Anchor pile for 10 kilovolt distribution line construction
By designing the cone, movable plate and stable block structures of anchor piles for construction of 10 kV power distribution lines, the problem of imperfect connection between traditional anchor piles and foundations is solved, and the stability and grip of anchor piles are improved to ensure distribution Safe operation of electrical circuit equipment.
Patent Information
- Application Number
- CN202420813658.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-04-19
AI Technical Summary
Traditional anchor piles are not connected firmly to the foundation and are prone to shake, resulting in insufficient grip during transverse loads of power distribution line equipment, which is easy to pour and damage.
A 10 kV distribution line construction anchor pile is designed, including cone table, movable plate, inverted tip, fixed sleeve, fixed disk, insertion rod, fixing screw, stabilizer, gripping rod and connecting rod, through these The combined structure of components improves the support effect and stability of anchor piles and foundations, reduces silt and sand resistance, and enhances grip.
It effectively improves the connection stability between anchor piles and foundations, prevents shaking and pouring, and ensures the stable operation of distribution line equipment during transverse loads.
Smart Images

Figure CN222120219U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of anchor piles, and more specifically, to an anchor pile for 10 kV power distribution line construction. Background Art
[0002] Distribution line construction anchor piles are important engineering components used to support and fix distribution line equipment. Similar to construction anchor rods, construction anchor piles go deep underground to provide solid support for distribution line equipment to prevent it from tilting or moving due to wind, vibration or other external forces. Construction anchor piles have a certain bearing capacity and can withstand the weight of power equipment and the force of the external environment to ensure safe and reliable operation of the equipment.
[0003] In the existing technology, the traditional anchor pile installation method is to drill a hole through the anchor pile body and then place the anchor pile into the drilled hole. However, this method makes the connection between the anchor pile and the foundation not strong enough, which easily causes the anchor pile to shake. Secondly, the side wall of the traditional anchor pile has a poor anchoring support effect and is prone to shaking with the drilled hole on the ground surface, resulting in the overall instability of the anchor pile. When the transmission line is subjected to lateral loads such as shaking and vibration, the grip of this anchor pile is insufficient and it is easy to shake left and right, causing the pile to loosen from the ground, causing the transmission line to fall and be damaged. Utility Model Content
[0004] In view of the problems existing in the prior art, the utility model provides an anchor pile for the construction of a 10 kV distribution line to solve the technical problem of poor connection between the anchor pile and the foundation mentioned in the background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an anchor pile for 10 kV distribution line construction, comprising an anchor pile body, the anchor pile body comprising a fixed sleeve, a positioning platform is provided on the bottom of the fixed sleeve, a frustum is provided at the bottom of the fixed sleeve, a movable plate is rotatably provided on the frustum, a chamfer is provided on the movable plate, a fixed disk is provided in the fixed sleeve, an insertion rod is hingedly provided on the fixed disk, an insertion hole is provided on the fixed sleeve, the insertion rod abuts against the insertion hole, a fixed screw is rotatably provided in the fixed sleeve, the fixed screw is rotatably connected to the fixed disk, a stabilizing device is provided on the top of the fixed sleeve, the stabilizing device comprises a stabilizing block, a gripping rod is rotatably provided on the stabilizing block, a connecting rod is provided between the gripping rod and the stabilizing block.
[0006] The utility model is further configured that the movable plate is provided with a flow groove, which plays a role in guiding the sediment and reducing the resistance.
[0007] The utility model is further configured that the positioning platform is provided with a guide groove, which further plays a role in guiding the sediment and reducing the resistance.
[0008] The utility model is further configured that first connecting grooves are provided on both sides of the stabilizing block, and a connecting block matched with the first connecting grooves is provided on the fixing sleeve to prevent the stabilizing block from circumferential rotation.
[0009] The utility model is further configured that a second connecting groove is provided on the stabilizing block, and connecting plates are provided between the stabilizing blocks to facilitate installation and fixation of the stabilizing blocks.
[0010] The utility model is further configured that the connecting plate is provided with connecting bolts, and the connecting bolts are threadedly connected to the connecting plate, the connecting block and the stabilizing block, so as to facilitate the connection and fixation of the connecting plate, the connecting block and the stabilizing block.
[0011] The utility model is further configured that the fixing screw is provided with a fixing knob to facilitate driving the fixing screw to rotate.
[0012] The utility model is further configured that the fixing knob is provided with a fixing spline, and the fixing screw is provided with a spline groove, so as to facilitate the connection between the fixing knob and the fixing screw.
[0013] Compared with the prior art, the utility model provides an anchor pile for 10 kV distribution line construction, which has the following beneficial effects:
[0014] 1. By setting up a frustum, it is convenient to drive the anchor pile body into the ground. By setting up a movable plate and an inverted tip on the frustum, an umbrella-shaped cone tip is formed, which can prevent the anchor pile body from moving in the opposite direction. By setting up a flow groove and a diversion groove, it plays a role in diverting sediment and reducing resistance.
