Tunnel pipe external pressure test device

By designing the external pressure test device for tunnel pipes, using components such as cylinder, support frame, conveying hoop and flange, the complex problems of existing tunnel pipe test operations are solved, and the external pressure strength and stability within the range of 0 to 2MPa are achieved. Testing, simplifying operation and improving efficiency.

CN222124974UActive Publication Date: 2024-12-06北京天兵科技有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323451578.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-18
Publication Date
2024-12-06
Estimated Expiration
2033-12-18

AI Technical Summary

Technical Problem

When the existing tunnel pipe is subjected to strength test after assembly with the storage tank, if the test fails, it needs to be disassembled from the storage tank, which is complicated to operate.

Method used

A tunnel pipe external pressure test device is designed, including a cylinder, support frame, conveying hoop, flange and sealing ring, which is connected to the external hydraulic system through a blind cavity and joint to achieve external pressure strength and stability within the range of 0 to 2MPa. In order to test the transmission hoops are used to support and locate tunnel pipes, simplifying the installation and disassembly process.

Benefits of technology

The external pressure strength test and verification of tunnel pipes according to different specifications is achieved. It is simple to operate, economical and reliable, reducing damage and labor costs during disassembly and improving work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222124974U_ABST
    Figure CN222124974U_ABST
Patent Text Reader

Abstract

The utility model provides a tunnel pipe external pressure test device. The tunnel pipe external pressure test device comprises a cylinder body, a support frame arranged at the lower part of the cylinder body, a to-be-tested tunnel pipe arranged in the cylinder body, and a transmission hoop arranged on the outer side of the to-be-tested tunnel pipe, a blind cavity is formed between the cylinder body and the tunnel pipe to be tested; the conveying hoop is arranged in the blind cavity and connected to the inner wall of the cylinder in a rolling mode. One end of a to-be-tested tunnel pipe is connected with the front end of the cylinder through a front-end flange, and the other end of the to-be-tested tunnel pipe is connected with the rear end of the cylinder through a rear-end flange. A first pipe joint and a second pipe joint are arranged outside the rear-end flange; the first pipe joint and the second pipe joint are connected with the blind cavity. According to the tunnel pipe external pressure test device, external pressure strength test verification of tunnel pipes of different specifications can be completed only by replacing the front end flange, the rear end flange and the transition flange, and the tunnel pipe external pressure test device is easy to operate, economical and reliable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of launch vehicle tunnel pipes, in particular to an external pressure test device for a tunnel pipe. Background Art

[0002] Liquid launch vehicles usually use oxidizers and fuels to deliver to the engine to provide rocket thrust. The oxidizer tank and fuel tank and their propellant delivery pipelines are arranged correspondingly on the upper and lower parts of the rocket body. In order to reduce the propellant flow resistance and reduce the weight of the delivery pipeline, a tunnel pipe is usually set in the lower tank, and the delivery pipe of the upper tank passes through the tunnel pipe of the lower tank to be delivered to the engine. The tunnel pipe is not only a part of the lower tank, which undertakes the propellant carrying task of the lower tank, but also provides a normal temperature and pressure environment for the propellant delivery pipe of the upper tank. Therefore, the external pressure stability and external pressure strength of the tunnel pipe are related to the reliability of the booster delivery system of the launch vehicle, and its external pressure strength and stability need to be tested and verified. At the current stage, the tunnel pipe is subjected to strength test after it is assembled with the tank. If the test fails, the tunnel pipe needs to be disassembled from the tank, which is complicated.

[0003] In summary, the prior art has the following problems: the existing tunnel pipe is subjected to a strength test after being assembled with the tank. If the test fails, the tunnel pipe needs to be disassembled from the tank, which is a complicated operation. Utility Model Content

[0004] The utility model provides a tunnel pipe external pressure test device, which solves the technical problem that in the existing tunnel pipe, after being assembled with a tank, a strength test is performed and if the test fails, the tunnel pipe needs to be disassembled from the tank, which causes complicated operation.

[0005] In order to achieve the above-mentioned purpose, the utility model provides a tunnel pipe external pressure test device, comprising:

[0006] A cylinder, a support frame arranged at the bottom of the cylinder, and a tunnel pipe to be tested arranged inside the cylinder;

[0007] A blind cavity is provided between the cylinder and the tunnel pipe to be tested;

[0008] One end of the tunnel pipe to be tested is connected to the front end of the cylinder through a front end flange, and the other end of the tunnel pipe to be tested is connected to the rear end of the cylinder through a rear end flange;

[0009] A first pipe joint and a second pipe joint are arranged on the outer side of the rear end flange; the first pipe joint and the second pipe joint are both connected to the blind cavity.

