Transfer bracket for steel tower column of cable-stayed bridge

By designing a transfer bracket for cable-stayed bridge steel tower columns, using trolley and cross beam structures combined with plastic gaskets and mobile seats, the deformation and safety problems during the transfer of steel tower segments are solved, and the steel mixing is achieved Combined with stable transport of the section and effective protection of other steel components.

CN222117355UInactive Publication Date: 2024-12-06POLY CHANGDA ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420959679.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-06
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure CN222117355U_ABST
    Figure CN222117355U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of cable-stayed bridge steel tower column construction tools, in particular to a transfer bracket for a cable-stayed bridge steel tower column, the steel tower column comprises a steel-concrete combined section, the transfer bracket comprises a transfer frame body and two trolleys, the transfer frame body comprises a first cross beam and a second cross beam, the trolleys are provided with cross beam seats, and the first cross beam and the second cross beam are arranged on the cross beam seats. The first cross beam and the second cross beam are erected on cross beam seats of the two trolleys at intervals, two mounting grooves for mounting steel-concrete combined sections are formed in the corresponding positions of the first cross beam and the second cross beam respectively, plastic gaskets are arranged on the inner walls of the mounting grooves, and a connecting rod is arranged between the first cross beam and the second cross beam. The steel tower section transfer trolley not only can be used for transferring steel tower sections of a steel-concrete combined section, but also can be used for transferring other steel members, meanwhile, deformation of the transferred steel members in the transfer process can be reduced, and the transferred steel members are well protected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of cable-stayed bridge steel tower construction tools, in particular to a transfer bracket used for cable-stayed bridge steel towers. Background Art

[0002] A large cable-stayed bridge is provided with several steel tower segments. During the construction of the steel tower segments, after the steel tower segments are assembled and welded, they need to be removed from the assembly frame and transported to a storage site. When the steel tower is erected, they are transferred from the storage site to the loading dock, and the segments are loaded and transported. The steel tower segments are large in size and heavy in weight, making them difficult to transport. At the same time, the steel tower segments are composed of a plate structure composed of several plates. Therefore, how to ensure the safety of the steel segments during transportation and reduce the deformation of the steel tower segments during transportation is a key point in the transportation of the steel tower segments, especially the shear key part of the steel-concrete joint section, because it is a cavity in the middle and surrounded by plates. Therefore, reducing its deformation during transportation is even more difficult. Utility Model Content

[0003] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a transfer bracket for a steel tower column of a cable-stayed bridge, the steel tower column includes a steel-concrete combined section, the transfer bracket includes a transfer frame body, two trolleys, the transfer frame body includes a first crossbeam and a second crossbeam, the trolley is provided with a crossbeam seat, the first crossbeam and the second crossbeam are arranged on the crossbeam seats of the two trolleys at intervals, the first crossbeam and the second crossbeam are respectively provided with two installation grooves for installing the steel-concrete combined section at corresponding positions, plastic gaskets are provided on the inner walls of the installation grooves, and a connecting rod is provided between the first crossbeam and the second crossbeam.

[0004] Preferably, the transfer bracket also includes a moving seat and a third cross beam, the moving seats are respectively arranged on two trolleys, the moving seat is provided with a moving groove, each end of the moving groove is provided with a bearing seat, a screw rod is provided between the two bearing seats, a nut block is threaded on the screw rod, a moving block is provided on the nut block, one end of the screw rod extends out of the moving seat and is provided with a handle, the top surface of the moving block is on the same horizontal plane as the top surface of the cross beam seat, and the end of the third cross beam is connected to the moving block and moves with the movement of the moving block.

[0005] Preferably, it also includes a second connecting rod, a fixed block, a fixing bolt, and a movable block. The second connecting rod is located on the side of the third beam corresponding to the second beam. The second beam is provided with a connecting groove connected to the second connecting rod. The connecting groove is provided with an upper opening and two side openings. The two side openings are connected. The upper opening is step-shaped. One end of the second connecting rod is inserted into the side opening. Screw holes are provided in the middle of the fixed block and the movable block. The fixed block is provided on the upper step of the upper opening. The fixed block is movably provided in the connecting groove of the upper opening. The fixing bolt fixes the second connecting rod to the second beam through the screw hole, the fixed block, and the movable block.

[0006] Preferably, temporary fixing strips are provided on the outer sides of the top surfaces of the first crossbeam and the third crossbeam.

[0007] Preferably, the first cross beam, the second cross beam and the third cross beam are provided with lifting ears on both sides.

