Battery powder conveying system and battery production line
Through the design and isolation of material preparation and storage workshop, combined with feeder, vacuum feeder and automatic guide vehicle and other technologies, the workshop pollution and space occupation problems caused by powder conveying in the lithium battery production line are solved, achieving high efficiency and safety powder conveying system.
Patent Information
- Application Number
- CN202323270045.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-01
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2033-12-01
AI Technical Summary
In the existing lithium battery production line, the powder conveying process leads to pollution in the workshop, the number of unpacking stations and metering chambers is large, and the space is occupied, and the positive pressure conveying of auxiliary materials has the risk of leakage and high energy consumption.
A battery powder conveying system was designed. By setting up isolation between the material preparation workshop and the material storage workshop, the powder feeding process is located in the material preparation workshop, and dust does not contaminate other areas. The system includes an unpacking station, an unpacking temporary storage bin, a main and auxiliary material metering bin, a feeder, a vacuum loader and a transport mechanism, which reduces the number of understanding of the packaging station and metering bin, and uses vacuum loading and automatic guide vehicles. and other technologies have improved the efficiency and safety of conveying.
It effectively avoids dust pollution in most areas of the workshop, reduces the number of understanding stations and metering bins, reduces the space occupied in the workshop, improves the conveying efficiency and safety, and reduces energy consumption.
Smart Images

Figure CN222462959U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of battery production equipment, and in particular to a battery powder conveying system and a battery production line. Background Art
[0002] At present, the layout of lithium battery production plant is a two-story structure: the first floor is the mixing workshop, and the second floor is the powder workshop. The powder material conveying process includes conveying the main materials and auxiliary materials in the powder workshop to the mixer in the mixing workshop.
[0003] The operating procedures for main material transportation are as follows: the main material unpacking station and the main material metering bin are located directly above the mixer and are generally configured in a "one-to-one" and "one-to-two" manner with the mixer. The powder material ton bag pallet is manually transferred to the bottom of the overhead crane by a forklift, and the employee connects the overhead crane to the ton bag and lifts the ton bag to the steel platform unpacking station on the upper part of the second-floor material distribution workshop to unpack the ton bag, and uses gravity feeding to feed the material in the ton bag to the main material metering bin for storage. After the central control system issues a demand for pulping and feeding the main material, the powder system sends a request signal to the mixer. After the employee confirms that the mixer status meets the requirements, he can click the allow button to reply to the allow signal, the valve of the feeding pipe opens, and the feeding screw under the main material metering bin starts to feed powder to the mixer. The synchronous metering scale starts weighing, and after reaching the preset slow weighing value, the screw slows down and weighs slowly until it reaches the set powder feeding weight, stops, and returns a completion signal.
[0004] The operating procedures for auxiliary material transportation are as follows: auxiliary materials generally have 1 to 3 categories according to the formula, and different first-level metering tanks are designed according to the types of auxiliary materials, and the first-level metering sending tank is designed according to the configuration of "one to many" mixers. The bagged powder is manually transferred to the suction room and the material is transported to the auxiliary material first-level metering tank by negative pressure feeding. After the central control system issues a demand for pulping auxiliary materials, the powder system sends a request signal to the mixer. After the employee confirms that the mixer status meets the requirements, he can click the allow button to reply to the allow signal. The valve of the material discharge pipe opens, and the feeding screw under the first-level metering bin of the auxiliary materials required by the formula starts to feed powder to the mixer. The synchronous metering scale starts weighing. After reaching the preset slow weighing value, the screw slows down and weighs slowly until it reaches the set powder weight and stops. After the metering of different types of auxiliary materials is completed, they are transported to the designated mixer by positive pressure sending from the sending tank.
