Bridge support leveling and mounting device
By using the leveling and installation device of telescopic sleeves and rotating gear devices in the installation of bridge support, the problem of inaccurate support installation in the prior art is solved, and the uniform force of the support and the safety of the bridge structure are achieved. promote.
Patent Information
- Application Number
- CN202323431857.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-15
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2033-12-15
AI Technical Summary
The prior art is difficult to achieve precise leveling and elevation control in the installation of bridge bearings, resulting in uneven force, short life and overall structural safety threats.
The bridge support leveling and installation device including telescopic sleeves, rotation and adjustment gear devices are adopted. Through the combination of frame structure, angle adjustment device, height adjustment device and locking device, it can adapt to different specifications of support to ensure leveling accuracy and simplicity of installation.
Accurate leveling and elevation control of the bearing are achieved, ensuring uniform stress on the bearing, extending the service life, and improving the safety of the overall structure of the bridge.
Smart Images

Figure CN222477202U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of bridge supports, and more specifically, relates to a bridge support leveling and installation device. Background Art
[0002] As an important part of the bridge structure, the bridge bearing is a connection point between the upper and lower structures of the bridge. It is also an important part that carries the safety and life of the bridge and cannot be replaced. Therefore, it is very important to ensure the accuracy of the bearing installation position and the accurate determination of the bearing elevation. With the increasing development of construction projects, the types and specifications of bridge bearings are gradually increasing, and the scale of construction is also gradually increasing. Therefore, it is very important to ensure the safety of bearing installation, the accuracy of position and the accuracy of elevation.
[0003] At present, there are no technical measures or means to accurately locate the bearings and their elevations at the construction sites. Usually, the bearings are installed at the position and elevation of cushion stones, and the position and elevation are controlled by steel bars. In the existing patent, a bridge bearing leveling wedge connection method 202110110488.3 includes the following steps: when prefabricating the bridge deck, the upper steel plate is embedded in the prefabricated bridge deck according to the bearing position in the design drawing, and the lower plane of the embedded upper steel plate is flush with the bottom surface of the prefabricated bridge deck, and the prefabricated pedestal bottom membrane does not need to be grooved; according to the wedge block size in the design drawing, the steel wedge block is customized to better meet the variable wedge block size and precision requirements; after the prefabricated bridge deck enters the beam storage area, the steel wedge block is spliced with the embedded upper steel plate; the steel wedge block is welded to the embedded upper steel plate on all sides; the upper steel plate, steel wedge block and welding point are rust-proofed, but this patent requires the steel wedge block to be customized according to the design drawing, and the customized steel wedge block cannot accurately level the bearing.
[0004] The above-mentioned prior art method of installing the bearing based on the position and elevation of the cushion stone may lead to inaccurate control of the bearing elevation due to the inaccurate control of the cushion stone elevation, resulting in insufficient contact between the bearing and the bridge beam and slab, causing uneven force on the bearing or the existence of emptying, seriously affecting the service life of the bearing and endangering the overall structural safety of the bridge. In the method of using steel bars to position and control the position and elevation, there will be certain errors in the processing and production of steel bars, resulting in the inability to accurately control the installation elevation of the bearing, and also causing waste of steel bar raw materials, which is uneconomical and cannot achieve accurate positioning and control. Therefore, it is of great significance to develop a leveling device and construction method for the installation of bearings that is easy to carry and can be used in a turnover manner. Utility Model Content
[0005] In view of the above defects or improvement needs of the prior art, the utility model provides a bridge bearing leveling and installation device and a construction method thereof. By adopting a telescopic sleeve, a rotating and adjusting gear device, it can be suitable for bearings of different specifications to ensure the accuracy of bearing leveling. At the same time, the installation and operation are simple and convenient, and can be used in rotation.
[0006] In order to achieve the above-mentioned object, according to the first aspect of the utility model, a bridge bearing leveling and installation device is provided.
[0007] A bridge support leveling and installation device, characterized in that it comprises: a frame structure, an angle adjustment device, a height adjustment device, and a locking device;
[0008] The frame structure is a polygonal frame structure composed of a plurality of rods;
[0009] There are multiple angle adjustment devices, which are respectively located at each corner point of the frame structure;
[0010] There are multiple height adjustment devices, which are respectively arranged at the end of each rod of the frame structure;
[0011] The height adjustment device comprises a gear shaft, a rotating shaft, a rotating gear, and a plate-shaped bearing frame; the rotating shaft is connected to the rotating gear and can drive the rotating gear to rotate; the rotating gear is in contact with the gear shaft and can drive the gear shaft to rise and fall; the height of the gear shaft can be fixed by the locking device;
[0012] The locking device is arranged around the rotating shaft.
