Protection device for horizontal pipe under foundation pit

By designing the combination of inclined horizontal pipe sections and steel protective components under the foundation pit, the efficiency and safety of the horizontal pipe construction of the ground source heat pump system under the height difference of the foundation pit raft slab is solved, and the construction period is shortened and the pipeline safety is achieved. run.

CN222120301UActive Publication Date: 2024-12-06BGI ENG CONSULTANTS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420082277.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-12
Publication Date
2024-12-06
Estimated Expiration
2034-01-12

AI Technical Summary

Technical Problem

When there is a height difference in the foundation pit raft slab and is affected by the cross-construction of the earthwork unit, the horizontal pipe of the ground source heat pump system needs to be constructed in advance to avoid damage, and it is difficult for the existing technology to solve this problem efficiently.

Method used

A horizontal pipe protection device under foundation pit was designed, including inclined horizontal pipe sections, steel protective components and rubber-plastic insulation layer. Through the embedded steel protective components and concrete filling layer, the horizontal pipe is ensured at the height difference of the foundation pit. Safety and stability.

Benefits of technology

This device can shorten the construction period, ensure the safety of the operation of the horizontal pipe, avoid construction complexity and safety hazards caused by height difference, and improve construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120301U_ABST
    Figure CN222120301U_ABST
Patent Text Reader

Abstract

The utility model discloses a foundation pit lower horizontal pipe protection device which comprises a foundation pit, a raft plate is arranged at the top of the foundation pit, a horizontal pipe is laid at the upper end in the foundation pit, the horizontal pipe comprises an inclined pipe section, a first rubber and plastic heat preservation layer is arranged on the outer side of the inclined pipe section, and a second rubber and plastic heat preservation layer is arranged on the outer side of the first rubber and plastic heat preservation layer. A first rubber and plastic heat preservation layer is arranged on the outer side of the horizontal pipe, a first steel protection component and a second steel protection component are arranged on the outer side of the first rubber and plastic heat preservation layer, and first steel plates are fixedly arranged on the outer side of the first steel protection component and the outer side of the second steel protection component. After the first steel protection component and the second steel protection component are additionally arranged on the inclined section of a conventional horizontal buried pipe, direct pre-burying can be achieved, then the horizontal pipe is subjected to climbing construction, and the construction period can be shortened. In addition, the operation safety of the horizontal pipe can be ensured during pipe ditch backfilling.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of horizontal pipe protection equipment, and specifically relates to a horizontal pipe protection device under a foundation pit. Background Art

[0002] The horizontal pipe protection device under the foundation pit usually refers to a structural measure used to protect underground pipelines in the foundation pit support design. In urban construction, it is often necessary to carry out foundation pit excavation operations above existing underground facilities such as water pipes, sewage pipes, cable pipes, etc. In order to prevent the foundation pit excavation from causing damage to the pipelines below, a corresponding protective structure needs to be set up.

[0003] With the popularization of ground source heat pump system, it is more and more common to arrange vertical buried pipe heat exchangers under the foundation pit raft. The buried holes are arranged under the foundation pit raft. The horizontal pipes of the ground source heat pump are generally laid at the same elevation. If there is a height difference in the foundation pit raft and it is affected by the cross-construction of the earthwork unit (such as skip-bin construction), it is necessary to construct the horizontal buried pipe in advance at the height difference of the foundation pit raft. Utility Model Content

[0004] The technical problem to be solved by the utility model is to overcome the existing defects and provide a horizontal pipe protection device under the foundation pit to solve the problem raised in the above background technology that with the popularization of the application of ground source heat pump systems, it is becoming more and more common to arrange vertical buried pipe heat exchangers under the foundation pit raft. The buried holes are arranged under the foundation pit raft, and the horizontal pipes of the ground source heat pump are generally laid at the same elevation. If there is a height difference in the foundation pit raft and it is affected by the cross-construction of the earthwork unit, it is necessary to carry out early construction of the horizontal buried pipe at the height difference of the foundation pit raft.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a horizontal pipe protection device under a foundation pit, comprising a foundation pit, a raft is arranged on the top of the foundation pit, a horizontal pipe is paved at the upper end of the interior of the foundation pit, the horizontal pipe comprises an inclined inclined pipe section, a first rubber-plastic insulation layer is arranged on the outer side of the inclined pipe section, a first steel protection component and a second steel protection component are respectively arranged on the outer side of the first rubber-plastic insulation layer, a first steel plate is fixedly arranged on the outer side of the first steel protection component and the second steel protection component, a second steel plate is fixedly arranged between the first steel protection component and the second steel protection component, a water supply pipe and a water return pipe are arranged in layers inside the first steel protection component and the second steel protection component, and the water supply pipe is located below the water return pipe; the interior of the first steel protection component and the second steel protection component is filled with a concrete filling layer, and the outer sides of the water supply pipe and the water return pipe are wrapped with a second rubber-plastic insulation layer.

