T-beam diaphragm thick steel bar positioning device
Through the design of the T -beam horizontal partition thick reinforcement positioning device, the problem of poor positioning of the cross -partial connection connection and the inaccurate positioning of the lower horizontal reinforcement has been solved, and the accurate positioning of the reliable connection between the horizontal partition and the middle beam and the lower horizontal reinforcement position , Improve the intensity and stability of the overall structure.
Patent Information
- Application Number
- CN202420443702.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-07
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-03-07
AI Technical Summary
The connection strength of existing T-beam transverse partitions is poor, and the positioning of the lower transverse steel bars is inaccurate.
A T -beam cross -barrier coarse reinforcement positioning device is designed, including the transverse editorial pouring mold and the lower horizontal steel positioning mechanism. The edge partitioning mold is composed of bottom templates, side templates, and end templates. The end templates are equipped with a lower horizontal reinforcement positioning mechanism. The positioning mechanism consists of a fixed connection board, a dynamic connection board, a thread tension rod and a locking nut. Through these The component is accurate to position the underlying steel bars underneath.
A reliable connection between the crossover and the middle beam is realized, ensuring the accurate positioning of the lower horizontal steel bars, and improving the intensity and stability of the overall structure.
Smart Images

Figure CN222412633U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge construction, in particular to a T-beam transverse diaphragm coarse steel bar positioning device. Background Art
[0002] The T-beam includes a middle beam extending in the longitudinal direction and a top beam connected to the upper end of the middle beam. The top beam outputs the middle beam in the transverse direction to both sides. The middle beam includes a middle beam steel frame and middle beam concrete cast with the middle beam steel frame. Some T-beams have a plurality of diaphragms distributed in the longitudinal direction on both sides of the transverse direction of the middle beam. The diaphragms include a diaphragm steel frame and diaphragm concrete cast with the diaphragm steel frame. The diaphragm steel frame is connected with the middle beam steel, and the middle beam concrete is cast with the diaphragm concrete. For T-beams with diaphragms, the diaphragms and the middle beams are not cast together at one time, but are subsequently cast by building a fixed diaphragm casting mold on both sides of the middle beam. It is troublesome to install and disassemble the diaphragm mold when casting the diaphragm with the existing mold; the connection strength between the diaphragm and the middle beam is poor, and the thick steel bars (lower transverse steel bars) of the diaphragm steel frame cannot be accurately positioned. Utility Model Content
[0003] The utility model aims to provide a T-beam cross diaphragm coarse steel bar positioning device with reliable connection between the cross diaphragm and the middle beam and accurate positioning of the lower transverse steel bar, which solves the problem of poor connection strength of the existing T-beam cross diaphragm and inaccurate positioning of the lower transverse steel bar.
[0004] The above technical problems are solved by the following technical solutions: a T-beam diaphragm coarse steel bar positioning device, the T-beam includes a middle beam extending along the longitudinal bridge direction and a top beam connected to the upper end of the middle beam, the top beam outputs the middle beam on both sides along the transverse bridge direction, and a number of diaphragms distributed along the longitudinal bridge direction are arranged on both sides of the transverse bridge direction of the middle beam, the middle beam includes a middle beam steel bar skeleton and middle beam concrete for casting the middle beam steel bar skeleton, the diaphragm includes a diaphragm steel bar skeleton and diaphragm concrete for casting the diaphragm steel bar skeleton, the diaphragm steel bar skeleton is connected to the middle beam steel bar, the middle beam concrete is cast together with the diaphragm concrete, the diaphragms located on both sides of the middle beam are aligned one by one, and it is characterized in that it also includes a diaphragm casting mold for casting the diaphragms one by one, and the diaphragm steel bar skeleton includes a diaphragm steel bar skeleton along the transverse bridge direction A plurality of extended lower transverse steel bars are located on both sides of the middle beam and aligned with the transverse partitions, one end of the lower transverse steel bars are connected together and the other end extends out of the transverse partition casting mold, and the transverse partition casting mold is provided with a lower transverse steel bar positioning mechanism, the lower transverse steel bar positioning mechanism includes a fixed connecting plate, a movable connecting plate and a threaded tensioning rod with one end fixed to the fixed connecting plate, the fixed connecting plate is fixed to the transverse partition casting mold, the other end of the threaded tensioning rod passes through the movable connecting plate and is threadedly connected to the tightening nut, and the movable connecting plate is provided with a plurality of positioning tubes; the process of positioning the lower transverse steel bars is as follows: when installing the lower transverse steel bars, the lower transverse steel bars are made to pass through the fixed connecting plate and be arranged in the positioning tube one by one, and then the locking nut is rotated to press the movable connecting plate against the end of the lower transverse steel bar, thereby achieving reliable positioning.