[0005] The operations of unpacking and feeding powder and feeding into the mixer are both located in the same space. The partial leakage of dust during feeding can easily directly pollute the workshop environment. Since there are strict requirements on the inclination angle of the gravity feeding pipeline, according to the current plan, at least one main material metering bin is configured to be connected to two mixers at the same time. For lithium batteries with dual main material formulas, the powder workshop needs to densely arrange a large number of main material metering tanks and corresponding unpacking stations, which greatly increases the investment cost; the utilization rate of the unpacking station is low, and employees need to frequently transfer ton bags to unpacking stations in different locations, which is labor-intensive. The powder feeding time and rhythm of the materials are controlled by the employees. If the feeding is not timely, it will affect the production line capacity. There is a risk of leakage when the auxiliary materials are sent to the mixer using positive pressure conveying, and the energy consumption is high. Utility Model Content
[0006] The purpose of this application is to provide a battery powder conveying system and a battery production line, which can avoid pollution to most areas of the workshop, and can greatly reduce the number of unpacking stations and metering bins, and reduce the space occupied by the workshop.
[0007] The present application provides a battery powder conveying system, including a material preparation workshop, a material storage workshop and a transport mechanism;
[0008] The material preparation workshop and the material storage workshop are isolated from each other; the material preparation workshop is provided with an unpacking station and an unpacking temporary storage warehouse located below the unpacking station; the material storage workshop is provided with a main material metering warehouse; a first connecting pipe is provided between the unpacking temporary storage warehouse and the main material metering warehouse;
[0009] The material storage workshop is also provided with a material unloading station, and the material unloading station is connected to the mixer in an on-off manner; the transport mechanism is used to transport the main material of the main material metering bin to the material unloading station.
[0010] In the above technical solution, further, the first communicating pipeline includes a feeder, a first valve, a first pipeline and a first vacuum feeder;
[0011] The feeder and the first vacuum loader are both connected to the first pipeline; the feeder is arranged at the bottom outlet of the unpacking temporary storage bin, the first vacuum loader is arranged at the entrance of the main material metering bin, and the first valve is installed on the first pipeline.
[0012] In the above technical solution, further, the material preparation workshop is provided with an auxiliary material suction room, the material storage workshop is provided with an auxiliary material metering bin, and a second connecting pipe is provided between the auxiliary material suction room and the auxiliary material metering bin;
[0013] The transport mechanism is used to transport the auxiliary materials in the auxiliary material metering bin to the unloading station.
[0014] In the above technical solution, further, the second communicating pipeline includes a second valve, a second pipeline and a second vacuum feeder;
[0015] The second pipeline is connected to the outlet of the auxiliary material suction room, the second vacuum loader is connected to the second pipeline, and the second vacuum loader is arranged at the inlet of the auxiliary material metering bin, and the second valve is installed on the second pipeline.
[0016] In the above technical solution, further, the transport mechanism includes a transport vehicle and a plurality of transfer tanks, and any of the transfer tanks can be detachably mounted on the transport vehicle;
[0017] The transfer tank is used to load the main material and / or the auxiliary material;
[0018] The unloading station is provided with a unloading docking device and a material dropping pipe, and the unloading docking device is connected with the mixer through the material dropping pipe; the transport vehicle is used to transport the transfer tank to the unloading station so that the transfer tank is connected with the unloading docking device.
[0019] In the above technical solution, further, the transport mechanism also includes a batching vehicle, and any of the transfer tanks can be detachably mounted on the batching vehicle;
[0020] The main material metering bin and the auxiliary material metering bin are both provided with a batching docking device, and the batching vehicle equipped with the transfer material tank moves along a preset path so that the transfer material tank is connected to any of the batching docking devices;
[0021] The transfer tank can be transferred between the batching vehicle and the transport vehicle.
[0022] In the above technical solution, further, the carrier vehicle is an automatic guided vehicle, and the batching vehicle is a rail-guided vehicle.
[0023] In the above technical solution, further, the material preparation workshop is also provided with a ton bag feeding mechanism;
[0024] The ton bag loading mechanism includes a loading vehicle, an elevator and a conveyor line;
[0025] The elevator can dock with the loading vehicle to lift the pallet carrying the ton package to the height of the unpacking station;
[0026] The elevator can be docked with the conveyor line so that the conveyor line transports the pallet to the side of the unpacking station.
[0027] In the above technical solution, further, the ton-bag feeding mechanism also includes a traveling crane, and the traveling crane is detachably connected to the ton-bag to transport the ton-bag on the conveyor line to the upper part of the unpacking station.
[0028] The present application also provides a battery production line, including the battery powder conveying system described in the above scheme.
