Composite pile protecting and retaining structure for deep foundation pit at waterside light and shade excavation joint section of railway tunnel
By adopting composite pile protective structures of steel sheet piles, double-tube rotary spray piles and drilled piles in the crossing section of the water-facing and dark excavation of railway tunnels, the problems of high construction costs, slow speed and complex process are solved, and the deep foundation pit opening is achieved The safety, efficiency and economical effect of mining.
Patent Information
- Application Number
- CN202421199824.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-29
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-05-29
AI Technical Summary
The excavation of deep foundation pits in the crossing section of the light and dark excavation of the railway tunnel in the light and dark water is problematic, with high construction costs, slow speed and complex process.
The composite pile protective support structure adopts steel sheet piles, double-tube rotary spray piles and drilled cast piles. The steel sheet piles are used to prevent water leakage, the double-tube rotary spray piles are used to reinforce the foundation, and the drilled cast piles are used to strengthen the anti-seepage and connect to form a composite support system.
It significantly reduces the amount of concrete and engineering cost, shortens the construction cycle, improves the strength of the strata and anti-seepage performance, reduces the amount of later maintenance, and ensures construction safety and economic benefits.
Smart Images

Figure CN222120260U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of retaining structures, and in particular relates to a composite pile protective retaining structure for a deep foundation pit at a junction section of open and dark excavation near water in a railway tunnel. Background Art
[0002] As the scale of underground space development in my country becomes larger and larger, the requirements for deep foundation pit support technology are also getting higher and higher, and the foundation pit is constantly developing in the direction of "deep, large, and close". In order to ensure the smooth construction of foundation pit projects in complex environments, the safety of the main underground structure and the surrounding environment of the foundation pit, the requirements for the support, reinforcement and protection measures of the side walls of the foundation pit, the surrounding soil, and the surrounding environment are getting higher and higher. For this reason, deep foundation pit excavation and support have attracted widespread attention from all parties, and new technologies, methods, and processes have also emerged continuously.
[0003] Common support forms for deep foundation pits include slope reduction, soil nail wall, cement soil wall, underground continuous wall, and pile support.
[0004] "Larsen" steel sheet piles have greater rigidity, and they interlock with each other through the lock mouth, so they have good sealing performance and are basically watertight. High-pressure jet grouting piles use drilling rigs, grouting pipes, high-pressure pumps and other devices to make the nozzle spray out high-pressure jets. During the process of rotating and lifting the drill rod at a certain speed, the high-pressure jet cuts and destroys the original foundation soil, and mixes the slurry with the damaged soil particles. After the slurry solidifies, a consolidation body with a certain strength is formed in the soil, thereby achieving the purpose of strengthening the soil. Bored and cast-in-place piles refer to piles made by forming pile holes in the foundation soil at the construction site through mechanical drilling, steel pipe squeezing or manual excavation, and placing steel cages and pouring concrete inside. Utility Model Content
[0005] The present application provides a composite pile protection and retaining structure for a deep foundation pit at the junction of open and dark excavation near water in a railway tunnel, with the purpose of solving the problems of high cost, slow speed and complicated process in the traditional construction of deep foundation pits at the junction of open and dark excavation near water in existing railway tunnels.
[0006] To this end, the utility model adopts the following technical solutions:
[0007] A composite pile protection and retaining structure for a deep foundation pit at the junction of an open and concealed excavation section near water in a railway tunnel comprises a row of steel sheet piles constructed along the waterside edge, the steel sheet piles being used to prevent water infiltration in the river; a row of double-tube rotary jet piles being constructed inside the steel sheet piles and adjacent to the tunnel foundation pit, the double-tube rotary jet piles being parallel to the steel sheet piles, the pile depth of the double-tube rotary jet piles being greater than the pile depth of the steel sheet piles, and the double-tube rotary jet piles being used to reinforce the foundation and enhance anti-seepage; bored cast-in-place piles being constructed along the pit wall of the tunnel foundation pit, the pile depth of the bored cast-in-place piles being greater than the pile depth of the double-tube rotary jet piles, and mesh spraying concrete reinforcement connection between the cast-in-place piles.