[0005] Preferably, a connecting thread sleeve is fixed on the fixed connecting plate, and the threaded tensioning rod is threadedly connected in the connecting thread sleeve and fixed together with the fixed connecting plate. When not in use, the lower transverse positioning mechanism can be folded up.
[0006] Preferably, the transverse diaphragm reinforcement skeleton includes a plurality of upper transverse reinforcements extending in the transverse direction of the bridge, and the upper transverse reinforcements of the transverse diaphragms located on both sides of the middle beam and aligned with each other are connected together, so as to improve the connection reliability between the middle beam and the transverse diaphragm.
[0007] Preferably, the middle beam is provided with a transverse through hole for the upper transverse reinforcement to pass through, and the transverse diaphragm concrete is poured into the transverse through hole and poured together with the middle beam concrete, which can facilitate the connection of the upper transverse reinforcement and further improve the connection reliability.
[0008] Preferably, the intermediate beam reinforcement skeleton includes two lower longitudinal reinforcements exposed in the lower side of the transverse bridge through hole and extending in the longitudinal bridge direction, a lower limiting groove is formed between the two lower longitudinal reinforcements, and the upper transverse reinforcement is provided with a hook head which penetrates through the transverse bridge through hole and hooks into the lower limiting groove. The upper transverse reinforcement can be positioned more accurately, and the connection reliability between the upper transverse reinforcement and the intermediate beam is improved.
[0009] Preferably, it also includes an isolation membrane sleeve, and two of the upper transverse steel bars are passed through a through hole of a cross bridge, and the two upper transverse steel bars can be passed through the isolation membrane sleeve at the same time. Two exhaust channels are surrounded between the upper transverse steel bars and the isolation membrane sleeve, and a pull rod is passed through the exhaust channel, and a cutting knife for cutting the isolation membrane sleeve is provided at the inner end of the pull rod. During the casting of the transverse diaphragm, the upper transverse steel bar is passed through the box into the transverse bridge through hole and the hook head is hooked in the limiting groove, and the two pull rods are passed one by one into the two upper and lower grooves formed by the two upper transverse steel bars, and then the isolation magic sleeve is put on the upper transverse steel bar and the pull rod to the isolation membrane sleeve to reach the lower longitudinal steel bar, and the cutting knife is located outside the inner end of the isolation membrane sleeve. When casting the transverse diaphragm concrete, the concrete flows into the transverse bridge through hole from between the isolation membrane sleeve and the transverse bridge through hole, and the pull rod is pulled out synchronously with the outflow of concrete in the transverse bridge through hole. The cutting knife is always located inside the concrete, so that the cutting knife cuts the isolation membrane sleeve and discharges the concrete, which increases the exhaust effect and improves the density of the concrete in the transverse bridge through hole. After the casting is completed, the two ends of the upper transverse steel bar are connected to the two ends of the power supply to generate a short circuit and heat up to melt the isolation membrane sleeve, thereby avoiding the membrane sleeve causing poor casting effect of concrete and upper transverse steel bars.
[0010] Preferably, the intermediate beam reinforcement skeleton further comprises two upper longitudinal reinforcements exposed in the upper side of the transverse bridge through hole and extending in the longitudinal bridge direction, an upper limit groove is formed between the two upper longitudinal reinforcements, a lower hook on one upper transverse reinforcement is hooked in the lower limit groove, and a lower hook on another upper transverse reinforcement is hooked in the upper limit groove. The two upper transverse reinforcements can be reliably pulled and positioned even when the strength of the longitudinal reinforcement is low.