[0029] Compared with the prior art, the beneficial effects of this application are:
[0030] The battery powder conveying system provided by the present application isolates the material preparation workshop and the material storage workshop from each other, so that the powder feeding process is located in the material preparation workshop, and the generated dust only spreads in the independent space of the material preparation workshop, and will not pollute most of the rest of the workshop. In the material storage workshop, the transport mechanism transports the main material to the mixer according to the needs of the mixer. There is no need to set up a set of unpacking stations and metering bins above each mixer or every two mixers, which can also greatly reduce the number of the above-mentioned devices and reduce the occupation of the workshop space by the above-mentioned devices.
[0031] The present application also provides a battery production line, including the battery powder conveying system described in the above solution. Based on the above analysis, it can be seen that the battery production line also has the above beneficial effects, which will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] In order to more clearly illustrate the specific implementation methods of the present application or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0033] Figure 1 A schematic diagram of the front view of the battery powder conveying system provided in this application;
[0034] Figure 2 This is a schematic diagram of the top view of the battery powder conveying system provided in this application.
[0035] In the figure: 101- material preparation workshop; 102- material storage workshop; 103- unpacking station; 104- unpacking temporary storage warehouse; 105- main material metering warehouse; 106- ton bag; 107- mixer; 108- feeder; 109- first valve; 110- first pipeline; 111- first vacuum loader; 112- auxiliary material suction room; 113- auxiliary material metering warehouse; 114- second pipeline; 115- second vacuum loader; 116- carrier; 117- transfer tank; 118- unloading docking device; 119- material dropping pipeline; 120- batching vehicle; 121- batching docking device; 122- loading vehicle; 123- elevator; 124- conveyor line; 125- overhead crane. DETAILED DESCRIPTION
[0036] The technical solution of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application.
[0037] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present application. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0038] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0039] Embodiment 1
[0040] See also Figure 1 and Figure 2 As shown, the battery powder conveying system provided in the present application includes a material preparation workshop 101, a material storage workshop 102 and a transport mechanism.
[0041] The material preparation workshop 101 and the material storage workshop 102 are isolated from each other. The material preparation workshop 101 is provided with an unpacking station 103 and an unpacking temporary storage bin 104 located below the unpacking station 103, which is the unpacking area. When the powder ton bag 106 loaded with the main material is transported to the unpacking station 103, the unpacking station 103 can centrally unpack the powder ton bag 106 so that the main material falls into the unpacking temporary storage bin 104 for storage, that is, the powder feeding process is located in the material preparation workshop 101, and the generated dust only spreads in the independent space of the material preparation workshop 101, and will not pollute most other areas of the workshop.
[0042] The material storage workshop 102 is provided with a main material metering bin 105, and a first connecting pipe is provided between the unpacking temporary storage bin 104 and the main material metering bin 105, and the main material in the unpacking temporary storage bin 104 can be sent to the main material metering bin 105 for storage through the first connecting pipe. The main material dropping time is 180s shorter than the sending time. The unpacking temporary storage bin 104 is designed below the unpacking station 103, so that the dropping process and the sending process can be separated, which can improve the feeding efficiency.
[0043] When the central control system of the powder material dispatches work in combination with the production status of the mixer 107 and the work order task, a specific production of the mixer 107 can be formulated. When the formulated mixer 107 reaches the feeding conditions, the central control system determines whether the storage status of the main material metering bin 105 of the storage workshop 102 meets the formula requirements. If it does, it sends a task to the carrier to dispatch the carrier to the main material metering bin 105. The main material metering bin 105 can accurately weigh the main material and transport the preset amount of main material to the carrier. The carrier transports the main material to the unloading station set in the storage workshop 102. The unloading station is connected to the mixer 107 so that the main material loaded by the carrier can enter the mixer 107, and the mixer 107 can perform the mixing program. The overall coordination and dispatching by the central control system and the coordinated transportation by the logistics system can reduce the delay of the production plan caused by human intervention and improve production efficiency.
[0044] That is to say, in the material storage workshop 102, the transport mechanism transports the main material to the mixer 107 according to the needs of the mixer 107. It is not necessary to set up a set of unpacking station 103 and metering bin above each mixer 107 or every two mixers 107, which can also greatly reduce the number of the above devices and reduce the occupation of the workshop space by the above devices. Taking the single-line setting of 10 mixers 107 as an example (including 6 cathodes and 4 anodes), the number of metering bins configured for the dual main material powder system is reduced from 10 sets to 4 sets, which greatly saves the occupation of workshop space.
