Assembly type prefabricated concrete primary support arch frame connecting assembly
Through the prefabricated precast concrete primary support arch connecting components, the problems of large steel usage, long construction period and harsh construction environment in the traditional concealed tunnel primary support structure are solved, and efficient, safe and environmentally friendly construction results are achieved.
Patent Information
- Application Number
- CN202421049033.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-14
- Publication Date
- 2024-12-13
- Estimated Expiration
- 2034-05-14
AI Technical Summary
In the initial support structure of traditional concealed tunnels, the steel arch frame + jet concrete has large steel usage, high cost and poor jet quality. The grille arch frame + jet concrete cannot be supported in time, the construction period is long, and the construction environment is harsh, which affects the health of workers. and construction progress.
Prefabricated prefabricated concrete primary support arch frame connection components, including prefabricated concrete primary support arch frame, node components, longitudinal distributed steel bar joints, locking anchor rods and jet concrete. After production in the prefabricated factory, it will be quickly assembled on site to improve standardization degree and construction efficiency.
It reduces the amount of steel and construction costs, shortens the construction period, improves the working environment of workers, improves the construction speed and construction safety, and ensures the stability and environmental protection of surrounding rocks.
Smart Images

Figure CN222162642U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of initial support structure engineering of dark-digging tunnels, and in particular relates to an assembled prefabricated concrete initial support arch frame connection component in the initial support of dark-digging tunnels. Background Art
[0002] With the continuous development of urbanization in my country, underground space development has shown a rapid development momentum, and there are more and more underground projects such as underground pedestrian walkways, cross-river tunnels, and urban rail transit. Affected by factors such as the limitation of open excavation space on the ground, the current difficulties in traffic organization, and the protection of existing underground pipelines, the mining method has been widely used, and the selection of primary support structure has become a key node, which is related to the safety of the dark excavation support system and the control of on-site construction progress, and has become the key to the success or failure of the project.
[0003] For the traditional primary support selection and on-site construction, the current engineering practice generally uses steel arch frame or grid arch frame combined with on-site shotcrete construction. After years of engineering practice demonstration, the following problems are found:
[0004] (1) Steel arch frame + shotcrete, which uses a large amount of steel, has a high overall cost and a relatively poor cost-effectiveness. The shotcrete quality within the width of the steel flange is poor, which fails to meet the design intent and subsequently becomes a water passage, eventually becoming a disease that is difficult to eradicate;
[0005] (2) Grid arch + shotcrete, which cannot be supported in time, the surrounding rock deformation is relatively large, the shotcrete needs to be equally strong, the construction period is long, and the overall construction progress is affected;
[0006] (3) Spraying concrete in a limited space in the tunnel creates a harsh working environment, which has a significant impact on the health of workers and requires high ventilation during the construction process;
[0007] (4) Low degree of standardization, low production efficiency, and poor energy-saving and environmental protection indicators. Utility Model Content
[0008] The purpose of the utility model is to overcome the above-mentioned defects and provide an assembled prefabricated concrete primary support arch frame connection component that is easy to install, timely and rigidly supports the surrounding rock, is energy-saving and environmentally friendly, has high cost performance, strong operability, short construction period, high degree of standardization, and strong applicability. The component improves the standardization of the primary support structure, is more conducive to on-site assembly, has good integrity and stability, improves the construction speed, effectively reduces the deformation of the face and the ground, is more conducive to protecting the safety of the surrounding environment, and ensures the safety of the dark excavation tunnel support.
