Integral concrete prefabricated inspection well for electric power
By setting an annular connecting block and through holes in the wellbore adjustment block of the inspection well, placing steel bars and filling the mortar, the sealing problem of the inspection well under lateral force is solved, and higher lateral force tolerance and sealing are achieved , prevents soil moisture from entering.
Patent Information
- Application Number
- CN202420631551.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-29
AI Technical Summary
During the installation process, the lateral force caused by the difference in soil density causes the rubber ring to be squeezed and reduce the sealing, causing moisture in the soil to enter the inspection well, affecting maintenance.
An integral concrete prefabricated inspection well is adopted. By setting an annular connecting block and through holes in the wellbore adjustment block, rebars are placed and mortar are filled, the lateral force tolerance of the wellbore is enhanced, and the sealing ability is improved through the mortar sealing groove.
It effectively improves the ability of the inspection well to withstand lateral forces, avoids the entry of moisture in the soil, and enhances the connection strength and sealing between the wellbore and the inspection well body.
Smart Images

Figure CN222100950U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of inspection wells, in particular to an integral concrete prefabricated inspection well for electric power. Background Art
[0002] Inspection wells are set up for the maintenance of urban underground infrastructure such as power supply, water supply, drainage, sewage, communication, cable TV, gas pipes, street light lines, etc., and are easy to install. They are generally set up at the intersection of pipelines, bends, places where pipe diameters or slopes change, and at regular intervals on straight pipe sections to facilitate regular inspection of auxiliary structures. In order to facilitate regular inspection, cleaning and dredging or inspection of well operations, well-shaped structures made of plastic one-piece injection molding or bricks are used.
[0003] When installing an inspection well, multiple well adjustment blocks are usually used to form a complete well, which is connected by a tongue-and-groove method and is used in conjunction with a rubber ring to ensure the sealing of the well. However, during use, the soil around the inspection well may have different soil densities at different locations and heights due to human or natural factors, causing one side of the inspection well to be subjected to a large lateral force. In addition, since the well composed of well adjustment blocks uses a tongue-and-groove method, one side of the rubber ring used to increase the sealing is squeezed. Over a long period of time, the elasticity of the squeezed part of the rubber ring gradually decreases and cannot be fully restored, resulting in gaps between the well adjustment blocks when the lateral force on the well changes, allowing moisture in the soil to enter the inspection well, affecting the staff's entry into the inspection well for maintenance. Utility Model Content
[0004] The utility model aims to provide an integral prefabricated concrete inspection well for electric power, which can improve the bearing capacity of the shaft of the inspection well for lateral force and prevent moisture in the soil from entering the inspection well.
[0005] In order to achieve the above-mentioned purpose, an integral prefabricated concrete inspection well for electric power is provided, comprising: an inspection well body, one end of the inspection well is provided with a cable threading hole and a communication threading hole, and a plurality of cable threading holes are provided, the upper end of the inspection well body is fixedly connected with a wellhead, and the wellhead is connected with the inspection well body, the upper end of the wellhead is provided with an annular placement groove, the upper end of the wellhead is provided with an annular wellbore adjustment block, the lower middle part of the wellbore adjustment block is fixedly connected with an annular connecting block, and the connecting block is located in the placement groove and slidably connected with the side wall of the placement groove, the upper end of the wellbore adjustment block is provided with a circular through hole, and the through hole passes through the wellbore adjustment block and the connecting block downward in sequence, and steel bars are placed in the through hole. It can improve the bearing capacity of the wellbore of the inspection well for lateral force and prevent moisture in the soil from entering the inspection well.
[0006] According to the one-piece prefabricated concrete inspection well for electric power, a lifting nut is installed at the upper end of the inspection well body, and four lifting nuts are arranged and distributed in a rectangular shape at the upper end of the inspection well, so as to be used for lifting equipment to lift the inspection well body.
[0007] According to the one kind of monolithic prefabricated concrete inspection well for electric power, an annular sealing groove is provided at the bottom of the placement groove, and the sealing groove is located in the middle of the placement groove, and the sealing groove extends downward to the wellhead, and the sealing groove is filled with mortar. The gap between the inspection well body and the wellbore adjustment block can be eliminated, and the connection strength between the two can be improved.
[0008] According to the monolithic prefabricated concrete inspection well for electric power, the diameter of the steel bar is smaller than the diameter of the through hole, and the lower end of the steel bar extends to the bottom of the sealing groove, and the gap between the side wall of the through hole and the steel bar is filled with mortar to prevent the steel bar from shaking in the through hole and ensure the bearing capacity of the wellbore against lateral force.