[0011] Preferably, it also includes a steel bar assembly locator, wherein one of the two lower longitudinal steel bars is positioned beyond the other lower longitudinal steel bar in the lower longitudinal direction, and the steel bar assembly locator includes a clamp for fixing on the upper transverse steel bar, a comparison rod connected to the clamp and a scale plate provided with an elastic connecting seat, the elastic connecting seat is used to insert into the transverse through hole to fix the scale plate at the end of the transverse through hole, the scale plate is provided with a limiting notch for the upper transverse steel bar to pass through and two groups of reference line groups located on the upper and lower sides of the limiting notch, the reference line group including a near-notch side reference line and a far-notch side reference line; when the scale plate is fixed in the transverse through hole through the elastic connecting seat, the near-notch side reference line in the lower reference line group is located on the same horizontal plane as the highest point of the lower longitudinal steel bar that is higher on the upper side, and the far-notch side reference line is located on the same horizontal plane as the highest point of the lower longitudinal steel bar that is lower on the upper side. The process of passing the upper transverse steel bar into the transverse bridge through hole is as follows: insert an upper transverse steel bar from the side where the lower longitudinal steel bar is located on the upper side until the hook head is abutted against the upper lower steel bar, the hook head on the upper transverse steel bar is directly below the upper transverse steel bar, the scale plate is fixed on the port of the transverse bridge through hole and an upper transverse steel bar is passed through the gap, the hoop is fixed on an upper transverse steel bar and the comparison rod is directly below the upper transverse steel bar, the hoop is spaced apart from the scale plate, the upper transverse steel bar is rotated in one direction until the comparison rod is located between the near gap side reference line and the far gap side reference line of the reference line group below the gap, an upper transverse steel bar is pushed inward to the limit position so that the hook head is on the upper side higher lower longitudinal steel bar, and an upper transverse steel bar is rotated in the other direction until the comparison rod is located directly below the upper transverse steel bar so that the hook head of an upper transverse steel bar is hooked in the lower limit groove, the hoop is removed from an upper transverse steel bar and the comparison plate is removed from the transverse bridge through hole; The transverse steel bar is inserted from the side of the lower longitudinal steel bar on the upper side, and the hook head is abutted with the lower steel bar on the upper side. The hook head on the other upper transverse steel bar is directly below the other upper transverse steel bar. The scale plate is equivalent to fixing one upper transverse steel bar, and then rotated 180° and fixed on the port of the cross bridge to the through hole, so that the other upper transverse steel bar is inserted into the gap. The hoop is fixed on the other upper transverse steel bar and the comparison rod is directly below the other upper transverse steel bar. The hoop is spaced apart from the scale plate. The upper transverse steel bar is rotated in one direction until the comparison rod is located between the near gap side reference line and the far gap side reference line of the reference line group below the gap. The other upper transverse steel bar is pushed inward to the limit position so that the hook head is on the lower longitudinal steel bar with the upper side height. The upper transverse steel bar is rotated in the other direction until the comparison rod is located directly above the upper transverse steel bar so that the hook head of the other upper transverse steel bar is hooked in the upper limit groove. The hoop is removed from the other upper transverse steel bar and the comparison plate is removed from the cross bridge to the through hole. The upper transverse steel bar can be easily installed in place.
[0012] Preferably, a diaphragm casting mold for casting the diaphragm is also included, the diaphragm casting mold includes a bottom template, two side templates distributed along the longitudinal bridge direction and connected to the bottom template at the lower end, and an end template connecting one end of the two side templates together, and a positioning through hole is provided on the inner surface of the end template, and the upper transverse steel bar is passed through the positioning through hole, so that the upper transverse steel bar can maintain the set position.
[0013] Preferably, a convex column is fixed to the inner surface of the end template, the positioning through hole passes through the convex column, the upper transverse reinforcement is only located in the convex column, and the end surface of the upper transverse reinforcement is at least 2 cm away from the inner surface of the end template. After removing the crossbar casting mold, the transverse partition has a pit formed by the convex column, the end of the upper transverse reinforcement is sunken in the pit, and the pit is filled with concrete to close the pit. This can prevent the upper transverse reinforcement from being exposed.