[0045] More specifically, the first connecting pipeline includes a feeder 108, a first valve 109, a first pipeline 110 and a first vacuum feeder 111. The feeder 108 and the first vacuum feeder 111 are both connected to the first pipeline 110. The feeder 108 is arranged at the bottom outlet of the unpacking temporary storage bin 104. The powder material can be accurately weighed by cooperating with the feeder 108 and the weighing scale of the unpacking temporary storage bin 104. The first vacuum feeder 111 is arranged at the entrance of the main material metering bin 105 so that the material is sucked into the main material metering bin 105, so as not to block the first pipeline 110. The first valve 109 is installed on the first pipeline 110 to realize the connection or shutoff of the first pipeline 110.
[0046] It should be noted that the type of main ingredients can be one or more, which is specifically set according to the actual formula. Correspondingly, the number of unpacking stations 103 for processing the main ingredients, the number of unpacking temporary storage bins 104, the number of first connecting pipes and the number of main ingredient metering bins 105 are set according to the type of main ingredients. Figure 1 and Figure 2 The device structure corresponding to the two main materials is shown in FIG.
[0047] In the optional solution of this embodiment, the material preparation workshop 101 is further provided with an auxiliary material suction room 112, which is used to suck bagged auxiliary materials. The material storage workshop 102 is provided with an auxiliary material metering bin 113, which is used to store and accurately weigh auxiliary materials, and a second connecting pipe is provided between the auxiliary material suction room 112 and the auxiliary material metering bin 113; the auxiliary materials sucked by the auxiliary material suction room 112 can be transported to the auxiliary material metering bin 113 for storage through the second connecting pipe.
[0048] When the central control system of the powder material combines the production status of the mixer 107 and the work order task for dispatching work, the specific production of the mixer 107 can be formulated. When the formulated mixer 107 meets the feeding conditions, the central control system determines whether the storage status of the auxiliary material metering bin 113 in the storage workshop 102 meets the formula requirements. If so, the task is sent to the transport mechanism to dispatch the transport mechanism to the auxiliary material metering bin 113. The auxiliary material metering bin 113 can accurately weigh the main material and transport a preset amount of auxiliary material to the transport mechanism. The transport mechanism transports the auxiliary material to the unloading station set up in the storage workshop 102. The unloading station is connected to the mixer 107 so that the auxiliary material loaded by the transport mechanism can enter the mixer 107, and the mixer 107 can execute the mixing program.
[0049] More specifically, the second communication pipeline includes a second valve, a second pipeline 114 and a second vacuum feeder 115. The second pipeline 114 is connected to the outlet of the auxiliary material suction room 112, and the second vacuum feeder 115 is connected to the second pipeline 114. The second vacuum feeder 115 is arranged at the entrance of the auxiliary material metering bin 113 so that the material is sucked into the auxiliary material metering bin 113, so as not to block the second pipeline 114. The second valve is installed on the second pipeline 114 to realize the connection or shutoff of the second pipeline 114.
[0050] In the optional solution of this embodiment, Figure 1 As shown, the transport mechanism includes a transport vehicle 116, a batching vehicle 120 and a plurality of transfer tanks 117, and any transfer tank 117 can be detachably mounted on the transport vehicle 116 and the batching vehicle 120. Specifically, the transport vehicle 116 is an automatic guided vehicle, i.e., AGV; the batching vehicle 120 is a rail-guided vehicle, i.e., RGV; and the transfer tank 117 is an IBC tank.
[0051] The specific batching process is as follows: when the central control system sends a task to the AGV scheduling system, the AGV scheduling system can schedule the AGV to transfer the IBC tank to the batching area equipped with the main material metering bin 105 and the auxiliary material metering bin 113. The batching area is equipped with RGV, and the AGV can transfer the IBC tank to the RGV. A batching docking device 121 is provided below the main material metering bin 105 and the auxiliary material metering bin 113. The batching docking device 121 includes a feeding screw and an automatic docking interface. The RGV can move along a preset path to accurately transplant the IBC tank to the bottom of the main material metering bin 105 and the auxiliary material metering bin 113, so that the IBC tank can be connected to the automatic docking interface of any batching docking device 121. After the feeding screw is started, the material can be accurately weighed and fed according to the formula, and the main material and auxiliary material can be distributed to the IBC tank in proportion.