[0008] Preferably, the height of the middle parts of the first cross beam, the second cross beam and the third cross beam is greater than the height of the two sides.

[0009] Compared with the prior art, the beneficial effects of the utility model are:

[0010] The utility model can not only transport the steel tower sections of the steel-concrete combined sections, but also transport other steel components. At the same time, it can reduce the deformation of the transported steel components during the transport process, and play a good protective role for the transported steel components. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 The structural diagram of the transfer bracket and the steel-concrete combination section of Example 1 provided by the utility model;

[0012] Figure 2 Installation diagram of the transfer bracket and the steel-concrete combination section of Example 1 provided by the utility model;

[0013] Figure 3 A schematic structural diagram of a transfer bracket according to Embodiment 4 of the present invention;

[0014] Figure 4 Structural exploded view of the second crossbeam provided by the utility model;

[0015] Explanation of the numbers in the figure: first crossbeam 11, mounting groove 111, first connecting rod 112, lifting ear 113, second crossbeam 12, fixed block 1221, movable block 1222, fixing bolt 1223, upper opening 1211, side opening 1212, third crossbeam 13, second connecting rod 131, temporary fixing strip (132; 114), positioning angle bracket (133; 115), trolley 2, crossbeam seat 21, movable seat 22, movable groove 221, screw rod 222, movable block 223, handle 224, steel-concrete combined section 3. DETAILED DESCRIPTION

[0016] The technical solution in one embodiment of the utility model will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0017] See also Figure 1-4 :

[0018] Embodiment 1:

[0019] A transfer bracket for a steel tower column of a cable-stayed bridge, the steel tower column includes a steel-concrete combination section 3, the transfer bracket includes a transfer bracket body, two trolleys 2, the transfer bracket body includes a first crossbeam 11 and a second crossbeam 12, the trolley 2 is provided with a crossbeam seat 21, the first crossbeam 11 and the second crossbeam 12 are arranged on the crossbeam seats 21 of the two trolleys 2 at intervals, two installation grooves 111 for installing the steel-concrete combination section 3 are respectively arranged at corresponding positions of the first crossbeam 11 and the second crossbeam 12, a plastic gasket is arranged on the inner wall of the installation groove 111, and a first connecting rod 112 is arranged between the first crossbeam 11 and the second crossbeam 12. This solution can facilitate the stable transfer of the steel-concrete combination section 3 through the two trolleys 2 and the two crossbeams, and the first crossbeam 11 and the second crossbeam 12 are provided with installation grooves 111 for limiting the steel-concrete combination section 3, which can prevent the steel-concrete combination section 3 from shifting during the transfer process. Since the lower end of the steel-concrete combination section 3 is a shear key and the middle is a cavity, plastic gaskets (not shown) are provided on the bottom and inner wall of the installation groove 111 to prevent deformation of the lower part of the shear key and protect the shear key.

[0020] Embodiment 2:

[0021] In this embodiment, on the basis of embodiment 1, the transfer bracket further includes a moving seat 22 and a third cross beam 13. The moving seat 22 is respectively arranged on the two trolleys 2. The moving seat 22 and the cross beam seat 21 are an integral structure or a split structure. In this embodiment, an integral structure is preferably preferred. The moving seat 22 is provided with a moving groove 221. A bearing seat (not shown) is provided at each end of the moving groove 221. A screw rod 222 is provided between the two bearing seats. A nut block (not shown) is screwed on the screw rod 222. A moving block 223 is provided on the nut block. One end of the screw rod 222 extends A handle 224 is provided outside the moving seat 22. The top surface of the moving block 223 is on the same horizontal plane as the top surface of the beam seat 21. The end of the third beam 13 is connected to the moving block 223 and moves with the movement of the moving block 223. By setting a movable third beam 13, the utility model can not only transport the steel-concrete combined section 3, but also transport other steel components, such as other steel tower columns, etc. In addition, for transporting large steel components, the transport process is more stable due to the support of the first beam, the second beam and the third beam. During use, the screw rod is rotated by turning the handle, and the moving block is moved by the nut block, thereby driving the movement of the third beam.