[0008] Furthermore, the steel sheet piles are constructed 4-6 meters from the water edge.
[0009] Furthermore, the steel sheet piles are SP-IV type steel sheet piles with a length of 10-16 meters.
[0010] Furthermore, the specification of the double-tube jet grouting pile is φ800@600mm, and the pile length is 12-16m.
[0011] Furthermore, the double-tube jet grouting piles are 18-22m away from the steel sheet piles.
[0012] Furthermore, the double-tube jet-jet pile is 4-6m away from the bored pile.
[0013] The beneficial effects of the utility model are:
[0014] The retaining structure of this application adopts the composite pile protection design method, which greatly reduces the amount of concrete used and the project cost, and has significant economic benefits; the construction cost and the above-mentioned saved construction costs directly save a total of about 200,000 yuan. It reduces labor costs and saves material turnover costs and machinery turnover costs.
[0015] The composite pile protection design method of this application effectively ensures the safety of deep foundation pit excavation of the tunnel. The composite pile protection construction technology effectively ensures the smooth progress of foundation pit excavation, improves the strength and anti-seepage performance of the stratum on the left side of the line, and reduces the workload of later tunnel maintenance. It provides convenience and safety for the later operation and use and maintenance of the tunnel. Compared with traditional deep foundation protection construction, the tunnel open excavation deep foundation composite pile protection construction technology has a short construction period, is safe and controllable, and large machinery can be used during construction, and the excavation impact range is small. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the composite protective retaining structure of the utility model;
[0017] In the figure: 1- steel sheet piles, 2- double-tube rotary jet piles, 3- bored cast-in-place piles, 4- tunnel foundation pit. DETAILED DESCRIPTION
[0018] The utility model is further described below in conjunction with the accompanying drawings and specific embodiments:
[0019] like Figure 1As shown, a composite pile protection and retaining structure for a deep foundation pit at the junction of an open and concealed excavation section near a waterway in a railway tunnel is provided. Before the construction of the open excavation section, the 30m range between the foundation pit 4 of the railway tunnel section and the pond (sewage sedimentation tank) is backfilled and compacted. The composite pile protection and retaining structure includes a row of steel sheet piles 1 constructed 4-6 meters along the waterside edge, and the steel sheet piles 1 are used to prevent water infiltration; the steel sheet piles 1 are SP-IV type steel sheet piles 1, with a length of 12m, driven 11m underground, and 1m exposed.
[0020] A row of double-tube rotary jet piles 2 is constructed near the tunnel foundation pit 4. The double-tube rotary jet piles 2 are parallel to the steel sheet piles 1. The double-tube rotary jet piles 2 are used to reinforce the foundation and enhance anti-seepage. The specifications of the double-tube rotary jet piles 2 are φ800@600mm, the pile length is 14m, the distance between the double-tube rotary jet piles 2 and the steel sheet piles 1 is 18-22m, and the distance between the double-tube rotary jet piles 2 and the cast-in-place piles is 4-6m.
[0021] Bored cast-in-place piles 3 are constructed on both sides of the foundation pit, and the piles are reinforced with mesh and concrete spraying. The specifications of the cast-in-place piles are Φ800@1200.
