Sludge water treatment facility

By centrally arranging the pool body and setting up partition holes in the tap water sludge and water treatment facilities, the problem of silt and sand blockage is solved, the maintenance cost and floor area are reduced, and the treatment efficiency is improved.

CN222342057UActive Publication Date: 2025-01-14CHONGQING WATER GROUP PUBLIC ENGINEERING CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420654491.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-01
Publication Date
2025-01-14
Estimated Expiration
2034-04-01

AI Technical Summary

Technical Problem

In tap water sludge and water treatment facilities, the problem of silt and sand blocking pipelines leads to high maintenance costs, increased management difficulties, and a large area of ​​land.

Method used

The water inlet distribution area, concentration tank, sedimentation tank, outlet area, balance tank and sludge pump room are arranged centrally, and the water and sludge holes and sludge holes are installed through the partition wall to shorten the conveying distance between the pools, reduce pipeline connections, and reduce Risk of blockage.

Benefits of technology

It effectively reduces blockage, reduces maintenance costs, reduces floor area, and improves processing efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222342057U_ABST
    Figure CN222342057U_ABST
Patent Text Reader

Abstract

The utility model discloses a sludge water treatment facility, and belongs to the technical field of tap water production. The system comprises water inlet distribution areas, concentration tanks, sedimentation tanks, a water outlet area, balance tanks and a sludge pump room, the water inlet distribution areas and the concentration tanks are sequentially arranged in two rows and symmetrically arranged on the left side and the right side of the sludge pump room, the balance tanks and sludge discharge grooves are sequentially arranged in the left row and the right row behind the sludge pump room, and the rear portions of the two concentration tanks are connected with the sedimentation tanks respectively. The rear parts of the two sedimentation tanks are jointly connected into a water outlet area, adjacent tank bodies are separated by a partition wall, and the partition wall is provided with an orifice for water flow or sludge flow to pass through. The utility model has the technical effects that the conveying distance of muddy water treatment between the tank bodies is shortened, the blockage is reduced, the maintenance and repair cost is reduced, and the occupied area is also reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of tap water production, and in particular relates to a muddy water treatment facility in the process of tap water production. Background Art

[0002] During the tap water production process, the sediment separated and deposited in the sedimentation tank gathers at the bottom of the sedimentation tank. To ensure the water quality of the sedimentation tank, the bottom sediment needs to be regularly cleaned and discharged. Since the discharged mud water pollutes the environment to a certain extent and wastes some water resources, in order to achieve energy conservation and emission reduction and protect the environment, the discharged mud water needs to be treated.

[0003] At present, the tap water sludge water treatment usually adopts the method of building sludge pool, concentration pool, balance pool and pump room separately, and the pools are connected by pipes. However, according to the running tap water sludge water treatment facilities, it is found that tap water sludge water is mainly inorganic and has a large sand content. During the transportation between the process units, the sludge often blocks the pipes, which greatly increases the maintenance workload, increases the operating cost, and increases the difficulty of management. Utility Model Content

[0004] In view of the problems existing in the prior art, the technical problem to be solved by the utility model is to provide a mud water treatment facility, which can shorten the transportation distance of mud water treatment between pools, reduce blockage, reduce maintenance and repair costs, and reduce floor space.

[0005] The technical problem to be solved by the utility model is achieved through such a technical scheme, which includes a water inlet distribution area, a concentration tank, a sedimentation tank, a water outlet area, a balancing tank and a sludge pump room. The water inlet distribution area and the concentration tank are arranged in two rows in sequence and symmetrically on the left and right sides of the sludge pump room. Behind the sludge pump room, there are also balancing tanks and mud discharge troughs arranged in two rows in sequence. The rear parts of the two concentration tanks are respectively connected to a sedimentation tank, and the rear parts of the two sedimentation tanks are connected to the water outlet area together. The adjacent tank bodies are separated by a partition wall, and the partition wall has an opening for water flow or mud flow to pass through.

[0006] The technical effects of the utility model are:

[0007] The water inlet distribution area, concentration tank, sedimentation tank, water outlet area, balance tank, and sludge pump room are centrally arranged to shorten the transportation distance of mud and water treatment between tanks, effectively reduce the occurrence of blockage, and reduce maintenance and repair costs. Water holes or mud holes are set between each partition wall according to the direction of water flow and mud flow, where the water holes are arranged on the upper part of the partition wall and the mud holes are arranged on the bottom of the partition wall. This arrangement greatly reduces the sludge pipes and sewage pipes between multiple tanks and reduces the floor space. BRIEF DESCRIPTION OF THE DRAWINGS

[0008] The accompanying drawings of the present utility model are as follows:

[0009] Figure 1 It is the plan layout of the utility model;

[0010] In the figure, 1. Sludge discharge pipe of the water plant sedimentation tank; 2. Water inlet distribution area; 3. Concentrator; 4. Sedimentation tank; 5. Outlet area; 6. Return water pipe; 7. Overflow drain pipe; 8. Balance tank; 9. Sludge pump room; 10. Sludge pump output pipe; 11. Concentrator truss; 12. Sludge discharge trough. DETAILED DESCRIPTION

[0011] The utility model is further described below in conjunction with the accompanying drawings and embodiments:

[0012] In order to clearly describe the content of the utility model, this patent application uses the directional words "front", "rear", "left", and "right" for distinction. The "front", "rear", "left", and "right" are determined based on the layout of the above drawings. When the actual use direction of the utility model changes, the directional designation changes accordingly, which cannot be regarded as a limitation on the scope of patent protection. The "front" refers to the muddy water inflow end, and the "rear" refers to the treated water outflow end.

