Pipeline construction device for bridge and culvert construction

By designing a pipeline construction device for bridge and culvert construction, using technical means such as rotary winding plates, jaws and clamping components, the problem of pipeline interface damage caused by poor construction environment is solved, and the stable and smooth docking of the pipeline is achieved. Efficient construction.

CN222500013UActive Publication Date: 2025-02-18JIANG AO BAI ROAD & BRIDGE ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421730770.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2025-02-18
Estimated Expiration
2034-07-22

AI Technical Summary

Technical Problem

During the construction docking process of existing pipelines, due to the poor construction environment, the pipeline needs to be continuously moved to the appropriate position, resulting in damage at the pipeline interface, affecting the overall pipeline docking performance.

Method used

A pipeline construction device for bridge and culvert construction is designed, including connecting the carrier, the first rotary winding disk and the second rotary winding disk. These components assist in the expansion and retraction adjustment of the spring winding rope and the central spring winding rope, and use the The jaws and clamping components position and clamp the pipes, and adjust them through segmented winding and wiring adjustments, so that the pipes gradually decrease, reduce shaking bias, and improve docking performance.

Benefits of technology

Through this device, the pipeline can be down and docked stably and smoothly during construction, reducing the risk of damage to the pipeline interface and improving the overall construction effect and connection stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222500013U_ABST
    Figure CN222500013U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipeline construction device for bridge and culvert construction, relates to the technical field of pipeline construction devices, and aims to solve the problems that in the construction butt joint process of an existing pipeline, due to the fact that the construction environment is poor, the pipeline needs to be stirred continuously to reach a proper position, a pipeline connector is damaged, the overall pipeline butt joint performance is affected, and the construction cost is lowered. The wire spool comprises two groups of connecting carriers, a first rotary wire spool and a second rotary wire spool, the two groups of connecting carriers are oppositely arranged, the first rotary wire spool is positioned between the two groups of connecting carriers, a cross rod is transversely arranged in the middle of the first rotary wire spool in a penetrating manner, and the first rotary wire spool and the second rotary wire spool are oppositely arranged. And the number of the second rotating wire reels is two, the two second rotating wire reels are distributed on the outer side of the connecting carrier frame, the first clamping assembly and the second clamping assembly are arranged along the outer side of the connecting carrier frame, and the overall construction effect is improved through the first rotating wire reels and the second rotating wire reels.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline construction devices, in particular to a pipeline construction device for bridge and culvert construction. Background Art

[0002] Bridge and culvert construction is a complex engineering process involving multiple stages and multiple aspects. Bridges and culverts are a general term for bridges and culverts. Before construction, it is necessary to comprehensively analyze the engineering requirements, including the project background and objectives, the covered traffic routes and river characteristics, the selection of materials and equipment, and safety and environmental protection requirements. Before installing the pipeline, the quality of the pipeline should be checked to ensure that there is no damage or cracks. During the installation process, the stability and sealing of the pipeline must be ensured to avoid leakage or dislocation. At the same time, the connection method of the pipeline also needs to be selected according to the specific situation to ensure that the connection is firm and reliable. At present, the existing pipelines need to be constantly moved to the appropriate position during the construction and docking process due to the poor construction environment, which causes damage to the pipeline interface, affecting the overall pipeline docking performance, requiring secondary treatment, and reducing the overall construction effect; Therefore, we propose a pipeline construction device for bridge and culvert construction to solve the above problems. Utility Model Content

[0003] The utility model aims to provide a pipeline construction device for bridge and culvert construction, so as to solve the problem that the existing pipelines proposed in the above background technology need to be constantly moved to a suitable position due to a poor construction environment, resulting in damage to the pipeline interface.

[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a pipeline construction device for bridge and culvert construction, comprising a connecting carrier, a first rotating wire drum and a second rotating wire drum, the connecting carrier is provided with two groups, the two groups of connecting carriers are arranged opposite to each other, the first rotating wire drum is located between the two groups of connecting carriers, a cross bar is horizontally passed through the middle of the first rotating wire drum, the second rotating wire drum is provided with two groups, the two groups of the second rotating wire drum are distributed on the outside of the connecting carrier, and a first clamping assembly and a second clamping assembly are provided along the outside of the connecting carrier.