[0009] In order to achieve the above purpose, the technical contents of the utility model are as follows:
[0010] An assembled precast concrete primary support arch frame connection assembly, comprising a precast concrete primary support arch frame, a node component, a longitudinal distribution reinforcement steel bar joint piece, a locking anchor rod, shotcrete and longitudinal distribution reinforcement;
[0011] The precast concrete primary arch frame comprises primary arch frame stress-bearing main reinforcement, end-sealing steel plates, and embedded longitudinal connecting reinforcements;
[0012] The node components include H-shaped steel, connecting steel plates, bolt holes, and stiffening ribs;
[0013] The longitudinal distribution reinforcement steel bar joint piece is a longitudinal distribution reinforcement joint component, which is arranged in the precast concrete primary support arch frame, and has pre-embedded longitudinal connecting reinforcements arranged in a circumferential direction;
[0014] The joint connection strength shall meet the requirements of relevant specifications and shall not be lower than the longitudinal reinforcement parent material. The reinforcement joint parts shall include all the scopes that meet the engineering requirements;
[0015] The locking foot anchor rod shall include all the scopes that meet the bearing capacity and engineering requirements, and shall be effectively welded with the node components to meet the deformation and force requirements;
[0016] The longitudinal distribution reinforcement and the longitudinal distribution reinforcement joints are effectively connected, which should include all ranges that meet the bearing capacity and conform to the engineering requirements.
[0017] Furthermore, the precast concrete primary support arch frame segment division is carried out according to the design requirements, the arch frame main reinforcement, stirrups and structural reinforcement should be implemented in accordance with the design requirements, the cross-section is rectangular, the transverse width should meet the initial support force requirements and should not be less than 300mm, the longitudinal width is the same as the transverse width, and the longitudinal sides of the tunnel need to be roughened.
[0018] Furthermore, the main force reinforcement of the primary arch frame is arranged along the corner of the cross section, with a diameter of not less than φ22, and the main force reinforcement of the primary arch frame is threaded at both ends of each segment, with a threading length of not less than 50mm, and the total length reserved at the end of the main force reinforcement of the primary arch frame is not less than 70mm after exceeding the outer edge of the end-sealed steel plate, and is welded on the inner side of the end-sealed steel plate;
[0019] The end-sealing steel plate is a rectangular steel plate with the same plane size as the precast concrete arch cross section, and the thickness of the steel plate is not less than 20 mm. It is a precast concrete arch end-sealing member, and is provided with steel bar perforations. The main force-bearing bars of the primary arch are passed through the end-sealing steel plate and welded.
[0020] The embedded longitudinal connecting reinforcement is embedded, with a diameter of not less than φ16, and both ends are mechanically connected to the longitudinal distribution reinforcement joints, and are evenly arranged along the ring with an arrangement spacing of not more than 1000mm.
[0021] Furthermore, the height of the H-beam is the height of the end steel plate minus 2h. f , including 2h f The height of the weld, the flange width is the same as the size of the end steel plate, and the longitudinal length is not less than 200mm; and it can meet the bolt fastening space requirements, and the model selection should meet the node force requirements;
[0022] The connecting steel plate is a rectangular steel plate with the same plane dimensions as the end-sealing steel plate, a steel plate thickness of not less than 20 mm, and is fully welded to the H-shaped steel and stiffening ribs on both sides;
[0023] The bolt holes are arranged on the connecting steel plate, and the number and position thereof correspond to the steel bar perforations of the end-sealed steel plate, and the hole diameter is preferably 4 to 6 mm larger than the diameter of the main reinforcement;
[0024] Stiffening ribs, two pieces are symmetrically arranged on both sides of the H-beam web, are rectangular steel plates with a thickness of not less than 16mm, a height equal to the longitudinal length of the H-beam, and a width of not less than 100mm. They are fully welded to the H-beam web and the connecting steel plate on both sides. The models and sizes of the H-beam, connecting steel plate and stiffening ribs should include all ranges that meet the requirements of the project.
[0025] Furthermore, the H-shaped steel, connecting steel plate and stiffening ribs are connected by welding, the main force-bearing reinforcement of the initial support arch frame and the end-sealing steel plate are connected by welding, and the weld height between the end-sealing steel plate and the connecting steel plate is determined by calculation and is not less than 10 mm in structure.
[0026] Furthermore, when the force is required, a welding connection is added between the end steel plate and the connecting steel plate in the node member.
