Network reconstruction equipment for 10kV feeder line fault

By installing a repeater and segmenter on a 10kV feeder, combining voltage sensors and current transformers, the fault segments are automatically detected and isolated, and the problems of fault processing time and safety threats in the existing technology are solved, and rapid recovery of non-infrared Power supply to the faulty section.

CN222107589UActive Publication Date: 2024-12-03QUANZHOU WEIDUN ELECTRIC CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322902155.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-28
Publication Date
2024-12-03
Estimated Expiration
2033-10-28

AI Technical Summary

Technical Problem

When a 10kV feeder fails, the existing technology relies on manual processing, which takes a long time and has a great threat to operator safety, making it difficult to quickly restore power supply to non-fault sections.

Method used

Design a network reconstruction device, including installing a repeater and segmenter on a 10kV feeder, equipped with a voltage sensor and a current transformer, recording and transmitting line operation information through an information management unit, automatically detecting fault segments and isolating them, shortening the network Reconstruct the time.

Benefits of technology

It realizes rapid identification and isolation of faulty segments, shortens network reconstruction time, improves power supply and recovery efficiency of non-faulty segments, and reduces the risk and time-consuming of manual operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222107589U_ABST
    Figure CN222107589U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of power distribution network feeder line processing, and discloses a network reconstruction device in 10kV feeder line fault, which comprises two reclosers and a plurality of sectionalizers installed on a 10kV feeder line, the two reclosers are installed on the 10kV feeder line close to a feeder line outlet end of a transformer substation, the plurality of sectionalizers are connected in series into the 10kV feeder line, and the sectionalizers are connected in series with the 10kV feeder line. Six voltage sensors and six current transformers are arranged in each sectionalizer; the recloser and the sectionalizers are connected with an information management unit through wires in 10kV feeder lines of adjacent intervals, and the information management unit records operation information of the power transmission line and reports and transmits the operation information to a server for security alert. According to the utility model, the network reconstruction time is shortened, and the power supply recovery time of a non-fault section after a fault is effectively saved; and each line area is connected with the information management unit, so that maintenance personnel can be informed of the maintenance area, work assignment is quickly performed, and line maintenance is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of distribution network feeder processing, in particular to a network reconstruction device when a 10kV feeder fails. Background Art

[0002] Due to natural disasters or other factors, transmission lines are inevitably damaged and connection faults occur. Common faults of 10kv overhead lines include short circuit faults, which include the following two situations: one is the instantaneous short circuit fault of the line (generally the circuit breaker reclosing is successful); the other is the permanent short circuit fault of the line (generally the circuit breaker reclosing is unsuccessful).

[0003] In case of permanent short circuit fault on the line, the outlet circuit breaker in the substation will trip. Based on the tripping situation, the duty personnel can clearly inform the feeder operation and maintenance personnel which feeder has a short circuit fault. The general way for operation and maintenance personnel to handle line short circuit faults is to cooperate with the outgoing line switch of the substation to test pull and test send the circuit breaker or load switch on the faulty line in sections. According to the test pull and test send process of the outgoing line switch of the substation and the circuit breaker on the line and the tripping situation of the outgoing line switch of the substation during the process, the fault section is determined. The manual fault handling method is time-consuming and poses a certain threat to the personal safety of operators at the fault site.

[0004] To this end, we propose a network reconstruction device for 10kV feeder fault to solve the above problems. Utility Model Content

[0005] The purpose of the utility model is to provide a network reconstruction device when a 10kV feeder fails, so as to solve the problems raised in the above background technology.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a network reconstruction device in case of a 10kV feeder fault, comprising two reclosers and a plurality of sectionalizers installed on the 10kV feeder line, the two reclosers being installed at the feeder outlet end of the 10kV feeder line close to the substation, the plurality of sectionalizers being connected in series to the 10kV feeder line, and the plurality of sectionalizers being each equipped with six voltage sensors and six current transformers;

[0007] The 10kV feeder lines of the recloser and multiple sectioners in adjacent sections are all connected to the information management unit through wires. The information management unit records the operation information of the transmission line and reports it to the server for safety alert.

[0008] As an optional solution for the network reconstruction device when the 10kV feeder line fails in the utility model, the voltage sensor is used to detect the voltage change on both sides of the switch and the magnitude and phase angle of the zero-sequence voltage.

