Landscape trestle steel pipe pile

By setting up anchor components and driving components on steel pipe piles, combining protection components and waterproof rubber rings, the effect of improving the stability of steel pipe piles and shortening construction time in urban rivers is achieved, and the long construction time of traditional steel pipe piles is solved. Issues with great environmental impact.

CN222349663UActive Publication Date: 2025-01-14JIANGSU NATURAL ENVIRONMENT CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421218106.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-30
Publication Date
2025-01-14
Estimated Expiration
2034-05-30

AI Technical Summary

Technical Problem

When constructing landscape trests in urban rivers, due to the soft soil quality and poor foundation of the riverbed, traditional steel pipe piles require long steel pipe piles and deep insertion, resulting in long construction time, high noise, and great impact on the environment, which needs to be improved The stability and construction efficiency of steel pipe piles.

Method used

The anchor assembly and drive assembly are arranged on the steel pipe pile body. By protecting the assembly, the anchor assembly is restricted by static insertion and punching with the reaction frame and the gravity-driven anchor assembly of the steel cage and the driving assembly of the drive assembly breaks through the limitations and improves the steel. Stability of pipe piles and the use of multiple segmented anchoring and waterproof rubber rings simplifies operation and reduces environmental impact.

Benefits of technology

The stability of the landscape trest pile foundation is improved without increasing the depth of steel pipe piles, shortening construction time, reducing environmental impact, simple operation and low cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222349663U_ABST
    Figure CN222349663U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of landscape trestle construction, in particular to a landscape trestle steel pipe pile, and aims to solve the problem that in the prior art, the stability of a landscape trestle pile foundation is improved by increasing the length of a steel pipe pile, the landscape trestle steel pipe pile comprises a steel pipe pile body and a reinforcement cage arranged in the steel pipe pile body, and an anchoring assembly is arranged on the steel pipe pile body; the anchoring assembly can be inserted into a riverbed and used for fixing the steel pipe pile body. The anchoring assembly is movably arranged on the steel pipe pile body, a driving assembly is arranged on the reinforcement cage, and the driving assembly can be matched with the anchoring assembly to drive the anchoring assembly to move; a protection assembly is installed on the peripheral wall of the outer side of the steel pipe pile body and used for limiting movement of the anchoring assembly. The method has the effect of improving the stability of the steel pipe pile under the condition that the length of the steel pipe pile is not increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of landscape trestle construction, and in particular to a landscape trestle steel pipe pile. Background Art

[0002] Landscape trestle bridges are mostly set up inside scenic spots and parks to facilitate tourists to view the scenery and cross the river. This plan requires the construction of landscape trestle bridges on both sides of the urban river. The existing residential buildings along the river are densely distributed, and the impact of construction on the surrounding environment needs to be considered.

[0003] The construction of the landscape trestle includes driving steel pipe piles on the riverbed, setting steel cages inside the steel pipe piles, pouring cement into the steel pipe piles, and then laying the bridge deck and installing the bridge deck system. Since the riverbed soil of the urban river is relatively soft and the foundation is relatively poor, the traditional steel pipe pile construction requires the use of longer steel pipe piles and driving them very deep to provide a sufficiently stable pile foundation. The construction time is long, the noise is very loud, and the impact on the environment is relatively large, so it needs to be improved. Utility Model Content

[0004] In order to improve the stability of steel pipe piles without increasing the length of the steel pipe piles, the present application provides a landscape trestle steel pipe pile.

[0005] The present application provides a landscape trestle steel pipe pile adopts the following technical solution:

[0006] A landscape trestle steel pipe pile comprises a steel pipe pile body and a steel cage arranged in the steel pipe pile body, the steel pipe pile body is provided with an anchoring assembly, the anchoring assembly can be inserted in a riverbed to fix the steel pipe pile body; the anchoring assembly is movably arranged on the steel pipe pile body, the steel cage is provided with a driving assembly, the driving assembly can cooperate with the anchoring assembly to drive the anchoring assembly to move; a protection assembly is installed on the outer peripheral wall of the steel pipe pile body, the protection assembly is used to limit the movement of the anchoring assembly.

