Isolation pile structure with inflatable bag deviation rectifying function

By setting up air bags and related devices on the isolation piles, active deviation correction and displacement control of the tunnel are achieved, passive protection and soil pollution in the existing technology are solved, and more effective tunnel protection and environmentally friendly construction methods are provided.

CN222100814UActive Publication Date: 2024-12-03CHINA UNITED ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420887906.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-26
Publication Date
2024-12-03
Estimated Expiration
2034-04-26

AI Technical Summary

Technical Problem

The existing isolation pile technology is a passive protective measure, and it cannot be effectively and proactively corrected, resulting in serious impact on deformation transmission of tunnels during foundation pit excavation, and the traditional grouting correction process has soil pollution problems.

Method used

Design an isolation pile structure with an air bag correction function. By setting up multiple air bags and related supporting devices on the isolation pile, the air bag is expanded by inflating to generate a deviation correction force, combining the flexible control of the air bag and the grouting pipe. Achieve active deviation correction and retain the grouting liquid in the airbag to avoid soil contamination.

Benefits of technology

It realizes precise control of tunnel displacement and active correction, strengthens the protection effect of isolation piles, avoids soil pollution, and provides flexible correction forms and efficient protection measures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222100814U_ABST
    Figure CN222100814U_ABST
Patent Text Reader

Abstract

The utility model provides an isolation pile structure with an inflatable bag deviation rectifying function, which can realize active deviation rectifying and strengthen the protection effect of an isolation pile. The structure comprises isolation piles, a tunnel and a foundation pit, wherein the isolation piles are arranged between the tunnel and the foundation pit; the grouting device is characterized by further comprising an air inflation bag deviation rectifying structure, and the air inflation bag deviation rectifying structure comprises an air inflation bag, a fixing piece, an air inflation opening, a grouting opening, an air inflation pipe, a grouting pipe, an air inflation pipe valve and a grouting pipe valve; a plurality of air inflation bags are arranged on the sides, close to the tunnel, of the isolation piles and are sequentially arranged from top to bottom. The inflatable bag is fixed on the isolation pile through a fixing piece; a grouting opening and an inflation opening are formed in the fixing part and are both communicated with the inflation bag; the inflation inlet is connected with an inflation tube, and an inflation tube valve is arranged on the inflation tube; the grouting opening is connected with a grouting pipe, and a grouting pipe valve is arranged on the grouting pipe.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to an isolation pile structure with an inflatable bag deviation correction function. Background Art

[0002] The utilization of urban underground space is becoming increasingly tight, and foundation pit excavation projects near existing operating subway tunnels are common. The excavation of the foundation pit will cause the unloading of the surrounding soil, resulting in corresponding deformation of the foundation pit retaining structure. The soil outside the foundation pit will move accordingly, causing stress redistribution in the soil on one side of the tunnel, which will cause deformation of the nearby existing tunnel, thereby affecting the normal operation of the tunnel and even damaging the tunnel structure. The subway tunnel itself is sensitive to deformation and needs to be controlled at the millimeter level. Therefore, certain measures need to be taken in actual engineering to protect the existing tunnel.

[0003] One of the common protection measures is to set up isolation piles between the foundation pit and the tunnel. The isolation piles are set between the foundation pit and the operating tunnel, which can limit the displacement of the soil between the foundation pit and the tunnel to a certain extent, weaken the deformation transfer process, and thus protect the tunnel. However, in actual engineering, there are gaps between the entire row of isolation piles, and the restriction effect on the soil is not very ideal. It is not economical to simply increase the pile diameter or reduce the pile spacing to enhance the protection effect, and it is easy to cause greater construction disturbances, endangering the safety of existing tunnels. In addition, the setting of isolation piles is a passive protection measure for the tunnel, which needs to be laid in advance before the foundation pit is excavated. When the tunnel is too deformed, it cannot play an active correction function and cannot effectively reduce the deformation development of the tunnel. Utility Model Content

[0004] The purpose of the utility model is to overcome the above-mentioned deficiencies in the prior art and to provide an isolation pile structure with an inflatable bag correction function, which can realize active correction and enhance the protective effect of the isolation pile.

