Building detection ruler for constructional engineering
By introducing protective boxes and measurement components into the building inspection ruler, the problem of reduced accuracy and difficult operation when the traditional rear-end inspection is solved, and the accurate reading of data and improving work efficiency is achieved after lowering the rear-end inspection ruler. Effect.
Patent Information
- Application Number
- CN202422705376.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-11-07
AI Technical Summary
When traditional pointer rulers are detected at high altitudes, the measurement accuracy is reduced and the operation is difficult, which increases the risk of high-altitude operations because construction workers need to indirectly observe the pointers and dials, resulting in human error and inconvenient operation.
A building inspection ruler is designed, including a protective box and a measuring assembly, through the abutment of the positioning cylinder and the positioning ring, allowing the rotation angle of the pointer to be accurately observed after the ruler is lowered, and the hand extension and twisting is reduced through the lifting ring, simplifying the operate.
It improves the accuracy and efficiency of measurement, reduces measurement time, reduces the risk of high-altitude operations, and enhances operation convenience.
Smart Images

Figure CN222104564U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, in particular to a building detection ruler for construction engineering. Background Art
[0002] A building inspection ruler (also called a level or a ruler) used in construction projects is a specially designed measuring tool used to detect and ensure key geometric parameters such as the flatness, verticality and horizontality of walls, floors or other building surfaces during the construction process. The main function of this tool is to help construction workers calibrate the geometric properties of building elements to ensure that the building meets design specifications and quality standards.
[0003] Traditional pointer-type rulers are usually equipped with a pointer and a dial. When in use, after the ruler is attached to the wall, construction workers judge the measurement result by observing the position of the pointer. The scale value pointed by the pointer represents the height difference or deviation between the wall and the ruler. When the ruler is placed at a higher position for inspection, construction workers cannot intuitively observe the state of the pointer. Construction workers need to indirectly judge the measurement results, which will lead to reduced measurement accuracy. Indirect observation is usually not as accurate as direct observation and is prone to human errors. In order to accurately observe the state of the pointer and dial, construction workers may need to climb ladders or stand in unstable positions, which increases the risk of high-altitude operations, and the difficulty and potential dangers of operations will increase. Utility Model Content
[0004] In view of the deficiencies of the prior art, the utility model provides a building inspection ruler for construction engineering, which solves the problems of the prior art.
[0005] To achieve the above purpose, the utility model is implemented through the following technical solutions: a building inspection ruler for construction engineering, comprising a ruler body and a protective box fixedly connected to the surface of the ruler body, wherein a measuring component is installed inside the protective box;
[0006] The measuring assembly includes an outer box fixedly connected to the inside of the protective box, a rotating groove is provided inside the outer box, a dial is fixedly connected to the surface of the outer box, a rotating assembly is installed inside the rotating groove, a heavy ball is fixedly connected to the end of the rotating assembly, a sealing groove is provided inside the outer box, a sealing plate is sealingly and slidably connected inside the sealing groove, a connecting rod is fixedly connected at the bottom center of the sealing plate, a spring is movably installed inside the sealing groove, a pull rope is fixedly connected to the end face of the connecting rod, and a lifting ring is fixedly connected to the end face of the pull rope.
[0007] Preferably, the rotating assembly includes a fixed shaft fixedly connected to the inside of the outer box, the outer surface of the fixed shaft is rotatably connected to a rotating rod through a bearing, the top of the rotating rod is fixedly connected to a pointer, the surface of the rotating rod is fixedly connected to a positioning ring, a sliding groove is opened inside the outer box, the internal sealing and sliding connection of the sliding groove is a piston, the end of the piston close to the rotating rod is fixedly connected to a positioning cylinder through a piston rod, the inside of the outer box is fixedly connected to a connecting pipe, and the sliding groove is connected to the sealing groove through the connecting pipe.
[0008] Preferably, protrusions are equidistantly arranged on the end faces of the positioning tube and the positioning ring, and the caliber of the positioning ring is larger than the diameter of the fixed shaft.
[0009] Preferably, one end of the fixed shaft away from the positioning cylinder extends to the inside of the rotating groove, and a long groove is opened at the bottom of the outer box. The lower end of the rotating rod can rotatably pass through the long groove and be fixedly connected to the heavy ball.
[0010] Preferably, the outer surface of the pull rope is movably connected to the inside of the ruler body, and the end of the pull rope extends to the outer surface of the ruler body, and the lifting ring is located outside the ruler body.
[0011] Compared with the prior art, the utility model has the following beneficial effects:
[0012] 1. The construction engineering building inspection ruler is provided with a measuring component. After the main body of the ruler is placed against the wall for inspection, the rotation of the rotating rod can be positioned by the abutment of the positioning tube against the positioning ring, so that the surveyor can still accurately observe the rotation angle of the pointer after putting down the main body of the ruler. This design allows the surveyor to read the data after putting down the ruler, simplifies the operation process, reduces the measurement time, and the surveyor can complete more measurement work in a shorter time, thereby improving the overall work efficiency.
