Shear wall structure for building

By using rubber blocks and guide holes in the shear wall structure, the problem of inaccurate docking caused by bending vertical steel bars during transportation is solved, and the docking accuracy and waterproof sealing of the shear wall are improved.

CN222500667UActive Publication Date: 2025-02-18FUZHOU INSTITUE OF TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420918990.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-29
Publication Date
2025-02-18
Estimated Expiration
2034-04-29

AI Technical Summary

Technical Problem

During the transportation of prefabricated shear walls, vertical steel bars are prone to bend, resulting in the inability to accurately dock during assembly and docking, affecting construction.

Method used

The rubber block and its guide holes are used to adjust the microbending of each vertical steel bar, and the clamping force and fitting sealing of the vertical steel bars are improved by the rubber block under pressure deformation.

Benefits of technology

The butt accuracy and waterproof sealing of vertical steel bars and steel sleeves are improved, ensuring the stability and construction efficiency of the shear wall.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222500667U_ABST
    Figure CN222500667U_ABST
Patent Text Reader

Abstract

The utility model discloses a building shear wall structure which comprises an upper shear wall and a lower shear wall, vertical steel bars of the upper shear wall are inserted into steel bar sleeves of the lower shear wall, a rubber block is arranged on the lower shear wall, a plurality of guide holes coaxial with the vertical steel bars are formed in the rubber block, each guide hole is in an inverted frustum shape, and the vertical steel bars are arranged in the guide holes. A mounting groove for embedding the rubber block is formed in the lower end surface of the upper shear wall; when the rubber block is in a normal state, the diameter of the upper end of the guide hole is larger than the outer diameter of the vertical reinforcement, the diameter of the lower end is equal to the outer diameter of the vertical reinforcement, and the waist slope of the rubber block is larger than that of the mounting groove. And when the upper shear wall and the lower shear wall are attached and butted, the rubber blocks are pressed to deform, so that the inner walls of the guide holes of the rubber blocks are attached and clamped to the outer walls of the vertical steel bars, and the waist edge surfaces of the rubber blocks are attached to the inner walls of the mounting grooves. The prefabricated shear wall has the effect of improving the splicing accuracy and waterproof sealing performance of the prefabricated shear wall.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building technology, and in particular to a shear wall structure for building. Background Art

[0002] At present, shear walls are also called wind-resistant walls, earthquake-resistant walls or structural walls. They are walls in houses or structures that mainly bear horizontal and vertical loads caused by wind loads or earthquakes to prevent structural shear damage. They are also called earthquake-resistant walls and are generally made of reinforced concrete.

[0003] In on-site construction, shear walls are increasingly prefabricated and assembled, and prefabricated shear walls are usually connected by grouting of steel sleeves. This connection method requires the exposed vertical steel bars on the upper shear wall to enter the sleeves on the lower shear wall.

[0004] With respect to the above-mentioned related technologies, the inventors believe that the following defects exist: during the transportation of prefabricated shear walls, vertical steel bars are prone to bending. Large bending angles can be corrected manually, but some small bending angles are not discovered in time by construction workers, resulting in inaccurate docking during assembly and docking, affecting construction, and therefore needs to be improved. Utility Model Content

[0005] In order to improve the above problems, the present application provides a shear wall structure for construction.

[0006] The present application provides a shear wall structure for construction that adopts the following technical solution:

[0007] A shear wall structure for construction, comprising an upper shear wall and a lower shear wall, wherein the vertical steel bars of the upper shear wall are inserted into the steel bar sleeves of the lower shear wall, and a rubber block is arranged on the lower shear wall, wherein the cross section of the rubber block is arranged in an isosceles trapezoidal shape, the length of the rubber block is extended along the arrangement direction of each vertical steel bar, the rubber block is provided with a plurality of guide holes coaxially arranged with each vertical steel bar, each of the guide holes is arranged in an inverted cone shape, and the lower end surface of the upper shear wall is provided with an installation groove for embedding the rubber block; wherein, in a normal state, the upper end diameter of the guide hole of the rubber block is larger than the outer diameter of the vertical steel bar and the lower end diameter is equal to the outer diameter of the vertical steel bar, and the waist slope of the rubber block is larger than the waist slope of the installation groove; when the upper shear wall and the lower shear wall are fitted and docked, the rubber block is deformed under pressure, so that the inner wall of the guide hole of the rubber block is fitted and clamped to the outer wall of the vertical steel bar, and the waist surface of the rubber block is fitted to the inner wall of the installation groove.

