Building plastering machine
By setting up inclined chutes in the middle of the plastering board and using traction ropes to drive the plastering board to move upward, the problem of concrete mortar accumulation and excessive load on the plastering board during the plastering process is solved, and the plastering efficiency and quality are improved.
Patent Information
- Application Number
- CN202420437974.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-07
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2034-03-07
AI Technical Summary
During the plastering process, the plastering board of the plastering machine will apply pressure to the wall, making the concrete mortar stick tightly. However, due to the thick concrete mortar on the wall surface, it will be squeezed onto the plastering board, resulting in mortar accumulation , increase the plastering board sports load, affect the plastering quality, and increase the working steps of staff to reduce plastering efficiency.
Set up an inclined trough in the middle of the plastering board to incline both ends of the inclined trough downwards to avoid concrete mortar accumulation on the plastering board. At the same time, the plastering board is driven upwards by traction ropes to reduce the movement load of the plastering board.
It effectively avoids the accumulation of concrete mortar on the plastering board, reduces the movement load of the plastering board, reduces the working steps of staff, and improves the plastering efficiency and quality.
Smart Images

Figure CN222478053U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building decoration, in particular to a building plastering machine. Background Art
[0002] Plastering refers to applying cement mortar, mixed mortar, or lime mortar to the wall surface. Indoor and outdoor wall plastering is a job that is done after the building structure is completed. Scientific plastering can prevent moisture, weathering, and heat insulation, and prevent the building walls from being eroded by wind, rain, snow, etc.
[0003] During the plastering process, the sandblasting machine sprays the mixed concrete mortar on the wall, and then the plastering machine is used to smooth the sprayed wall. During the smoothing process, the plastering board of the plastering machine will apply a certain amount of pressure to the wall to make the concrete mortar more tightly adhere to the wall. In this process, since the concrete mortar on some wall surfaces is relatively thick, it will be squeezed onto the plastering board of the plastering machine. When these concrete mortars stay on the plastering board, it will not only increase the load of the plastering board moving up and down, but when the concrete mortar accumulates to a certain extent, it will also affect the plastering quality of the plastered wall. Usually, the staff will scrape off the concrete attached to the plastering board when the plastering machine stops and changes position. This work will increase the plastering work steps of the staff and reduce the plastering efficiency. Utility Model Content
[0004] The utility model aims to provide a building plastering machine to solve the problem proposed in the above background technology that during the leveling process, the plastering board of the plastering machine will exert a certain pressure on the wall surface to make the concrete mortar more tightly adhere to the wall surface. In this process, since the concrete mortar on some wall surfaces is relatively thick, it will be squeezed onto the plastering board of the plastering machine. When these concrete mortars stay on the plastering board, it will not only increase the load of the plastering board moving up and down, but also affect the plastering quality of the plastered wall when the concrete mortar accumulates to a certain extent. Usually, the staff will scrape off the concrete attached to the plastering board when the plastering machine stops and changes position. This work will increase the plastering work steps of the staff and reduce the plastering efficiency.
[0005] To achieve the above object, the utility model provides the following technical solutions: a building plastering machine, comprising a machine body, a guide rod is arranged on one side of the machine body, a slider is slidably installed inside the guide rod, a plastering board is installed on the slider, a traction rope is extended from the machine body for pulling the plastering board to move upward smoothly, an inclined groove is arranged in the middle of the plastering board, and both ends of the inclined groove are arranged to be inclined downward;
[0006] A horizontally placed mounting plate is arranged on one side of the plastering plate away from the guide rod, and a plastering plate used for contacting and pressing the wall surface is arranged on the mounting plate.
[0007] Furthermore, a connecting piece is provided on the end surface of the trowel plate facing the mounting plate, a mounting through hole is provided on the connecting piece, a matching through hole is provided on the mounting plate, and the connecting piece and the mounting plate are mounted to each other by bolts.
[0008] Furthermore, the middle part of the trowel plate is vertically arranged, and the upper and lower ends of the trowel plate are inclined toward the direction of the mounting plate.
[0009] Furthermore, the slider is provided with a mounting rod, the mounting rod is provided with a supporting groove which matches the contour of the lower side of the plastering board, and the plastering board is provided with connecting through holes for mounting the plastering board on the mounting rod by bolts.
[0010] Furthermore, a connecting rod is also provided on the mounting rod, and the connecting rod is used to be connected to one end of the traction rope and drive the plastering plate to move upward.
[0011] Furthermore, it also includes a placing rack, which is used to place an ash hopper containing concrete. The placing rack is provided with two groups, and the two groups of placing racks are respectively located directly below the outlets on both sides of the inclined trough.
[0012] Furthermore, a support plate is provided on the side of the guide rod, and the placement rack is installed on the support plate.
[0013] Compared with the prior art, the beneficial effects of the utility model are:
[0014] The utility model provides an inclined groove in the middle of the plastering board and makes the two ends of the inclined groove inclined downward, so that the concrete falling into the inclined groove can flow out from the two ends of the inclined groove along the inclined groove, so as to avoid the accumulation of concrete mortar on the plastering board. While reducing the load of the plastering board moving upward, it can also reduce the working steps of the plastering workers, so that the working efficiency of the workers is higher. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the overall structure of a building plastering machine according to the utility model;
[0016] Figure 2 This is an exploded view of a building plastering machine of the utility model;
[0017] Figure 3 The utility model is an exploded view of the overall structure of a plastering plate of a building plastering machine.
