Excavation and support operation rack for high-speed tunnel construction

By introducing a bidirectional cylinder and support rod structure into the high-speed tunnel construction operation bench, dynamic adjustment of the spacing between the side of the workbench and the tunnel wall is achieved, and the problem that traditional benches cannot effectively compensate for side gaps is solved, which improves the convenience of workers' operations and construction efficiency, and improve safety performance.

CN222350713UInactive Publication Date: 2025-01-14CHONGQING ZHONGHUAN CONSTR
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421252817.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2025-01-14
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The traditional high-speed tunnel construction excavation support operation tray cannot effectively compensate for the gap between the side of the gantry and the tunnel, resulting in inconvenience of workers when installing anchor rods and guard plates, which increases inconvenience and safety hazards during construction.

Method used

A operating table including a workbench, a two-way cylinder, a support rod, a moving plate and an extension plate was designed. The dynamic adjustment of the spacing between the workbench side and the tunnel wall through the telescopic structure of the two-way cylinder and a support rod is achieved, and the support stability is increased. and flexibility, and control the movement range of the support rod through the limit panel to ensure safety.

Benefits of technology

The dynamic adjustment of the spacing between the side of the workbench and the tunnel wall is achieved, which improves the convenience of workers' operation and construction efficiency, reduces inconvenience and safety hazards, and improves the safety performance of the overall system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222350713U_ABST
    Figure CN222350713U_ABST
Patent Text Reader

Abstract

The utility model discloses an excavation support operation rack for high-speed tunnel construction, which relates to the technical field of tunnel construction and comprises a working table and two support plates, two bidirectional cylinders are mounted on the bottom surface of the working table, clamping grooves are formed in the two side surfaces of the working table, support rods are slidably connected in the clamping grooves, and the two support plates are arranged on the two side surfaces of the working table. The ends, away from the workbench, of the supporting rods are fixedly connected with a movable plate, the telescopic ends of the two-way air cylinders are installed on the movable plate, and an extension plate is arranged between the movable plate and the workbench. According to the utility model, the design structure is reasonable, the two sides of the workbench are provided with the two-way cylinders, and the supporting rods and the moving plates connected with the two-way cylinders, so that the function of dynamically adjusting the distance between the side part of the workbench and the tunnel wall is realized, and the problem that the traditional fixed portal frame cannot effectively compensate the side clearance is solved; the operation of workers during anchor rod and guard plate installation and the like is greatly facilitated, the working efficiency is improved, and inconvenience and potential safety hazards in construction are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel construction, in particular to an excavation and support operating platform for high-speed tunnel construction. Background Art

[0002] The construction platform is a mobile (wheeled, rail-mounted or skid-mounted) or assembled work frame manufactured to facilitate the construction of excavation, support, waterproof boards, etc. It is generally composed of a gantry, a telescopic (folding) work platform, a wind, water and electricity interface, a lifting equipment, a traveling mechanism, etc. In the process of excavation and support of high-speed tunnel construction, manual pneumatic drills are often used for excavation, and the operating platform is a working platform that facilitates workers to excavate and support.

[0003] A Chinese patent with announcement number CN206655701U discloses a tunnel excavation support gantry, which is convenient for lifting heavy objects, has high reliability and good safety. By installing rollers and a drive device at the bottom of the trolley gantry, independent movement of the gantry is achieved, which is convenient for operation. By opening a through hole on the trolley gantry, the manufacturing cost and weight of the trolley gantry can be reduced, and it is convenient for construction workers to climb through the through hole, which can shorten the process operation time and reduce the process connection time.

[0004] In the above scheme, the size of the gantry is fixed, and the distance between the gantry and the top of the tunnel can be reduced by adding a structure on the top of the gantry. However, the distance between the side of the gantry and the tunnel is difficult to effectively compensate, which makes it extremely inconvenient for workers to install anchor rods and guard plates. To this end, we provide a high-speed tunnel construction excavation support operation platform to solve the above problems. Utility Model Content

[0005] 1) Technical issues solved

[0006] The purpose of the utility model is to make up for the deficiencies of the prior art and to provide an excavation support operating stand for high-speed tunnel construction.

[0007] 2) Technical solution

[0008] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a high-speed tunnel construction excavation support operation platform, including a workbench and two support plates, two two-way cylinders are installed on the bottom surface of the workbench, and slots are provided on both side surfaces of the workbench. Support rods are slidably connected in the slots, and one end of the support rod away from the workbench is fixedly connected to a movable plate, the telescopic end of the two-way cylinder is installed on the movable plate, an extension plate is arranged between the movable plate and the workbench, a fixed plate is installed on the support plate, a movable plate is arranged on the fixed plate, a linkage rod is fixedly connected to the movable plate, and the top end of the linkage rod is fixedly connected to the movable plate.