[0005] Through the first rotating winding drum and the second rotating winding drum, the auxiliary spring winding rope and the central spring winding rope can be telescopically adjusted. According to the length of the embedded pipe, the claws are used to clamp the front end, and the first clamping assembly and the second clamping assembly can be used to position and clamp the rear end of the pipe. As the pipe gradually sinks into the dug groove, the rear ends of the first rotating winding drum and the second rotating winding drum release the wire, and the synchronous multi-group segmented winding turntables perform local release and adjustment, so that the pipe gradually descends, reducing the shaking and deviation of the pipe, thereby increasing the stable docking performance.

[0006] Furthermore, a first connecting rope and a second connecting rope are respectively wound in the middle of the first rotating winding drum and the second rotating winding drum, one end of the first connecting rope is extended and connected to a central spring winding rope, one end of the second connecting rope is extended and connected to an auxiliary spring winding rope, and both the central spring winding rope and the auxiliary spring winding rope are provided with segmented winding turntables, and the segmented winding turntables are provided with multiple groups, and the multiple groups of segmented winding turntables are linearly arranged along the central spring winding rope and the auxiliary spring winding rope. Through the first rotating winding drum and the second rotating winding drum, the auxiliary spring winding rope and the central spring winding rope can be telescopically adjusted, and according to the length of the embedded pipe, the claws are used to clamp the part near the front end.

[0007] Furthermore, a driving controller is provided at the center of the segmented winding turntable, and a mounting disk is provided at one end of the central spring winding rope away from the first rotating winding disk. The mounting disk is provided with docking holes, and the docking holes are provided with multiple groups. The multiple groups of docking holes are evenly distributed on the mounting disk. Different clamping structures can be installed according to needs through the mounting disk and the docking holes, thereby facilitating the clamping and positioning of the pipeline.

[0008] Furthermore, a claw is provided at one end of the auxiliary spring winding rope away from the second rotating winding disk, and the claw is composed of two groups of ring claws. A clamping electric control machine is provided in the middle of the claw. According to the length of the embedded pipeline, the claw is used to clamp the part near the front end.

[0009] Furthermore, a positioning telescopic end is provided at the connection point where the cross bar extends to both sides and is connected to the connecting carrier, a telescopic frame is provided on the outer side of the positioning telescopic end, a telescopic groove for telescoping the telescopic frame is provided on the positioning telescopic end, a controller is provided inside the positioning telescopic end, the telescopic frame is connected to the second rotating winding drum away from the positioning telescopic end, a driver is provided at the center of the outer end of the second rotating winding drum, and a seismic isolation sleeve is provided on the outer side of the telescopic frame. According to the position of the actual environment, the positioning telescopic end can be used to adjust the telescopic frame to drive the second rotating winding drum to extend and retract.

[0010] Furthermore, the first clamping assembly and the second clamping assembly both include a swing frame, an extension frame and a clamping ring claw, the clamping ring claw is located at one end of the extension frame, a rotating rod is provided between the swing frame and the extension frame, and a rotating motor is provided at one end of the rotating rod. The use of a swing frame and an extension frame can increase the flexibility of adjustment.