[0027] Correspondingly, the utility model also provides a method for constructing an assembled prefabricated concrete primary support arch connection assembly:
[0028] Step 1: According to the design requirements, determine the cross-sectional dimensions of the precast concrete primary arch frame, the type of the primary arch frame main reinforcement, the size and thickness of the end steel plate and the size of the holes on the end steel plate, the thread length at both ends of the main reinforcement, the embedded longitudinal connecting reinforcement and the longitudinal distribution reinforcement joints, and the centralized prefabrication production according to the arch frame segments, and the maintenance to meet the design requirements;
[0029] Step 2: According to the requirements of force and stability, determine the size of each node component, weld and process the H-shaped steel, connecting steel plate and stiffening ribs, and reserve bolt holes in the connecting steel plate in advance;
[0030] Step 3: After the tunnel face is excavated and the erection conditions are met, the segments of the precast concrete primary support arch frame are bolted together using node components;
[0031] Step 4: The beams are connected into a whole through the reserved longitudinal distribution reinforcement joints using the longitudinal distribution reinforcement. The whole meets the stress and deformation requirements. The locking anchor rods are set according to the requirements and welded firmly to the node components.
[0032] Step 5: Carry out spraying concrete spraying construction;
[0033] Step 6: Finally, the overall primary support structure is formed, thus completing a cycle and proceeding to the next cycle of construction.
[0034] Furthermore, the size and type of each component can be adjusted according to the specific conditions of the project and the site conditions, and should include all size ranges that meet the requirements of the project.
[0035] In the technical solution of the utility model, the components are installed and connected by welding. The height and quality of the welds during the welding process must meet the requirements of the current relevant specifications, and the welds must meet the bearing capacity and structural requirements. If necessary, the welds must be inspected in accordance with the relevant specifications and can only be implemented after passing the inspection.
[0036] The utility model has the following beneficial technical effects:
[0037] The utility model adopts precast concrete primary support arch frame. Compared with the traditional steel arch frame or grid arch frame, the precast concrete arch frame has the advantages of light weight and simple construction, which can reduce the amount of steel, reduce the overall cost and improve the cost performance. In addition, the flange width of the precast concrete arch frame can be flexibly adjusted according to the design requirements to ensure that the quality of the shotcrete meets the design requirements and avoid subsequent defects.
[0038] This technology uses prefabricated concrete primary support arch connection components to achieve fast and efficient construction. After the prefabricated concrete arch and related connectors are prefabricated in the factory, they are directly transported to the construction site for assembly and installation, without the need for on-site welding, which reduces on-site construction time, shortens the construction period, and avoids the impact of surrounding rock deformation on the strength development of shotcrete.
[0039] Since this technology uses prefabricated concrete primary support arch connection components, the impact of tunnel construction on workers' health can be greatly reduced. The assembly of prefabricated concrete arches can be carried out in a relatively closed and safe factory environment, reducing the long hours of work for workers in harsh environments, while reducing the requirements for ventilation facilities and improving the safety and comfort of the working environment.
[0040] In summary, the assembled precast concrete primary support arch connection component technology effectively solves many technical problems in traditional tunnel construction, including reducing steel consumption, shortening construction period, improving working environment, etc., and has significant technical advantages and economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Figure 1 This is a diagram of the connection assembly of the prefabricated precast concrete primary support arch frame;
[0042] Figure 2 This is the structural drawing of the prefabricated concrete primary support arch connection;
[0043] Figure 3 It is a longitudinal section view of the assembled precast concrete primary support arch frame;
[0044] Figure 4 This is the joint condition diagram of the precast concrete primary support arch;
[0045] Figure 5 It is the side view of the node component;
[0046] Figure 6 This is the front view of the H-beam of the node component;
[0047] Figure 7 This is the front view of the node component connection plate.