[0009] Furthermore, a slot is provided on the bottom surface of the extension plate, and the extension plate is installed on the support rod through the slot.

[0010] Furthermore, one end of the support rod away from the movable plate is fixedly connected to the limiting plate.

[0011] Furthermore, a guide groove is provided on the movable plate, and the movable plate is slidably connected to the fixed plate through the guide groove. A reinforcement rod is fixedly connected to the fixed plate, and one end of the reinforcement rod away from the fixed plate is fixedly connected to the support plate.

[0012] Furthermore, a through slot is provided on the workbench, a guard platform is fixedly connected to the workbench, and the guard platform matches the through slot, an electric hoist is arranged above the guard platform, a support is installed on the electric hoist, and the bottom end of the support is fixedly connected to the guard platform.

[0013] Furthermore, the bottom surface of the support plate is fixedly connected to a base, and rollers arranged at equal intervals are installed on the bottom surface of the base.

[0014] 3) Beneficial effects:

[0015] Compared with the existing technology, the high-speed tunnel construction excavation support operation platform has the following beneficial effects:

[0016] 1. The utility model realizes the dynamic adjustment function of the distance between the side of the workbench and the tunnel wall by arranging two-way cylinders and supporting rods and movable plate structures connected thereto on both sides of the workbench. This design overcomes the problem that the traditional fixed gantry cannot effectively compensate for the side gap, greatly facilitates the operation of workers when performing operations such as anchor rod and guard plate installation, improves work efficiency, and reduces inconvenience and safety hazards in construction.

[0017] 2. The utility model adopts the design of installing the extension plate on the support rod by means of a slot, which not only increases the support stability of the workbench, but also makes the entire frame structure more flexible and adaptable to tunnel environments of different diameters and shapes. At the same time, the setting of the limit plate ensures that the movement range of the support rod is controlled during the adjustment process, avoiding safety risks caused by excessive extension and improving the safety performance of the overall system. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 The three-dimensional Figure 1 ;

[0019] Figure 2 The three-dimensional Figure 2 ;

[0020] Figure 3 It is a cross-sectional view of the utility model.

[0021] In the figure: 1. workbench; 2. support plate; 3. two-way cylinder; 4. movable plate; 5. extension plate; 6. support rod; 7. limit plate; 8. fixed plate; 9. movable plate; 10. guide groove; 11. linkage rod; 12. base; 13. roller; 14. through groove; 15. guardrail; 16. support; 17. electric hoist; 18. reinforcement rod; 19. slot. DETAILED DESCRIPTION

[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0023] like Figure 1-3 As shown, the utility model provides a technical solution: a high-speed tunnel construction excavation support operation platform, comprising a workbench 1 and two support plates 2, the workbench 1 and the two support plates 2 forming a door frame structure, the workbench 1 is also designed with a ladder, so that workers can climb onto the workbench 1, two two-way cylinders 3 are installed on the bottom surface of the workbench 1, the two two-way cylinders 3 are both two-way push rods, and they have two telescopic ends, which can be synchronously telescoped, and slots 19 are provided on both side surfaces of the workbench 1, and support rods 6 are slidably connected in the slots 19, and the end of the support rod 6 away from the workbench 1 is fixedly connected to a movable plate 4, and the end of the support rod 6 away from the movable plate 4 is fixedly connected to a limiting plate 7, and the limiting plate 7 limits the sliding of the support rod 6 in the slot 19.

[0024] The telescopic end of the two-way cylinder 3 is installed on the moving plate 4, which can push the two moving plates 4 to move closer to or away from each other, thereby adjusting the distance between the moving plate 4 and the inner wall of the tunnel. An extension plate 5 is arranged between the moving plate 4 and the workbench 1. A slot 19 is provided on the bottom surface of the extension plate 5, and the extension plate 5 is installed on the support rod 6 through the slot 19. During the movement of the moving plate 4, the support rod 6 will be driven to extend from the inside of the workbench 1, and multiple extension plates 5 are laid on the support rod 6 in turn through the slot 19, so that the extension plate 5 and the workbench 1 form a platform to support the workers, and the length of the platform can be adjusted by moving the moving plate 4.