[0010] Specifically, the tunnel pipe external pressure test device further comprises a transmission hoop arranged outside the tunnel pipe to be tested, the transmission hoop is arranged in the blind cavity, and the transmission hoop is rollingly connected to the inner wall of the cylinder;

[0011] The number of the conveying hoops is n, the length of the tunnel pipe to be tested is L, and the diameter is D; wherein: L / 8*D≤n≤L / 4*D.

[0012] Specifically, a transition flange is provided at one end of the tunnel pipe to be tested, and the transition flange is connected to the front end flange.

[0013] Specifically, a roller is arranged on the outer side of the conveying hoop, and the roller is in rolling contact with the inner wall of the cylinder.

[0014] Specifically, a first sealing ring is arranged between the front end flange and the front end of the cylinder; and a second sealing ring is arranged between the rear end flange and the rear end of the cylinder.

[0015] Specifically, a sealing groove is provided at the rear end of the cylinder, the second sealing ring is provided in the sealing groove, the rear end flange is sealed and connected to the cylinder via bolts, and the front end flange is sealed and connected to the cylinder via bolts.

[0016] Specifically, the first pipe joint is connected to an external hydraulic test system.

[0017] Specifically, the second pipe joint is connected to an external pressure gauge.

[0018] Specifically, a third sealing ring is provided between the tunnel pipe to be tested and the transition flange.

[0019] Specifically, the blind cavity is a sealed cavity.

[0020] The utility model has the beneficial effect that: by using the tunnel pipe external pressure test device of the utility model, the external pressure strength and stability test verification within the range of 0 to 2 MPa can be completed according to the use conditions of the tunnel pipe to be tested. By using the tunnel pipe external pressure test device of the utility model, only the front end flange, the rear end flange and the transition flange need to be replaced to complete the external pressure strength test verification of tunnel pipes of different specifications, which is simple to operate, economical and reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a structural schematic diagram of a tunnel pipe external pressure test device provided by an embodiment of the utility model;

[0022] Figure 2 It is a right side view of the tunnel pipe external pressure test device of the utility model;

[0023] Figure 3It is a left side view of the tunnel pipe external pressure test device of the utility model;

[0024] Figure 4 For the utility model Figure 1 Partial enlarged view of Ⅰ;

[0025] Figure 5 For the utility model Figure 1 Ⅱ partial enlarged view;

[0026] Figure 6 For the utility model Figure 2 AA section view;

[0027] Figure 7 For the utility model Figure 2 BB section view.

[0028] Description of Figure Numbers:

[0029] 1. Cylinder; 2. Support frame; 3. Conveying hoop; 4. Tunnel pipe to be tested; 5. Front end flange; 7. Rear end flange; 8. Transition flange; 9. First sealing ring; 10. Third sealing ring; 11. Second sealing ring; 16. Third pipe joint; 17. First pipe joint; 18. DN8 pipe joint; 19. Second pipe joint; 32. Hydraulic elbow; 33. DN15 ball valve. DETAILED DESCRIPTION

[0030] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0031] In the embodiment of the present utility model, Figure 1 As shown, a tunnel pipe external pressure test device is provided, comprising:

[0032] The cylinder 1, the support frame 2 arranged at the bottom of the cylinder 1 and the tunnel pipe 4 to be tested arranged inside the cylinder 1; there is a blind cavity between the cylinder 1 and the tunnel pipe 4 to be tested; the blind cavity is a sealed cavity. Figure 3 As shown, one end of the tunnel pipe 4 to be tested is connected to the front end of the cylinder 1 through the front end flange 5, and the other end of the tunnel pipe 4 to be tested is connected to the rear end of the cylinder 1 through the rear end flange 7; Figure 2 , Figure 6 , Figure 7As shown, a first pipe joint 17 and a second pipe joint 19 are arranged outside the rear end flange 7; both the first pipe joint 17 and the second pipe joint 19 are connected to the blind cavity. The first pipe joint 17 is a DN4 pipe joint, and the second pipe joint 19 is a DN4 pipe joint.

[0033] DN4 and DN8 refer to the nominal diameter of the pipe, which is a standard size of pipe specifications. DN4 means a pipe with a nominal diameter of 4 mm, and DN8 means a pipe with a nominal diameter of 8 mm.

