BIM (Building Information Modeling) system trunking fixing device

By using the design of mounting seat, support plate, slider and connecting screw in the BIM wire trough fixing device, the time-consuming and labor-intensive position adjustment of the BIM wire trough is solved, and the flexible position adjustment and accurate verticality of the wire trough shell are achieved Installation improves installation accuracy and use efficiency.

CN222169198UActive Publication Date: 2024-12-13SHANXI INSTALLATION GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420131332.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-19
Publication Date
2024-12-13
Estimated Expiration
2034-01-19

AI Technical Summary

Technical Problem

When the existing BIM wire trough is installed vertically, the wire trough shell is fixed by multiple bolts, which requires disassembly and adjustment when the position is installed, which is time-consuming and laborious.

Method used

Design a BIM system wire trough fixing device, including mounting base, support plate, moving groove, slider and connecting screw. Through sliding and threaded connection of slider and connecting plate, the left and vertical position adjustment of the wire trough shell is realized, and The limit block and fastening bolts are precisely fixed.

Benefits of technology

It realizes flexible position adjustment of the wire trench shell, avoids tilt after installation, improves installation accuracy, reduces errors, saves time and effort, and has a wide range of applications.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222169198U_ABST
    Figure CN222169198U_ABST
Patent Text Reader

Abstract

The utility model discloses a BIM system trunking fixing device in the technical field of BIM trunking installation, which comprises an installation seat, supporting plates are fixedly installed on the front side and the rear side between the left inner wall and the right inner wall of the installation seat, moving grooves are formed in inner cavities of the two supporting plates, and moving mechanisms are arranged in the two moving grooves. After a worker places the trunking shell on the mounting base, the sliding block and the connecting plate are fixed and limited through the connecting screw rod, at the moment, the worker can move the trunking shell left and right to adjust the mounting position of the trunking shell, and the position of the trunking shell can be adjusted through the connecting plate and the sliding block before mounting; the installation position of the wire duct shell can be flexibly changed, the application range is wide, time and labor are saved, the equipment does not need to be disassembled after wrong installation, and the practicability is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of BIM wire duct installation, in particular to a BIM system wire duct fixing device. Background Art

[0002] The BIM system for electromechanical pipelines relies on computer-aided drafting to simulate the pipeline layout of electromechanical installation projects after construction, that is, to "pre-assemble" drawings on the computer according to the construction drawings before construction. After "pre-assembly", in-depth designers can intuitively find problems on the design drawings, which is to find the location conflicts and elevation overlaps of equipment pipelines between different disciplines, and make adjustments and modifications to ensure that the construction can be executed.

[0003] The existing patent publication number is CN213212963U, which discloses a BIM system cable duct fixing device for electromechanical pipes, including a support frame, a sliding groove and a second mounting frame, a fixing plate is provided on one side of the support frame, a first fixing screw hole is provided on the surface of the fixing plate, a mounting hole is provided on the surface of the first mounting plate, a first screw is connected inside the first mounting frame, a first fixing piece is connected to one end of the first screw, a second fixing screw hole is provided on the surface of the first fixing piece, the second mounting frame is provided on the side of the support frame, a second mounting plate is provided at the bottom of the second mounting frame, a second screw is connected inside the second mounting frame, and a second fixing piece is connected to one end of the second screw. The sliding groove of the BIM system cable duct fixing device for electromechanical pipes is provided inside the groove of the support frame, the first screw runs through the support frames on both sides of the equipment, and the first fixing pieces are connected to both sides of the first screw. The distance between the support frames can be conveniently adjusted by rotating the first screw.

[0004] When the existing BIM cable duct is installed vertically, the cable duct shell is fixed by multiple bolts. When there is a difference in the installation position, the bolts need to be removed and the installation position of the cable duct needs to be adjusted, which is time-consuming and laborious. To this end, we propose a BIM system cable duct fixing device to solve the above-mentioned problems. Utility Model Content

[0005] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the abstract of the specification and the name of the utility model to avoid blurring the purpose of this section, the abstract of the specification and the name of the utility model, and such simplifications or omissions cannot be used to limit the scope of the utility model.