[0022] Embodiment 3:

[0023] On the basis of Example 2, in order to stabilize the third crossbeam 13, the present invention further includes a second connecting rod 131, a fixed block 1221, a fixing bolt 1223, and a movable block 1222. The second connecting rod 131 is located on the side of the third crossbeam 13 corresponding to the second crossbeam 12. The second crossbeam 12 is provided with a connecting groove connected to the second connecting rod 131. The connecting groove is provided with an upper opening 1211 and two side openings 1212. The two side openings 1212 are connected. The upper opening 1211 is stepped. One end of the second connecting rod 131 is inserted into the side opening 1212. Screw holes are provided in the middle of the fixed block 1221 and the movable block 1222. The fixed block 1221 is provided on the upper step of the upper opening 1211. The fixed block 1221 is movably provided in the connecting groove of the upper opening 1211. The fixing bolt 1223 is provided in the movable block 1222. The bolt 1223 fixes the second connecting rod 131 to the second beam 12 through the screw hole, the fixed block 1221, and the movable block 1222. In this scheme, a connecting groove is provided on the second beam 12, and a fixing structure of the second connecting rod 131 is set in the connecting groove to fix the second connecting rod in the connecting groove, wherein the fixing structure includes the fixed block 1221, the fixing bolt 1223, and the movable block 1222. In this way, when the third beam 13 moves with the movement of the movable block, the second connecting rod 131 can move in the connecting groove. Since the connecting groove is provided on the second beam 12, when the distance between the third beam 13 and the second beam 12 is small, the second connecting rod 131 will extend between the first beam 11 and the second beam 12, so it will not extend out of the beam, thereby ensuring safety in use and making the third beam 13 more stable.

[0024] Embodiment 4:

[0025] On the basis of Example 3, in order to facilitate the positioning of other steel components except the steel-concrete combined section 3 on the beam, the top outer side of the first beam 11 and the third beam 13 is provided with temporary fixing strips (132; 114), and the temporary fixing strips (132; 114) can be temporarily welded with positioning angle brackets to limit the positioning of other steel components on the beam, so that other steel components can be transported stably. To facilitate the installation of the beam, the first beam 11, the second beam 12 and the third beam 13 are provided with lifting ears 113 on both sides. Due to the large total amount of steel components, the height of the middle part of the first beam 11, the second beam 12 and the third beam 13 is greater than the height of the two sides, so as to improve the bearing capacity of the beam.

[0026] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A transport bracket for a steel tower column of a cable-stayed bridge, wherein the steel tower column comprises a steel-concrete combined section, It is characterized in that The transfer bracket includes a transfer frame body and two trolleys. The transfer frame body includes a first crossbeam and a second crossbeam. The trolley is provided with a crossbeam seat. The first crossbeam and the second crossbeam are arranged on the crossbeam seats of the two trolleys at intervals. The corresponding positions of the first crossbeam and the second crossbeam are respectively provided with two installation grooves for installing the steel-concrete combined section. Plastic gaskets are provided on the inner walls of the installation grooves. A connecting rod is provided between the first crossbeam and the second crossbeam.

2. A transfer bracket for a steel tower column of a cable-stayed bridge according to claim 1, It is characterized in that The transfer bracket also includes a moving seat and a third cross beam, the moving seats are respectively arranged on two trolleys, the moving seat is provided with a moving groove, each end of the moving groove is provided with a bearing seat, a screw rod is provided between the two bearing seats, a nut block is screwed on the screw rod, a moving block is provided on the nut block, one end of the screw rod extends out of the moving seat and is provided with a handle, the top surface of the moving block is on the same horizontal plane as the top surface of the cross beam seat, and the end of the third cross beam is connected to the moving block and moves with the movement of the moving block.

3. A transfer bracket for a steel tower column of a cable-stayed bridge according to claim 2, It is characterized in that It also includes a second connecting rod, a fixed block, a fixing bolt, and a movable block. The second connecting rod is located on the side of the third beam corresponding to the second beam. The second beam is provided with a connecting groove connected to the second connecting rod. The connecting groove is provided with an upper opening and two side openings. The two side openings are connected. The upper opening is step-shaped. One end of the second connecting rod is inserted into the side opening. Screw holes are provided in the middle of the fixed block and the movable block. The fixed block is provided on the upper step of the upper opening. The fixed block is movably provided in the connecting groove of the upper opening. The fixing bolt fixes the second connecting rod to the second beam through the screw hole, the fixed block, and the movable block.

4. A transfer bracket for a steel tower column of a cable-stayed bridge according to claim 2, It is characterized in that Temporary fixing strips are arranged on the outer sides of the top surfaces of the first crossbeam and the third crossbeam.

5. A transfer bracket for a cable-stayed bridge steel tower column according to claim 2, It is characterized in that Lifting ears are arranged on both sides of the first cross beam, the second cross beam and the third cross beam.

6. A transfer bracket for a steel tower column of a cable-stayed bridge according to claim 2, It is characterized in that The height of the middle parts of the first cross beam, the second cross beam and the third cross beam is greater than the height of the two sides.