[0007] By adopting the above technical solution, the construction workers install the protection component on the steel pipe pile body, and then use the reaction frame to statically drive the steel pipe pile until the designed depth is reached. During the driving process of the steel pipe pile, the protection component restricts the anchoring component to be in a retracted state. The construction workers control the steel cage to align the driving component with the top of the steel pipe pile body, lower the steel cage, and the steel cage drives the driving component to move vertically downward. Until the driving component contacts the anchoring component, the gravity of the steel cage and the driving component drives the anchoring component to break through the restriction of the protection component, extend out of the steel pipe pile body and be inserted into the riverbed, thereby improving the stability of the steel pipe pile; compared with the prior art, the present application does not need to increase the driving depth of the steel pipe pile to improve the stability of the pile foundation of the landscape trestle; the construction speed is fast and the impact on the environment is small.

[0008] Optionally, the anchor assembly includes a plurality of anchors, and the plurality of anchors are arranged along the length direction of the steel pipe pile body. A protection assembly is correspondingly arranged for each anchor, and the driving assembly cooperates with each anchor in turn to drive the anchor to move.

[0009] By adopting the above technical solution, when lowering the steel cage, the driving assembly first cooperates with the anchor located above, and the anchor located above is inserted into the riverbed. Then the driving assembly and the steel cage pass through the anchor located above until they cooperate with the anchor located below, and the anchor located below is inserted into the riverbed. Anchoring is performed in multiple times along the length direction of the steel pipe pile body to improve the stability of the steel pipe pile body. The driving assembly cooperates with only one anchor at a time, the operation process is simple, the construction speed is fast, and the impact on the environment is reduced.

[0010] Optionally, the anchor comprises a plurality of anchor rods, and the plurality of anchor rods are arranged along the circumference of the steel pipe pile body; a sleeve is installed on the inner circumferential wall of the steel pipe pile body, and the end of the sleeve away from the circumferential wall of the steel pipe pile body is arranged toward the axis of the steel pipe pile body; the sleeve penetrates the circumferential wall of the steel pipe pile body, and the end of the sleeve close to the circumferential wall of the steel pipe pile body does not protrude from the outer circumferential wall of the steel pipe pile body; the anchor rod is inserted in the sleeve, and the outer circumferential wall of the anchor rod is slidably matched with the inner circumferential wall of the sleeve, and the length of the anchor rod is greater than the length of the sleeve; the protection component can limit the anchor rod from extending out of the outer circumferential wall of the steel pipe pile body, and the driving component can drive the anchor rod to break through the limitation of the protection component to protrude from the outer circumferential wall of the steel pipe pile body and be inserted into the riverbed.

[0011] Optionally, the anchor rod is arranged at an angle, and the end of the anchor rod away from the axis of the steel pipe pile body is inclined downward; a plug is installed at the end of the anchor rod close to the axis of the steel pipe pile body, and the plug is used to prevent the anchor rod from escaping from the casing; a water-blocking part is provided at the end of the anchor rod close to the plug, and the plug can press the water-blocking part against the end wall of the casing; when the anchor rod is in a retracted state, the plug is attached to the adjacent plug; and the driving assembly drives the anchor rod to move via the plug.

[0012] Optionally, the driving assembly includes a driving head, which is shaped like an inverted cone, and the side wall of the driving head slides with the end wall of the plug away from the anchor rod. When the driving head descends, the anchor rod is driven to move along the inner wall of the casing and extend out of the steel pipe pile body.

[0013] By adopting the above technical solution, when the protective component restricts the anchor rod to be in a retracted state, multiple plugs belonging to the same anchor piece are pressed against each other, and the anchor rod is difficult to slip out of the casing during the insertion process. When lowering the steel cage, the construction personnel lower the steel cage and the drive head, and the tip of the drive head is inserted between the four plugs. As the drive head descends, the side wall of the drive head transfers the weight of the steel cage and the drive head to the plug, and the plug drives the anchor rod downward along the length direction of the casing to break through the restriction of the protective component and be inserted into the riverbed. The water-blocking component can prevent water and sediment in the riverbed from entering the steel pipe pile body. Improve the stability of the steel pipe pile body; and the operation process is simple, and the operation can be completed with the help of the gravity of the steel cage itself, without the need for external power assistance, and has little impact on the environment.