[0011] Furthermore, a balance plate is provided at the lower end of the connecting carrier, and a plug-in hole is provided on the surface of the balance plate. Slide rails are provided at the front and rear ends of the balance plate. A blocking component is provided on the slide rail, and a sliding sleeve is provided at one end of the blocking component. The blocking component slides along the slide rail through the sliding sleeve. The blocking component includes a positioning column, a driving motor and a blocking plate. The driving motor is located at one end of the positioning column. A plurality of blocking plates are provided, and a plurality of groups of blocking plates are arranged around the outer end of the positioning column. A snap-in groove is provided on the blocking plate. The plug-in hole on the balance plate can be directly connected with a positioning pin according to different construction environments to position and connect the overall structure. The blocking plate on the blocking component can be rotated to adapt to the slope, sinking and uneven ground of the construction environment. Secondary plug-in installation is performed through the snap-in groove to increase the overall connection stability.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] 1. The utility model can adjust the extension and contraction of the auxiliary spring winding rope and the central spring winding rope through the first rotating winding drum and the second rotating winding drum. According to the length of the embedded pipeline, the claws are used to clamp the front end, and the first clamping assembly and the second clamping assembly can be used to position and clamp the rear end of the pipeline. As the pipeline gradually sinks into the dug groove, the rear ends of the first rotating winding drum and the second rotating winding drum release the wire, and the synchronous multi-group segmented winding turntables perform local release and adjustment, so that the pipeline gradually descends, reducing the shaking and deviation of the pipeline, thereby increasing the stable docking performance.

[0014] 2. Through the plug-in holes on the balance board, the positioning pins can be directly plugged in according to the different construction environments to position and connect the overall structure. Then, the blocking plate on the blocking assembly can be rotated to adapt to the slope, sinking and uneven ground of the construction environment, and the secondary plug-in installation can be performed through the card slot to increase the overall connection stability. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0016] Figure 2 This is a schematic diagram of a first clamping assembly of the utility model;

[0017] Figure 3 This is a schematic diagram of the central spring rope of the utility model;

[0018] Figure 4 This is a schematic diagram of the structure of the utility model when viewed from above;

[0019] Figure 5 It is a schematic diagram of the barrier component of the present utility model.

[0020] In the figure: 1. connecting carrier; 2. balance plate; 3. first rotating winding drum; 4. second rotating winding drum; 5. telescopic frame; 6. positioning telescopic end; 7. auxiliary spring winding rope; 8. center spring winding rope; 9. first clamping assembly; 10. second clamping assembly; 11. plug-in hole; 12. seismic isolation sleeve; 13. drive; 14. swing frame; 15. extension frame; 16. clamping ring claw; 17. segmented winding turntable; 18. mounting plate; 19. docking hole; 20. slide rail; 21. slide sleeve; 22. drive motor; 23. baffle plate; 24. cross bar; 25. baffle assembly. DETAILED DESCRIPTION

[0021] See also Figure 1-5 The utility model provides an embodiment: a pipeline construction device for bridge and culvert construction, comprising a connecting carrier 1, a first rotating wire drum 3 and a second rotating wire drum 4, wherein the connecting carrier 1 is provided with two groups, and the two groups of the connecting carriers 1 are arranged opposite to each other, the first rotating wire drum 3 is located between the two groups of the connecting carriers 1, a cross bar 24 is horizontally penetrated in the middle of the first rotating wire drum 3, the second rotating wire drum 4 is provided with two groups, and the two groups of the second rotating wire drum 4 are distributed on the outside of the connecting carrier 1, and a first clamping assembly 9 and a second clamping assembly 1 are provided along the outside of the connecting carrier 1. 0, through the first rotating winding drum 3 and the second rotating winding drum 4, the auxiliary spring winding rope 7 and the central spring winding rope 8 can be telescopically adjusted. According to the length of the embedded pipeline, the claws are used to clamp the front end, and the first clamping assembly 9 and the second clamping assembly 10 can be used to position and clamp the rear end of the pipeline. As the pipeline gradually sinks into the dug groove, the rear ends of the first rotating winding drum 3 and the second rotating winding drum 4 release the wire, and the synchronous multi-group segmented winding turntable 17 performs local release adjustment, so that the pipeline gradually descends, reducing the shaking and deviation of the pipeline, thereby increasing the stable docking performance.