[0014] The beneficial effects of the utility model are as follows: the connection between the transverse partition and the middle beam is reliable; and the upper transverse reinforcement is accurately positioned. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of pouring a transverse diaphragm in Embodiment 1 of the present utility model;
[0016] Figure 2 for Figure 1 A local enlarged schematic diagram of point C;
[0017] Figure 3 It is the lower structure of the casting mold for the diaphragm;
[0018] Figure 4 This is a schematic diagram of pouring a diaphragm in Embodiment 2 of the present utility model;
[0019] Figure 5 for Figure 4 A local enlarged schematic diagram of point A;
[0020] Figure 6 for Figure 4 A local enlarged schematic diagram of point B;
[0021] Figure 7 It is a schematic diagram of an upper transverse steel bar passing through a through hole in the transverse direction when viewed in the transverse direction;
[0022] Figure 8 It is a schematic diagram when observing from the transverse direction when another upper transverse steel bar passes through the transverse through hole;
[0023] Fig. 9 Schematic diagram of the isolation membrane sleeve being installed on the upper transverse reinforcement.
[0024] In the figure: middle beam 1, top beam 2, top beam steel frame 3, top beam concrete 4, exposed part 5, bottom formwork 6, side formwork 7, end formwork 8, lifting mechanism 9, longitudinal push-pull rod 10, side telescopic push-pull rod 11, upper telescopic push-pull rod 12, axle pin 13, walking wheel 14, support foot 15, longitudinal hinge shaft 16, support rod 17, first longitudinal connecting rod 18, second longitudinal connecting rod 19, crank 20, middle beam widening section 21, middle beam step 22, side formwork widening section 23, side formwork step 24, transverse steel bar 25, transverse bridge through hole 26, elastic connecting seat 27, lower longitudinal steel bar 29, upper longitudinal steel bar 30, upper limit groove 31, one An upper transverse steel bar 32, another upper transverse steel bar 33, an isolation membrane sleeve 34, an exhaust channel 35, a pull rod 36, a cutting knife 37, a clamp 38, a comparison rod 39, a scale plate 40, a limit notch 41, a reference line group 42, a reference line on the near notch side 43, a reference line on the far notch side 44, a positioning through hole 45, a boss 46, a base frame 47, a lower limit groove 48, a lower hook head 50 on another upper transverse steel bar, a movable base frame 51, a lower pull rod 53, a cross partition is provided with a lower transverse steel bar 60, a lower transverse steel bar positioning mechanism 61, a fixed connecting plate 54, a movable connecting plate 55, a threaded tensioning rod 56, a locking nut 57, a positioning cylinder 58, and a connecting threaded sleeve 59. DETAILED DESCRIPTION
[0025] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments; based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0026] Example 1, see Figures 1 to 3A device for positioning coarse steel bars of a T-beam diaphragm, wherein the T-beam comprises an intermediate beam 1 extending in the longitudinal direction and a top beam 2 connected to the upper end of the intermediate beam. The top beam outputs the intermediate beam on both sides in the transverse direction, and the top beam comprises a top beam steel bar skeleton 3 and a top beam concrete 4 cast on the top beam steel bar skeleton. Both ends of the top beam steel bar skeleton in the transverse direction are exposed to the top beam concrete to form an exposed portion 5. A plurality of diaphragms distributed in the longitudinal direction are arranged on both sides of the intermediate beam in the transverse direction. The intermediate beam comprises an intermediate beam steel bar skeleton and an intermediate beam concrete cast on the intermediate beam steel bar skeleton. The diaphragm comprises a diaphragm steel bar skeleton and a diaphragm concrete cast on the diaphragm steel bar skeleton. The diaphragm steel bar skeleton is connected to the intermediate beam steel bar, and the intermediate beam concrete is cast together with the diaphragm concrete. The invention comprises a casting mold for a transverse diaphragm for casting a transverse diaphragm, the casting mold for the transverse diaphragm comprises a bottom template 6, two side templates 7 distributed along the longitudinal bridge direction and connected to the bottom template at the lower end, and an end template 8 connecting one end of the two side templates together, and the end template is specifically connected to the side template by bolts and nuts. The bottom template is connected to the movable base frame 51 through a lifting mechanism 9, and the upper ends of the two side templates are connected together through a longitudinal push-pull rod 10 extending in the longitudinal bridge direction. The side template can be connected to the longitudinal push-pull rod 10 movably along the longitudinal bridge direction, the lower end of the side template is hinged to the bottom template, the upper end is hinged to the upper end of the side telescopic push-pull rod 11, and the lower end of the side telescopic push-pull rod is hinged to the bottom template. The longitudinal push-pull rod is hinged to one end of an upper telescopic push-pull rod 12 driving the longitudinal push-pull rod to move toward the middle beam. The