[0005] The technical solution adopted by the utility model to solve the above-mentioned problems is: an isolation pile structure with an inflatable bag correction function, comprising an isolation pile, a tunnel and a foundation pit, wherein the isolation pile is arranged between the tunnel and the foundation pit; it is characterized in that: it also includes an inflatable bag correction structure, the inflatable bag correction structure includes an inflatable bag, a fixing part, an inflation port, a grouting port, an inflation pipe, a grouting pipe, an inflation pipe valve and a grouting pipe valve; an inflatable bag is arranged on the side of the isolation pile close to the tunnel, and there are multiple inflatable bags, which are arranged in sequence up and down; the inflatable bag is fixed to the isolation pile by a fixing part; a grouting port and an inflation port are installed on the fixing part, and both the grouting port and the inflation port are connected to the inflatable bag; the inflation port is connected to the inflation pipe, and an inflation pipe valve is arranged on the inflation pipe; the grouting port is connected to the grouting pipe, and a grouting pipe valve is arranged on the grouting pipe.

[0006] The fixing member of the utility model is provided with two upper and lower channels, wherein the upper channel is provided with an air filling port, and the lower channel is provided with a grouting port.

[0007] The inflation port and the grouting port described in the utility model are both hollow tubes.

[0008] The gas filling port and the grouting port described in the utility model are both bent at the tail, wherein the tail of the gas filling port is bent upward, and the tail of the grouting port is bent downward.

[0009] The utility model provides a bag storage box on the isolation pile, and the inflatable bag is stacked in the bag storage box.

[0010] The bag storage box of the utility model is provided with an opening, and two bag protection door panels which can be opened and closed up and down are provided at the opening.

[0011] The inflatable bags of the utility model are symmetrically arranged up and down with the buried depth of the tunnel axis as the center.

[0012] In the utility model, adhesive tape is pasted on the board seam between two bag protection door panels for temporary sealing.

[0013] Compared with the prior art, the utility model has the following advantages and effects:

[0014] The utility model comprises an inflatable bag, a grouting pipe and an inflating pipe.

[0015] The isolation pile of the utility model is provided with a pile cap on the top and a metal pile tip on the bottom.

[0016] 1) Realize active deviation correction and enhance the protective effect of isolation piles.

[0017] The traditional isolation pile technology is a passive protection measure, which reduces the impact of foundation pit excavation on the existing tunnel by hindering the transmission of soil deformation, and the protection effect is limited. The utility model adds an inflatable bag and related supporting devices on this basis, which can expand the corresponding inflatable bag arranged on the isolation pile by inflation, and the inflatable bag itself has a certain hardness and can expand evenly after inflation. It can generate a stable correcting force close to the tunnel side and is used to correct the tunnel. It is a combination of active and passive control measures to further enhance the protection of the tunnel.

[0018] 2) The airbag can be inflated or deflated multiple times, and the correction method is flexible.

[0019] The utility model provides an independent inflation pipe, grouting pipe and valve for each inflatable bag. When it is necessary to inflate air into a certain inflatable bag, the inflation pipe valve can be opened and the grouting pipe valve can be closed to realize the inflation process and correct the deviation of the tunnel. In the actual engineering construction process, when the influence of the tunnel excavation by the foundation pit is reduced, the displacement of the tunnel that needs to be corrected will also be reduced. In this case, the previous expansion of the inflatable bag is too large, which may cause the tunnel to deform away from the foundation pit. At this time, the grouting pipe valve can be opened to slowly deflate and monitor the tunnel displacement in real time to return to the normal range. The inflation-type deviation correction can adjust the size of the correction that has been made according to the complex on-site conditions. This feature is not available in the grouting correction, and the correction form is more flexible.

[0020] 3) Realize the control of tunnel displacement.