[0008] By adopting the above technical scheme, a rubber block and guide holes thereon are provided, and the guide holes are used to perform micro-bending adjustments on each vertical steel bar, thereby improving the docking accuracy between the vertical steel bar and the steel bar sleeve. At the same time, the guide holes are provided in an inverted cone shape, and when the upper shear wall is compressed and deformed, the rubber block can be used to improve the clamping force and fit sealing of the rubber block on the vertical steel bar, thereby improving the waterproof sealing of the upper shear wall and the lower shear wall.

[0009] Preferably, a deformation seam is provided on the upper end surface of the rubber block, the deformation seam extends along the arrangement direction of the guide holes, the deformation seam is connected to the guide holes, and the depth of the deformation seam is less than the depth of the guide holes.

[0010] By adopting the above technical solution, the setting of the deformation joint can provide a more flexible deformation space for the deformation of the upper end of the rubber block.

[0011] Preferably, both side surfaces of the rubber block are coated with waterproof glue.

[0012] By adopting the above technical solution, the provision of waterproof glue can further improve the waterproof sealing between the rubber block and the upper shear wall.

[0013] Preferably, a plurality of pre-positioning columns are provided, each of which is pre-inserted and connected between the guide hole and the corresponding steel sleeve, and the length of the pre-positioning column is less than one fifth of the length of the steel sleeve.

[0014] By adopting the above technical solution, since there are tolerances in the positions of each steel sleeve during the actual construction process, the setting of the pre-positioning column can ensure that each steel sleeve and the guide hole are coaxially arranged before the upper shear wall and the lower shear wall are spliced, thereby providing positioning and guiding effects for the subsequent precise insertion of the vertical steel bars and the steel sleeves, and improving the insertion stability of the vertical steel bars and the steel sleeves.

[0015] Preferably, the vertical steel bars are arranged side by side in at least two rows, the number of the steel bar sleeves is consistent with the number of the vertical steel bars, and the number of the rubber blocks is consistent with the number of rows of the vertical steel bars.

[0016] By adopting the above technical solution, at least two rows of vertical steel bars are arranged to improve the connection stability between the upper shear wall and the lower shear wall.

[0017] Preferably, a connecting belt is connected between two adjacent rubber blocks, and the connecting belt is located on a side of the rubber block that contacts the lower shear wall.

[0018] By adopting the above technical solution, the provision of the connecting belt facilitates the installation of the rubber block.

[0019] Preferably, the upper end of the lower shear wall is provided with an embedding groove for installing the rubber block and the connecting belt.

[0020] By adopting the above technical solution, the provision of the embedding groove will facilitate the installation of the connecting belt and the rubber block.

[0021] Preferably, a raised portion is provided on the upper end surface of the middle portion of the connecting belt.

[0022] By adopting the above technical solution, the setting of the raised part can make most of the pressure force applied to the connecting belt by the upper shear wall act on the raised part, so that the upper and lower surfaces of the raised part are in closer contact with the upper shear wall and the lower shear wall, further improving the waterproof sealing.

[0023] In summary, the present application includes at least one of the following beneficial technical effects:

[0024] By setting the rubber block and the guide holes thereon, the guide holes are used to adjust the micro-bending of each vertical steel bar, thereby improving the docking accuracy between the vertical steel bar and the steel bar sleeve. At the same time, the guide holes are set in an inverted cone shape. When the upper shear wall is compressed and deformed, the clamping force and the fitting sealing of the rubber block on the vertical steel bar can be improved, thereby improving the waterproof sealing of the upper shear wall and the lower shear wall.