[0013] like Figure 1 As shown, the utility model includes a water inlet distribution area 2, a concentration tank 3, a sedimentation tank 4, a water outlet area 5, a balancing tank 8 and a sludge pump room 9. The water inlet distribution area 2 and the concentration tank 3 are arranged in two rows in sequence and symmetrically arranged on the left and right sides of the sludge pump room 9. Behind the sludge pump room 9, there are also balancing tanks 8 (the balancing tank 8 is used to balance the mud concentration) and a mud discharge trough 12 arranged in two rows in sequence. The rear parts of the two concentration tanks 3 are respectively connected to the sedimentation tank 4, and the rear parts of the two sedimentation tanks 4 are connected to the water outlet area 5 together. The adjacent tank bodies are separated by a partition wall, and the partition wall has an opening for water flow or mud flow to pass through.

[0014] The mud discharge pipe 1 of the water plant sedimentation tank is connected to two water inlet distribution areas 2. The mud and water in the water inlet distribution area 2 enter the concentration tank 3 through the opening of the partition wall. The water holes on the upper part of the partition wall of the concentration tank 3 are connected to the sedimentation tank 4, and the water holes on the upper part of the partition wall of the sedimentation tank 4 are connected to the water outlet area 5; the water outlet area 5 is connected to the return water pipe 6 and the overflow drainage pipe 7; a mud scraper is arranged in the sedimentation tank 4, and the partition wall at the bottom of the sedimentation tank 4 is connected to the lower part of the concentration tank 3 through a mud hole, and the bottom of the sedimentation tank 4 is connected to the mud discharge trough 12 near the central area, and the partition wall between the mud discharge trough 12 and the concentration tank 3 is connected through a mud hole; the bottom partition wall between the concentration tank 3 and the balancing tank 8 is connected through a mud hole; the bottom partition wall between the left and right balancing tanks 8 and the sludge pump room 9 is connected through a mud hole, and the sludge pump room 9 is equipped with a sludge pump output pipe 10 for sending sludge to the dewatering machine.

[0015] exist Figure 1 In the concentrator tank 3, a concentrator truss 11 is installed.

[0016] The operation process of the utility model is:

[0017] The sludge water pipe 1 of the water plant sedimentation tank inputs the sludge water to the water inlet distribution area 2, and then enters the sedimentation tank 4 through the concentration tank 3. The concentration tank 3 is divided into two parts: the sedimented sludge with higher density is concentrated at the bottom of the tank, and the newly entered sludge water with lower density is in the upper part of the tank. The sludge water in the upper part of the concentration tank flows into the sedimentation tank 4 along the water hole on the upper part of the partition wall. The sedimentation tank 4 is equipped with a sludge scraper. The sludge water here is fully precipitated, and the relatively clear supernatant flows into the water outlet area 5. After mixing with the raw water through the return water pipe 6, it is reused again to save water resources. The sludge scraper at the bottom of the sedimentation tank 4 scrapes and flows back through the sludge hole into the concentration tank 3. After concentration, it enters the balance tank 8, and finally passes through the sludge pump room 9 and is pumped out to the desludge machine. When the sludge water treatment facility is abnormal, the sludge water can be urgently discharged to the municipal sewage network through the overflow drain pipe 7 to avoid slurry overflow in the sludge water treatment facility and endanger the safety of related electromechanical equipment.

[0018] The utility model has a centralized arrangement of the water inlet distribution area 2, the concentration tank 3, the sedimentation tank 4, the water outlet area 5, the balancing tank 8, and the sludge pump room 9, which shortens the transportation distance of the sludge and water treatment between the tank bodies, effectively reduces the occurrence of blockage, and reduces the maintenance and repair costs. Water holes or mud holes are respectively set between the partition walls according to the water flow direction and the mud flow direction, wherein the water holes are arranged on the upper part of the partition wall, and the mud holes are arranged on the bottom of the partition wall. This arrangement greatly reduces the sludge and sewage pipes between multiple tank bodies and reduces the floor space.

Claims

1. A sludge water treatment facility, comprising an inlet distribution area (2), a concentration tank (3), a sedimentation tank (4), an outlet area (5), a balancing tank (8) and a sludge pump room (9), characterized in that: The water inlet distribution area (2) and the thickening tank (3) are arranged in two rows in sequence and symmetrically on the left and right sides of the sludge pump room (9). Behind the sludge pump room (9), there are also a balancing tank (8) and a sludge discharge trough (12) arranged in two rows in sequence. The rear of the two thickening tanks (3) is connected to a sedimentation tank (4). The rear of the two sedimentation tanks (4) is connected to the water outlet area (5). The adjacent tanks are separated by a partition wall, and the partition wall has an opening for water flow or mud flow to pass through.

2. The sludge water treatment facility according to claim 1 is characterized in that: The mud water pipe (1) of the sedimentation tank of the water plant is connected to two water inlet distribution areas (2). The mud water in the water inlet distribution area (2) enters the concentration tank (3) through the hole of the partition wall. The water hole on the upper part of the partition wall of the concentration tank (3) is connected to the sedimentation tank (4). The water hole on the upper part of the partition wall of the sedimentation tank (4) is connected to the water outlet area (5). The water outlet area (5) is connected to a return water pipe (6) and an overflow drainage pipe (7). A mud scraper is arranged in the sedimentation tank (4). The partition wall at the bottom of the sedimentation tank (4) is connected to the lower part of the concentration tank (3). The bottom of the sedimentation tank (4) is connected to a mud trough (12) near the center area. The partition wall at the bottom of the sedimentation tank (4) is connected to the mud hole. The partition wall at the bottom of the concentration tank (3) is connected to the mud hole. The partition wall at the bottom of the concentration tank (3) is connected to the mud hole. The partition wall at the bottom of the balance tank (8) is connected to the mud pump room (9). The mud pump room (9) is equipped with a mud pump output pipe (10).