upper end of the upper telescopic push-pull rod is rotatably connected to an axle pin 13 fixed to the exposed part. The push-pull rod and the axle pin are detachably connected together. The movable base frame is provided with a running wheel 14, and the bottom template is connected with a supporting foot 15 in a lifting manner. When the diaphragm casting mold is moved into place, the supporting foot is extended and supported on the ground to lift the running wheel off the ground. The lifting mechanism includes a base frame 47 slidably connected to the movable base along the transverse bridge direction, a longitudinal hinge shaft 16 extending along the longitudinal bridge direction, and two groups of support rods 17 distributed along the longitudinal bridge direction. One group of support rods has two support rods and the middle part is cross-connected together through the longitudinal hinge shaft. The lower end of the support rod is slidably connected to the base frame along the transverse bridge direction, and the upper end is slidably connected to the bottom template along the transverse bridge direction. The upper end of one of the two support rods in the two groups of support rods is rotatably connected to the first longitudinal connecting rod 18, and the upper end of the other support rod is rotatably connected to the second longitudinal connecting rod 19. The first longitudinal connecting rod is rotatably connected to one end of the tie rod 52 with a threaded structure, and the second longitudinal connecting rod is threadedly connected to the middle screw of the tie rod. The other end of the tie rod is provided with a crank 20. When in use, the lifting mechanism is lifted or lowered by rotating the crank to rotate the pull rod, which is convenient for lifting or lowering.The lower end of the middle beam is provided with a middle beam widening section 21, and a middle beam step 22 is formed between the middle beam widening section and the middle beam. The upper end of the side template facing the middle beam is provided with a side template widening section 23, and a side template step 24 is formed between the side template widening section and the side template facing the middle beam. When the side template widening abuts against the upper end of the middle beam, the lower end of the side template facing the middle beam abuts against the middle beam widening section, and the side template step is sealed and abutted with the middle beam step. The lower end of the lifting mechanism is movably connected to the movable chassis along the transverse bridge direction, and the side template can be moved to the side facing the middle beam beyond the movable base. The transverse partitions are distributed on both sides of the middle beam in an aligned manner. The movable chassis located on both sides are connected together by a lower pull rod 53.
[0027] The process of casting the diaphragm is as follows: the diaphragm casting mold is moved to the position of the middle beam where the diaphragm is set by the mobile base and connected together, and then the two are connected by the lower pull rod to prevent movement. The height of the diaphragm casting mold is adjusted to the required height by the lifting structure, and the diaphragm steel frame is located in the diaphragm casting mold, so that the upper telescopic push-pull rod is extended to make the diaphragm casting mold and the middle beam close together, and the diaphragm casting mold and the middle beam form a diaphragm cavity, and concrete is poured into the diaphragm cavity and cast together with the diaphragm steel frame to form a diaphragm. In the process of moving the mobile base to make the diaphragm casting mold approach and move away from the middle beam, the diaphragm casting mold is located in the middle of the mobile base to improve the stability during the movement. When the mobile base approaches the middle beam to the set position, the diaphragm casting mold is moved on the mobile base beyond the mobile base and abuts against the middle beam. When demoulding, first remove the end template, then retract the side telescopic push-pull rod to disengage the side template from the diaphragm, and retract the top telescopic push-pull rod to disengage the side template from the middle beam. The diaphragm is provided with a lower transverse steel bar 60, and one end of the lower transverse steel bars of the diaphragms located on both sides of the middle beam and aligned with each other are connected together, and the other end extends out of the end template of the diaphragm casting mold. A lower transverse steel bar positioning mechanism 61 is provided on the end template. The lower transverse steel bar positioning mechanism includes a fixed connecting plate 54, a movable connecting plate 55, and a threaded tensioning rod 56 whose one end is fixed to the fixed connecting plate, and the fixed connecting plate is fixed to the diaphragm casting mold. The other end of the threaded tensioning rod passes through the movable connecting plate and is threadedly connected to the locking nut 57. A plurality of positioning cylinders 58 are provided on the movable connecting plate. A connecting thread sleeve 59 is fixed on the fixed connecting plate, and the threaded tensioning rod is threadedly connected in the connecting thread sleeve and fixed to the fixed connecting plate.