[0015] 2. The fixing screw is driven to rotate by the fixing knob. After the fixing screw is rotated, the fixing plate moves on the fixing screw, driving the insertion rod to be inserted into the soil through the insertion hole, thereby improving the supporting and anchoring effect of the anchor pile body and the soil.
[0016] 3. By setting the gripping rod and connecting rod on the stabilizing block, it is convenient to support the top of the anchor pile body on the ground, thereby improving the stability of the top of the anchor pile body and preventing the left and right shaking due to insufficient gripping force when lateral loads such as shaking and vibration occur. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the overall structure of the anchor pile body in the utility model;
[0018] Figure 2 It is a schematic diagram of the matching structure of the frustum, the positioning platform and the movable plate in the utility model;
[0019] Figure 3 This is a schematic diagram of the cross-sectional structure of the stabilizing device in the utility model;
[0020] Figure 4This is a schematic diagram of the internal structure of the fixed sleeve in the utility model;
[0021] Figure 5 It is a structural schematic diagram of the utility model.
[0022] In the figure: 1. Anchor pile body; 2. Fixed sleeve; 3. Positioning platform; 4. Cone; 5. Movable plate; 6. Chamfer; 7. Fixed plate; 8. Insert rod; 9. Insert hole; 10. Fixed screw; 11. Stabilizing block; 12. Grip rod; 13. Connecting rod; 14. Flow groove; 15. Guide groove; 16. First connecting groove; 17. Connecting block; 18. Second connecting groove; 19. Connecting plate; 20. Connecting bolt; 21. Fixed knob; 22. Fixed spline; 23. Spline groove. DETAILED DESCRIPTION
[0023] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present utility model will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0024] It should be noted that, unless otherwise specified, all technical and scientific terms used in this application have the same meanings as commonly understood by ordinary technicians in the technical field to which this application belongs.
[0025] In the present invention, unless otherwise specified, directions such as "up" and "down" are usually used in reference to the directions shown in the drawings, or in reference to the vertical, perpendicular or gravity direction; similarly, for ease of understanding and description, "left" and "right" are usually used in reference to the left and right shown in the drawings; "inside" and "outside" refer to the inside and outside relative to the outline of each component itself, but the above-mentioned directions are not used to limit the present invention.
[0026] See also Figure 1-5 , an anchor pile for 10 kV distribution line construction, including an anchor pile body 1, the anchor pile body 1 includes a fixed sleeve 2, a positioning platform 3 is provided on the bottom of the fixed sleeve 2, a frustum 4 is provided at the bottom of the fixed sleeve 2, a movable plate 5 is rotatably provided on the frustum 4, and a chamfer 6 is provided on the movable plate 5, a fixed disk 7 is provided in the fixed sleeve 2, an insertion rod 8 is hingedly provided on the fixed disk 7, an insertion hole 9 is provided on the fixed sleeve 2, and the insertion rod 8 abuts against the insertion hole 9, a fixed screw 10 is rotatably provided in the fixed sleeve 2, and the fixed screw 10 is rotatably connected with the fixed disk 7, a stabilizing device is provided at the top of the fixed sleeve 2, and the stabilizing device includes a stabilizing block 11, a gripping rod 12 is rotatably provided on the stabilizing block 11, a connecting rod 13 is provided between the gripping rod 12 and the stabilizing block 11, a fixing knob 21 is provided on the fixing screw 10, a fixing spline 22 is provided on the fixing knob 21, a spline groove 23 is provided on the fixing screw 10, a flow groove 14 is provided on the movable plate 5, and a guide groove 15 is provided on the positioning platform 3.
[0027] In this embodiment, during installation, the anchor pile body 1 is driven into the ground below, and the guide groove 15 on the positioning platform 3 and the flow groove 14 on the movable plate 5 reduce the resistance of the anchor pile body 1 when it moves. The movable plate 5 is movably arranged on the frustum 4 in an umbrella shape. When the anchor pile body 1 is disturbed and moves upward, the umbrella-shaped movable plate 5 spreads outward to prevent the anchor pile body 1 from further moving. At the same time, after the anchor pile body 1 is driven into the ground, the fixed spline 22 of the fixed knob 21 is inserted into the spline groove 23, and the fixed knob 21 is rotated. The fixed knob 21 drives the fixed screw 10 to rotate, and the fixed screw 10 drives the fixed disk 7 to move downward. The fixed disk 7 inserts the insertion rod 8 into the soil through the insertion hole 9, thereby improving the support and anchoring effect of the anchor pile body 1 and the soil.
[0028] See also Figure 5 As an implementation method of an anchor pile for 10 kV distribution line construction for a stabilizing device: a first connecting groove 16 is provided on both sides of the stabilizing block 11, a connecting block 17 matching the first connecting groove 16 is provided on the fixing sleeve 2, a second connecting groove 18 is provided on the stabilizing block 11, a connecting plate 19 is provided between the stabilizing blocks 11, a connecting bolt 20 is provided on the connecting plate 19, and the connecting bolt 20 is threadedly connected to the connecting plate 19, the connecting block 17 and the stabilizing block 11.