[0025] Since there are tolerances in the positions of each steel sleeve during the actual construction process, the setting of pre-positioning columns can ensure that each steel sleeve and the guide hole are coaxially arranged before the upper shear wall and the lower shear wall are spliced, thereby providing positioning and guiding functions for the subsequent precise connection of the vertical steel bars and the steel sleeves, and improving the connection stability of the vertical steel bars and the steel sleeves. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the structure of the shear wall structure before installation of an embodiment of the present application.

[0027] Figure 2 It is a schematic diagram of the structure of the shear wall structure after installation according to an embodiment of the present application.

[0028] Figure 3 yes Figure 2 A is a partial enlarged schematic diagram in FIG.

[0029] Figure 4 1 is a top plan view of a rubber block according to an embodiment of the present application.

[0030] Description of reference numerals:

[0031] 1. Upper shear wall; 2. Lower shear wall; 3. Vertical steel bars; 4. Steel bar sleeves; 5. Rubber blocks; 6. Guide holes; 7. Mounting grooves; 8. Connecting strips; 9. Mounting grooves; 10. Raised parts; 11. Expansion joints; 12. Pre-positioning columns. DETAILED DESCRIPTION

[0032] The following is combined with Figure 1-4 This application is described in further detail.

[0033] The present application embodiment discloses a shear wall structure for construction. Figure 1 , Figure 2 , Figure 3 as well as Figure 4 The building shear wall structure includes an upper shear wall 1 and a lower shear wall 2. The vertical steel bars 3 of the upper shear wall 1 are inserted into the steel sleeves 4 of the lower shear wall 2. A rubber block 5 is fixed to the lower shear wall 2. The cross section of the rubber block 5 is in the shape of an isosceles trapezoid. The length of the rubber block 5 extends along the arrangement direction of each vertical steel bar 3. The rubber block 5 is provided with a plurality of guide holes 6 coaxially arranged with each vertical steel bar 3. Each guide hole 6 is in the shape of an inverted cone. The lower end of the upper shear wall 1 The surface is provided with an installation groove 7 for the rubber block 5 to be embedded; wherein, when the rubber block 5 is in a normal state, the upper end diameter of the guide hole 6 is larger than the outer diameter of the vertical steel bar 3 and the lower end diameter is equal to the outer diameter of the vertical steel bar 3, and the waist slope of the rubber block 5 is larger than the waist slope of the installation groove 7; when the upper shear wall 1 and the lower shear wall 2 are fitted and docked, the rubber block 5 is compressed and deformed, so that the inner wall of the guide hole 6 of the rubber block 5 is fitted and clamped to the outer wall of the vertical steel bar 3, and the waist surface of the rubber block 5 is fitted to the inner wall of the installation groove 7.

[0034] Specifically, the vertical steel bars 3 are arranged side by side in at least two rows, the number of the steel bar sleeves 4 is consistent with the number of the vertical steel bars 3, and the number of the rubber blocks 5 is consistent with the number of rows of the vertical steel bars 3. In this embodiment, the vertical steel bars 3 are arranged in two rows.

[0035] Furthermore, a connecting belt 8 is connected between two adjacent rubber blocks 5, and the connecting belt 8 is located on the side where the rubber block 5 contacts the lower shear wall 2. An embedding groove 9 is provided at the upper end of the lower shear wall 2 for installing the rubber block 5 and the connecting belt 8. A raised portion 10 is provided on the upper end surface of the middle portion of the connecting belt 8, and the raised portion 10 is provided in an arc shape.

[0036] Furthermore, a deformation joint 11 is provided on the upper end surface of the rubber block 5, and the deformation joint 11 extends along the arrangement direction of the guide holes 6, and the deformation joint 11 is connected to the guide holes 6, and the depth of the deformation joint 11 is less than the depth of the guide holes 6. Both waist sides of the rubber strip are coated with waterproof glue.