[0021] The inflatable bags are arranged at different isolation piles and at different depths, and can achieve precise correction through differentiated expansion, that is, first correct the main deformation section, and then correct the secondary deformation area. When choosing inflatable bags at different depths, the inflatable bags at the same depth as the tunnel burial depth can be inflated first, mainly to correct horizontal deformation, and then the upper or lower inflatable bags can be inflated to correct the vertical displacement of the tunnel.

[0022] 4) Avoid large amounts of slurry from polluting the soil, which is green and environmentally friendly.

[0023] In the utility model, in addition to a part of slurry seeping out of the bedrock for fixing the isolation piles, inflation is mainly used in the soil for correction. The cement slurry injected for filling in the later stage is also retained in the inflatable bag, avoiding the pollution caused by large-scale grouting in the soil in the traditional grouting correction process. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a side structural schematic diagram of an embodiment of the utility model;

[0025] Figure 2 It is a schematic diagram of the planar structure of an embodiment of the utility model;

[0026] Figure 3 It is a side view structural schematic diagram of the assembly of the isolation pile and the inflatable bag deviation correction structure of the embodiment of the utility model;

[0027] Figure 4 It is a schematic diagram of the planar structure of the isolation pile and the inflatable bag deviation correction structure assembled in the embodiment of the utility model;

[0028] Figure 5 This is a schematic diagram of the structure of the inflatable bag before inflation in the embodiment of the utility model;

[0029] Figure 6 This is a schematic diagram of the structure of the inflatable bag after inflation according to the embodiment of the utility model;

[0030] Figure 7 This is a schematic diagram of the inflatable bag structure after grouting filling according to an embodiment of the utility model. DETAILED DESCRIPTION

[0031] The present invention will be further described in detail below with reference to the accompanying drawings and through examples. The following examples are provided to explain the present invention, but the present invention is not limited to the following examples.

[0032] The embodiment of the utility model comprises an isolation pile 1, a tunnel 2, a foundation pit 3 and an inflatable bag deviation correction structure.

[0033] During the excavation of foundation pit 3, the side wall will deform into the pit, causing the tunnel 2 to deform toward one side of foundation pit 3; the isolation pile 1 is arranged between tunnel 2 and foundation pit 3, which can hinder the deformation transmission of soil to a certain extent, and play a role in initially reducing the deformation of tunnel 2. A pile cap 5 is arranged on the top of the isolation pile 1, and a metal pile tip 6 is arranged on the bottom. The metal pile tip 6 is inserted into the bedrock layer. The upper pile body of the metal pile tip 6 is circumferentially provided with end and tail slurry holes 7, which can seep out cement slurry during the internal pouring of concrete, and play a role in stabilizing the isolation pile 1. There are multiple isolation piles 1, which are arranged in a straight line, and the arrangement direction is parallel to the direction of tunnel 2. The arrangement center is close to the maximum displacement of tunnel 2, and the two sides are arranged symmetrically; adjacent isolation piles 1 are connected and reinforced by a crown beam. The isolation pile 1 has an isolation pile casing 15.

[0034] The inflatable bag deviation correction structure includes an inflatable bag 4, a bag storage box 8, a bag protection door panel 9, a fixing part 10, an inflating port 11, a grouting port 12, an inflating pipe 13, a grouting pipe 14, an inflating pipe valve 16 and a grouting pipe valve 17.

[0035] An inflatable bag 4 is arranged on one side of the middle section of the isolation pile 1 near the tunnel 2. The inflatable bag 4 is made of a high-elasticity, high-strength rubber film and has a certain hardness. After being inflated, it can expand evenly in an elliptical shape under the action of soil pressure. Before being inflated, the inflatable bag 4 can be folded and contracted in the bag storage box 8; there are multiple inflatable bags 4, which are arranged in sequence up and down. The number of inflatable bags 4 installed should be designed in advance according to the possible correction amount of the tunnel 1, and it is advisable to arrange them symmetrically up and down with the buried depth of the tunnel axis as the center. In this embodiment, a total of 3 inflatable bags 4 are arranged up and down along the isolation pile 1. In the correction process, the inflatable bags 4 on the isolation pile 1 in the main deformation area are first inflated for correction, and then the inflatable bags 4 on the isolation pile 1 in the secondary deformation area are inflated for correction. During the correction process, the size of the inflation amount and the inflation position need to be adjusted according to the real-time displacement monitoring results of the tunnel. At the same time, during the correction process, the middle airbag 4 is inflated first, mainly to correct the horizontal displacement deformation of the tunnel 2. Then, if the tunnel 2 has downward settlement deformation, the airbag 4 at the lower end can be inflated. If the tunnel 2 has upward displacement deformation, the airbag 4 at the upper end can be inflated. The specific inflation amount and inflation position can be flexibly adjusted according to the real-time displacement monitoring results of the tunnel. It should be noted that the displacement of the tunnel after inflation has a certain lag, and the inflation process should be slow and smooth, and adjustments should be made in full combination with the deformation of the tunnel.