[0009] As an optional solution for the network reconstruction device when the 10kV feeder fails in the utility model, the current transformer is used to detect the magnitude and phase angle of the power frequency and harmonic current and zero-sequence voltage flowing in the switch.

[0010] As an optional solution for the network reconstruction equipment when the 10kV feeder line fails in the utility model, the information management unit includes a section operation information recording module, which detects the line voltage to wirelessly transmit the coincidence power supply status of the lines in each area to the server.

[0011] As an optional solution for the network reconstruction device when the 10kV feeder line fails in the utility model, the information management unit includes a section power outage warning module, which is used to record the line power outage maintenance area and report it to the server.

[0012] Compared with the prior art, the utility model has the following beneficial effects:

[0013] 1. The network reconstruction equipment for the 10kV feeder failure includes a recloser and multiple sectionalizers installed on the 10kV feeder line. The recloser is installed at the input end of the 10kV feeder line and close to the feeder outlet output end of the substation. Multiple intelligent sectionalizers are connected in series to the 10kV feeder line. Six voltage sensor detection devices and current detection device transformers are installed on multiple sectionalizers. If the first reclosing fails, the line fault is judged to be a permanent fault. At this time, the sectionalizer on the main line counts two voltage loss counts, and all sectionalizers on the main network of the 10kV feeder line are opened. Then, the faulty section is isolated according to the voltage and current changes and time, and the normal power supply of the non-faulty section is restored. If the sectionalizer does not detect another voltage loss within the fault confirmation delay time Y after closing, the sectionalizer will temporarily close its voltage loss opening function, thereby constituting network reconstruction. The network reconstruction time is shortened, and the time for restoring power supply to the non-faulty section after the fault is effectively saved.

[0014] 2. The network reconstruction equipment in case of 10kV feeder failure, each line area is connected to the information management unit, in which the interval operation information recording module detects the line voltage to upload the coincidence power supply situation of each area line. During the process, the information of the line power outage maintenance area recorded in the interval operation information recording module is transmitted to the interval power outage warning module, and then uploaded to the server. The server records the network reconstruction process, which can inform the maintenance personnel of the maintenance area and quickly assign work; similarly, after the repair is completed, the information management unit remotely detects the line power supply situation and quickly informs the maintenance personnel of the work progress, which is convenient for line maintenance and use. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of the utility model;

[0016] Figure 2 It is a schematic diagram of the structural frame of the information management unit of the utility model. DETAILED DESCRIPTION

[0017] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0018] See also Figure 1-Figure 2 The utility model provides a technical solution: a network reconstruction device for a 10kV feeder fault, including two reclosers and multiple segmenters installed on the 10kV feeder line, and the two reclosers are installed at the feeder outlet end of the 10kV feeder line close to the substation, which are recloser CH1 and recloser CH2 respectively.

[0019] The recloser handle switch L is installed between the outlet CH1 of the 10kV feeder line near the substation and the substation CH2.

[0020] Multiple sectioners are connected in series to the 10kV feeder line, including sectioner F1, sectioner F2, sectioner F3 and sectioner F4 in sequence. Sectioners F1, sectioner F2, sectioner F3 and sectioner F4 are connected in series to the 10kV feeder line. The recloser handle switch L is located between sectioner F2 and sectioner F3. Six voltage sensors and six current transformers are built-in on each sectioner of the equipment. The time relay is connected in series with the voltage sensor and in parallel with the corresponding sectioner and current transformer.

[0021] It should be noted that the voltage sensor is used to detect the voltage changes on both sides of the switch and the magnitude and phase angle of the zero-sequence voltage; the current transformer is used to detect the power frequency and harmonic current flowing through the switch, the magnitude and phase angle of the zero-sequence voltage.

[0022] Network reconstruction steps:

[0023] S1. If a short circuit fault occurs on the feeder, the recloser trips for the first time. In order to distinguish whether the fault is a transient fault, the first reclosing of the substation outlet recloser is used to eliminate the transient 10kV feeder line fault. If the first reclosing fails, the line fault is judged to be a permanent short circuit fault;

[0024] When the voltage loss count of the sectionalizer on the main line in S2 is reached twice, the sectionalizers on all main networks on the 10kV feeder line in S1 are opened, and then the faulty section is isolated according to the voltage and current changes and time, and the normal power supply of the non-faulty section is restored;

[0025] If the sectionalizers in S3 and S2 do not detect another loss of pressure within the fault confirmation delay time Y after closing, the sectionalizer will temporarily shut down its loss of pressure tripping function, thereby effectively shortening the network reconstruction time after the fault occurs.