[0013] The polygon is a triangle, a rectangle or a square.
[0014] The frame structure comprises a support outer shell portion and a support inner core portion;
[0015] The support shell part and the support inner core part cooperate with each other and are respectively connected with different angle adjustment devices; the support shell part and the support inner core part can be telescopic, and the support inner core part can be retracted into the support shell part.
[0016] The angle adjustment device comprises a rotating shaft;
[0017] The rotating shaft is arranged at each corner point of the frame structure, and respectively connects the support outer shell part and the support inner core part of two adjacent frame structures; the angle formed by the connected support outer shell part and the support inner core part can be changed.
[0018] The gear shaft is provided with an inverted L gear and a cylinder; the cylinder is provided with a scale, arranged inside the rotating shaft, and can be extended and retracted up and down inside the rotating shaft to adjust the height;
[0019] The rotating gear is arranged on a plate-shaped bearing frame inside the rotating shaft, the rotating shaft is fixedly connected to the intermediate shaft of the rotating gear, and the rotating gear is meshed with the inverted L gear.
[0020] The locking device comprises a latch;
[0021] The latch is arranged on a bearing plate of a plate-shaped bearing frame on which the rotating shaft is mounted, and can fix the rotating gear to determine the height of the height adjustment device.
[0022] According to a second aspect of the utility model, a construction method of a bridge support leveling and installation device is provided, comprising the following steps:
[0023] S100, device in place: adjust the size of the telescopic device, determine the positioning of the four corners of the device, and fix the position of the device;
[0024] Specifically, the support outer shell part 1 and the support inner core part 2 are pulled to adjust the sleeve length and device size of the telescopic device, the rotating shaft 3 is rotated to adjust the angle between adjacent telescopic device sleeves, and the device size is adjusted to meet the installation requirements of the support; and the positioning of the four corners of the device is determined by positioning measurement.
[0025] S200, support elevation control: according to the position positioning of the device, the elevations of the four corners of the support are calculated and positioned, and the device is fixed to the elevation position of the elevation positioning;
[0026] Specifically, according to the accurate positioning of the four corners of the device in step S100, the entire device is placed on the support pad 8, and the specific elevations of the four corners of the device during setting are calculated according to the elevations required by the support design; the rotating shaft 5 is twisted to drive the height of the gear shaft 4 to be adjusted, and the adjusted height is accurately judged by observing the scale on the gear shaft 4, so that the elevations of the four corners of the device are the same as the elevations required by the support design; after the gear shaft 4 reaches the height corresponding to the elevation value, the pin 6 is inserted to fix the rotating shaft to keep the gear shaft at a fixed height.
[0027] S300, support installation: based on the elevation value adjustment device, hoist the support, pour the support grouting material and consolidate it;
[0028] Specifically, if Figure 4 As shown, the device is placed on the support pedestal 8, and based on the elevation values of the four corners of the device support in step S200, the support is hoisted and the support 7 is placed on the gear shaft 4; the height of the gear shaft 4 is fine-tuned to make the entire device fully contact with the bridge beam and slab to ensure that the bridge support device is uniformly stressed; the support grouting material is poured into the telescopic device sleeve to connect the support pedestal 8 and the support 7, and the grouting material is consolidated to complete the leveling, fixation and installation of the bridge support.
[0029] S400, device disassembly and circulation: by adjusting the size of the device, the device can be taken out from the support and the size of the device can be reduced to facilitate carrying and multiple circulation use;
[0030] Specifically, after the support is fixed and stabilized in step S300, the rotating shaft 5 and the latch 6 are adjusted to lower the gear shaft 4, the size of the support shell part 1 and the support core part 2 are stretched to the maximum, and then the device is removed from the fixed support to complete the disassembly; after the support is taken out, the device is minimized by adjusting the support shell part 1, the support core part 2 and the rotating shaft 3 to facilitate carrying, storage and multiple turnover use.