[0036] The inflatable bag 4 is fixed to the wall of the isolation pile casing 15 by the fixing part 10. The fixing part 10 is embedded in the isolation pile casing 15, and the gap is tightly sealed; the fixing part 10 is cylindrical, and its height is the same as the wall thickness of the isolation pile casing 15, and the fixing part 10 is arranged near one side of the tunnel 2. Two upper and lower channels are reserved on the fixing part 10, and the inflation port 11 is installed in the upper channel, and the grouting port 12 is installed in the lower channel. The inflation port 11 and the grouting port 12 are both hollow tubes with bent tails, wherein the tail of the inflation port 11 pipe is bent upward, and the tail of the grouting port 12 pipe is bent downward; the grouting port 12 and the inflation port 11 are both connected to the inflatable bag 4. The inflation port 11 is connected to the inflation pipe 13, which is laid along the left side of the inner wall of the isolation pile casing 15 and eventually leads to the ground, and an independent inflation pipe valve 16 is set at the end; the grouting port 12 is connected to the grouting pipe 14, which is laid along the right side of the isolation pile casing 15 and eventually leads to the ground, and an independent grouting pipe valve 17 is set at the end. One inflatable bag 4 is equipped with a grouting pipe 14 and an inflation pipe 13. The inflation pipes 13 leading to different inflatable bags 4 are independent of each other, neatly arranged, and uniformly located on the left side of the bag storage box 8. The grouting pipes 14 leading to different inflatable bags 4 are independent of each other, neatly arranged, and uniformly located on the right side of the bag storage box 8. Each inflation pipe 13 and grouting pipe 14 leading to the ground need to be independently numbered to facilitate identification during subsequent inflation and grouting.

[0037] With the fixing member 10 as the center, a bag storage box 8 is arranged on the isolation pile sleeve 15, and the bottom of the side wall of the bag storage box 8 is close to the isolation pile sleeve 15. The bag storage box 8 is provided with an opening, and two bag protection door panels 9 that can be opened and closed are arranged at the opening. One end of the bag protection door panel 9 is installed on the upper and lower ends of the bag storage box 8, and the other end is in contact with each other, which can completely cover the top of the bag storage box 8; before inflation, the upper and lower bag protection door panels 9 at the opening of the bag storage box 8 are in a closed state, and the board seam between the two bag protection door panels 9 is affixed with tape for temporary sealing to prevent them from opening outwards during the sinking of the isolation pile 1; the inflatable bag 4 is stacked in the bag storage box 8, and the inflatable bag 4 will push open the bag protection door panel 9 and expand outwards after inflation. When the air bag 4 is inflated using the inflation tube 13 and the inflation port 11, the air bag 4 gradually expands and squeezes the bag door panel 9. When its pressure is greater than the external water and soil pressure, the upper and lower bag door panels 9 will be squeezed outward, and the air bag 4 will further expand outward, squeezing the surrounding soil, thereby forming a correcting force toward one side of the tunnel 4 to correct the tunnel 2. When the construction of the foundation pit 3 is completed and will not cause further deformation to the tunnel 2, the grouting pipe 14 is connected to the grouting equipment, the grouting pipe valve 17 is opened, and the grouting pipe 14 is used to perform high-pressure grouting filling in the inflatable bag 4 that has been inflated. During the grouting filling process, the inflation pipe valve 16 is opened at the same time. During the grouting process, the gas of equal volume inside is released at the same speed to ensure that the inflatable bag 4 will not further expand or shrink rapidly. When the amount of gas discharged from one end of the inflation pipe 13 is significantly reduced and the slurry overflows, the grouting is stopped, the inflation pipe valve 16 and the grouting pipe valve 17 are closed, the grouting equipment is removed, and the grouting filling inside the inflatable bag 4 is completed. Avoid the subsequent slow leakage of the inflatable bag 4 over time to affect the displacement of the tunnel 2.