[0026] In a specific embodiment, in S3, the fault confirmation delay Y after the sectionalizer is closed includes Y=2s.

[0027] Assuming that the short-circuit fault occurs between the sectionalizer F2 and the sectionalizer F3 handle switch L, the recloser CH1 near the substation outlet will trip quickly, and then reclose for the first time (to determine whether the fault is a transient fault). If the reclosing fails, it will trip for the second time. The handle switch starts the pressure loss X timing on one side. At this time, the pressure loss counts of the sectionalizers F1 and F2 on the main line twice reach the opening. A command is issued to disconnect the sectionalizers F2 and F3, and the power supply line between the two stations is cut off together with the fault. At the same time, substation CH2 quickly starts the backup power supply automatic transfer function, the dedicated line recloser CH1 closes for the third time, and the sectionalizer F1 side detects voltage delay when closing, and there is no fault voltage pulse within Y time, and automatically closes its voltage loss tripping function for a short time; F2 side detects voltage delay when closing, but closes on the fault; recloser CH1 trips for the third time; because F2 detects voltage fault pulse within Y time, and the handle switch L detects voltage fault pulse within X on one side of the voltage loss timing, F2 automatically opens and locks after CH1 trips for the third time, and the handle switch automatically locks in the open state.

[0028] CH1 is reclosed for the fourth time. Since F1 temporarily turns off its undervoltage tripping function, there is no need to perform tripping and delayed closing operations, which effectively shortens the time for network reconstruction. At this point, the network reconstruction is completed. Except for the power outage between the fault section F2 and the handle switch L, all other non-fault areas are powered normally. Power is supplied to the sectionalizer F4, completing the power supply to the sectionalizers F3 and F4. The utility model reduces the time for network reconstruction and effectively saves and shortens the time for restoring power supply to the non-fault section after a fault.

[0029] As a further improvement of this embodiment:

[0030] The 10kV feeder lines of the recloser and multiple section switches in adjacent sections are connected to the information management unit through wires. The information management unit records the operation information of the transmission line and reports it to the server for safety alerts.

[0031] Among them, the information management unit includes an interval operation information recording module, which detects the line voltage to upload the coincidence power supply situation of the lines in each area, and wirelessly transmits the connection to the server.

[0032] The information management unit also includes a section power outage warning module, which is used to record the line power outage maintenance area and report it to the server.

[0033] Note: The line power outage maintenance area information recorded in the interval operation information recording module is transmitted to the interval power outage warning module, and then uploaded to the server. The server records the network reconstruction process, which can inform the maintenance personnel of the maintenance area and quickly assign work. Similarly, after the repair is completed, the information management unit remotely detects the line power supply situation and quickly informs the maintenance personnel of the work progress, which is convenient for line maintenance.

[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A network reconstruction device for a 10kV feeder failure, characterized in that: It includes two reclosers and multiple sectionalizers installed on the 10kV feeder line. The two reclosers are installed at the feeder outlet end of the 10kV feeder line close to the substation. Multiple sectionalizers are connected in series to the 10kV feeder line. Six voltage sensors and six current transformers are built in the multiple sectionalizers. The 10kV feeder lines of the recloser and multiple sectioners in adjacent sections are all connected to the information management unit through wires. The information management unit records the operation information of the transmission line and reports it to the server for safety alert.

2. A network reconstruction device for a 10kV feeder failure according to claim 1, characterized in that: The voltage sensor is used to detect the voltage change at both sides of the switch and the magnitude and phase angle of the zero-sequence voltage.

3. A network reconstruction device for a 10kV feeder failure according to claim 2, characterized in that: The current transformer is used to detect the magnitude and phase angle of the power frequency and harmonic current and zero-sequence voltage flowing through the switch.

4. A network reconstruction device for a 10kV feeder failure according to claim 3, characterized in that: The information management unit includes an interval operation information recording module, which detects the line voltage and wirelessly transmits the coincidence power supply status of the lines in each area to the server.

5. A network reconstruction device for a 10kV feeder failure according to claim 4, characterized in that: The information management unit includes a section power outage warning module, which is used to record the line power outage maintenance area and report it to the server.