[0006] Preferably, the middle portion of the raft is inclined, and the top of the raft is provided with an underground first floor base and an underground second floor base, respectively, and the underground first floor base and the underground second floor base are not in the same horizontal plane.

[0007] Preferably, an underground base is provided between the foundation pit and the raft slab.

[0008] Preferably, underground heat exchange holes are provided at the bottom of the foundation pit.

[0009] Preferably, the first steel protective component and the second steel protective component are fixedly connected, and the first rubber-plastic insulation layer runs through the interior of the first steel protective component and the second steel protective component.

[0010] Preferably, the width of the first steel protection member and the second steel protection member is (n-1)

[0011] *d+100mm, the length of the first steel protective member and the second steel protective member is calculated according to the height difference H and the slope α as H / sinα, the height of the first steel protective member and the second steel protective member is the horizontal pipe outer diameter D+100mm, the steel protective member is divided into two layers, the outer diameter of the pipe is 50mm, and the height of the upper and lower layers is 150mm.

[0012] Preferably, the first steel protection member and the second steel protection member are closed up and down and left and right, and open front and back, with the front opening flush with the high horizontal tube and the rear opening flush with the low horizontal tube.

[0013] Preferably, the thickness of the second rubber insulation layer is 20 mm.

[0014] Compared with the prior art, the utility model provides a horizontal pipe protection device under the foundation pit, which has the following beneficial effects:

[0015] 1. The utility model sets a horizontal pipe protection device under the foundation pit. Conventional horizontal buried pipes climbing the slope or soil nail wall generally use external rubber-plastic protective sleeves. If there is a height difference in the foundation pit, it is necessary to communicate with the earthwork professionals in advance about the construction period of the trench where the horizontal pipe climbs, the horizontal pipe climbing and the trench backfilling construction period. After adding the first steel protection component and the second steel protection component, it can be directly pre-buried, and then the horizontal pipe climbing construction can be carried out, which helps to shorten the construction period. In addition, the operation safety of the horizontal pipe can also be ensured when the trench is backfilled.

[0016] The parts not involved in the device are the same as the existing technology or can be implemented by using the existing technology. The utility model has a scientific and reasonable structure, is safe and convenient to use, and provides great help to people. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0018] Figure 1 This is a schematic diagram of the system principle structure of a horizontal pipe protection device under a foundation pit proposed by the utility model;

[0019] Figure 2 This is a schematic diagram of the structure of a steel protection component of a horizontal pipe protection device under a foundation pit proposed by the utility model;

[0020] Figure 3 This is a schematic diagram of the bottom view of the steel protection component structure of a horizontal pipe protection device under a foundation pit proposed by the utility model;

[0021] Figure 4 This is a schematic diagram of the front view of the steel protection component structure of a horizontal pipe protection device under a foundation pit proposed by the utility model;

[0022] Figure 5 This is a schematic diagram of the cross-sectional structure of a steel protection component of a horizontal pipe protection device under a foundation pit proposed by the utility model;