[0013] 2. The design of the lifting ring of the construction engineering building inspection ruler allows construction workers to control the position of the positioning tube more easily, especially in high places or inaccessible areas, reducing the stretching and twisting of the hands and improving the convenience of operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the structure of the utility model;
[0015] Figure 2 It is a connection diagram of the protection box and the measuring component in the utility model;
[0016] Figure 3 It is a schematic diagram of the connection between the measuring component and the heavy ball in the utility model;
[0017] Figure 4 for Figure 3The enlarged view of point A in the middle;
[0018] Figure 5 It is a connection schematic diagram of the positioning ring and the positioning cylinder in the utility model.
[0019] In the figure: 1. ruler body; 2. protection box; 3. measuring assembly; 31. outer box; 32. rotating groove; 33. dial; 34. rotating assembly; 341. fixed shaft; 342. rotating rod; 343. pointer; 344. positioning ring; 345. sliding groove; 346. piston; 347. positioning cylinder; 348. connecting pipe; 35. sealing groove; 36. sealing plate; 37. connecting rod; 38. spring; 39. pull rope; 310. lifting ring; 4. heavy ball. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] See also Figure 1-Figure 5 The utility model provides a technical solution: a building inspection ruler for construction engineering, comprising a ruler body 1 and a protection box 2 fixedly connected to the surface of the ruler body 1, wherein a measuring component 3 is installed inside the protection box 2.
[0022] The measuring assembly 3 comprises an outer box 31 fixedly connected to the inside of the protective box 2 , a rotation groove 32 is provided inside the outer box 31 , a dial 33 is fixedly connected to the surface of the outer box 31 , and a rotating assembly 34 is installed inside the rotation groove 32 .
[0023] The rotating assembly 34 includes a fixed shaft 341 fixedly connected to the inside of the outer box 31, the outer surface of the fixed shaft 341 is rotatably connected to a rotating rod 342 through a bearing, a long groove is provided at the bottom of the outer box 31, the lower end of the rotating rod 342 can rotatably pass through the long groove and extend downward, a pointer 343 is fixedly connected to the top of the rotating rod 342, a positioning ring 344 is fixedly connected to the surface of the rotating rod 342, the diameter of the positioning ring 344 is larger than the diameter of the fixed shaft 341, a sliding groove 345 is provided inside the outer box 31, and the inner sealing sliding groove 345 is provided inside the sliding groove The piston 346 is movably connected, and one end of the piston 346 close to the rotating rod 342 is fixedly connected to the positioning cylinder 347 through the piston rod. The end of the fixed shaft 341 away from the positioning cylinder 347 extends to the interior of the rotating groove 32. The positioning cylinder 347 and the positioning ring 344 are evenly spaced on the end faces adjacent to the end faces. By arranging the protrusions on the positioning cylinder 347 and the positioning ring 344, the friction between the positioning cylinder 347 and the positioning ring 344 can be enhanced, and the rotating rod 342 can maintain its position unchanged after the rotating rod 342 rotates, thereby enhancing stability.
[0024] In this embodiment, a plurality of slide grooves 345 are arranged in an annular shape at equal intervals, a piston 346 is arranged in each slide groove 345 , and each piston 346 is fixedly connected to a positioning cylinder 347 via a piston rod.
[0025] A connecting pipe 348 is fixedly connected to the inside of the outer box 31 . A sealing groove 35 is also provided on the outer box 31 . The sealing groove 35 is located at the lower side of the positioning tube 347 . The sliding groove 345 is connected to the sealing groove 35 through the connecting pipe 348 .
[0026] A heavy ball 4 is fixedly connected to the end of the rotating component 34. Furthermore, a heavy ball 4 is fixed to the lower end of the rotating rod 342. A sealing plate 36 is slidably connected to the internal sealing of the sealing groove 35. A connecting rod 37 is fixedly connected to the bottom center of the sealing plate 36. A pull rope 39 is fixedly connected to the end face of the connecting rod 37. A spring 38 is movably installed inside the sealing groove 35. The spring 38 is located on the lower side of the sealing plate 36. Under normal circumstances, the sealing plate 36 slides upward due to the elasticity of the spring 38, and the sealing groove 35 and the sliding groove 345 are both in a high-pressure state. A lifting ring 310 is fixedly connected to the end face of the pulling rope 39. The outer surface of the pulling rope 39 is movably connected to the inside of the ruler body 1, and the end of the pulling rope 39 extends to the outside of the ruler body 1. The lifting ring 310 is located outside the ruler body 1.