[0006] Therefore, the purpose of the utility model is to provide a BIM system cable duct fixing device, which can solve the problem that when the existing BIM cable duct is installed vertically, the cable duct shell is fixed by multiple bolts. When there is a difference in the installation position, the bolts need to be removed and the installation position of the cable duct needs to be adjusted, which is time-consuming and labor-intensive.

[0007] In order to solve the above technical problems, the utility model provides a BIM system cable duct fixing device, which adopts the following technical solution: comprising a mounting seat, support plates are fixedly installed on both the front and rear sides between the inner walls on the left and right sides of the mounting seat, and the inner cavities of the two support plates are each provided with a moving groove, and the insides of the two moving grooves are each provided with a moving mechanism;

[0008] The moving mechanism includes two sliders, both of which are embedded in the moving grooves at corresponding positions, and both of the sliders are slidably set in the moving grooves at corresponding positions. The surfaces of the two sliders are threadedly connected with connecting screws, and the bottoms of the two connecting screws are threadedly connected with first fastening bolts, and the upper surfaces of the two first fastening bolts are both in contact with the bottom of the support plate.

[0009] Optionally, a wire trough shell is provided on the top of the mounting seat, and connecting plates are fixedly installed on the left and right sides of the wire trough shell. The two connecting plates are horizontally placed on the upper surfaces of the front and rear support plates in a front-to-back manner. The connecting screws all penetrate the surfaces of the connecting plates at corresponding positions, and the connecting screws are movably connected to the connecting plate threads at corresponding positions.

[0010] By adopting the above technical solution, this solution places the wire trough shell on the mounting seat, and then passes four connecting screws through the connecting plates at corresponding positions to fix the wire trough shell. At this time, the wire trough shell can be moved left and right on the two support plates to adjust the installation position.

[0011] Optionally, a connecting shell is fixedly installed on the outside of the wire trough shell, and limit plates are fixedly installed on both left and right sides of the connecting shell.

[0012] By adopting the above technical solution, the present solution has a connecting shell fixedly installed on the outside of the wire trough shell, and both left and right sides of the connecting shell are provided with limiting plates, which can be used for vertical limitation of the wire trough shell.

[0013] Optionally, limiting blocks are fixedly installed on the front and rear sides of the two limiting plates, and each of the limiting blocks is located directly above the sliding block at the corresponding position.

[0014] By adopting the above technical solution, this solution provides limit blocks on both the front and rear sides of the limit plate, and each limit block is located directly above the slider at the corresponding position. Therefore, by installing the limit block directly above the slider, the vertical position of the wire trough shell can be accurately installed.

[0015] Optionally, each of the connecting screws passes through the surface of the limiting block at the corresponding position, and each of the connecting screws is movably connected to the limiting block thread at the corresponding position.

[0016] By adopting the above technical solution, the solution adjusts the vertical position of the wire trough shell by connecting the limit block and the slider through threaded movably connecting them one by one through the connecting screw.

[0017] Optionally, the top end of each connecting screw rod is threadedly movably connected to a second fastening bolt, and the lower surface of each second fastening bolt is fitted on the top of a limiting block at a corresponding position.

[0018] By adopting the above technical solution, the second fastening bolt is movably connected to the top thread of the connecting screw, so that after the slider and the limit block are installed on the connecting screw, the second fastening bolt is used to reinforce the position of the connecting screw.

[0019] In summary, the utility model includes at least one of the following beneficial effects: 1. By setting up a moving mechanism, after the staff places the wire trough shell on the mounting seat, they use the connecting screws to fix the slider and the connecting plate. At this time, the staff can move the wire trough shell left and right to adjust the installation position of the wire trough shell, so that the connecting plate and the slider can be used to adjust the position of the wire trough shell before installation, and the installation position of the wire trough shell can be flexibly changed. It has a wide range of applications, saves time and effort, and does not need to disassemble the equipment after installation errors. It is highly practical.