[0009] According to the one-piece prefabricated concrete inspection well for electric power, a sewage pipe is fixedly connected to the lower end of the inspection well body, and the sewage pipe is connected to the inspection well body, so as to discharge sewage in the inspection well.
[0010] According to the one-piece prefabricated concrete inspection well for electric power, an annular connecting groove is provided in the middle of the upper end of the well adjustment block, and the connecting groove has the same shape and size as the placement groove, and the through hole is located in the middle of the connecting groove, so that the well adjustment block can be assembled conveniently and the well height can be freely changed.
[0011] According to the monolithic prefabricated concrete inspection well for electric power, a plurality of through holes are provided, and the plurality of through holes are equidistantly distributed around the well adjustment block, thereby improving the bearing capacity of each part of the well adjustment block against lateral forces.
[0012] According to the one kind of monolithic prefabricated concrete inspection well for electric power, the side wall of the connection groove is fixedly connected with a rubber pad to ensure the sealing performance when multiple shaft adjustment blocks are connected.
[0013] The beneficial effects of the utility model are as follows:
[0014] 1. Assemble the wellbore adjusting block and the inspection well body by cooperating the placement groove in the wellhead of the inspection well body with the connecting block at the lower end of the wellbore adjusting block. Add mortar to the sealing groove so that the mortar can play a bonding role when the wellbore adjusting block is connected to the inspection well body, and improve the sealing between the wellbore adjusting block and the inspection well body.
[0015] 2. By utilizing the connection grooves and connection blocks on the shaft adjusting blocks, it is convenient to combine multiple shaft adjusting blocks into a shaft, and by placing steel bars in the through holes of the shaft adjusting blocks, the shaft composed of the shaft adjusting blocks can be improved in its ability to withstand lateral forces.
[0016] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The utility model is further described below in conjunction with the accompanying drawings and embodiments;
[0018] Figure 1 This is a three-dimensional structural diagram of an integral prefabricated concrete inspection well for power use according to the utility model;
[0019] Figure 2 This is a cross-sectional structural diagram of the main body of an integral prefabricated concrete inspection well for electric power use according to the utility model;
[0020] Figure 3 This is a cross-sectional structural diagram of a shaft adjustment block assembly of an integral prefabricated concrete inspection shaft for electric power use according to the utility model;
[0021] Figure 4 for Figure 2 Enlarged structural diagram of point A in the middle.
[0022] Legend:
[0023] 1. Shaft adjustment block; 2. Lifting nut; 3. Inspection well body; 4. Drain pipe; 5. Cable threading hole; 6. Communication threading hole; 7. Wellhead; 8. Connection block; 9. Rebar; 10. Connection groove; 11. Through hole; 12. Placement groove; 13. Sealing groove. DETAILED DESCRIPTION
[0024] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.
[0025] Reference Figure 1-4The utility model embodiment is an integral concrete prefabricated inspection well for electric power, which includes: an inspection well body 3, one end of the inspection well is provided with a cable threading hole 5 and a communication threading hole 6, and the cable threading hole 5 is provided with a plurality of them, the upper end of the inspection well body 3 is fixedly connected with a wellhead 7, and the wellhead 7 is communicated with the inspection well body 3, the upper end of the wellhead 7 is provided with an annular placement groove 12, the upper end of the wellhead 7 is provided with an annular wellbore adjustment block 1, the middle part of the lower end of the wellbore adjustment block 1 is fixedly connected with an annular connecting block 8, and the connecting block 8 is located in the placement groove 12 and is slidably connected to the side wall of the placement groove 12, the upper end of the wellbore adjustment block 1 is provided with a circular through hole 11, and the through hole 11 passes through the wellbore adjustment block 1 and the connecting block 8 downward in sequence, and a steel bar 9 is placed in the through hole 11.
[0026] A lifting nut 2 is installed at the upper end of the inspection well body 3, and four lifting nuts 2 are provided and distributed in a rectangular shape at the upper end of the inspection well.
[0027] An annular sealing groove 13 is provided at the bottom of the placement groove 12 , and the sealing groove 13 is located in the middle of the placement groove 12 . The sealing groove 13 extends downward to the wellhead 7 , and the sealing groove 13 is filled with mortar.
[0028] The diameter of the steel bar 9 is smaller than the aperture of the through hole 11 , and the lower end of the steel bar 9 extends to the bottom of the sealing groove 13 , and the gap between the side wall of the through hole 11 and the steel bar 9 is filled with mortar.
[0029] A sewage pipe 4 is fixedly connected to the lower end of the inspection well body 3 , and the sewage pipe 4 is communicated with the inspection well body 3 .