[0014] Optionally, the protection component includes a waterproof rubber ring, a placement groove is opened on the outer circumferential wall of the steel pipe pile body, the waterproof rubber ring is arranged in the placement groove, and the outer circumferential wall of the waterproof rubber ring is flush with the outer circumferential wall of the steel pipe pile body; the end wall of the anchor rod away from the plug is in contact with the inner wall of the waterproof rubber ring.

[0015] By adopting the above technical solution, before inserting the steel pipe pile, the construction workers tighten the waterproof rubber ring in the placement groove, and the waterproof rubber ring restricts the anchor rod to be in a retracted state. When the anchor rod is extended, the tip of the anchor rod can easily pierce the waterproof rubber ring and insert it into the riverbed. In this process, the waterproof rubber ring prevents water and sediment in the riverbed from entering the steel pipe pile body. The operation is simple, and the cost of the waterproof rubber ring is low.

[0016] Optionally, the wall thickness of the steel pipe pile body is set to 15 mm, and the thickness of the waterproof rubber ring is set to 4 mm.

[0017] By adopting the above technical solution, since it is necessary to groove the steel pipe pile, steel pipe piles with larger wall thickness are selected to reduce the influence of the groove on the strength of the steel pipe pile body and reduce the deformation and fracture of the steel pipe pile during the driving process.

[0018] Optionally, one of the anchoring members includes four anchoring rods, and the anchoring rods of adjacent anchoring members are staggered.

[0019] By adopting the above technical solution, four anchor rods can provide sufficient supporting force. Compared with setting more anchor rods, more holes need to be opened on the steel pipe pile, which will reduce the strength of the steel pipe pile body.

[0020] Optionally, a triangular iron is provided on the casing, one side of the triangular iron is connected to the inner peripheral wall of the steel pipe pile body, and the other side of the triangular iron is connected to the outer peripheral wall of the casing.

[0021] By adopting the above technical solution, the triangle iron is used to support the sleeve to prevent the sleeve from being deformed when the driving head squeezes the plug.

[0022] In summary, the present application includes at least one of the following beneficial technical effects:

[0023] 1. Improve the stability of steel pipe piles; compared with the prior art, this application can improve the stability of the landscape trestle pile foundation without increasing the depth of steel pipe pile insertion; the construction speed is fast and the impact on the environment is small;

[0024] 2. When the protection component restricts the anchor rod to be in a retracted state, multiple plugs belonging to the same anchor piece are pressed against each other, and it is difficult for the anchor rod to fall out of the casing during the insertion process. When lowering the steel cage, the construction personnel lower the steel cage and the drive head, and the tip of the drive head is inserted between the four plugs. As the drive head descends, the side wall of the drive head transfers the weight of the steel cage and the drive head to the plug, and the plug drives the anchor rod downward along the length of the casing to break through the restriction of the protection component and be inserted into the riverbed. Improve the stability of the steel pipe pile body; and the operation process is simple, and the operation can be completed with the help of the gravity of the steel cage itself, without the need for external power assistance, and has little impact on the environment;

[0025] 3. Before inserting the steel pipe pile, the construction workers tighten the waterproof rubber ring in the placement groove, and the waterproof rubber ring restricts the anchor rod to be in a retracted state. When the anchor rod is extended, the tip of the anchor rod can easily pierce the waterproof rubber ring and insert it into the riverbed. In this process, the waterproof rubber ring prevents water and sediment in the riverbed from entering the steel pipe pile body. The operation is simple and the cost of the waterproof rubber ring is low. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a structural schematic diagram of a landscape trestle steel pipe pile according to an embodiment of the present application.

[0027] Figure 2 It is a schematic diagram of the structure of the anchoring assembly and the driving assembly of the embodiment of the present application.

[0028] Explanation of the accompanying reference numerals: 1. Steel pipe pile body; 11. Placement groove; 2. Steel cage; 3. Anchor assembly; 31. Anchor piece; 311. Anchor rod; 312. Casing; 313. Plug; 314. Water-blocking member; 4. Drive assembly; 41. Drive head; 5. Protection assembly; 51. Waterproof rubber ring; 6. Triangle iron. DETAILED DESCRIPTION

[0029] The following is combined with Figure 1-2 This application is described in further detail.

