Post-cast strip beam different-strength-grade concrete intercepting, separating and reinforcing construction device
By designing a heavier -level concrete interception division reinforcement construction device for high -rise construction of construction after high -rise buildings, the problem of difficult to effectively intercept and separate the intensity level concrete in the existing technology, and achieve more efficient and higher quality Construction effect.
Patent Information
- Application Number
- CN202420235190.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-31
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-01-31
AI Technical Summary
In the construction of post-pouring strips of high-rise buildings, it is difficult to effectively intercept and separate concrete of different strength grades, resulting in serious phenomena such as honeycombs, slurry leakage, and staggered joints.
Design a rear -pouring beam different strength grade concrete intercepting separation and reinforcement construction device, including lower beams, lower row longitudinal tendons, upper beams and upper vertical tendons. Interception and separation.
This device can strengthen the back lin of the wire mesh, reduce the deformation of the concrete shock of the wire mesh, effectively solve the problem of slurry problems on the side and ground, improve the construction efficiency, simplify the construction steps, improve the quality of construction, and save labor costs.
Smart Images

Figure CN222414059U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a post-cast belt beam with different strength grade concrete interception, separation and reinforcement construction device. Background Art
[0002] According to 3.4.13 of the Technical Code for Concrete Structures of High-Rise Buildings JGJ3-2010, the concrete of the post-casting strip should be poured after 45 days; 5.2.2 of the Technical Code for Waterproofing of Underground Engineering GB50108-2008 stipulates that the post-casting strip should be constructed after the concrete age on both sides reaches 42 days; the construction of the post-casting strip of high-rise buildings should be carried out according to the prescribed time. Therefore, during the construction of the main structure, the post-casting strip needs to be reserved first and poured in batches, which requires blocking on both sides of the post-casting strip and taking separation measures on the side of the post-casting strip beam.
[0003] According to previous construction experience, the interception measures for the post-cast joints of the basement top slab beams are usually to use wire mesh tied to the beam stirrups at the junction of concrete of different strength grades in the post-cast joints of the beams to intercept and separate the concrete of different strength grades in the post-cast joints of the beams. Often the interception parts are not reinforced in place, resulting in serious phenomena such as honeycombs, rough surfaces, leakage, and misalignment. Utility Model Content
[0004] The utility model aims to provide a post-cast strip beam with different strength grade concrete interception, separation and reinforcement construction device to overcome the above-mentioned defects in the prior art.
[0005] A post-cast strip beam with different strength grade concrete interception, separation and reinforcement construction device comprises a lower cross beam, a lower row of longitudinal bars, an upper cross beam and an upper row of longitudinal bars, the lower cross beam is sleeved with a plurality of sleeves 1, the bottom of each sleeve 1 is provided with a lower row of longitudinal bars, both ends of the upper cross beam are sleeved with sleeves 2 respectively, the bottom of the sleeves 2 is provided with an upper row of longitudinal bars, and the lower end of each upper row of longitudinal bars is provided with a sleeve 3 sleeved on the lower cross beam.
[0006] Preferably, the number of the sleeves 1 is nine.
[0007] Preferably, the lower row of longitudinal ribs is a "Z"-shaped structure.
[0008] Preferably, the upper crossbeam, the lower crossbeam, the upper row of longitudinal bars and the lower row of longitudinal bars are all threaded steel bars with a diameter of 14 mm.
[0009] Preferably, the sleeve one, sleeve two and sleeve three are all DN20 galvanized steel pipes with a length of 3 cm.
[0010] The utility model has the following advantages:
[0011] 1. When the utility model is used, the wire mesh is first tied to the beam reinforcement, and then the lower row of longitudinal reinforcement of the device is inserted. The function of the device is to strengthen the backing of the wire mesh, reduce the deformation of the wire mesh due to the impact of concrete, and better solve the problem of leakage on the side and ground. It is easy to disassemble and the disassembly time can be controlled within one minute.
[0012] 2. Through design optimization and reasonable construction, the construction efficiency of interception measures in the core area of the beam post-cast strip has been greatly improved, the construction steps have been simplified, and the construction quality has been improved. The concrete interception tools of different strength grades in the core area of the beam post-cast strip have greatly improved the construction efficiency of the basement of the main building, avoiding the trouble of roughening the post-cast strip and re-supporting the formwork in the later stage, and saving a lot of labor costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the utility model.
[0014] Figure 2 It is a front view of the utility model.
[0015] Figure 3 It is a structural schematic diagram of the utility model when in use.