[0022] In actual use, a first connecting rope and a second connecting rope are respectively wound in the middle of the first rotating winding drum 3 and the second rotating winding drum 4, one end of the first connecting rope is extended to be connected to a central spring winding rope 8, and one end of the second connecting rope is extended to be connected to an auxiliary spring winding rope 7, and both the central spring winding rope 8 and the auxiliary spring winding rope 7 are provided with a segmented winding turntable 17, and the segmented winding turntable 17 is provided with a plurality of groups, and the plurality of groups of segmented winding turntables 17 are linearly arranged along the central spring winding rope 8 and the auxiliary spring winding rope 7. The winding disk 4 can make the auxiliary spring winding rope 7 and the central spring winding rope 8 telescopically adjustable. According to the length of the embedded pipe, the claws are used to clamp the part near the front end. A driving controller is provided at the center of the segmented winding turntable 17. An installation disk 18 is provided at the end of the central spring winding rope 8 away from the first rotating winding disk 3. The installation disk 18 is provided with docking holes 19. The docking holes 19 are provided in multiple groups, and the multiple groups of docking holes 19 are evenly distributed on the installation disk 18. Through the installation disk 18 and the docking holes 19, different clamping structures can be installed according to needs, thereby facilitating the clamping and positioning of the pipe.

[0023] In addition, a claw is provided at one end of the auxiliary spring winding rope 7 away from the second rotating winding drum 4, and the claw is composed of two groups of ring claws. A clamping electric control machine is provided in the middle of the claw. According to the length of the embedded pipeline, the claw is used to clamp the part near the front end. The cross bar 24 extends to both sides and is connected with the connecting carrier 1. A positioning telescopic end 6 is provided at the outer side of the positioning telescopic end 6. A telescopic frame 5 is provided on the positioning telescopic end 6. A telescopic groove for the telescopic frame 5 is opened on the positioning telescopic end 6. A controller is provided inside the positioning telescopic end 6. The telescopic frame 5 is connected to the second rotating winding drum 4 away from the positioning telescopic end 6. A driver 13 is provided at the center of the outer end of the second rotating winding drum 4. An isolation sleeve 12 is provided on the outer side of the telescopic frame 5. According to the position of the actual environment, the positioning telescopic end 6 can be used to adjust the telescopic frame 5 to drive the second rotating winding drum 4 to extend and retract.

[0024] Specifically, the first clamping assembly 9 and the second clamping assembly 10 both include a swing frame 14, an extension frame 15 and a clamping ring claw 16, the clamping ring claw 16 is located at one end of the extension frame 15, a rotating rod is provided between the swing frame 14 and the extension frame 15, and a rotating motor is provided at one end of the rotating rod. The swing frame 14 and the extension frame 15 are used to increase the flexibility of adjustment. A balance plate 2 is provided at the lower end of the connecting carrier 1, and a plug hole 11 is provided on the surface of the balance plate 2. The front and rear ends of the balance plate 2 are both provided with a slide rail 20, and a blocking assembly 25 is provided on the slide rail 20. A sliding sleeve 21 is provided at one end of the blocking assembly 25. The component 25 slides along the slide rail 20 through the sliding sleeve 21, and the blocking component 25 includes a positioning column, a driving motor 22 and a blocking plate 23. The driving motor 22 is located at one end of the positioning column. The blocking plate 23 is provided with a plurality of groups, and the plurality of groups of blocking plates 23 are arranged around the outer end of the positioning column. The blocking plate 23 is provided with a snap-in groove, and the plug-in hole 11 on the balance plate 2 can directly plug in the positioning pin according to the different construction environments to position and connect the overall structure, and then the blocking plate 23 on the blocking component 25 is rotated to adapt to the slope, sinking and uneven ground of the construction environment, and the secondary plug-in installation is performed through the snap-in groove to increase the overall connection stability.

[0025] In summary, the utility model provides a pipeline construction device for bridge and culvert construction, including a connecting carrier 1, a first rotating wire drum 3 and a second rotating wire drum 4. The connecting carrier 1 is provided with two groups, and the two groups of the connecting carriers 1 are arranged opposite to each other. The first rotating wire drum 3 is located between the two groups of the connecting carriers 1. A cross bar 24 is horizontally penetrated in the middle of the first rotating wire drum 3. The second rotating wire drum 4 is provided with two groups, and the two groups of the second rotating wire drum 4 are distributed on the outside of the connecting carrier 1. A first clamping assembly 9 and a second clamping assembly 10 are provided along the outside of the connecting carrier 1. Through the first rotating winding drum 3 and the second rotating winding drum 4, the auxiliary spring winding rope 7 and the central spring winding rope 8 can be telescopically adjusted. According to the length of the embedded pipe, the claws are used to clamp the front end, and the first clamping assembly 9 and the second clamping assembly 10 can be used to position and clamp the rear end of the pipe. As the pipe gradually sinks into the dug groove, the rear ends of the first rotating winding drum 3 and the second rotating winding drum 4 are released, and the synchronous multi-group segmented winding turntable 17 performs local release adjustment, so that the pipe gradually descends, reducing the shaking deviation of the pipe, thereby increasing the stable docking performance.