[0031] In general, the above technical solutions conceived by the utility model can achieve the following beneficial effects compared with the prior art:
[0032] 1. The utility model can be installed on supports of different sizes by providing a telescopic device and a rotating device, thus achieving the purpose of the device being used cyclically;
[0033] 2. The utility model ensures the accuracy of the support installation position through precise positioning of the scale, solving the problem of inaccurate support installation position and elevation;
[0034] 3. The utility model ensures the accuracy of the support installation elevation by adjusting the height of the four angle gears, thereby ensuring that the support is fully in contact with the bridge beam and slab, ensuring that the support is evenly stressed, and giving full play to the role of the support to a great extent, solving the problem of short support life;
[0035] 4. The utility model can be easily removed after installation by arranging the telescopic device and the rotating device, which can be used for turnover, minimized and convenient to carry, thus solving the problem of installation and portability; BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0037] Figure 2 This is a schematic diagram of the corner structure of the utility model;
[0038] Figure 3 This is a cross-sectional view of the corner structure of the utility model;
[0039] Figure 4 This is a schematic diagram of the installation completion of the utility model;
[0040] Figure 5 This is a flow chart of the construction method of the utility model.
[0041] In all the drawings, the same figure marks represent the same technical features, specifically: 1-support outer shell part, 2-support inner core part, 3-rotating shaft, 4-gear shaft, 41-inverted L gear, 42-cylinder, 5-rotating shaft, 51-rotating gear, 52-plate bearing frame, 6-pin, 7-support, 8-support pad stone. DETAILED DESCRIPTION
[0042] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the utility model and are not used to limit the utility model. In addition, the technical features involved in each embodiment of the utility model described below can be combined with each other as long as they do not conflict with each other.
[0043] according to Figure 1-4 As shown, the utility model provides a bridge support leveling and installation device, including: a frame structure, an angle adjustment device, a height adjustment device, and a locking device;
[0044] The frame structure is a polygonal frame structure composed of a plurality of rods;
[0045] There are multiple angle adjustment devices, which are respectively located at each corner point of the frame structure;
[0046] There are multiple height adjustment devices, which are respectively arranged at the end of each rod of the frame structure;
[0047] The height adjustment device includes a gear shaft 4, a rotating shaft 5, a rotating gear 51, and a plate-shaped bearing frame 52; the rotating shaft 5 is connected to the rotating gear 51 and can drive the rotating gear 51 to rotate; the rotating gear 51 is in contact with the gear shaft 4 and can drive the gear shaft 4 to rise and fall; the locking device can fix the height of the gear shaft 4;
[0048] The locking device is arranged around the rotating shaft 5 .
[0049] The polygon is a triangle, a rectangle or a square.
[0050] The frame structure comprises a support outer shell part 1 and a support inner core part 2;
[0051] The support shell part 1 and the support inner core part 2 cooperate with each other and are respectively connected to different angle adjustment devices; the support shell part 1 and the support inner core part 2 can be telescopic, and the support inner core part 2 can be retracted into the support shell part 1.
[0052] The angle adjustment device comprises a rotating shaft 3;
[0053] The rotating shaft 3 is arranged at each corner point of the frame structure, and respectively connects the support outer shell part 1 and the support inner core part 2 of two adjacent frame structures; the angle formed by the connected support outer shell part 1 and the support inner core part 2 can be changed.
[0054] The gear shaft 4 is provided with an inverted L gear 41 and a cylinder 42; the cylinder 42 is provided with a scale, arranged inside the rotating shaft 3, and can be extended and retracted up and down inside the rotating shaft 3 to adjust the height;
[0055] The rotating gear 51 is arranged on a plate-shaped bearing frame 52 inside the rotating shaft 5 . The rotating shaft 5 is fixedly connected to the intermediate shaft of the rotating gear 51 . The rotating gear 51 is meshed with the inverted L gear 41 .
[0056] The locking device comprises a latch 6;
[0057] The latch 6 is disposed on a bearing plate of a plate-shaped bearing frame 52 mounted on the rotating shaft 5, and can fix the rotating gear 51 to determine the height of the height adjustment device.
[0058] The construction method of the utility model bridge support leveling and installation device is as follows: Figure 5 As shown, the steps are as follows:
[0059] S100, device in place: adjust the size of the telescopic device, determine the positioning of the four corners of the device, and fix the position of the device;
[0060] Specifically, the support outer shell part 1 and the support inner core part 2 are pulled to adjust the sleeve length and device size of the telescopic device, the rotating shaft 3 is rotated to adjust the angle between adjacent telescopic device sleeves, and the device size is adjusted to meet the installation requirements of the support; and the positioning of the four corners of the device is determined by positioning measurement.
