Mounting structure of embedded base of horizontal tubular pump
By designing a horizontal flow pump embedded base installation structure including anchor hook, flower basket bolt and adjustment hose, the problems of complex installation, inability to adjust the position and not firmly fixed in the prior art are solved, and the installation is simplified. , precise positioning and firm fixing effect.
Patent Information
- Application Number
- CN202421099157.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-20
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2034-05-20
AI Technical Summary
The installation structure of the existing horizontal flow pump is complex and difficult to install, cannot be precisely adjusted, and is not fixed firmly, resulting in easy displacement during the pouring process.
An installation structure including an embedded base and a reserved installation port is designed. The reserved installation port penetrates the floor slab of the pump room. The outer wall of the embedded base is equipped with anchor hooks and bolts connected to the flower basket. A support block and adjustment horn are provided at the bottom. The height of the basket bolts and adjust the hose achieves a fine position and is fixed by the second phase concrete to ensure stability.
The installation process of the embedded base is simplified, the installation difficulty is reduced, and the function of fine-tuning position is realized, ensuring the firm fixation of the embedded base is avoided, and the risk of displacement during the pouring process is avoided.
Smart Images

Figure CN222456247U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of large-scale water conservancy projects, in particular to an installation structure of a pre-buried base of a horizontal tubular pump. Background Art
[0002] The existing embedded base installation structure is as follows Figure 1 Described, it comprises a pre-embedded base 1 and a reserved installation opening 2, the reserved installation opening 2 is opened in the pump room wall 3 cast by prefabricated concrete, the pre-embedded base 1 is installed in the reserved installation opening 2, the pre-embedded base 1 is a truncated cone-shaped cylinder, and the pump room wall 3 is cast with protruding steel bars, and the protruding ends of the protruding steel bars extend into the reserved installation opening 2; a circle of anchor bolts 4 are evenly arranged on the outer wall of the pre-embedded base 1 through bolt holes, and the anchor bolts 4 are respectively welded to the protruding steel bars. After the pre-embedded base 1 and the protruding steel bars are welded, they are fixed in the reserved installation opening 2 by pouring the second phase of concrete.
[0003] This embedded seat installation structure requires the embedded base to be hoisted from the horizontal direction and pushed horizontally into the reserved installation opening when installing the embedded base. The hoisting installation is difficult, and the installation position cannot be fine-tuned after hoisting to the specified position. The bottom of the embedded base is an arc, which is easy to roll during installation, resulting in inconvenience in installation and adjustment. There is a gap between the bolt holes of the anchor bolts and the embedded base, which is easy to loosen. Therefore, it is necessary to first fix a circle of anchor bolts in the reserved installation opening by pouring concrete or welding protruding steel bars, and then install the embedded base on the anchor bolts, resulting in a complicated and difficult installation process. Before pouring the second phase of concrete, the embedded base was only fixed by welding the protruding steel bars, which was not firmly fixed. During the pouring of the second phase of concrete, the embedded base was prone to displacement. Summary of the invention
[0004] In view of the shortcomings of the existing installation structure of the embedded base of the horizontal cross-flow pump, such as the complex and difficult installation process, the inability to fine-tune the position, and the loose fixation, which causes the embedded base to be displaced during the pouring process, the utility model provides an installation structure of the embedded base of the horizontal cross-flow pump, which is easy to install, can fine-tune the position, is firmly fixed, and will not be displaced during the pouring process.