[0038] The construction method of the utility model embodiment comprises the following steps:

[0039] 1) Scheme design: Comprehensively consider the excavation size, depth, distance from tunnel 2, support conditions of foundation pit 3 and other factors, judge the impact of foundation pit 3 excavation on tunnel 2 and its scope, and formulate the layout plan of isolation pile 1 and inflatable bag 4 correction structure in combination with the safety protection standard of tunnel and bedrock depth. Isolation pile 1 should be arranged in a straight line and parallel to the direction of tunnel 2. The center of arrangement should be placed at the position with the largest deformation of tunnel. The installation of inflatable bag 4 should be symmetrical in the form of up and down symmetry, and the center of symmetry should be flush with the buried depth of the axis of tunnel 2 to be corrected.

[0040] 2) On-site measurement, positioning and material preparation: Level the construction site, measure and mark the points of the isolation pile 1 at the construction site according to the design plan, and prefabricate the inflatable bag 4, isolation pile casing 15, metal pile tip 6, bladder box 8, inflation tube 13, grouting tube 14, steel cage and other materials in advance.

[0041] 3) Installation of the inflatable bag 4: According to the layout of the inflatable bag 4, determine the installation position of the inflatable bag 4 on the isolation pile casing 15 and mark it; first, insert the hollow tubes corresponding to the inflation port 11 and the grouting port 12 into the reserved holes on the fixing part 10. During installation, pay attention to the inflation port 11 being set at the upper end, and the tail end of the pipe being bent upward, and the grouting port 12 being set at the lower end, and the tail end of the pipe being bent downward. After installation, check that the gap between the hollow tube and the hole is filled tightly to ensure that there is no air leakage; connect the inflation pipe 13 and the grouting pipe 14 of corresponding length to the inflation port 11 and the grouting port 12 respectively to ensure that the connection is firm; drill holes at the marked installation position of the inflatable bag 4, and the size of the holes should be It should be ensured that the inflatable bag 4 structure can be taken out from the inside of the casing; one end of the inflatable bag 4 is inserted into the casing from the top of the isolation pile casing 15, and the inflatable bag 4 is taken out from the hole, and then the fixing part 10 is fixed to the hole by hot melting. The larger hole is filled with the same material as the isolation pile casing 15 to ensure stable installation; the inflatable tube 13 and the grouting tube 14 are fixed at a certain distance by iron wire so that the two are close to the inner wall of the isolation pile casing 15; all the inflatable bags 4, inflatable tubes 13, and grouting tubes 14 are installed in place in the same way to ensure the installation quality. The inflatable tube 13 and the grouting tube 14 are numbered at the end exposed to the ground to distinguish them.

[0042] 4) Installation of the bag storage box 8: Install the bag storage box 8 at the position of each air bag 4. The installation position is centered on the fixing piece 10. The bottom of the side wall fits tightly with the isolation pile sleeve 15. Buffer materials are set on the upper and lower side walls to fix them firmly to prevent them from falling off during the sinking of the isolation pile 1. The air bags 4 are neatly stacked in the bag storage box 8 before being inflated. The bag protection door panels 9 are ensured to be able to be opened up and down smoothly. After the inspection, stick sealing tape on the gap between the upper and lower bag protection door panels 9 to prevent the bag protection door panels 9 from opening outwards during the sinking of the isolation pile 1. After all the bag storage boxes 8 are installed, the isolation pile sleeves 15 are uniformly placed for standby use.