Claims

1. A pipeline construction device for bridge and culvert construction, comprising a connecting carrier, a first rotating winding drum and a second rotating winding drum, characterized in that: The connecting carriers are provided with two groups, and the two groups of connecting carriers are arranged opposite to each other. The first rotating winding drum is located between the two groups of connecting carriers, and a cross bar is horizontally passed through the middle of the first rotating winding drum. The second rotating winding drum is provided with two groups, and the two groups of the second rotating winding drums are distributed on the outside of the connecting carriers. A first clamping assembly and a second clamping assembly are provided along the outside of the connecting carrier.

2. The pipeline construction device for bridge and culvert construction according to claim 1, characterized in that: A first connecting rope and a second connecting rope are respectively wound in the middle of the first rotating winding disk and the second rotating winding disk, one end of the first connecting rope is extended and connected to a central spring winding rope, one end of the second connecting rope is extended and connected to an auxiliary spring winding rope, and both the central spring winding rope and the auxiliary spring winding rope are provided with segmented winding turntables, and the segmented winding turntables are provided with multiple groups, and the multiple groups of segmented winding turntables are linearly arranged along the central spring winding rope and the auxiliary spring winding rope.

3. The pipeline construction device for bridge and culvert construction according to claim 2 is characterized in that: A driving controller is provided at the center of the segmented winding turntable, and a mounting disk is provided at the end of the central spring winding rope away from the first rotating winding disk. The mounting disk is provided with docking holes, and the docking holes are provided in multiple groups, and the multiple groups of docking holes are evenly distributed on the mounting disk.

4. The pipeline construction device for bridge and culvert construction according to claim 2 is characterized in that: A clamping claw is provided at one end of the auxiliary spring winding rope away from the second rotating winding disk. The clamping claw is composed of two groups of ring claws, and a clamping electric control machine is provided in the middle of the clamping claw.

5. The pipeline construction device for bridge and culvert construction according to claim 1, characterized in that: The cross bar extends to both sides and is connected with the connecting carrier at a positioning telescopic end, a telescopic frame is provided on the outer side of the positioning telescopic end, a telescopic groove for telescoping the telescopic frame is opened on the positioning telescopic end, a controller is provided inside the positioning telescopic end, the telescopic frame is connected to the second rotating winding drum away from the positioning telescopic end, a driver is provided at the outer end center of the second rotating winding drum, and a seismic isolation sleeve is provided on the outer side of the telescopic frame.

6. The pipeline construction device for bridge and culvert construction according to claim 1 is characterized in that: The first clamping assembly and the second clamping assembly both include a swing frame, an extension frame and a clamping ring claw, the clamping ring claw is located at one end of the extension frame, a rotating rod is provided between the swing frame and the extension frame, and a rotating motor is provided at one end of the rotating rod.

7. The pipeline construction device for bridge and culvert construction according to claim 1 is characterized in that: A balance plate is provided at the lower end of the connecting carrier, a plug hole is provided on the surface of the balance plate, slide rails are provided at the front and rear ends of the balance plate, a blocking component is provided on the slide rail, a sliding sleeve is provided at one end of the blocking component, the blocking component slides along the slide rail through the sliding sleeve, the blocking component includes a positioning column, a driving motor and a blocking plate, the driving motor is located at one end of the positioning column, a plurality of blocking plates are provided, the plurality of blocking plates are arranged around the outer end of the positioning column, and a snap-in groove is provided on the blocking plate.