[0052] After the batching process is completed, the RGV can transfer the IBC tank to the AGV, and the AGV transfers the IBC tank to the unloading station. The unloading station is equipped with a unloading docking device 118 and a material dropping pipe 119. The unloading docking device 118 is connected to the mixer 107 through the material dropping pipe 119. When the AGV transports the IBC tank to the top of the unloading station, the unloading docking device 118 can automatically dock with the IBC tank and initiate a unloading request signal to the mixer 107. The unloading will be carried out after the employee confirms the status of the mixer 107 and replies to the permission signal. After the unloading is completed, the AGV scheduling system will determine whether the IBC tank will be transferred to the IBC tank temporary storage area or the batching area to continue batching according to whether there are tasks queued up later.
[0053] Embodiment 2
[0054] The battery powder conveying system in the second embodiment is an improvement on the above embodiment, and the technical contents disclosed in the above embodiment will not be described repeatedly, and the contents disclosed in the above embodiment also belong to the contents disclosed in the second embodiment.
[0055] See also Figure 1 and Figure 2 As shown, in an optional scheme of this embodiment, the material preparation workshop 101 is also provided with a ton bag loading mechanism; the ton bag loading mechanism includes a loading vehicle 122, an elevator 123 and a conveyor line 124; the elevator 123 can be docked with the loading vehicle 122 to lift the pallet carrying the ton bag 106 to the height of the unpacking station 103; the elevator 123 can be docked with the conveyor line 124, so that the conveyor line 124 transports the pallet to the side of the unpacking station 103.
[0056] Specifically, before executing the batching process, the material preparation process needs to be executed first. The material preparation process is as follows: the powder central control system predicts in advance whether material preparation is needed based on the storage material levels of the main material metering bin 105 and the auxiliary material metering bin 113 in the batching area. If the storage weight has reached the material preparation warning level, the central control system initiates the material preparation demand, and the AGV scheduling system dispatches the AGV to transfer the designated ton bag pallet from the powder line side bin to the top of the elevator 123 in the unpacking area. The elevator 123 lifts the powder pallet to the conveyor line 124 flush with the unpacking station 103, and the conveyor line 124 transfers the ton bag 106 to the designated unpacking station 103. The ton bag 106 is transferred to the unpacking station 103 by automatic logistics. There is no need for manual assistance to transport the ton bag 106 below the unpacking station 103, which can reduce labor costs and reduce employee labor intensity.
[0057] Furthermore, the ton-bag loading mechanism also includes a traveling crane 125 , which is detachably connected to the ton-bag 106 to transport the ton-bag 106 on the conveyor line 124 to the upper part of the unpacking station 103 .
[0058] In this embodiment, the ton bag 106 can be transferred to the top of the unpacking station 103 by manually operating the overhead crane 125. The manual unpacking and blanking time is about 60 seconds, the negative pressure conveying speed is about 100kg / min, the weight of a single ton bag 106 is 400kg, and the conveying is completed in 240 seconds. The powder is temporarily stored in the unpacking temporary storage bin 104. After the manual unpacking and blanking is completed, the packaging materials of the ton bag 106 can be processed and prepared for the next ton bag 106 to be fed. At the same time, the unpacking temporary storage bin 104 sends the materials to the main material metering bin 105, which greatly improves the material preparation efficiency.
[0059] Embodiment 3
[0060] Embodiment 3 of the present application provides a battery production line, including a battery powder conveying system of any of the above embodiments, and thus has all the beneficial technical effects of the battery powder conveying system of any of the above embodiments, which will not be elaborated here.
[0061] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them; although the present application is described in detail with reference to the above embodiments, a person skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some or all of the technical features can be replaced by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present application. In addition, a person skilled in the art can understand that although some embodiments herein include certain features included in other embodiments but not other features, the combination of features of different embodiments means being within the scope of the present application and forming different embodiments.