[0043] 5) Construction of isolation pile 1: Use a drilling machine to drill holes at the marked points in sequence. During the drilling process, the drilling angle needs to be strictly controlled to ensure verticality. The drilling depth needs to ensure that the hole is drilled into the bedrock layer for a certain distance, and the end and tail grouting holes 7 can enter the bedrock layer; when the hole reaches the specified depth, sink the pile pipe of the isolation pile 1, and ensure that it is inserted vertically during the sinking process, and the installation side of the air bag 4 needs to face the direction of the tunnel 2; after the pile pipe is inserted to the specified depth, sink the pre-prepared steel cage into the pile pipe, and then pour concrete into it, vibrating while pouring to ensure the quality of the pile, while avoiding damage to the inner inflation pipe 13 and grouting pipe 14 ; It should be noted that a small section of steel bar is reserved on the top of the isolation pile 1. Since the end slurry holes 7 are set on the surface of the isolation pile 1 inserted into the bedrock section, the poured concrete slurry can penetrate from the inside of the isolation pile 1 into the surrounding bedrock gaps, further increasing the stability of the isolation pile 1; when all the isolation columns 1 are driven, the steel bars reserved on the top of the isolation pile 1 are used to cast the pile cap 5, and the crown beam is used to connect the isolation piles 1 into a whole to enhance the deformation resistance of the isolation pile 1; during the construction process, the inflation pipe 13 and the grouting pipe 14 exposed on the ground are wrapped and protected. After the construction of the isolation pile 1 is completed, each pipe is numbered separately and managed in a unified manner.

[0044] 6) Installation of deformation monitoring device in tunnel 2: Before excavation of foundation pit 3, a real-time deformation monitoring device is first installed in the section of tunnel 2 that may be affected by deformation. A fully automatic total station is used to monitor the displacement changes of tunnel 2 during the subsequent excavation of foundation pit 3 and the correction process of inflatable bag 4. Multiple monitoring sections are set in the monitoring section, and each monitoring section has five deformation monitoring points on both sides of the tunnel vault, arch waist and roadbed.

[0045] 7) Dynamic correction process of tunnel 2 deformation: During the excavation of foundation pit 3, if the deformation of tunnel 2 is too large, the inflatable bag 4 on each isolation pile 1 is used for inflation correction; when inflating a certain inflatable bag 4, it is first necessary to find the corresponding inflatable pipe 13 and grouting pipe 14 on the ground according to the number, open the inflatable pipe valve 16, close the grouting pipe valve 17, and then connect the inflatable pipe 13 to the inflation device to slowly inflate the corresponding inflatable bag 4. If the correction amount is too large, the inflation can be stopped and the grouting pipe valve 17 can be opened to perform a slow deflation operation to reduce the correction effect. When a certain inflatable bag 4 reaches the designed correction effect, the inflatable pipe valve 16 and the grouting pipe valve 17 can be closed at the same time. The slurry pipe valve 17 maintains the shape of the inflatable bag 4; for the inflatable bags 4 on different isolation piles 1, it is advisable to first select the isolation pile 1 closest to the larger deformation area of ​​the tunnel for inflation and correction, and then simultaneously inflate the inflatable bags 4 on the isolation piles 1 on both sides to correct the secondary deformation area of ​​the tunnel 2; for the inflatable bags 4 on the same isolation pile 1, it is advisable to first select the inflatable bag 4 with the same depth as the axis of the tunnel 2 to correct the horizontal displacement of the tunnel 2, and then use the inflatable bag 4 on the upper or lower side to correct the vertical displacement of the tunnel 2; during the correction process, it is necessary to monitor the displacement of the tunnel 1 in real time, dynamically adjust the inflation and deflation process of each inflatable bag 4, and realize the real-time dynamic correction of the displacement of the tunnel by the inflatable bag 4;