[0037] Furthermore, a plurality of pre-positioning columns 12 are provided, each of which is pre-inserted and connected between the guide hole 6 and the corresponding steel sleeve 4. The length of the pre-positioning column 12 is less than one-fifth of the length of the steel sleeve 4. When the upper shear wall 1 and the upper shear wall 2 are fitted and spliced, the vertical steel bars 3 just push the pre-positioning column 12 to the bottom of the steel sleeve 4.

[0038] The implementation principle of a shear wall structure for construction in an embodiment of the present application is as follows: a rubber block 5 and a connecting belt 8 are installed on a lower shear wall 2, concrete slurry is poured into a steel sleeve 4, and a pre-positioning column 12 is installed between the rubber block 5 and the steel sleeve 4. During installation, the upper shear wall 1 is downwardly butt-jointed and attached to the lower shear wall 2.

[0039] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A shear wall structure for construction, comprising an upper shear wall (1) and a lower shear wall (2), wherein the vertical steel bars (3) of the upper shear wall (1) are inserted into the steel bar sleeves (4) of the lower shear wall (2), characterized in that: The lower shear wall (2) is provided with a rubber block (5), the cross section of which is in the shape of an isosceles trapezoid. The length of the rubber block (5) is extended along the arrangement direction of each vertical steel bar (3). The rubber block (5) is provided with a plurality of guide holes (6) coaxially arranged with each vertical steel bar (3), each of which is in the shape of an inverted cone. The lower end surface of the upper shear wall (1) is provided with a mounting groove (7) for embedding the rubber block (5); wherein the rubber block (5) is normally In the present embodiment, the diameter of the upper end of the guide hole (6) is greater than the outer diameter of the vertical steel bar (3) and the diameter of the lower end is equal to the outer diameter of the vertical steel bar (3), and the waist slope of the rubber block (5) is greater than the waist slope of the installation groove (7); when the upper shear wall (1) and the lower shear wall (2) are fitted and connected, the rubber block (5) is compressed and deformed, so that the inner wall of the guide hole (6) of the rubber block (5) is fitted and clamped to the outer wall of the vertical steel bar (3), and the waist surface of the rubber block (5) is fitted to the inner wall of the installation groove (7).

2. A shear wall structure for construction according to claim 1, characterized in that: The upper end surface of the rubber block (5) is provided with a deformation seam (11), the deformation seam (11) is extended along the arrangement direction of the guide holes (6), the deformation seam (11) is connected to the guide holes (6), and the depth of the deformation seam (11) is less than the depth of the guide holes (6).

3. A shear wall structure for construction according to claim 1, characterized in that: Both side surfaces of the rubber block (5) are coated with waterproof glue.

4. A shear wall structure for construction according to claim 1, characterized in that: A plurality of pre-positioning columns (12) are also provided, each of the pre-positioning columns (12) is pre-inserted and connected between the guide hole (6) and the corresponding steel sleeve (4), and the length of the pre-positioning column (12) is less than one fifth of the length of the steel sleeve (4).

5. The shear wall structure for construction according to claim 1, characterized in that: The vertical steel bars (3) are arranged side by side in at least two rows, the number of the steel bar sleeves (4) is the same as the number of the vertical steel bars (3), and the number of the rubber blocks (5) is the same as the number of rows of the vertical steel bars (3).

6. A shear wall structure for construction according to claim 5, characterized in that: A connecting belt (8) is connected between two adjacent rubber blocks (5), and the connecting belt (8) is located on a side of the rubber block (5) that contacts the lower shear wall (2).

7. A shear wall structure for construction according to claim 6, characterized in that: The upper end of the lower shear wall (2) is provided with an embedding groove (9) for installing the rubber block (5) and the connecting belt (8).

8. The shear wall structure for construction according to claim 6, characterized in that: A raised portion (10) is provided on the upper end surface of the middle portion of the connecting belt (8).