[0048] Numbers in the figure:
[0049] 1. Precast concrete primary arch frame; 101. Primary arch frame main reinforcement, 102. End-sealing steel plate, 103. Embedded longitudinal connecting reinforcement; 2. Node member, 201. H-shaped steel, 202. Connecting steel plate, 203. Bolt hole, 204. Stiffening rib; 3. Longitudinal distribution reinforcement joints; 4. Locking anchor rods; 5. Shotcrete; 6. Longitudinal distribution reinforcement. DETAILED DESCRIPTION
[0050] The present invention is further described below in conjunction with specific embodiments. It should be understood that these embodiments are only used to illustrate the present invention and are not used to limit the scope of the present invention. In addition, it should be understood that after reading the content taught by the present invention, those skilled in the art can make various changes or modifications to the present invention, and these equivalent forms also fall within the scope defined by the claims attached to this application.
[0051] Aiming at the shortcomings of the existing initial support arch frame, such as the high rigidity of the steel arch frame, the difficulty of construction and erection, the high cost, the need for the strength of the grid arch frame, the weak initial support effect on the surrounding rock, the large deformation of the surrounding rock, and the long construction period, the utility model proposes a component and construction method that is convenient for on-site installation, has a high degree of standardization, is easy to process in the factory, has a short construction period, is economical, energy-saving and environmentally friendly, effectively controls deformation, and has strong applicability. The utility model can be used in the initial support structure of subways, railways, municipal administration, and underground space dark excavation tunnels, and has good applicability.
[0052] The assembled precast concrete primary support arch frame connection assembly used in this embodiment includes component 1 (precast concrete primary support arch frame), component 2 (node component), component 3 (longitudinal distribution reinforcement steel bar joint), component 4 (locking anchor rod), component 5 (sprayed concrete) and component 6 (longitudinal distribution reinforcement).
[0053] Step 1: According to the design requirements, determine the cross-sectional dimensions of component 1 (precast concrete primary arch frame), the model of the primary arch frame force-bearing main reinforcement 101, the size and thickness of the end steel plate 102 and the size of the holes on the end steel plate, the threading length at both ends of the main reinforcement, the embedded longitudinal connecting reinforcement 103 and component 3 (longitudinal distribution reinforcement steel bar joint), and divide the prefabrication production into arch frame segments, and maintain them to meet the design requirements;
[0054] Step 2: According to the requirements of force and stability, the dimensions of each component of component 2 (node component) are determined, the H-shaped steel 201, the connecting steel plate 202 and the stiffening rib 204 are welded and processed, and the bolt holes 203 are reserved in the connecting steel plate 202 in advance;
[0055] Step 3: After the tunnel face is excavated and the erection conditions are met, the segments of component 1 (precast concrete primary support arch frame) are bolted together using component 2 (node component);
[0056] Step 4: The beams are connected into a whole through the reserved component 3 (longitudinal distribution reinforcement joint) and the component 6 (longitudinal distribution reinforcement). The whole meets the requirements of force and deformation. The component 4 (locking foot anchor rod) is set according to the requirements and welded firmly with the component 2 (node component);
[0057] Step 5: Carry out spraying construction of component 5 (sprayed concrete);
[0058] Step 6: Finally, the overall primary support structure is formed, thus completing a cycle and proceeding to the next cycle of construction.
[0059] The components in component 1 and component 2 are not limited to those shown in the figure and can be adjusted according to the specific conditions of the project and on-site installation conditions. The adjustment principle is to facilitate on-site installation, reasonable force, meet the bearing capacity and stability requirements, and should include all size ranges that meet the project requirements.
[0060] The above contents are further detailed descriptions of the present invention in combination with specific preferred implementations, and it cannot be determined that the specific implementation of the present invention is limited to the above descriptions. For ordinary technicians in the technical field to which the present invention belongs, several simple deductions or substitutions can be made without departing from the concept of the present invention, which should be regarded as falling within the protection scope of the present invention.
