached to the back side of the new concrete guardrail.
6. The central dividing strip guardrail structure for highway reconstruction and expansion according to claim 1 is characterized by: The integrated pipeline is arranged along the length direction of the new concrete guardrail and is laid out within the range of the back side of the new concrete guardrail and the top surface or bottom surface of the old concrete guardrail after cutting.
7. The central dividing strip guardrail structure for highway reconstruction and expansion according to claim 1 is characterized by: The green belt is arranged along the length direction of the new concrete guardrail and is arranged within the range of the back surface of the new concrete guardrail and the top surface of the old concrete guardrail.