[0030] An annular connecting groove 10 is provided in the middle of the upper end of the shaft adjusting block 1 , and the connecting groove 10 is the same in shape and size as the placement groove 12 , and the through hole 11 is located in the middle of the connecting groove 10 .
[0031] A plurality of through holes 11 are provided, and the plurality of through holes 11 are equidistantly distributed around the circumference of the wellbore adjustment block 1 .
[0032] A rubber pad is fixedly connected to the side wall of the connecting groove 10 .
[0033] Working principle: When in use, use a lifting device with the lifting nut 2 to put the inspection well body 3 into the pit, then install the wellbore adjustment block 1 on the upper end of the wellhead 7 of the inspection well body 3, first fill the sealing groove 13 in the wellhead 7 with mortar, then put the connecting block 8 at the lower end of the wellbore adjustment block 1 into the placement groove 12 to complete the connection between the wellbore adjustment block 1 and the inspection well body 3, and according to the wellbore height that the wellbore adjustment block 1 needs to be assembled into, cut off a number of steel bars 9, and put the steel bars 9 into the through hole 11 of the wellbore adjustment block 1, so that the lower end of the steel bars 9 Enter the mortar in the sealing groove 13. When the wellbore adjusting block 1 is assembled, the wellbore adjusting block 1 to be installed is lifted and moved above the installed wellbore adjusting block 1, so that the connecting block 8 of the wellbore adjusting block 1 is downward, and the through holes 11 between the wellbore adjusting blocks 1 are overlapped, so that the steel bar 9 enters the through hole 11 of the wellbore adjusting block 1 to be installed, and the connecting groove 10 between the wellbore adjusting blocks 1 is combined with the connecting block 8 to form a wellbore, and finally mortar is added to the through hole 11 to avoid gaps between the steel bar 9 and the inner wall of the through hole 11.
[0034] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.
Claims
1. An integral prefabricated concrete inspection well for electric power, characterized in that: include: An inspection well body (3), one end of which is provided with a cable threading hole (5) and a communication threading hole (6), and a plurality of cable threading holes (5); the upper end of the inspection well body (3) is fixedly connected with a wellhead (7), and the wellhead (7) is communicated with the inspection well body (3); the upper end of the wellhead (7) is provided with an annular placement groove (12); the upper end of the wellhead (7) is provided with an annular wellbore adjustment block (1); the middle part of the lower end of the wellbore adjustment block (1) is fixedly connected with an annular connecting block (8), and the connecting block (8) is located in the placement groove (12) and is slidably connected to the side wall of the placement groove (12); the upper end of the wellbore adjustment block (1) is provided with a circular through hole (11), and the through hole (11) sequentially passes through the wellbore adjustment block (1) and the connecting block (8) downwardly; a steel bar (9) is placed in the through hole (11).
2. The integral prefabricated concrete inspection well for electric power according to claim 1 is characterized in that: A lifting nut (2) is installed at the upper end of the inspection well body (3), and four lifting nuts (2) are provided and distributed in a rectangular shape at the upper end of the inspection well.
3. The integral prefabricated concrete inspection well for electric power according to claim 1 is characterized in that: An annular sealing groove (13) is provided at the bottom of the placement groove (12), and the sealing groove (13) is located in the middle of the placement groove (12). The sealing groove (13) extends downward into the wellhead (7), and mortar is filled in the sealing groove (13).
4. The integral prefabricated concrete inspection well for electric power according to claim 3 is characterized in that: The diameter of the steel bar (9) is smaller than the hole diameter of the through hole (11), and the lower end of the steel bar (9) extends to the bottom of the sealing groove (13), and the gap between the side wall of the through hole (11) and the steel bar (9) is filled with mortar.
5. The integral prefabricated concrete inspection well for electric power according to claim 1, characterized in that: The lower end of the inspection well body (3) is fixedly connected with a sewage discharge pipe (4), and the sewage discharge pipe (4) is in communication with the inspection well body (3).
6. The integral prefabricated concrete inspection well for electric power according to claim 1, characterized in that: An annular connecting groove (10) is provided in the middle of the upper end of the shaft adjusting block (1), and the connecting groove (10) is the same in shape and size as the placement groove (12), and the through hole (11) is located in the middle of the connecting groove (10).
7. The integral prefabricated concrete inspection well for electric power according to claim 1, characterized in that: A plurality of through holes (11) are provided, and the plurality of through holes (11) are equidistantly distributed around the circumference of the wellbore adjustment block (1).
8. The integral prefabricated concrete inspection well for electric power according to claim 6, characterized in that: A rubber pad is fixedly connected to the side wall of the connection groove (10).
Citation Information
Cited By
Prefabricated inspection well and construction method thereof
CN119531414A