[0034] The tunnel pipe external pressure test device also includes a conveying hoop 3 arranged on the outside of the tunnel pipe 4 to be tested, the conveying hoop 3 is arranged in the blind cavity, and the conveying hoop 3 is rollingly connected to the inner wall of the cylinder 1; the number of conveying hoops 3 is n, the length of the tunnel pipe 4 to be tested is L, and the diameter is D; wherein: L / 8*D≤n≤L / 4*D. A roller is arranged on the outside of the conveying hoop 3, and the roller is in rolling contact with the inner wall of the cylinder 1.

[0035] like Figure 1 As shown, when the embodiment of the utility model is used for the external pressure test of the tunnel pipe, the tunnel pipe 4 to be tested is installed inside the cylinder 1. Considering that the tunnel pipe 4 to be tested is a thin-walled pipe, before the tunnel pipe 4 to be tested is installed inside the cylinder 1, a plurality of conveying hoops 3 with rollers are arranged at intervals outside the tunnel pipe 4 to be tested. The tunnel pipe 4 to be tested is a thin-walled pipe, which may be easily deformed or damaged during the installation or disassembly process. The conveying hoop 3 can effectively reduce the damage to the tunnel pipe 4 to be tested through the support and conveying function of the roller, and ensure the stability and safety during the installation or disassembly process. The conveying hoop 3 can help accurately locate the tunnel pipe 4 to be tested, ensure its correct position during the installation process, and thus ensure the accuracy and stability of the tunnel pipeline system. Through the design of the conveying hoop 3, the installation or disassembly efficiency of the tunnel pipe 4 to be tested can be improved, the manpower and time costs can be reduced, and the work efficiency can be improved. Therefore, the design of the conveying hoop 3 plays the role of support, conveyance and positioning during the external pressure test of the tunnel pipe, solves the technical problems in the installation or disassembly process, reduces the damage during the disassembly process, and improves the installation or disassembly efficiency and safety.

[0036] A transition flange 8 is provided at one end of the tunnel pipe 4 to be tested, and the transition flange 8 is connected to the front end flange 5 .

[0037] like Figure 4As shown, a first sealing ring 9 is arranged between the front end flange 5 and the front end of the cylinder 1; a second sealing ring 11 is arranged between the rear end flange 7 and the rear end of the cylinder 1. A sealing groove is arranged at the rear end of the cylinder 1, and the second sealing ring 11 is arranged in the sealing groove. The rear end flange 7 and the cylinder 1 are sealed and connected by bolts, and the front end flange 5 and the cylinder 1 are sealed and connected by bolts. A third sealing ring 10 is arranged between the tunnel pipe 4 to be tested and the transition flange 8. The two ends of the tunnel pipe 4 to be tested are respectively fixed to the cylinder 1 by bolts through the front end flange 5 and the rear end flange 7. Specifically, a sealing member is arranged on the butt flange surface. Before the flanges are butt-jointed, the sealing gasket is first installed in the sealing groove of the flange surface. After the flanges are butt-jointed, the sealing gasket is pressed by the pre-tightening force of the bolts. In order to ensure reliable sealing, the compression amount of the sealing gasket is not less than 0.5 mm.

[0038] The first pipe joint 17 is connected to an external hydraulic test system. The second pipe joint 19 is connected to an external pressure gauge. The first pipe joint 17 is connected to the compressed air of the hydraulic test system to step-by-step pressurize the blind cavity to the tunnel pipe test pressure and maintain the pressure for 15 minutes. The second pipe joint 19 is connected to the pressure gauge to observe the pressure condition in the blind cavity in real time.

[0039] As an implementation method, Figure 5 As shown, a third pipe joint 16 is arranged outside the rear end flange 7. The third pipe joint 16 is a DN4 pipe joint. The third pipe joint 16 includes a hydraulic elbow 32 and a DN15 ball valve (a ball valve with a nominal diameter of 15 mm) 33. The third pipe joint 16 is externally connected to a hydraulic test system. The hydraulic elbow 32 is connected to a DN8 pipe joint 18, and the DN8 pipe joint 18 is connected to a blind cavity. When the external pressure test is performed, the third pipe joint 16 and the first pipe joint 17 are used to pass the filling pipe of the hydraulic test system to allow deionized water to enter the blind cavity between the tunnel pipe 4 to be tested and the cylinder 1 through the 90° hydraulic elbow 32. When the amount of distilled water filled reaches 80% to 85% of the volume of the blind cavity, the DN15 ball valve 33 is closed and the filling is stopped. The first pipe joint 17 is externally connected to the compressed air of the hydraulic test system to step-by-step pressurize the blind cavity to the tunnel pipe test pressure and maintain the pressure for 15 minutes. The second pipe joint 19 is externally connected to a pressure gauge to observe the pressure condition in the blind cavity in real time. In addition, ball valves of other diameters can be selected to replace the DN15 ball valve 33 according to actual conditions.