[0018] In the figure: 1. body; 2. guide rod; 21. traction rope; 22. slider; 23. mounting rod; 24. connecting rod; 3. plastering plate; 301. inclined groove; 302. connecting through hole; 31. connecting piece; 3101. mounting through hole; 32. mounting plate; 3201. matching through hole; 33. plastering plate; 4. placement rack; 41. support plate. DETAILED DESCRIPTION
[0019] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0020] See also Figure 1-Figure 3 As shown, the utility model provides a technical solution: a building plastering machine, comprising a machine body 1, a guide rod 2 is arranged on one side of the machine body 1, a slider 22 is slidably installed inside the guide rod 2, a mounting rod 23 is arranged on the slider 22, a supporting groove which matches the contour of the lower side of the plastering plate 3 is arranged on the mounting rod 23, a connecting through hole 302 is arranged on the plastering plate 3 for mounting the plastering plate 3 on the mounting rod 23 by bolts, and a connecting rod 24 is also arranged on the mounting rod 23, and the connecting rod 24 is used to connect with one end of the traction rope 21 and drive the plastering plate 3 to move upward;
[0021] The slider 22 is provided with a plastering plate 3, and a traction rope 21 is extended from the body 1 to pull the plastering plate 3 to move upward smoothly. An inclined groove 301 is provided in the middle of the plastering plate 3, and both ends of the inclined groove 301 are inclined downward. The plastering plate 3 is formed by integral stamping.
[0022] A horizontally placed mounting plate 32 is provided on one side of the plastering plate 3 away from the guide rod 2 , and a trowel plate 33 for contacting and pressing the wall surface is provided on the mounting plate 32 .
[0023] In the utility model, by setting an inclined groove 301 in the middle of the plastering plate 3, and making the two ends of the inclined groove 301 inclined downward, the concrete falling into the inclined groove 301 can flow out from the two ends of the inclined groove 301 along the inclined groove 301, so as to avoid the accumulation of concrete mortar on the plastering plate 3. While reducing the load of the plastering plate 3 moving upward, it can also reduce the working steps of the plastering workers, so that the working efficiency of the workers is higher.
[0024] Furthermore, a connecting piece 31 is provided on the end surface of the trowel plate 33 facing the mounting plate 32, a mounting through hole 3101 is provided on the connecting piece 31, and a matching through hole 3201 is provided on the mounting plate 32. The connecting piece 31 and the mounting plate 32 are mounted to each other by bolts.
[0025] Furthermore, the middle of the trowel plate 33 is vertically arranged, and the upper and lower ends of the trowel plate 33 are inclined toward the direction of the mounting plate 32 .
[0026] Among them, by tilting the upper and lower ends of the trowel plate 33 toward the mounting plate 32, it is possible to prevent the trowel plate 33 from scratching the smoothed wall surface while following the up and down movement of the plastering plate 3. At the same time, it is also possible to reduce the amount of concrete mortar scratched off the wall surface, and to keep the concrete mortar of sufficient thickness attached to the wall surface.
[0027] Furthermore, it also includes a placing rack 4, which is used to place an ash hopper containing concrete. The placing rack 4 is provided with two groups, and the two groups of placing racks 4 are respectively located directly below the outlets on both sides of the inclined groove 301.
[0028] Furthermore, a support plate 41 is provided on the side of the guide rod 2 , and the placement rack 4 is installed on the support plate 41 .
[0029] Among them, by arranging the placement rack 4 on both sides of the guide rod 2, the concrete mortar falling from the outlets at both ends of the inclined groove 301 can be received, so as to avoid the concrete mortar from splashing when it falls to the ground. The splashed concrete is easy to fall and adhere to the wall surface, which will reduce the flatness of the wall surface.
[0030] Based on the embodiments of the present utility model, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present utility model.
Claims
1. A building plastering machine, comprising a machine body (1), a guide rod (2) being arranged on one side of the machine body (1), a slider (22) being slidably mounted inside the guide rod (2), a plastering board (3) being mounted on the slider (22), a traction rope (21) extending from the machine body (1) for traction of the plastering board (3) to move upward smoothly, characterized in that: The middle part of the plastering plate (3) is provided with an inclined groove (301), and both ends of the inclined groove (301) are arranged to be inclined downward; A horizontally placed mounting plate (32) is provided on one side of the plastering plate (3) away from the guide rod (2), and a plastering plate (33) for contacting and pressing the wall surface is provided on the mounting plate (32).
2. A building plastering machine according to claim 1, characterized in that: A connecting piece (31) is provided on the end surface of the trowel plate (33) facing the mounting plate (32); a mounting through hole (3101) is provided on the connecting piece (31); a matching through hole (3201) is provided on the mounting plate (32); and the connecting piece (31) and the mounting plate (32) are mounted to each other via bolts.
3. A building plastering machine according to claim 2, characterized in that: The middle part of the trowel plate (33) is arranged vertically, and the upper and lower ends of the trowel plate (33) are arranged obliquely in the direction of the mounting plate (32).
4. A building plastering machine according to claim 1, characterized in that: The slider (22) is provided with a mounting rod (23), the mounting rod (23) is provided with a support groove that matches the contour of the lower side of the plastering plate (3), and the plastering plate (3) is provided with a connecting through hole (302) for mounting the plastering plate (3) on the mounting rod (23) via bolts.
5. A building plastering machine according to claim 4, characterized in that: The installation rod (23) is also provided with a connecting rod (24), which is used to connect to one end of the traction rope (21) and drive the plastering plate (3) to move upward.
6. A building plastering machine according to claim 1, characterized in that: It also includes a placement rack (4), the placement rack (4) being used to place an ash hopper containing concrete, and the placement rack (4) is provided in two groups, the two groups of placement racks (4) being respectively located directly below the outlets on both sides of the inclined groove (301).