[0005] A mounting structure for a pre-embedded base of a horizontal through-flow pump, comprising a pre-embedded base and a reserved mounting opening, wherein the reserved mounting opening is opened in a pump room wall cast with prefabricated concrete, the pre-embedded base is mounted in the reserved mounting opening, the pre-embedded base is a truncated cone-shaped cylinder, an outwardly extending steel bar is cast in the pump room wall, and the extended end of the outwardly extending steel bar extends into the reserved mounting opening, characterized in that: the top of the reserved mounting opening passes through the pump room floor, a circle of anchor hooks are evenly arranged on the outer wall of the pre-embedded base, four anchor hooks in four corners are respectively connected to one end of a basket bolt, the other end of the basket bolt is connected to the outwardly extending steel bar, the basket bolt is retractable, the anchor hooks are respectively welded to the outwardly extending steel bar, a support block with a flat bottom surface is arranged at the bottom of the pre-embedded base, an adjustment pad is installed under the support block, and after the pre-embedded base completes position adjustment and the outwardly extending steel bar is completed by welding, the second phase of concrete is poured to fix it in the reserved mounting opening.
[0006] It is further characterized by:
[0007] The adjusting washer comprises a base and a slider, one side of the base is an inclined surface, and the other side is provided with an adjusting bolt, the slider can slide on the inclined surface, and one end of the slider is threadedly connected to the adjusting bolt;
[0008] The embedded base is connected to the anchor hook by welding;
[0009] The cylinder wall of the embedded base is provided with a plurality of concrete exhaust holes, and sealing covers are welded to the concrete exhaust ports after the second phase concrete pouring is completed.
[0010] In the above structure of the utility model, the reserved installation opening is connected with the pump room floor, and the embedded base can be vertically hoisted into the reserved installation opening, avoiding the lateral movement and pushing of the embedded base, reducing the difficulty of hoisting and installation, and simplifying the installation process. A support block with a flat bottom surface is provided at the bottom of the embedded base to prevent the embedded base from rolling during the installation process, thereby simplifying the installation process from the perspective of easy operation. The anchor hook is directly welded to the embedded base, and there is no need to reinforce each anchor hook separately, which further simplifies the installation process. The position of the embedded base can be fine-tuned by adjusting the length of the basket bolt and the height of the adjustment shim. The basket bolt can also play a tightening and fixing role, so that the embedded base is firmly fixed to ensure that the embedded base does not move when pouring the second phase concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a structural schematic diagram of the prior art;
[0012] Figure 2 It is a schematic diagram of the structure of the utility model;
[0013] Figure 3 for Figure 2 Schematic diagram of the Q direction;
[0014] Figure 4 This is a detailed schematic diagram of the bottom of the embedded base;
[0015] Figure 5 This is a schematic diagram of the structure of the adjustment pad. DETAILED DESCRIPTION
[0016] See Figures 2 to 4 , an installation structure of a pre-embedded base of a horizontal through-flow pump, which includes a pre-embedded base 1 and a reserved installation opening 2. The reserved installation opening 2 is opened in a pump room wall 3 cast with prefabricated concrete. The pre-embedded base 1 is installed in the reserved installation opening 2. The pre-embedded base 1 is a truncated cone-shaped cylinder. An extended steel bar 8 is cast in the pump room wall 3. The extended end of the extended steel bar 8 extends into the reserved installation opening 2. The top of the reserved installation opening 2 passes through the pump room floor. The pre-embedded base 1 can be vertically hoisted into the reserved installation opening 2, avoiding the lateral movement and pushing of the pre-embedded base 1, reducing the difficulty of hoisting and installation, and simplifying the installation process. A circle of anchor hooks 5 are evenly welded on the outer wall of the pre-embedded base 1. There are 12 anchor hooks 5 in the figure. After welding, there is no need to reinforce each anchor hook 5 separately, which further simplifies the installation process. The four anchor hooks 5 at the four corners are respectively connected to one end of the basket bolt 9, and the other end of the basket bolt 9 is connected to the protruding steel bar 8. The basket bolt 9 is retractable, and the position of the embedded base 1 can be fine-tuned by adjusting the length of the basket bolt 9. After the basket bolt 9 is tightened, it can also play a tightening and fixing role to ensure that the embedded base 1 does not move when pouring the second phase concrete.