[0025] A fixed plate 8 is installed on the support plate 2, and a movable plate 9 is arranged on the fixed plate 8. A linkage rod 11 is fixedly connected to the movable plate 9, and the top end of the linkage rod 11 is fixedly connected to the movable plate 4. When the movable plate 4 is moving, the linkage rod 11 will drive the movable plate 9 to move on the fixed plate 8, thereby synchronously adjusting the distance between the movable plate 9 and the inner wall of the tunnel.

[0026] A guide groove 10 is provided on the movable plate 9, and the movable plate 9 is slidably connected to the fixed plate 8 through the guide groove 10. A reinforcement rod 18 is fixedly connected to the fixed plate 8, and one end of the reinforcement rod 18 away from the fixed plate 8 is fixedly connected to the support plate 2, so that the movable plate 9 slides on the fixed plate 8 through the guide groove 10, which can ensure the stability of the movable plate 9 after adjustment on the fixed plate 8, and the fixed plate 8 is supported by the reinforcement rod 18, which can improve the structural strength of the fixed plate 8 on the support plate 2.

[0027] A through slot 14 is provided on the workbench 1, a guard platform 15 is fixedly connected to the workbench 1, and the guard platform 15 matches the through slot 14, an electric hoist 17 is provided above the guard platform 15, a support 16 is installed on the electric hoist 17, and the bottom end of the support 16 is fixedly connected to the guard platform 15, the hoisting end of the electric hoist 17 is extended to the bottom of the workbench 1 through the through slot 14, and the construction tools can be hoisted onto the workbench 1 by the electric hoist 17.

[0028] The bottom surface of the support plate 2 is fixedly connected to a base 12, and rollers 13 arranged at equal intervals are installed on the bottom surface of the base 12, so that the support plate 2 can move on the track through the rollers 13 on the base 12, so as to facilitate the movement of the device to the next support platform.

[0029] It should be noted that, in this article, the orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the utility model; the terms "first", "second", and "third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance. In addition, unless otherwise clearly specified and limited, the terms "fixed", "installed", "connected", and "connected" should be understood in a broad sense. For example, "installed" can be a fixed connection, a detachable connection, or an integral connection; "connected" can be a mechanical connection or an electrical connection; "connected" can be a direct connection, an indirect connection through an intermediate medium, or a connection between the two elements. For ordinary technicians in this field, the specific meanings of the above terms in the utility model can be understood according to specific circumstances.

[0030] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A high-speed tunnel construction excavation support operation platform, comprising a workbench (1) and two support plates (2), characterized in that: Two bidirectional cylinders (3) are installed on the bottom surface of the workbench (1), and slots (19) are provided on both sides of the workbench (1). A support rod (6) is slidably connected in the slot (19), and one end of the support rod (6) away from the workbench (1) is fixedly connected to a movable plate (4). The telescopic end of the bidirectional cylinder (3) is installed on the movable plate (4), and an extension plate (5) is arranged between the movable plate (4) and the workbench (1). A fixed plate (8) is installed on the support plate (2), and a movable plate (9) is arranged on the fixed plate (8). A linkage rod (11) is fixedly connected to the movable plate (9), and the top end of the linkage rod (11) is fixedly connected to the movable plate (4).

2. The high-speed tunnel construction excavation support operation platform according to claim 1, characterized in that: A clamping slot (19) is provided on the bottom surface of the extension plate (5), and the extension plate (5) is mounted on the support rod (6) through the clamping slot (19).

3. The high-speed tunnel construction excavation support operation platform according to claim 1, characterized in that: One end of the support rod (6) away from the movable plate (4) is fixedly connected to a limiting plate (7).

4. The high-speed tunnel construction excavation support operation platform according to claim 1, characterized in that: The movable plate (9) is provided with a guide groove (10), and the movable plate (9) is slidably connected to the fixed plate (8) through the guide groove (10); a reinforcing rod (18) is fixedly connected to the fixed plate (8), and one end of the reinforcing rod (18) away from the fixed plate (8) is fixedly connected to the support plate (2).

5. The high-speed tunnel construction excavation support operation platform according to claim 1, characterized in that: The workbench (1) is provided with a through slot (14), a guard platform (15) is fixedly connected to the workbench (1), and the guard platform (15) matches the through slot (14), an electric hoist (17) is arranged above the guard platform (15), a support (16) is installed on the electric hoist (17), and the bottom end of the support (16) is fixedly connected to the guard platform (15).

6. The high-speed tunnel construction excavation support operation platform according to claim 1, characterized in that: The bottom surface of the support plate (2) is fixedly connected to a base (12), and rollers (13) arranged at equal intervals are mounted on the bottom surface of the base (12).

Citation Information

Patent Citations

  • Tunnel excavation struts rack

    CN206655701U