[0020] 2. By arranging limit blocks on both sides of the front and rear of the limit plate, each limit block is located directly above the slider at the corresponding position. By installing the limit block directly above the slider, the vertical position of the wire trough shell can be accurately installed. After the limit block and the slider are threadedly connected one by one by connecting the screw, the vertical position of the wire trough shell can be adjusted, so that the vertical position of the entire wire trough shell can be adjusted, so that the wire trough shell can be accurately installed on the vertical line, avoiding the wire trough shell from tilting after installation, resulting in the inability to splice the wire ends, improving the installation accuracy of the BIM wire trough, and reducing installation errors. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0022] Figure 1 It is a schematic top view of part of the structure of the utility model;

[0023] Figure 2 For the utility model Figure 1 The enlarged structural diagram at A in the middle;

[0024] Figure 3 It is a schematic diagram of the bottom of the overall structure of the utility model;

[0025] Figure 4 It is a schematic diagram of the front side of the overall structure of the utility model.

[0026] Explanation of the accompanying drawings: 1. Mounting seat; 2. Support plate; 3. Moving groove; 4. Slider; 5. Connecting screw; 6. First fastening bolt; 7. Wire trough shell; 8. Connecting plate; 9. Connecting shell; 10. Limiting plate; 11. Limiting block; 12. Second fastening bolt. DETAILED DESCRIPTION

[0027] The following is combined with Figure 1-4 The utility model is described in further detail.

[0028] Embodiment 1, refer to Figure 1-3 In this embodiment, in order to solve the problem that when the existing BIM wire trough is installed vertically, the wire trough shell is fixed by multiple bolts, and when there is a difference in the installation position, the bolts need to be removed and the installation position of the wire trough needs to be adjusted, which is time-consuming and laborious, the utility model discloses a BIM system wire trough fixing device,

[0029] It comprises a mounting seat 1, support plates 2 are fixedly mounted on both the front and rear sides between the inner walls on the left and right sides of the mounting seat 1, and the inner cavities of the two support plates 2 are each provided with a moving groove 3, and the two moving grooves 3 are each provided with a moving mechanism;

[0030] The moving mechanism includes two sliders 4, both of which are embedded in the moving grooves 3 at corresponding positions, and both of which are slidably set in the moving grooves 3 at corresponding positions. The surfaces of the two sliders 4 are threadedly connected with connecting screws 5, and the bottoms of the two connecting screws 5 are threadedly connected with first fastening bolts 6, and the upper surfaces of the two first fastening bolts 6 are both in contact with the bottom of the support plate 2.

[0031] A wire slot shell 7 is provided on the top of the mounting base 1, and connecting plates 8 are fixedly installed on the left and right sides of the wire slot shell 7. The two connecting plates 8 are horizontally placed on the upper surfaces of the front and rear support plates 2 in a front-to-back manner. The connecting screws 5 all penetrate the surfaces of the connecting plates 8 at corresponding positions, and the connecting screws 5 are threadedly movably connected to the connecting plates 8 at corresponding positions.

[0032] The specific working principle is: after the staff places the wire trough shell 7 on the mounting seat 1, they then use the connecting screw 5 to fix the slider 4 and the connecting plate 8, and the slider 4 can slide in the movable groove 3 inside the support plate 2, so that the staff can move the wire trough shell 7 left and right to adjust the installation position, and then threadably connect the first fastening bolt 6 from under the connecting screw 5, so as to tighten the first fastening bolt 6 against the bottom of the support plate 2, thereby limiting the position of the wire trough shell 7 at this time.