[0030] The present application embodiment discloses a landscape trestle steel pipe pile. Figure 1 and Figure 2A landscape trestle steel pipe pile includes a steel pipe pile body 1, the bottom end of which is inserted into the riverbed. An anchor assembly 3 is provided at a section of the steel pipe pile body 1 inserted into the riverbed, and the anchor assembly 3 is movably provided on the steel pipe pile body 1. The anchor assembly 3 can be inserted into the riverbed to fix the steel pipe pile body 1. A steel cage 2 is provided in the steel pipe pile body 1, and a driving assembly 4 is provided at the bottom end of the steel cage 2. The driving assembly 4 can cooperate with the anchor assembly 3 to drive the anchor assembly 3 to move. A protective assembly 5 is installed on the outer peripheral wall of the steel pipe pile body 1, and the protective assembly 5 is used to limit the self-movement of the anchor assembly 3.

[0031] The construction personnel install the protection component 5 on the steel pipe pile body 1, and then use the reaction frame to statically drive the steel pipe pile until the designed depth is reached. During the driving process of the steel pipe pile, the protection component 5 limits the anchor component 3 to be in a retracted state. The construction personnel control the steel cage 2 to align the drive component 4 with the top of the steel pipe pile body 1, lower the steel cage 2, and the steel cage 2 drives the drive component 4 to move vertically downward. Until the drive component 4 contacts the anchor component 3, the gravity of the steel cage 2 and the drive component 4 drives the anchor component 3 to break through the restriction of the protection component 5, extend out of the steel pipe pile body 1 and be inserted into the riverbed, thereby improving the stability of the steel pipe pile; compared with the prior art, the present application does not need to increase the depth of steel pipe pile driving to improve the stability of the landscape trestle pile foundation; the construction speed is fast and the impact on the environment is small.

[0032] Reference Figure 1 The anchor assembly 3 includes a plurality of anchors 31, which are arranged along the length direction of the steel pipe pile body 1. In this embodiment, two anchors 31 are arranged on each steel pipe pile body 1, and each anchor 31 is correspondingly provided with a protection assembly 5. The driving assembly 4 cooperates with each anchor 31 in turn to drive the anchor 31 to move.

[0033] When lowering the steel cage 2, the driving assembly 4 first cooperates with the anchor 31 located above, and the anchor 31 located above is inserted into the riverbed. Then the driving assembly 4 and the steel cage 2 pass through the anchor 31 located above until they cooperate with the anchor 31 located below, and the anchor 31 located below is inserted into the riverbed. Anchoring is performed in multiple times along the length direction of the steel pipe pile body 1 to improve the stability of the steel pipe pile body 1. The driving assembly 4 cooperates with only one anchor 31 at a time, which is simple to operate, fast in construction, and reduces the impact on the environment.

[0034] Reference Figure 2 The anchor 31 includes a plurality of anchor rods 311, and the plurality of anchor rods 311 are arranged along the circumference of the steel pipe pile body 1. In this embodiment, one anchor 31 includes four anchor rods 311. The anchor rods 311 are arranged along the radial direction of the steel pipe pile body 1, and the anchor rods 311 on adjacent anchors 31 are staggered.

[0035] A sleeve 312 is installed on the inner peripheral wall of the steel pipe pile body 1. The sleeve 312 penetrates the peripheral wall of the steel pipe pile body 1, and one end of the sleeve 312 close to the peripheral wall of the steel pipe pile body 1 does not protrude from the outer peripheral wall of the steel pipe pile body 1. The sleeve 312 is fixed to the steel pipe pile body 1 by welding, and the internal space of the steel pipe pile body 1 is connected to the outside through the sleeve 312. The anchor rod 311 is inserted into the sleeve 312, and the outer peripheral wall of the anchor rod 311 is slidably matched with the inner peripheral wall of the sleeve 312, and the length of the anchor rod 311 is greater than the length of the sleeve 312. A triangle iron 6 is arranged on the sleeve 312, and one side of the triangle iron 6 is connected to the inner peripheral wall of the steel pipe pile body 1 by welding, and the other side of the triangle iron 6 is connected to the outer peripheral wall of the sleeve 312 by welding.