Claims
1. A battery powder conveying system, characterized in that: It includes a material preparation workshop (101), a material storage workshop (102) and a transport mechanism; The material preparation workshop (101) and the material storage workshop (102) are isolated from each other; the material preparation workshop (101) is provided with an unpacking station (103) and an unpacking temporary storage warehouse (104) located below the unpacking station (103); the material storage workshop (102) is provided with a main material metering warehouse (105); a first connecting pipe is provided between the unpacking temporary storage warehouse (104) and the main material metering warehouse (105); The material storage workshop (102) is also provided with a material unloading station, and the material unloading station is connected to the mixer (107) in an on-off manner; the transport mechanism is used to transport the main material in the main material metering bin (105) to the material unloading station.
2. The battery powder conveying system according to claim 1, characterized in that: The first communicating pipeline comprises a feeder (108), a first valve (109), a first pipeline (110) and a first vacuum feeder (111); The feeder (108) and the first vacuum loader (111) are both connected to the first pipeline (110); the feeder (108) is arranged at the bottom outlet of the unpacking temporary storage bin (104), the first vacuum loader (111) is arranged at the inlet of the main material metering bin (105), and the first valve (109) is installed on the first pipeline (110).
3. The battery powder conveying system according to claim 1, characterized in that: The material preparation workshop (101) is provided with an auxiliary material suction room (112), the material storage workshop (102) is provided with an auxiliary material metering bin (113), and a second connecting pipe is provided between the auxiliary material suction room (112) and the auxiliary material metering bin (113); The transport mechanism is used to transport the auxiliary materials in the auxiliary material metering bin (113) to the unloading station.
4. The battery powder conveying system according to claim 3, characterized in that: The second communicating pipeline comprises a second valve, a second pipeline (114) and a second vacuum loader (115); The second pipeline (114) is connected to the outlet of the auxiliary material suction room (112), the second vacuum loader (115) is connected to the second pipeline (114), and the second vacuum loader (115) is arranged at the inlet of the auxiliary material metering bin (113), and the second valve is installed on the second pipeline (114).
5. The battery powder conveying system according to claim 3, characterized in that: The transport mechanism comprises a transport vehicle (116) and a plurality of transfer tanks (117), and any of the transfer tanks (117) can be detachably mounted on the transport vehicle (116); The transfer tank (117) is used to load the main material and / or the auxiliary material; The unloading station is provided with a unloading docking device (118) and a material dropping pipe (119), and the unloading docking device (118) is connected to the mixer (107) through the material dropping pipe (119); the transport vehicle (116) is used to transport the transfer tank (117) to the unloading station so that the transfer tank (117) is connected to the unloading docking device (118).
6. The battery powder conveying system according to claim 5, characterized in that: The transport mechanism further comprises a batching vehicle (120), and any of the transfer tanks (117) can be detachably mounted on the batching vehicle (120); The main material metering bin (105) and the auxiliary material metering bin (113) are both provided with a batching docking device (121), and the batching vehicle (120) equipped with the transfer material tank (117) moves along a preset path so that the transfer material tank (117) is connected to any of the batching docking devices (121); The transfer tank (117) can be transferred between the batching vehicle (120) and the carrier vehicle (116).
7. The battery powder conveying system according to claim 6, characterized in that: The carrier vehicle (116) is an automatic guided vehicle, and the batching vehicle (120) is a track-guided vehicle.
8. The battery powder conveying system according to claim 1, characterized in that: The material preparation workshop (101) is also provided with a ton bag loading mechanism; The ton bag loading mechanism comprises a loading vehicle (122), an elevator (123) and a conveyor line (124); The lifting machine (123) can dock with the loading vehicle (122) to lift the pallet carrying the ton bag (106) to the height of the unpacking station (103); The elevator (123) can be docked with the conveyor line (124) so that the conveyor line (124) can transport the pallet to the side of the unpacking station (103).
9. The battery powder conveying system according to claim 8, characterized in that: The ton bag loading mechanism also includes a traveling crane (125), which is detachably connected to the ton bag (106) to transport the ton bag (106) on the conveying line (124) to the upper part of the unpacking station (103).
10. A battery production line, characterized in that: The invention comprises a battery powder conveying system as claimed in any one of claims 1 to 9.