[0017] The anchor hooks 5 are welded with the protruding steel bars 8 respectively. The number and direction of the protruding steel bars 8 welded by the anchor hooks 5 are determined by the specific construction conditions. In the figure, one protruding steel bar 8 is welded for each anchor hook 5. A support block 7 with a flat bottom surface is provided at the bottom of the embedded base 1, and an adjustment pad 6 is installed under the support block; the support block can prevent the embedded base 1 from rolling, which is convenient for installation and position adjustment. After the embedded base 1 is adjusted and the protruding steel bars 8 are welded, they are fixed in the reserved installation opening 2 by pouring the second phase concrete.
[0018] See Figure 5 The adjustment shim 6 includes a base 61 and a slider 62. One side of the base 61 is an inclined surface, and the other side is equipped with an adjusting bolt 63. The slider 62 can slide on the inclined surface, and one end of the slider 62 is threadedly connected to the adjusting bolt 63. By turning the adjusting bolt 63, the position of the slider on the inclined surface can be changed, thereby changing the height of the adjustment shim 6 and fine-tuning the height position of the embedded base 1.
[0019] The cylinder wall of the embedded base 1 is provided with a plurality of concrete exhaust holes 10, which are convenient for exhausting when pouring the second phase concrete to ensure that the concrete is poured solidly. After the second phase concrete is poured, a sealing cover is welded on the concrete exhaust port 10 to ensure the sealing effect and prevent water seepage.
[0020] The installation process is as follows: vertically hoist the embedded base 1 from above the pump room into the reserved installation opening 2, support the support block 7 on the adjustment pad 6, fine-tune the adjustment bolt 63 to keep the center height of the embedded base 1 consistent with the center line height of the water pump unit, use the basket bolt 9 to connect the four anchor hooks 5 and the protruding steel bar 5 in the four corners, adjust the basket bolt 9 to make the center line of the embedded base 1 coincide with the center line of the water pump unit, and then weld each anchor hook 5 to the protruding steel bar 5. If the position of the embedded base 1 is offset during or after welding, continue to adjust the basket bolt 9. After completing the position adjustment and welding, pour the second phase of concrete to complete the installation.
Claims
1. A mounting structure for a pre-embedded base of a horizontal through-flow pump, comprising a pre-embedded base and a reserved mounting opening, wherein the reserved mounting opening is provided in a pump room wall cast with prefabricated concrete, wherein the pre-embedded base is mounted in the reserved mounting opening, wherein the pre-embedded base is a truncated cone-shaped cylinder, wherein an outrigger steel bar is cast in the pump room wall, wherein the outrigger end of the outrigger steel bar extends into the reserved mounting opening, wherein: The top of the reserved installation opening passes through the pump room floor, and a circle of anchor hooks are evenly arranged on the outer wall of the embedded base. The four anchor hooks at the four corners are respectively connected to one end of the basket bolts, and the other end of the basket bolts is connected to the protruding steel bars. The basket bolts are retractable, and the anchor hooks are welded to the protruding steel bars respectively. A support block with a flat bottom surface is provided at the bottom of the embedded base, and an adjustment shim is installed under the support block. After the embedded base completes position adjustment and the protruding steel bars are completed by welding, it is fixed in the reserved installation opening by pouring second-phase concrete.
2. The installation structure of the embedded base of a horizontal throughflow pump according to claim 1 is characterized in that: The adjusting washer comprises a base and a slider, one side of the base is an inclined surface, and the other side is provided with an adjusting bolt, the slider can slide on the inclined surface, and one end of the slider is threadedly connected to the adjusting bolt.
3. The installation structure of the embedded base of a horizontal throughflow pump according to claim 1 is characterized in that: The embedded base is connected to the anchor hook by welding.
4. The installation structure of the embedded base of a horizontal throughflow pump according to claim 1 is characterized in that: The cylinder wall of the embedded base is provided with a plurality of concrete exhaust holes.