Claims
1. An assembled prefabricated concrete primary support arch connection assembly, Features: It comprises a precast concrete primary support arch frame (1), a node component (2), a longitudinal distribution reinforcement steel bar joint (3), a locking anchor rod (4), shotcrete (5) and longitudinal distribution reinforcement (6); The precast concrete primary support arch frame (1) comprises primary support arch frame stress-bearing main reinforcement (101), end-sealing steel plates (102), and embedded longitudinal connecting reinforcements (103); The node component (2) comprises an H-shaped steel (201), a connecting steel plate (202), bolt holes (203), and a stiffening rib (204); The longitudinal distribution reinforcement steel bar joint piece (3) is a longitudinal distribution reinforcement joint component, which is arranged in the precast concrete primary support arch frame (1) and has pre-buried longitudinal connection reinforcements (103) arranged in a circumferential direction; The locking foot anchor rod (4) is effectively welded to the node member (2) to meet deformation and force requirements; The longitudinal distribution ribs (6) are connected to the longitudinal distribution rib steel bar connector (3).
2. The assembled precast concrete primary support arch connection assembly according to claim 1, Features: The precast concrete primary support arch frame (1) is divided into segments according to the design requirements. The main reinforcement, stirrups and structural reinforcement of the arch frame should be implemented according to the design requirements. The cross section is rectangular. The transverse width should meet the primary support force requirements and should not be less than 300mm. The longitudinal width is the same as the transverse width. The longitudinal sides of the tunnel need to be roughened.
3. The assembled precast concrete primary support arch connection assembly according to claim 2, Features: The primary arch frame stress-bearing main reinforcement (101) is arranged along the cross-section corner, with a diameter of not less than φ22, and the primary arch frame stress-bearing main reinforcement (101) is threaded at both ends of each segment, with a threading length of not less than 50 mm, and the total length reserved at the end of the primary arch frame stress-bearing main reinforcement (101) is not less than 70 mm after exceeding the outer edge of the end-sealing steel plate (102), and is welded and connected on the inner side of the end-sealing steel plate (102); The end-sealing steel plate (102) is a rectangular steel plate, the plane size of which is the same as the cross section of the precast concrete arch frame, the thickness of which is not less than 20 mm, and is a precast concrete arch frame end-sealing member, on which steel bar holes are arranged, and the primary arch frame stress-bearing main reinforcement (101) is passed through the end-sealing steel plate (102) and welded; The embedded longitudinal connecting ribs (103) are embedded, have a diameter of not less than φ16, are mechanically connected to the longitudinal distribution rib steel bar joints (3) at both ends, are evenly arranged along a ring shape, and have an arrangement spacing of not more than 1000 mm.
4. The assembled precast concrete primary support arch connection assembly according to claim 1, Features: The height of the H-shaped steel (201) is equal to the height of the end-sealing steel plate (102) minus 2h. f , including 2h f is the height of the weld, the flange width is the same as the size of the end steel plate (102), and the longitudinal length is not less than 200 mm; The connecting steel plate (202) is a rectangular steel plate with the same planar dimensions as the end-sealing steel plate (102), a thickness of not less than 20 mm, and is fully welded to the H-shaped steel (201) and the stiffening rib (204) on both sides; The bolt holes (203) are arranged on the connecting steel plate (202), and the number and position thereof are arranged correspondingly to the steel bar holes of the end-sealing steel plate (102), and the hole diameter is preferably 4 to 6 mm larger than the diameter of the main reinforcement (101); The stiffening ribs (204) are two pieces symmetrically arranged on both sides of the web of the H-shaped steel (201), and are rectangular steel plates with a thickness of not less than 16 mm, a height equal to the longitudinal length of the H-shaped steel (201), and a width of not less than 100 mm. The stiffening ribs (204) are fully welded to the web of the H-shaped steel (201) and the connecting steel plate (202) on both sides.
5. The assembled precast concrete primary support arch connection assembly according to claim 1, Features: The H-shaped steel (201), the connecting steel plate (202) and the stiffening rib (204) are connected by welding, and the primary arch frame stress-bearing main reinforcement (101) and the end-sealing steel plate (102) are connected by welding. The height of the weld between the end-sealing steel plate (102) and the connecting steel plate (202) is determined by calculation and is not less than 10 mm in structure.
6. The assembled precast concrete primary support arch connection assembly according to claim 1, Features: When the force is required, a welding connection is added between the end-sealing steel plate (102) and the connecting steel plate (202) in the node member (2).