[0016] Among them: 1. Lower cross beam; 2. Sleeve one; 3. Lower row of longitudinal reinforcement; 4. Upper cross beam; 5. Sleeve two; 6. Upper row of longitudinal reinforcement; 7. Sleeve three. DETAILED DESCRIPTION
[0017] The specific implementation methods of the utility model are further explained in detail below by describing the embodiments with reference to the accompanying drawings, so as to help those skilled in the art to have a more complete, accurate and in-depth understanding of the concept and technical solution of the utility model.
[0018] like Figure 1-3 As shown, the utility model provides a post-cast belt beam with different strength grade concrete interception and separation reinforcement construction device, comprising a lower cross beam 1, a lower row of longitudinal bars 3, an upper cross beam 4 and an upper row of longitudinal bars 6, wherein the lower cross beam 1 is sleeved with a plurality of sleeves 2, the number of the sleeves 2 is nine, and the bottom of each sleeve 2 is provided with a lower row of longitudinal bars 3, and the lower row of longitudinal bars 3 is a "Z"-shaped structure;
[0019] The two ends of the upper cross beam 4 are respectively sleeved with a second sleeve 5, the bottom of the second sleeve 5 is provided with an upper row of longitudinal ribs 6, and the lower end of each upper row of longitudinal ribs 6 is provided with a third sleeve 7 sleeved on the lower cross beam 1;
[0020] It should be noted that the upper cross beam 4, the lower cross beam 1, the upper row of longitudinal bars 6 and the lower row of longitudinal bars 3 are all threaded steel bars with a diameter of 14 mm.
[0021] In addition, the sleeve 1 2 , sleeve 2 5 and sleeve 3 7 are all DN20 galvanized steel pipes with a length of 3 cm. The sleeve 1 2 , sleeve 2 5 and sleeve 3 7 can be slid on the lower beam 1 and the upper beam 4 to adjust their positions.
[0022] Specific implementation and principle:
[0023] When the utility model is actually applied, the wire mesh is first tied to the beam reinforcement, and then the sleeve 2 on the lower cross beam 1 is moved to move the lower row of longitudinal reinforcement 3 to a suitable position, and then the lower row of longitudinal reinforcement 3 is respectively inserted into different positions of the beam reinforcement, and water-stop steel plates are welded in the beam reinforcement and on the sides of the lower row of longitudinal reinforcement 3, and finally the core area of the beam post-cast strip is poured with concrete. Through this device, the backing of the wire mesh can be strengthened, the deformation of the wire mesh caused by the impact of concrete can be reduced, and the problem of leakage on the side and the ground can be better solved. It is also easy to disassemble, and the disassembly time can be controlled within one minute, which greatly improves the construction efficiency, avoids the trouble of roughening the post-cast strip and re-supporting the formwork in the later stage, and saves a lot of labor costs.
[0024] The utility model is described above by way of example in conjunction with the accompanying drawings. It is obvious that the specific implementation of the utility model is not limited to the above-mentioned method. As long as various non-substantial improvements are made using the concept and technical solution of the utility model, or the concept and technical solution of the utility model are directly applied to other occasions without improvement, they are all within the protection scope of the utility model.
Claims
1. A post-cast strip beam with different strength grade concrete interception, separation and reinforcement construction device, characterized in that: The invention comprises a lower cross beam (1), a lower row of longitudinal bars (3), an upper cross beam (4) and an upper row of longitudinal bars (6); the lower cross beam (1) is sleeved with a plurality of sleeves (2); the bottom of each sleeve (2) is provided with a lower row of longitudinal bars (3); both ends of the upper cross beam (4) are sleeved with sleeves (5); the bottom of each sleeve (5) is provided with an upper row of longitudinal bars (6); and the lower end of each upper row of longitudinal bars (6) is provided with a sleeve (7) sleeved on the lower cross beam (1).
2. According to claim 1, a post-cast strip beam different strength grade concrete interception and separation reinforcement construction device is characterized in that: The number of the sleeves one (2) is nine.
3. The device for intercepting, separating and reinforcing the post-cast strip beam with different strength grades of concrete according to claim 1 is characterized in that: The lower row of longitudinal ribs (3) is a "Z"-shaped structure.
4. The device for intercepting, separating and reinforcing the post-cast strip beam with different strength grades of concrete according to claim 1 is characterized in that: The upper crossbeam (4), the lower crossbeam (1), the upper row of longitudinal bars (6) and the lower row of longitudinal bars (3) are all threaded steel bars with a diameter of 14 mm.
5. The device for intercepting, separating and reinforcing the post-cast strip beam with different strength grades of concrete according to claim 1 is characterized in that: The sleeve one (2), sleeve two (5) and sleeve three (7) are all DN20 galvanized steel pipes with a length of 3 cm.