[0022] The construction sequence of the design method of this application is: riprap to squeeze silt → steel sheet pile 1 cofferdam + jet jet pile protection water stop → bored cast-in-place pile 3 construction → pile top crown beam and retaining wall construction → main structure construction → open hole opening construction. Bored cast-in-place pile 3 should first be prepared for construction. Before construction, trench excavation is required. The trench excavation depth is not less than 2m, and the excavation is carried out to the original soil to find out the underground pipeline. The site is leveled to replace the soft soil, compact it, and uniformly plan the mud pool. Mud making materials and mud pools: expansive soil is used for the wall mud soil, and prefabricated iron boxes are used as mud pools. During the drilling process, the decompression drilling method is used to ensure the verticality of the hole, and the elevation of the mud surface in the hole is always guaranteed. A mud pump is equipped to replenish the mud in the casing in time to achieve the wall protection hole. The steel sheet pile 1 is inserted and driven using a 50t crawler crane with a pile hammer to insert the steel sheet pile 1 to the designed elevation position, and the pile frame is kept vertical during insertion. Steel sheet pile 1 is 12m long with 1m exposed. The driving order starts from the upstream and closes at the downstream. Each side is driven from one corner to the other. When driving steel sheet pile 1, the verticality of the pile must be strictly controlled, especially the first pile must be controlled simultaneously from two mutually perpendicular directions to ensure verticality.
[0023] Implementation Cases:
[0024] The new Guandaoling Tunnel is located at the mileage of GTGDK173+445~GTGDK173+590, with a length of 145m. The tunnel passes under a pond and G201. The tunnel cover thickness is 2.5-3.5m. The open excavation method is used for construction. The foundation pit depth is 12.9-13.7m and the foundation pit width is 7m. On the left side of the open excavation foundation pit is an existing pond, which also serves as a sedimentation pool for the water company. How to prevent the adverse effects of groundwater seepage at the pond dam site on the foundation pit excavation and the construction of the base pile foundation is the key to the open excavation foundation pit construction in this section. The deep foundation pit adopts a composite support system consisting of 3 bored cast-in-place piles, rotary jet piles, and 1 steel sheet pile to solve the above problems well.
Claims
1. A composite pile protection and retaining structure for deep foundation pits at the junction of open and dark excavation in a railway tunnel near water, characterized in that: The method comprises constructing a row of steel sheet piles (1) along the waterside, wherein the steel sheet piles (1) are used to prevent water infiltration in the river; A row of double-tube jet grouting piles (2) is constructed inside the steel sheet piles (1) and adjacent to the tunnel foundation pit (4). The double-tube jet grouting piles (2) are parallel to the steel sheet piles (1). The pile depth of the double-tube jet grouting piles (2) is greater than the pile depth of the steel sheet piles (1). The double-tube jet grouting piles (2) are used to reinforce the foundation and enhance anti-seepage. Bored cast-in-place piles (3) are constructed along the pit wall of the tunnel foundation pit (4). The pile depth of the bored cast-in-place piles (3) is greater than the pile depth of the double-tube rotary jet piles (2). The piles of the cast-in-place piles are reinforced by mesh spraying and rolling concrete.
2. The composite pile protection and retaining structure for deep foundation pits in the junction section of open and concealed excavation near water in a railway tunnel according to claim 1 is characterized in that: The steel sheet piles (1) are constructed 4-6 meters from the water edge.
3. The composite pile protection and retaining structure for deep foundation pits in the junction section of open and concealed excavation near water in a railway tunnel according to claim 1 is characterized in that: The steel sheet pile (1) is an SP-IV type steel sheet pile (1) with a length of 10-16 meters.
4. The composite pile protection and retaining structure for deep foundation pits in the junction section of open and concealed excavation near water in a railway tunnel according to claim 1 is characterized in that: The specification of the double-tube jet grouting pile (2) is φ800@600mm, and the pile length is 12-16m.
5. The composite pile protection and retaining structure for deep foundation pits in the junction section of open and concealed excavation near water in a railway tunnel according to claim 4 is characterized in that: The double-tube jet grouting pile (2) is 18-22 m away from the steel sheet pile (1).
6. The composite pile protection and retaining structure for deep foundation pits in the junction section of open and concealed excavation near water in a railway tunnel according to claim 5 is characterized in that: The double-tube jet-jet pile (2) is 4-6 m away from the cast-in-place pile.