[0040] As an implementation mode, the tunnel pipe external pressure test device proposed in the utility model can complete the external pressure strength and stability test verification within the range of 0 to 2 MPa according to the use conditions of the tunnel pipe 4 to be tested. If the use condition of the tunnel pipe 4 to be tested is a low temperature environment, it is necessary to first test the sealing performance of the connection between the two ends of the tunnel pipe 4 to be tested through the front flange 5 and the rear flange 7 and the cylinder 1 at a test temperature slightly lower than the use condition, and strictly ensure that the leakage rate requirement of each connection part at the test temperature is not greater than 1×10 -7Pa·m 3 / s.

[0041] The tunnel pipe external pressure test device proposed in the utility model has the following test process:

[0042] a) Install the transition flange 8 and the sealing ring 10 at the front end of the tunnel pipe 4 to be tested to form a combination, and the gaps on each side of the flange joint surface are required to be basically the same;

[0043] b) Install the transmission hoop 3 at intervals outside the tunnel pipe 4 to be tested;

[0044] c) slowly feeding the tunnel pipe 4 to be tested into the interior of the cylinder 1 from one end of the cylinder 1;

[0045] d) Install the sealing ring in the sealing groove of the transition flange 8 and the cylinder 1, and then seal the front flange 5 with the transition flange 8 and the cylinder 1 respectively. The gaps on each side of the flange joint surface are required to be basically the same. Insert the bolts and install the flat washers, spring washers and nuts. Tighten them evenly and symmetrically in the circumferential direction. Measure with a feeler gauge to keep the gaps on each side consistent.

[0046] e) Install the sealing ring in the sealing groove of the rear flange 7 and the cylinder 1, and then seal the rear flange 7 with the tunnel pipe 4 to be tested and the cylinder 1, respectively. The gaps on each side of the flange joint surface are required to be basically the same. Insert the bolts and install the flat washers, spring washers and nuts. Tighten them evenly and symmetrically in the circumferential direction. Use a feeler gauge to measure and keep the gaps on each side consistent.

[0047] f) Confirm that all bolts have been tightened, apply torque according to the specifications of the flange seals, and record the applied torque value; perform symmetrical correction according to the specified torque until the nuts cannot rotate, perform correction three times in total, and measure the flange surface clearance;

[0048] g) After an interval of 8 hours, calibrate the nut in the circumferential direction with the final torque until the nut stops rotating;

[0049] h) After the test tunnel pipe 4 and the cylinder 1 are assembled, a hydraulic pressure test is performed on them using distilled water;

[0050] i) The combination of “90° hydraulic elbow 32, third pipe joint 16, first pipe joint 17, DN15 ball valve 33” is connected to the filling pipe of the hydraulic test system. Deionized water enters the blind cavity between the tunnel pipe 4 to be tested and the cylinder 1 through the 90° hydraulic elbow 32. When the amount of distilled water filled reaches 80% to 85% of the volume of the blind cavity, the DN15 ball valve 33 is closed and the filling is stopped;

[0051] j) The first pipe joint 17 is connected to the compressed air of the hydraulic test system, and the blind cavity is pressurized in a step-by-step manner to the tunnel pipe test pressure and maintained for 15 minutes. No leakage is allowed. The second pipe joint 19 is connected to the pressure gauge to record the blind cavity pressure value between the tunnel pipe and the cylinder in real time;

[0052] k) Perform soap bubble leak detection on the weld of the test tunnel pipe 4. If there is no bubble for 3 minutes, the leak rate is considered qualified;

[0053] l) After the hydraulic test, measure the flange sealing surface gap and sealing surface flatness and other parameters;

[0054] m) After the test is completed, after the pressure is released and the distilled water is discharged, the tunnel pipe 4 to be tested is disassembled in reverse and the surface moisture is dried;

[0055] n) Visually inspect the appearance of the test tunnel pipe to check for obvious damage such as cracks, protrusions, pits, etc., and on this basis, take photos of its welds for re-inspection;

[0056] o) When the external pressure test is a strength limit test, the pressure can be increased in steps until the tunnel pipe ruptures to obtain its ultimate bearing capacity.