[0046] 8) Grouting filling: When the construction of foundation pit 3 is completed and will not cause further deformation to tunnel 2, the inflation equipment is removed, the grouting pipe 14 is connected to the grouting equipment, the grouting pipe valve 17 is opened, and the grouting pipe 14 is used to perform high-pressure grouting filling in the inflatable bag 4 that has been inflated. During the grouting filling process, the inflation pipe valve 16 is opened at the same time. During the grouting process, the gas of equal volume inside is released at the same speed to ensure that the inflatable bag 4 will not further expand or shrink rapidly. When the amount of gas discharged from one end of the inflation pipe 13 is significantly reduced and the slurry overflows, the grouting is stopped, the inflation pipe valve 16 and the grouting pipe valve 17 are closed, and the grouting equipment is removed to complete the grouting filling inside the inflatable bag 4. Grouting filling is performed on all the inflatable bags 4 that have been inflated with gas in the same way to prevent the subsequent inflatable bags 4 from slowly leaking over time and affecting the displacement of tunnel 2.

[0047] In addition, it should be noted that the shapes and names of the parts and components of the specific embodiments described in this specification may be different, and the above content described in this specification is only an example of the structure of the utility model. All equivalent changes or simple changes made based on the structure, features and principles described in the patent concept of the utility model are included in the protection scope of the utility model patent. Technicians in the technical field of the utility model can make various modifications or supplements to the specific embodiments described or replace them in a similar manner, as long as they do not deviate from the structure of the utility model or exceed the scope defined by the claims, they should all fall within the protection scope of the utility model.

Claims

1. An isolation pile structure with an inflatable bag deviation correction function, comprising an isolation pile, a tunnel and a foundation pit, wherein the isolation pile is arranged between the tunnel and the foundation pit; characterized in that: It also includes an inflatable bag correction structure, which includes an inflatable bag, a fixing, an inflation port, a grouting port, an inflation pipe, a grouting pipe, an inflation pipe valve and a grouting pipe valve; an inflatable bag is arranged on the side of the isolation pile close to the tunnel, and there are multiple inflatable bags, which are arranged in sequence up and down; the inflatable bag is fixed to the isolation pile by a fixing; a grouting port and an inflation port are installed on the fixing, and the grouting port and the inflation port are both connected to the inflatable bag; the inflation port is connected to the inflation pipe, and an inflation pipe valve is provided on the inflation pipe; the grouting port is connected to the grouting pipe, and a grouting pipe valve is provided on the grouting pipe.

2. The isolation pile structure with an inflatable bag deviation correction function according to claim 1 is characterized in that: The fixing member is provided with two upper and lower channels, the upper channel is provided with an air filling port, and the lower channel is provided with a grouting port.

3. The isolation pile structure with self-inflating bag deviation correction function according to claim 2 is characterized by: The inflation port and the grouting port are both hollow tubes.

4. The isolation pile structure with self-inflating bag deviation correction function according to claim 3 is characterized by: The inflation port and the grouting port are both bent at the tail, wherein the tail of the inflation port is bent upwards, and the tail of the grouting port is bent downwards.

5. The isolation pile structure with an inflatable bag deviation correction function according to claim 1 is characterized in that: A bag storage box is arranged on the isolation pile, and the inflatable bag is stacked in the bag storage box.

6. The isolation pile structure with self-inflating air bag deviation correction function according to claim 5 is characterized by: The bag storage box is provided with an opening, and the opening is provided with two bag protection door panels which can be opened and closed up and down.

7. The isolation pile structure with an inflatable bag deviation correction function according to claim 1 is characterized in that: The inflatable bags are arranged symmetrically up and down with the buried depth of the tunnel axis as the center.

8. The isolation pile structure with self-inflating air bag deviation correction function according to claim 6 is characterized by: Tape is pasted on the seam between the two bag door panels for temporary sealing.

9. The isolation pile structure with self-inflating air bag deviation correction function according to claim 1 is characterized by: An inflatable bag is equipped with a grouting pipe and an inflation pipe.

10. The isolation pile structure with self-inflating air bag deviation correction function according to claim 1 is characterized in that: The top of the isolation pile is provided with a pile cap, and the bottom is provided with a metal pile tip.