[0029] More specifically, when installing the stabilizing device, the stabilizing block 11 is attached to the four sides of the fixing sleeve 2 through the cooperation of the first connecting groove 16 and the connecting block 17, and at the same time, the connecting plate 19 is installed on the second connecting groove 18 of the stabilizing block 11 and fixed by the connecting bolts 20. After the stabilizing block 11 is fixed, the gripping rod 12 is supported outwardly by the connecting rod 13, thereby improving the gripping force of the stabilizing device and the anchor pile body 1.
[0030] In summary, when the overall equipment is in use or running: during installation, the anchor pile body 1 is driven into the ground below, the guide groove 15 on the positioning platform 3 and the flow groove 14 on the movable plate 5 reduce the resistance of the anchor pile body 1 when it moves, and the movable plate 5 is movably arranged on the frustum 4 in an umbrella shape. When the anchor pile body 1 is disturbed and moves upward, the umbrella-shaped movable plate 5 spreads outward to prevent the anchor pile body 1 from further moving. At the same time, after the anchor pile body 1 is driven into the ground, the fixed spline 22 of the fixed knob 21 is inserted into the spline groove 23, and the fixed knob 21 is rotated. The fixed knob 21 drives the fixed screw 10 to rotate, and the fixed screw 10 drives the fixed disk 7 to move downward. The fixed disk 7 inserts the insertion rod 8 into the soil through the insertion hole 9, thereby improving the support and anchoring effect of the anchor pile body 1 and the soil.
[0031] When installing the stabilizing device, the stabilizing block 11 is attached to the four sides of the fixing sleeve 2 through the cooperation of the first connecting groove 16 and the connecting block 17. At the same time, the connecting plate 19 is installed on the second connecting groove 18 of the stabilizing block 11 and fixed by the connecting bolts 20. After the stabilizing block 11 is fixed, the gripping rod 12 is supported outwardly by the connecting rod 13, thereby improving the gripping force of the stabilizing device and the anchor pile body 1.
[0032] In all the schemes mentioned above, the connection between two parts can be selected according to actual conditions by welding, bolt and nut matching connection, bolt or screw connection or other well-known connection methods, which are not described here one by one. In the above, all fixed connections are preferably welded. Although the embodiments of the utility model have been shown and described, it can be understood by ordinary technicians in this field that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principle and spirit of the utility model. The scope of the utility model is defined by the attached claims and their equivalents.
Claims
1. An anchor pile for 10 kV power distribution line construction, comprising an anchor pile body (1), characterized in that: The anchor pile body (1) comprises a fixed sleeve (2), a positioning platform (3) is provided on the bottom of the fixed sleeve (2), a frustum (4) is provided on the bottom of the fixed sleeve (2), a movable plate (5) is rotatably provided on the frustum (4), a chamfer (6) is provided on the movable plate (5), a fixed disk (7) is provided in the fixed sleeve (2), an insertion rod (8) is hingedly provided on the fixed disk (7), an insertion hole (9) is provided on the fixed sleeve (2), the insertion rod (8) abuts against the insertion hole (9), a fixed screw (10) is rotatably provided in the fixed sleeve (2), the fixed screw (10) is rotatably connected to the fixed disk (7), a stabilizing device is provided on the top of the fixed sleeve (2), the stabilizing device comprises a stabilizing block (11), a gripping rod (12) is rotatably provided on the stabilizing block (11), a connecting rod (13) is provided between the gripping rod (12) and the stabilizing block (11).
2. The anchor pile for 10 kV power distribution line construction according to claim 1 is characterized in that: The movable plate (5) is provided with a flow groove (14).
3. The anchor pile for 10 kV power distribution line construction according to claim 1 is characterized in that: The positioning platform (3) is provided with a guide groove (15).
4. The anchor pile for 10 kV power distribution line construction according to claim 1 is characterized in that: First connecting grooves (16) are provided on both sides of the stabilizing block (11), and a connecting block (17) matching with the first connecting grooves (16) is provided on the fixing sleeve (2).
5. The anchor pile for 10 kV power distribution line construction according to claim 4 is characterized in that: A second connecting groove (18) is provided on the stabilizing block (11), and a connecting plate (19) is provided between the stabilizing blocks (11).
6. The anchor pile for 10 kV power distribution line construction according to claim 5 is characterized in that: The connecting plate (19) is provided with connecting bolts (20), and the connecting bolts (20) are threadedly connected to the connecting plate (19), the connecting block (17) and the stabilizing block (11).
7. The anchor pile for 10 kV power distribution line construction according to claim 1 is characterized by: The fixing screw rod (10) is provided with a fixing knob (21).
8. The anchor pile for 10 kV power distribution line construction according to claim 7 is characterized in that: The fixing knob (21) is provided with a fixing spline (22), and the fixing screw rod (10) is provided with a spline groove (23).