[0028] The process of positioning the lower transverse reinforcement is as follows: when installing the lower transverse reinforcement, the lower transverse reinforcement is passed through the fixed connecting plate and then arranged in the positioning cylinder one by one, and then the locking nut is rotated to press the movable connecting plate against the end of the lower transverse reinforcement, thereby achieving reliable positioning.
[0029] Embodiment 2 is different from Embodiment 1 in that:
[0030] See also Figures 4 to 9 The cross-diaphragm reinforcement skeleton includes a plurality of transverse steel bars 25 extending in the transverse direction, and the upper transverse reinforcements of the cross-diaphragms located on both sides of the middle beam and aligned are connected together. The middle beam is cast with a transverse through hole 26 for the upper transverse reinforcement to pass through, and the cross-diaphragm concrete is cast into the transverse through hole and cast together with the middle beam concrete. The middle beam reinforcement skeleton includes two lower longitudinal reinforcements exposed in the lower side of the transverse through hole extending in the longitudinal direction, and a lower limit groove 48 is formed between the two lower longitudinal reinforcements, and the upper transverse reinforcement is provided with a hook head that is inserted through the transverse through hole and hooked in the lower limit groove. One of the two lower longitudinal reinforcements (i.e., the upper lower longitudinal reinforcement 28) exceeds the other lower longitudinal reinforcement (i.e., the lower lower longitudinal reinforcement 29) upward. The middle beam reinforcement skeleton also includes two upper longitudinal reinforcements 30 exposed in the upper side of the transverse through hole extending in the longitudinal direction, and an upper limit groove 31 is formed between the two upper longitudinal reinforcements. Two upper transverse steel bars are inserted into a through hole of a transverse bridge. A lower hook 49 on an upper transverse steel bar 32 is hooked into the lower limit groove, and a lower hook 50 on another upper transverse steel bar 33 is hooked into the upper limit groove. It also includes an isolation film sleeve 34, and two upper transverse steel bars can be inserted into the isolation film sleeve at the same time. Two exhaust channels 35 are surrounded between the upper transverse steel bars and the isolation film sleeve. A pull rod 36 is inserted into the exhaust channel, and a cutter 37 for cutting the isolation film sleeve is provided at the inner end of the pull rod. It also includes a steel bar assembly positioner, which includes a hoop 38 for fixing on the upper transverse steel bar, a comparison rod 39 connected to the hoop, and a scale plate 40 provided with an elastic connection seat 27, the elastic connection seat is used to insert into the transverse bridge through hole to fix the scale plate at the end of the transverse bridge through hole, and the scale plate is provided with a limit notch 41 for the upper transverse steel bar to pass through and two groups of reference line groups 42 located at the upper and lower sides of the limit notch, and the reference line group includes a near-notch side reference line 43 and a far-notch side reference line 44; when the scale plate is fixed in the transverse bridge through hole through the elastic connection seat, the near-notch side reference line in the lower reference line group is located on the same horizontal plane as the highest point of the upper side higher lower longitudinal steel bar, and the far-notch side reference line is located on the same horizontal plane as the highest point of the upper side lower longitudinal steel bar. A positioning through hole 45 is provided on the inner surface of the end template, and the upper transverse steel bar is inserted into the positioning through hole. The inner surface of the end template is fixed with a protrusion 46, and the positioning through hole passes through the protrusion. The upper transverse reinforcement is only located in the protrusion, and the end surface of the upper transverse reinforcement is more than 2 cm away from the inner surface of the end template. After removing the crossbar casting mold, the transverse partition has a pit formed by the protrusion, and the end of the upper transverse reinforcement is sunken in the pit, and the pit is filled with concrete to close the pit.