[0033] Example 2, refer to Figure 1-4 In order to solve the problem that the existing BIM wire duct is offset and not on the vertical line when installed vertically, based on the same concept as the above-mentioned embodiment 1, the BIM system wire duct fixing device also includes:

[0034] A connection shell 9 is fixedly installed on the outside of the wire trough shell 7, and limit plates 10 are fixedly installed on both the left and right sides of the connection shell 9.

[0035] Limiting blocks 11 are fixedly mounted on both the front and rear sides of the two limiting plates 10 , and each limiting block 11 is located just above the sliding block 4 at the corresponding position.

[0036] Each connecting screw rod 5 penetrates through the surface of the limiting block 11 at the corresponding position, and each connecting screw rod 5 is threadably connected to the limiting block 11 at the corresponding position.

[0037] The top end of each connecting screw rod 5 is movably connected with a second fastening bolt 12 through a thread, and the lower surface of each second fastening bolt 12 is fitted on the top of the limiting block 11 at the corresponding position.

[0038] The specific working principle is: by arranging limit blocks 11 on both sides of the front and rear of the limit plate 10, each limit block 11 is located directly above the slider 4 at the corresponding position, so that the limit block 11 is installed directly above the slider 4 to accurately install the vertical position of the wire trough shell 7, and after the limit block 11 and the slider 4 are threadedly connected one by one through the connecting screw 5, the vertical position of the wire trough shell 7 is adjusted, and finally the second fastening bolt 12 is threadedly connected to the top of the connecting screw 5, so as to reinforce the connecting screw 5.

[0039] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.

Claims

1. A BIM system cable duct fixing device, comprising a mounting seat (1), characterized in that: Support plates (2) are fixedly mounted on both the front and rear sides of the mounting seat (1) between the inner walls on the left and right sides, and the inner cavities of the two support plates (2) are each provided with a movable groove (3), and the interiors of the two movable grooves (3) are each provided with a movable mechanism; The moving mechanism comprises two sliders (4), the two sliders (4) are both embedded in the moving grooves (3) at corresponding positions, and the two sliders (4) are both slidably arranged in the moving grooves (3) at corresponding positions, the surfaces of the two sliders (4) are both threadedly movably connected to connecting screws (5), the bottoms of the two connecting screws (5) are both threadedly movably connected to first fastening bolts (6), and the upper surfaces of the two first fastening bolts (6) are both in contact with the bottom of the support plate (2).

2. A BIM system cable duct fixing device according to claim 1, characterized in that: A wire slot shell (7) is provided on the top of the mounting seat (1), and connecting plates (8) are fixedly installed on the left and right sides of the wire slot shell (7), and the two connecting plates (8) are horizontally placed on the upper surfaces of the two front and rear support plates (2) in a front-to-back manner, and the connecting screws (5) all penetrate the surfaces of the connecting plates (8) at corresponding positions, and the connecting screws (5) are movably connected to the connecting plates (8) at corresponding positions by threads.

3. A BIM system cable duct fixing device according to claim 2, characterized in that: A connection shell (9) is fixedly mounted on the outside of the wire trough shell (7), and limit plates (10) are fixedly mounted on both left and right sides of the connection shell (9).

4. A BIM system cable duct fixing device according to claim 3, characterized in that: Limit blocks (11) are fixedly mounted on both the front and rear sides of the two limit plates (10), and each limit block (11) is located directly above the slider (4) at a corresponding position.

5. The BIM system cable duct fixing device according to claim 1, characterized in that: Each of the connecting screw rods (5) penetrates the surface of the limiting block (11) at the corresponding position, and each of the connecting screw rods (5) is movably connected to the limiting block (11) at the corresponding position by thread.

6. A BIM system cable duct fixing device according to claim 1, characterized in that: The top end of each connecting screw rod (5) is movably connected to a second fastening bolt (12) through a thread, and the bottom surface of each second fastening bolt (12) is fitted onto the top of a limiting block (11) at a corresponding position.