[0023] In the figure: foundation pit 1, raft 2, underground first floor base 3, underground second floor base 4, cushion layer 5, horizontal pipe 6, buried heat exchange hole 7, first rubber-plastic insulation layer 8, first steel protection member 9, second steel protection member 10, first steel plate 11, second steel plate 12, concrete filling layer 13, second rubber insulation layer 14, water supply pipe 15, return pipe 16, vertical heat exchange pipe 17. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] See also Figure 1-5The utility model provides a technical solution: a horizontal pipe protection device under a foundation pit, comprising a foundation pit 1, a raft 2 is arranged on the top of the foundation pit 1, a horizontal pipe 6 is paved at the upper end of the interior of the foundation pit 1, the horizontal pipe 6 comprises an inclined inclined pipe section, a first rubber-plastic insulation layer 8 is arranged on the outer side of the inclined pipe section, a first steel protection component 9 and a second steel protection component 10 are respectively arranged on the outer side of the rubber-plastic insulation layer 8, a first steel plate 11 is fixedly arranged on the outer side of the first steel protection component 9 and the second steel protection component 10, a second steel plate 12 is fixedly arranged between the first steel protection component 9 and the second steel protection component 10, a water supply pipe 15 and a water return pipe 16 are arranged in layers inside the first steel protection component 9 and the second steel protection component 10, and the water supply pipe 15 is located below the water return pipe 16. The first steel protection member 9 and the second steel protection member 10 are filled with a concrete filling layer 13, and a second rubber insulation layer 14 is fixedly arranged between the water supply and return pipe 15 and the concrete filling layer 13. Conventional horizontal buried pipes climbing slopes or soil nail walls generally use external rubber-plastic protective sleeves. If there is a height difference in the foundation pit, it is necessary to communicate with the earthwork professionals in advance about the construction period of the trench where the horizontal pipe climbs, the horizontal pipe climbing, and the trench backfilling construction period. After adding the rubber-plastic insulation layer, it can be directly pre-buried, and then the horizontal pipe climbing construction can be carried out, which helps to shorten the construction period. In addition, the operation safety of the horizontal pipe can also be ensured when the trench is backfilled.

[0026] In the present invention, preferably, the middle portion of the raft 2 is inclined, and the top of the raft 2 is provided with an underground first floor base 3 and an underground second floor base 4, respectively, and the underground first floor base 3 and the underground second floor base 4 are not in the same horizontal plane.

[0027] In the present invention, preferably, an underground basement 3 is provided between the foundation pit 1 and the raft 2 .

[0028] In the present utility model, preferably, a vertical underground heat exchange hole 7 is provided at the bottom of the foundation pit 1, and a vertical heat exchange pipe 17 is installed in the underground heat exchange hole.

[0029] In the utility model, preferably, the first steel protective component 9 and the second steel protective component 10 are fixedly connected, and the rubber-plastic insulation layer 8 runs through the interior of the first steel protective component 9 and the second steel protective component 10 .

[0030] In the utility model, preferably, the width of the first steel protective member 9 and the second steel protective member 10 is (n-1)*d+100 (with a margin of 50 mm on each side), and the length of the first steel protective member 9 and the second steel protective member 10 is calculated according to the height difference H and the slope α as H / sinα. The height of the first steel protective member (9) and the second steel protective member 10 is the outer diameter of the horizontal pipe D+100 mm. The steel protective members are divided into two layers, the outer diameter of the pipe is 50 mm, and the height of the upper and lower layers is 150 mm.

[0031] In the present utility model, preferably, the first steel protection member 9 and the second steel protection member 10 are closed up and down and left and right, and open front and back, the front end opening is flush with the high horizontal pipe, and the rear end is flush with the low horizontal pipe 6.

[0032] In the present invention, preferably, the thickness of the second rubber insulation layer 14 is 20 mm.