[0031] The process of passing the upper transverse steel bar into the transverse bridge through hole is as follows: insert an upper transverse steel bar from the side where the lower longitudinal steel bar is located on the upper side until the hook head is abutted against the upper lower steel bar, the hook head on the upper transverse steel bar is directly below the upper transverse steel bar, the scale plate is fixed on the port of the transverse bridge through hole and an upper transverse steel bar is passed through the gap, the hoop is fixed on an upper transverse steel bar and the comparison rod is directly below the upper transverse steel bar, the hoop is spaced apart from the scale plate, the upper transverse steel bar is rotated in one direction until the comparison rod is located between the near gap side reference line and the far gap side reference line of the reference line group below the gap, an upper transverse steel bar is pushed inward to the limit position so that the hook head is on the upper side higher lower longitudinal steel bar, an upper transverse steel bar is rotated in the other direction until the comparison rod is located directly below the upper transverse steel bar so that the hook head of an upper transverse steel bar is hooked in the lower limit groove, the hoop is removed from an upper transverse steel bar and the comparison plate is removed from the transverse bridge through hole; The transverse steel bar is inserted from the side where the lower longitudinal steel bar is located on the upper side until the hook head is in contact with the lower steel bar on the upper side, and the hook head on the other upper transverse steel bar is directly below the other upper transverse steel bar. The scale plate is rotated 180° to fix one upper transverse steel bar and then fixed on the port of the cross-bridge through hole, so that the other upper transverse steel bar is passed through the gap, the hoop is fixed on the other upper transverse steel bar and the comparison rod is directly below the other upper transverse steel bar, the hoop is spaced apart from the scale plate, the upper transverse steel bar is rotated in one direction until the comparison rod is located between the near-gap side reference line and the far-gap side reference line of the reference line group below the gap, the other upper transverse steel bar is pushed inward to the limit position so that the hook head is on the upper side higher lower longitudinal steel bar, the upper transverse steel bar is rotated in the other direction until the comparison rod is located directly above the upper transverse steel bar so that the hook head of the other upper transverse steel bar is hooked in the upper limit groove, the hoop is removed from the other upper transverse steel bar and the comparison plate is removed from the cross-bridge through hole. Insert two tie rods into two exhaust channels from one end of the transverse bridge through hole in a cutting knife-like manner, and set an isolation membrane sleeve on two upper transverse steel bars and two tie rods; insert the other two tie rods into two exhaust channels from the other end of the transverse bridge through hole in a cutting knife-like manner, and set another isolation membrane sleeve on two upper transverse steel bars and two tie rods. The cutter is located outside the inner end of the isolation membrane sleeve. When pouring the transverse diaphragm concrete, the concrete flows into the transverse bridge through hole from between the isolation membrane sleeve and the transverse bridge through hole. As the concrete in the transverse bridge through hole flows out, the tie rod is pulled out synchronously. The cutter is always located inside the concrete, so that the cutter cuts the isolation membrane sleeve and discharges the concrete, which increases the exhaust effect and improves the density of the concrete in the transverse bridge through hole. After the pouring is completed, the two ends of the upper transverse steel bar are connected to the two ends of the power supply to generate a short circuit and heat up to melt the isolation membrane sleeve, thereby avoiding the membrane sleeve causing poor pouring effect of concrete and upper transverse steel bars.
Claims
1. A T-beam diaphragm thick steel bar positioning device, the T-beam comprises an intermediate beam extending along the longitudinal bridge direction and a top beam connected to the upper end of the intermediate amount, the top beam outputs the intermediate beam along the transverse bridge direction on both sides, a plurality of diaphragms distributed along the longitudinal bridge direction are arranged on both sides of the transverse bridge direction of the intermediate beam, the intermediate beam comprises an intermediate beam steel bar skeleton and intermediate beam concrete cast in the intermediate beam steel bar skeleton, the diaphragm comprises a diaphragm steel bar skeleton and diaphragm concrete cast in the diaphragm steel bar skeleton, the diaphragm steel bar skeleton is connected with the intermediate beam steel bar, the intermediate beam concrete is cast with the diaphragm concrete, the diaphragms located on both sides of the intermediate beam are aligned one by one, and it is characterized in that It also includes a diaphragm casting mold for casting the diaphragms one by one, the diaphragm steel bar skeleton includes a plurality of lower transverse steel bars extending along the transverse direction of the bridge, one ends of the lower transverse steel bars of the diaphragms located on both sides of the middle beam and aligned are connected together, and the other ends extend out of the diaphragm casting mold, the diaphragm casting mold is provided with a lower transverse steel bar positioning mechanism, the lower transverse steel bar positioning mechanism includes a fixed connecting plate, a movable connecting plate and a threaded tensioning rod with one end fixed to the fixed connecting plate, the fixed connecting plate is fixed to the diaphragm casting mold, the other end of the threaded tensioning rod passes through the movable connecting plate and is threadedly connected to a locking nut, and the movable connecting plate is provided with a plurality of positioning tubes.