[0057] The utility model has the following beneficial effects:

[0058] The tunnel pipe external pressure test device provided by the utility model, in conjunction with helium mass spectrometer leak detection test equipment or soap bubble reagent, can complete the tunnel pipe external pressure bearing capacity test verification with a working pressure not greater than 2MPa.

[0059] The pressure condition in the blind cavity is observed in real time by using the first pipe joint 17 and the second pipe joint 19. The first pipe joint 17 is connected to the external hydraulic test system, and the second pipe joint 19 is connected to the external pressure gauge. The first pipe joint 17 is connected to the compressed air of the external hydraulic test system, and the blind cavity is pressurized to the tunnel pipe test pressure in a step-by-step manner and maintained for 15 minutes, and the pressure condition in the blind cavity is observed in real time.

[0060] The transmission hoop 3 is provided to improve the supporting and fixing effect of the tunnel pipe 4 to be tested, and plays a stabilizing role during the external pressure test of the tunnel pipe.

[0061] By adopting the tunnel pipe external pressure test device of the utility model, the external pressure strength and stability test verification within the range of 0 to 2 MPa can be completed according to the use conditions of the tunnel pipe to be tested. By adopting the tunnel pipe external pressure test device of the utility model, only the front end flange, the rear end flange and the transition flange need to be replaced to complete the external pressure strength test verification of tunnel pipes of different specifications. The operation is simple, economical and reliable.

[0062] The above description is only an illustrative specific implementation of the utility model, and is not intended to limit the scope of the utility model. The various components of the utility model can be combined with each other under non-conflicting conditions, and any equivalent changes and modifications made by any technician in the field without departing from the concept and principle of the utility model should fall within the scope of protection of the utility model.

Claims

1. A tunnel pipe external pressure test device, characterized in that: include: A cylinder (1), a support frame (2) arranged at the bottom of the cylinder (1), and a tunnel pipe (4) to be tested arranged inside the cylinder (1); A blind cavity is provided between the cylinder (1) and the tunnel pipe (4) to be tested; One end of the tunnel pipe to be tested (4) is connected to the front end of the cylinder (1) via a front end flange (5), and the other end of the tunnel pipe to be tested (4) is connected to the rear end of the cylinder (1) via a rear end flange (7); A first pipe joint (17) and a second pipe joint (19) are arranged on the outside of the rear end flange (7); the first pipe joint (17) and the second pipe joint (19) are both connected to the blind cavity.

2. A tunnel pipe external pressure test device according to claim 1, characterized in that: The tunnel pipe external pressure test device further comprises a transmission hoop (3) arranged outside the tunnel pipe (4) to be tested, the transmission hoop (3) being arranged in the blind cavity, and the transmission hoop (3) being rollingly connected to the inner wall of the cylinder (1); The number of the conveying hoops (3) is n, the length of the tunnel pipe (4) to be tested is L, and the diameter is D; wherein: L / 8*D≤n≤L / 4*D.

3. A tunnel pipe external pressure test device according to claim 1, characterized in that: A transition flange (8) is provided at one end of the tunnel pipe (4) to be tested, and the transition flange (8) is connected to the front end flange (5).

4. A tunnel pipe external pressure test device according to claim 2, characterized in that: A roller is arranged on the outer side of the conveying hoop (3), and the roller is in rolling contact with the inner wall of the cylinder (1).

5. The tunnel pipe external pressure test device according to claim 1, characterized in that: A first sealing ring (9) is provided between the front end flange (5) and the front end of the cylinder (1); and a second sealing ring (11) is provided between the rear end flange (7) and the rear end of the cylinder (1).

6. A tunnel pipe external pressure test device according to claim 5, characterized in that: The rear end of the cylinder (1) is provided with a sealing groove, the second sealing ring is arranged in the sealing groove, the rear end flange (7) is sealed and connected to the cylinder (1) by bolts, and the front end flange (5) is sealed and connected to the cylinder (1) by bolts.

7. The tunnel pipe external pressure test device according to claim 1, characterized in that: The first pipe joint (17) is connected to an external hydraulic test system.

8. The tunnel pipe external pressure test device according to claim 1, characterized in that: The second pipe joint (19) is connected to an external pressure gauge.

9. The tunnel pipe external pressure test device according to claim 3, characterized in that: A third sealing ring (10) is provided between the tunnel pipe to be tested (4) and the transition flange (8).

10. The tunnel pipe external pressure test device according to claim 3, characterized in that: The blind cavity is a sealed cavity.