[0033] Working principle and use process of the utility model: When in use, according to the number n of horizontal pipes in the horizontal pipe trench and the spacing d between adjacent horizontal pipes, the width of the first steel protection member 9 and the second steel protection member 10 is calculated as (n-1)*d+100. ( 50mm margin on each side), the length of the first steel protection member 9 and the second steel protection member 10 is calculated according to the height difference H and the slope α as H / sinα, and the height is the outer diameter of the horizontal pipe D+100mm. The first steel protection member 9 and the second steel protection member 10 are closed up and down, left and right, and open front and back. The front end opening is flush with the high horizontal pipe, and the rear end is flush with the low horizontal pipe, which is convenient for the laying of the horizontal pipe. Furthermore, the buried pipe passing through the first steel protection member 9 and the second steel protection member 10 is coated with a 20mm rubber-plastic insulation layer and protected by the buried pipe; further, the front ends of the first steel protection member 9 and the second steel protection member 10 need to be spot welded with blind plates when pre-buried to prevent sand and soil in the foundation pit from entering; further, if the horizontal pipes are arranged in layers, a partition needs to be installed between the first steel protection member 9 and the second steel protection member 10. After the slope is formed, the pipe is dug according to the design requirements. The trench is constructed by leveling the construction range of the horizontal pipe in the climbing area to ensure that there are no sharp particles in the horizontal pipe laying area. The first steel protection component 9 and the second steel protection component 10 are placed in the trench, and the horizontal pipes pass through in turn. Horizontal pipes of not less than 2 meters are reserved in the front and back to determine the positions of the high and low horizontal trenches, which is convenient for connecting the vertical buried branch pipes. When the horizontal pipes are laid, the pipes should not be broken or kinked, and the turns should be smooth. After the construction of the horizontal pipes is completed, the reserved sections of the pipes are protected as finished products to prevent damage caused by cross-construction. After the construction of the horizontal pipes is completed, concrete needs to be poured into the first steel protection component 9 and the second steel protection component 10 and filled.

[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A horizontal pipe protection device under a foundation pit, comprising a foundation pit (1), characterized in that: A raft (2) is arranged on the top of the foundation pit (1), a horizontal pipe (6) is laid at the upper end of the interior of the foundation pit (1), the horizontal pipe (6) comprises an inclined inclined pipe section, a first rubber-plastic thermal insulation layer (8) is arranged on the outside of the inclined pipe section, and a first steel protective component (9) and a second steel protective component (10) are respectively arranged on the outside of the first rubber-plastic thermal insulation layer (8), A first steel plate (11) is fixedly arranged on the outer sides of the first steel protection component (9) and the second steel protection component (10), a second steel plate (12) is fixedly arranged between the first steel protection component (9) and the second steel protection component (10), and a water supply pipe (15) and a water return pipe (16) are arranged in layers inside the first steel protection component (9) and the second steel protection component (10), and the water supply pipe (15) is located below the water return pipe (16); The interior of the first steel protection component (9) and the second steel protection component (10) is filled with a concrete filling layer (13), and the outer sides of the water supply pipe (15) and the water return pipe (16) are wrapped with a second rubber insulation layer (14).

2. A horizontal pipe protection device for a foundation pit according to claim 1, characterized in that: The middle part of the raft (2) is inclined, and the top of the raft (2) is provided with a first underground basement (3) and a second underground basement (4), respectively, and the first underground basement (3) and the second underground basement (4) are not in the same horizontal plane.

3. A horizontal pipe protection device under a foundation pit according to claim 2, characterized in that: An underground basement (3) is provided between the foundation pit (1) and the raft slab (2).

4. A protection device for horizontal pipes under foundation pit according to claim 3, characterized in that: A vertical underground heat exchange hole (7) is provided at the bottom of the foundation pit (1), and a vertical heat exchange pipe (17) is installed in the underground heat exchange hole (7).

5. The horizontal pipe protection device under the foundation pit according to claim 1 is characterized in that: The first steel protection component (9) and the second steel protection component (10) are fixedly connected, and the first rubber-plastic insulation layer (8) runs through the interior of the first steel protection component (9) and the second steel protection component (10).

6. A protection device for horizontal pipes under foundation pit according to claim 1, characterized in that: The width of the first steel protection member (9) and the second steel protection member (10) is (n-1)*d+100mm. The length of the first steel protection member (9) and the second steel protection member (10) is calculated based on the height difference H and the slope α to obtain H / sinα. The height of the first steel protection member (9) and the second steel protection member (10) is the horizontal pipe outer diameter D+100mm. The steel protection member is divided into two layers. The outer diameter of the pipe is 50mm, and the height of the upper and lower layers is 150mm.

7. The horizontal pipe protection device under the foundation pit according to claim 1 is characterized by: The first steel protection component (9) and the second steel protection component (10) are closed at the top and bottom and left and right, and open at the front and back, with the front opening flush with the upper horizontal pipe and the rear opening flush with the lower horizontal pipe (6).

8. The horizontal pipe protection device under the foundation pit according to claim 4 is characterized by: The thickness of the second rubber insulation layer (14) is 20 mm.