[0027] By setting the measuring component 3, after the ruler body 1 is placed against the wall for inspection, the positioning tube 347 abuts against the positioning ring 344, so that the rotation of the rotating rod 342 can be positioned, so that the position of the rotating rod 342 remains unchanged, so that the measurement personnel can still accurately observe the rotation angle of the pointer 343 after putting down the ruler body 1. This design allows the measurement personnel to read the data after putting down the ruler, simplifies the operation process, reduces the measurement time, and the measurement personnel can complete more measurement work in a shorter time, thereby improving the overall work efficiency.
[0028] When in use, place the ruler body 1 against the wall, and then pull the lifting ring 310, which drives the connecting rod 37 and the sealing plate 36 to slide downward through the pull rope 39. At this time, the internal pressure of the sealing groove 35 is reduced, and the internal pressure of the slide groove 345 is reduced through the connecting pipe 348, so that the piston 346 drives the positioning cylinder 347 to slide away from the positioning ring 344. When the positioning cylinder 347 is not in contact with the positioning ring 344, if the wall is tilted, the gravity of the heavy ball 4 will drive the rotating rod 342 to rotate, and the rotating rod 342 drives the pointer 343 to swing. When the rotating rod 342 stops rotating, the lifting ring 310 stops. External force is applied, and the sealing plate 36 slides upward through the elasticity of the spring 38. At this time, the internal pressure of the slide groove 345 increases, which can make the positioning cylinder 347 slide in the direction close to the positioning ring 344. The positioning cylinder 347 abuts against the positioning ring 344, so that the rotation of the rotating rod 342 can be positioned, so that the measurement personnel can still accurately observe the rotation angle of the pointer 343 after putting down the ruler body 1. This design allows the measurement personnel to read the data after putting down the ruler, simplifies the operation process, and reduces the measurement time. The measurement personnel can complete more measurement work in a shorter time, thereby improving the overall work efficiency.
[0029] Meanwhile, the contents not described in detail in this specification belong to the prior art known to those skilled in the art.
Claims
1. A construction inspection ruler for construction engineering, comprising a ruler body (1) and a protective box (2) fixedly connected to the surface of the ruler body (1), characterized in that: A measuring component (3) is installed inside the protective box (2); The measuring assembly (3) comprises an outer box (31) fixedly connected to the inside of the protective box (2); a rotating groove (32) is provided inside the outer box (31); a dial (33) is fixedly connected to the surface of the outer box (31); a rotating assembly (34) is installed inside the rotating groove (32); a heavy ball (4) is fixedly connected to the end of the rotating assembly (34); a sealing groove (35) is provided inside the outer box (31); a sealing plate (36) is sealingly and slidably connected inside the sealing groove (35); a connecting rod (37) is fixedly connected at the bottom center of the sealing plate (36); a spring (38) is movably installed inside the sealing groove (35); a pull rope (39) is fixedly connected to the end surface of the connecting rod (37); and a lifting ring (310) is fixedly connected to the end surface of the pull rope (39).
2. A construction measuring ruler for construction engineering according to claim 1, characterized in that: The rotating assembly (34) comprises a fixed shaft (341) fixedly connected to the inside of the outer box (31); the outer surface of the fixed shaft (341) is rotatably connected to a rotating rod (342) via a bearing; the top of the rotating rod (342) is fixedly connected to a pointer (343); the surface of the rotating rod (342) is fixedly connected to a positioning ring (344); a slide groove (345) is provided inside the outer box (31); a piston (346) is sealingly slidably connected inside the slide groove (345); one end of the piston (346) close to the rotating rod (342) is fixedly connected to a positioning cylinder (347) via a piston rod; a connecting pipe (348) is fixedly connected to the inside of the outer box (31); the slide groove (345) is connected to the sealing groove (35) via the connecting pipe (348).
3. A construction measuring ruler for construction engineering according to claim 2, characterized in that: The end surfaces of the positioning cylinder (347) and the positioning ring (344) adjacent to each other are provided with convex blocks at equal distances, and the caliber of the positioning ring (344) is larger than the diameter of the fixed shaft (341).
4. A construction measuring ruler for construction engineering according to claim 2, characterized in that: One end of the fixed shaft (341) away from the positioning cylinder (347) extends into the interior of the rotating groove (32). A long groove is provided at the bottom of the outer box (31). The lower end of the rotating rod (342) can rotatably pass through the long groove and be fixedly connected to the heavy ball (4).
5. The construction measuring ruler for construction engineering according to claim 1, characterized in that: The outer surface of the pull rope (39) is movably connected to the inside of the ruler body (1), and the end of the pull rope (39) extends to the outer surface of the ruler body (1), and the lifting ring (310) is located outside the ruler body (1).