[0061] S200, support elevation control: according to the position positioning of the device, the elevations of the four corners of the support are calculated and positioned, and the device is fixed to the elevation position of the elevation positioning;
[0062] Specifically, according to the accurate positioning of the four corners of the device in step S100, the entire device is placed on the support pad 8, and the specific elevations of the four corners of the device during setting are calculated according to the elevations required by the support design; the rotating shaft 5 is twisted to drive the rotation of the rotating gear 51 and the lifting and lowering of the inverted L gear in turn to adjust the height of the gear shaft 4, and the adjusted height is accurately judged by observing the scale on the gear shaft 4, so that the elevations of the four corners of the device are the same as the elevations required by the support design, and after the gear shaft 4 reaches the height corresponding to the elevation value, the pin 6 is inserted to fix the rotating shaft to keep the gear shaft at a fixed height.
[0063] S300, support installation: based on the elevation value adjustment device, hoist the support, pour the support grouting material and consolidate it;
[0064] Specifically, if Figure 4 As shown, the device is placed on the support pedestal 8, and based on the elevation values of the four corners of the device support in step S200, the support is hoisted and the support 7 is placed on the gear shaft 4; the height of the gear shaft 4 is fine-tuned to make the entire device fully contact with the bridge beam and slab to ensure that the bridge support device is uniformly stressed; the support grouting material is poured into the telescopic device sleeve to connect the support pedestal 8 and the support 7, and the grouting material is consolidated to complete the leveling, fixation and installation of the bridge support.
[0065] S400, device disassembly and circulation: by adjusting the size of the device, the device can be taken out from the support and the size of the device can be reduced to facilitate carrying and multiple circulation use;
[0066] Specifically, after the support is fixed and stabilized in step S300, the rotating shaft 5 and the latch 6 are adjusted to lower the gear shaft 4, the size of the support shell part 1 and the support core part 2 are stretched to the maximum, and then the device is removed from the fixed support to complete the disassembly; after the support is taken out, the device is minimized by adjusting the support shell part 1, the support core part 2 and the rotating shaft 3 to facilitate carrying, storage and multiple turnover use.
[0067] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.
Claims
1. A bridge support leveling and installation device, characterized in that: include: Frame structure, angle adjustment device, height adjustment device, locking device; The frame structure is a polygonal frame structure composed of a plurality of rods; There are multiple angle adjustment devices, which are respectively located at each corner point of the frame structure; There are multiple height adjustment devices, which are respectively arranged at the end of each rod of the frame structure; The height adjustment device comprises a gear shaft (4), a rotating shaft (5), a rotating gear (51), and a plate-shaped bearing frame (52); the rotating shaft (5) is connected to the rotating gear (51) and can drive the rotating gear (51) to rotate; the rotating gear (51) is in contact with the gear shaft (4) and can drive the gear shaft (4) to rise and fall; and the height of the gear shaft (4) can be fixed by the locking device; The locking device is arranged around the rotating shaft (5).
2. A bridge support leveling and installation device according to claim 1, characterized in that: The polygon is a triangle, a rectangle or a square.
3. The bridge support leveling and installation device according to claim 1, characterized in that: The frame structure comprises a support outer shell part (1) and a support inner core part (2); The support outer shell part (1) and the support inner core part (2) cooperate with each other and are respectively connected to different angle adjustment devices; the support outer shell part (1) and the support inner core part (2) can be extended and retracted, and the support inner core part (2) can be retracted into the support outer shell part (1).
4. The bridge support leveling and installation device according to claim 1, characterized in that: The angle adjustment device comprises a rotating shaft (3); The rotating shaft (3) is arranged at each corner point of the frame structure, and respectively connects the support outer shell part (1) and the support inner core part (2) of two adjacent sections of the frame structure; the angle formed by the connected support outer shell part (1) and the support inner core part (2) can be changed.
5. The bridge support leveling and installation device according to claim 1, characterized in that: The gear shaft (4) is provided with an inverted L gear (41) and a cylinder (42); the cylinder (42) is provided with a scale, is arranged inside the rotating shaft (3), and can be extended and retracted up and down inside the rotating shaft (3) to adjust the height; The rotating gear (51) is arranged on a plate-shaped bearing frame (52) inside the rotating shaft (5); the rotating shaft (5) is fixedly connected to the intermediate shaft of the rotating gear (51); and the rotating gear (51) is meshed with the inverted L gear (41).
6. A bridge support leveling and installation device according to any one of claims 1 to 5, characterized in that: The locking device comprises a latch (6); The latch (6) is arranged on a bearing plate of a plate-shaped bearing frame (52) mounted on the rotating shaft (5), and can fix the rotating gear (51) to determine the height of the height adjustment device.
Citation Information
Patent Citations
Bridge support leveling wedge block connecting method
CN112853952A