2. A T-beam transverse diaphragm thick steel bar positioning device according to claim 1, characterized in that: A connecting thread sleeve is fixed on the fixed connecting plate, and the threaded tensioning rod is threadedly connected in the connecting thread sleeve and fixed together with the fixed connecting plate.
3. A T-beam transverse diaphragm thick steel bar positioning device according to claim 1, characterized in that: The transverse diaphragm reinforcement skeleton includes a plurality of upper transverse reinforcements extending in the transverse direction of the bridge, and the upper transverse reinforcements of the transverse diaphragms located on both sides of the middle beam and aligned are connected together.
4. A T-beam transverse diaphragm thick steel bar positioning device according to claim 3, characterized in that: The middle beam is cast with a transverse through hole for the upper transverse reinforcement to pass through, and the transverse diaphragm concrete is cast into the transverse through hole and cast together with the middle beam concrete.
5. A T-beam transverse diaphragm thick steel bar positioning device according to claim 4, characterized in that: The intermediate beam steel bar skeleton includes two lower longitudinal steel bars exposed in the lower side of the transverse bridge through hole and extending along the longitudinal bridge direction, a lower limit groove is formed between the two lower longitudinal steel bars, and the upper transverse steel bar is provided with a hook head which passes through the transverse bridge through hole and then hooks into the lower limit groove.
6. A T-beam transverse diaphragm thick steel bar positioning device according to claim 5, characterized in that: It also includes an isolation membrane sleeve, and two upper transverse steel bars are inserted into a through hole of the cross bridge. The two upper transverse steel bars can be inserted into the isolation membrane sleeve at the same time. Two exhaust channels are surrounded between the upper transverse steel bars and the isolation membrane sleeve. A pull rod is inserted into the exhaust channel, and a cutting knife for cutting the isolation membrane sleeve is provided at the inner end of the pull rod.
7. A T-beam transverse diaphragm thick steel bar positioning device according to claim 6, characterized in that: The intermediate beam steel bar skeleton also includes two upper longitudinal steel bars exposed on the upper side of the transverse bridge through hole and extending along the longitudinal bridge direction. An upper limit groove is formed between the two upper longitudinal steel bars. The lower hook head on one upper transverse steel bar is hooked into the lower limit groove, and the lower hook head on the other upper transverse steel bar is hooked into the upper limit groove.
8. A T-beam transverse diaphragm thick steel bar positioning device according to claim 7, characterized in that: It also includes a steel bar assembly locator, one of the two lower longitudinal steel bars is positioned beyond the other lower longitudinal steel bar in the lower longitudinal direction, the steel bar assembly locator includes a clamp for fixing on the upper transverse steel bar, a comparison rod connected to the clamp and a scale plate provided with an elastic connecting seat, the elastic connecting seat is used to insert into the transverse through hole to fix the scale plate at the end of the transverse through hole, the scale plate is provided with a limiting notch for the upper transverse steel bar to pass through and two groups of reference line groups located on the upper and lower sides of the limiting notch, the reference line group including a near-notch side reference line and a far-notch side reference line; when the scale plate is fixed in the transverse through hole through the elastic connecting seat, the near-notch side reference line in the lower reference line group is located on the same horizontal plane as the highest point of the lower longitudinal steel bar that is higher on the upper side, and the far-notch side reference line is located on the same horizontal plane as the highest point of the lower longitudinal steel bar that is lower on the upper side.
9. A T-beam transverse diaphragm thick steel bar positioning device according to claim 4, 5, 6, 7 or 8, characterized in that: It also includes a diaphragm casting mold for casting the diaphragm, the diaphragm casting mold includes a bottom mold, two side molds distributed along the longitudinal direction of the bridge and connected to the bottom mold at the lower ends, and an end mold connecting one ends of the two side molds together, a positioning through hole is provided on the inner surface of the end mold, and the upper transverse steel bar is inserted into the positioning through hole.
10. A T-beam transverse diaphragm thick steel bar positioning device according to claim 9, characterized in that: A convex column is fixedly connected to the inner surface of the end template, the positioning through hole passes through the convex column, the upper transverse steel bar is only located in the convex column, and the end face of the upper transverse steel bar is more than 2 cm away from the inner surface of the end template.
Citation Information
Cited By
T-beam diaphragm plate thick steel bar installation method
CN118127928A