[0036] The anchor rod 311 is tilted, and the end of the anchor rod 311 away from the axis of the steel pipe pile body 1 is tilted downward. A plug 313 is installed at the end of the anchor rod 311 close to the axis of the steel pipe pile body 1, and the plug 313 is fixed to the anchor rod 311 by welding. The width of the plug 313 is greater than the inner diameter of the sleeve 312 to prevent the anchor rod 311 from slipping out of the sleeve 312. A water blocking member 314 is provided at the end of the anchor rod 311 close to the plug 313, and the plug 313 can press the water blocking member 314 against the end wall of the sleeve 312. In this embodiment, the water blocking member 314 is a rubber gasket. When the anchor rod 311 is in a retracted state, the plug 313 is attached to the plug 313 adjacent to it.

[0037] The driving assembly 4 includes a driving head 41, which is fixed to the steel cage 2 by welding. The driving head 41 is in the shape of an inverted cone, and the side wall of the driving head 41 is slidably matched with the end wall of the plug 313 away from the anchor rod 311. When the driving head 41 descends, the anchor rod 311 is driven to move along the inner wall of the casing 312 and extend out of the steel pipe pile body 1.

[0038] The protection component 5 includes a waterproof rubber ring 51. A placement groove 11 is provided on the outer peripheral wall of the steel pipe pile body 1. The waterproof rubber ring 51 is arranged in the placement groove 11. The outer peripheral wall of the waterproof rubber ring 51 is flush with the outer peripheral wall of the steel pipe pile body 1. The wall thickness of the steel pipe pile body 1 is set to 15 mm, and the thickness of the waterproof rubber ring 51 is set to 4 mm. The end wall of the anchor rod 311 away from the plug 313 is in contact with the inner wall of the waterproof rubber ring 51, and the tip of the anchor rod 311 can pierce the waterproof rubber ring 51.

[0039] The implementation principle of a landscape trestle steel pipe pile of the present application embodiment is as follows: before inserting the steel pipe pile, the construction personnel tighten the waterproof rubber ring 51 in the placement groove 11, and the waterproof rubber ring 51 restricts the anchor rod 311 to be in a retracted state. At this time, the four plugs 313 belonging to the same anchor 31 are close to each other, and the anchor rod 311 is difficult to escape from the sleeve 312 during the insertion process. When the steel pipe pile body 1 is inserted to the designed depth, the construction personnel lower the steel cage 2 and the driving head 41, and the tip of the driving head 41 is inserted between the four plugs 313. As the driving head 41 descends, the side wall of the driving head 41 transfers the weight of the steel cage 2 and the driving head 41 to the plug 313 and the anchor rod 311, driving the anchor rod 311 to pierce the waterproof rubber ring 51, extend out of the outer wall of the steel pipe pile body 1, and be inserted in the riverbed. In this process, the waterproof rubber ring 51 and the water blocking member 314 jointly prevent the water and sediment in the riverbed from entering the steel pipe pile body 1. When the steel cage 2 is inserted to the bottom, the construction personnel pour cement into the steel pipe pile body 1 to fix the anchor rod 311. The present application can improve the stability of the steel pipe pile. Compared with the prior art, the present application can improve the stability of the landscape trestle pile foundation without increasing the depth of the steel pipe pile insertion; the construction speed is fast and the impact on the environment is small.

[0040] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A landscape trestle steel pipe pile, characterized in that: The invention comprises a steel pipe pile body (1) and a steel cage (2) arranged in the steel pipe pile body (1); the steel pipe pile body (1) is provided with an anchoring assembly (3), and the anchoring assembly (3) can be inserted into a riverbed to fix the steel pipe pile body (1); the anchoring assembly (3) is movably arranged on the steel pipe pile body (1); the steel cage (2) is provided with a driving assembly (4), and the driving assembly (4) can cooperate with the anchoring assembly (3) to drive the anchoring assembly (3) to move; and a protection assembly (5) is installed on the outer peripheral wall of the steel pipe pile body (1), and the protection assembly (5) is used to limit the movement of the anchoring assembly (3).

2. A landscape trestle steel pipe pile according to claim 1, characterized in that: The anchoring assembly (3) comprises a plurality of anchors (31), the plurality of anchors (31) being arranged along the length direction of the steel pipe pile body (1), each anchor (31) being provided with a corresponding protection assembly (5), and the driving assembly (4) being matched with each anchor (31) in turn to drive the anchor (31) to move.

3. A landscape trestle steel pipe pile according to claim 2, characterized in that: The anchor (31) comprises a plurality of anchor rods (311), and the plurality of anchor rods (311) are arranged along the circumference of the steel pipe pile body (1); a sleeve (312) is installed on the inner peripheral wall of the steel pipe pile body (1), and the end of the sleeve (312) away from the peripheral wall of the steel pipe pile body (1) is arranged toward the axis of the steel pipe pile body (1); the sleeve (312) penetrates the peripheral wall of the steel pipe pile body (1), and the end of the sleeve (312) close to the peripheral wall of the steel pipe pile body (1) does not protrude from the outer peripheral wall of the steel pipe pile body (1). wall; the anchor rod (311) is inserted into the casing (312), the outer peripheral wall of the anchor rod (311) is slidably matched with the inner peripheral wall of the casing (312), and the length of the anchor rod (311) is greater than the length of the casing (312); the protection component (5) can limit the anchor rod (311) from extending out of the outer peripheral wall of the steel pipe pile body (1), and the driving component (4) can drive the anchor rod (311) to break through the limitation of the protection component (5) so as to protrude from the outer peripheral wall of the steel pipe pile body (1) and be inserted into the riverbed.

4. A landscape trestle steel pipe pile according to claim 3, characterized in that: The anchor rod (311) is arranged obliquely, and the end of the anchor rod (311) away from the axis of the steel pipe pile body (1) is inclined downward; the end of the anchor rod (311) close to the axis of the steel pipe pile body (1) is installed with a plug (313), and the plug (313) is used to prevent the anchor rod (311) from escaping from the sleeve (312); the end of the anchor rod (311) close to the plug (313) is provided with a water blocking member (314), and the plug (313) can press the water blocking member (314) against the end wall of the sleeve (312); when the anchor rod (311) is in a retracted state, the plug (313) is in contact with the adjacent plug (313); the driving component (4) drives the anchor rod (311) to move through the plug (313).

5. The landscape trestle steel pipe pile according to claim 4, characterized in that: The driving assembly (4) comprises a driving head (41) which is in the shape of an inverted conical table. The side wall of the driving head (41) is slidably matched with the end wall of the plug (313) away from the anchor rod (311). When the driving head (41) descends, the anchor rod (311) is driven to move along the inner wall of the casing (312) and extend out of the steel pipe pile body (1).

6. The landscape trestle steel pipe pile according to claim 4, characterized in that: The protection component (5) comprises a waterproof rubber ring (51); a placement groove (11) is provided on the outer peripheral wall of the steel pipe pile body (1); the waterproof rubber ring (51) is arranged in the placement groove (11); the outer peripheral wall of the waterproof rubber ring (51) is flush with the outer peripheral wall of the steel pipe pile body (1); and the end wall of the anchor rod (311) away from the plug (313) is in contact with the inner wall of the waterproof rubber ring (51).

7. The landscape trestle steel pipe pile according to claim 6, characterized in that: The wall thickness of the steel pipe pile body (1) is set to 15 mm, and the thickness of the waterproof rubber ring (51) is set to 4 mm.

8. The landscape trestle steel pipe pile according to claim 7, characterized in that: One of the anchoring members (31) comprises four anchoring rods (311), and the anchoring rods (311) of adjacent anchoring members (31) are staggered.

9. The landscape trestle steel pipe pile according to claim 8, characterized in that: A triangular iron (6) is provided on the casing (312), one side of the triangular iron (6) is connected to the inner peripheral wall of the steel pipe pile body (1), and the other side of the triangular iron (6) is connected to the outer peripheral wall of the casing (312).