Fabricated temporarily-built road
By adopting prefabricated temporary road technology and using prefabricated steel fiber concrete assembly for splicing construction, the problems of environmental protection and high cost in existing temporary road construction have been solved, and efficient and environmentally friendly construction results have been achieved.
Patent Information
- Application Number
- CN202421275522.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-05
- Publication Date
- 2025-02-28
- Estimated Expiration
- 2034-06-05
AI Technical Summary
The existing temporary road construction technology uses concrete pouring, which leads to a large amount of construction waste generated during the construction process, which violates environmental protection requirements, and consumes a lot of labor, material and machinery costs, and causes transportation costs during demolition.
The prefabricated temporary road is spliced by prefabricated assembly, including the first assembly and the second assembly poured by steel fiber concrete. The first assembly has a water guide groove and a reinforcement groove. The second assembly has a U-shaped design and a rainwater grate combination, which can be quickly assembled on site.
It significantly shortens the construction period, improves construction efficiency, saves materials, reduces construction waste and transportation costs, meets environmental protection requirements, and improves the stability of the road structure and lifting convenience.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of road construction, and in particular relates to an assembled temporary road. Background Art
[0002] At present, the projects under construction are large in size, wide in site, fast in construction speed and high in efficiency. When constructing temporary roads in the site, they are often directly poured with concrete. In this way, temporary roads need to be demolished as the construction progresses, which will generate a lot of construction waste. This construction technology does not meet the requirements of environmental protection construction, and will also generate a lot of labor costs, material costs, machinery costs, construction waste disposal costs and transportation costs. Utility Model Content
[0003] In order to address the deficiencies in the prior art, the utility model aims to provide an assembled temporary road. The pavement and drainage ditches of the structure are spliced by prefabricated assemblies in the factory. The on-site assembly construction is very simple and convenient, which can greatly shorten the construction period, improve construction efficiency, save a lot of construction materials, and is more economical and environmentally friendly.
[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0005] A prefabricated temporary road comprises a first assembly body which is spliced to form a road surface and a second assembly body which is spliced to form a drainage ditch base trench, wherein the first assembly body comprises an outer shell and a first plate body which is cast with steel fiber concrete, water guide grooves are provided inwardly on the side walls around the first assembly body, and a plurality of first threaded holes for hoisting are provided on the top surface of the first assembly body; the second assembly body comprises a second plate body which is cast with steel fiber concrete and has a U-shaped design, a plurality of second threaded holes for hoisting are provided at the upper opening of the second plate body, and a rainwater grate is also provided at the opening of the second plate body.
[0006] Preferably, a plurality of reinforcing rib grooves are formed upwardly at the bottom of the first assembly body.
[0007] Preferably, the shell is fixed on the bottom and side walls of the first plate body, and the upper opening edge of the shell is provided with a flange folded horizontally toward the middle, and the edge of the flange is provided with a downward buckle edge.
[0008] Preferably, a reinforcing steel cage or a grid structure is provided in the first plate body; the grid structure comprises a plurality of vertically staggered and fixedly connected grid plates.
[0009] Preferably, a first anchoring rib is fixedly provided in the first plate body, a first threaded sleeve is fixedly connected to the first anchoring rib, and an upper end of the first threaded sleeve is arranged flush with the top surface of the first plate body to form the first threaded hole.
[0010] Preferably, the first anchoring bar is of U-shaped or T-shaped design.
[0011] Preferably, tongue-and-groove grooves matching with rainwater grates are provided on both sides of the opening of the second plate body.
[0012] Preferably, a second anchoring rib is vertically provided in the second plate body, a second threaded sleeve is fixedly connected to the upper end of the second anchoring rib, and an upper end of the second threaded sleeve is flush with the bottom surface of the tongue-and-groove groove to form a second threaded hole.
[0013] Preferably, the second anchoring bar is of U-shaped design.
[0014] The beneficial effects of the utility model are:
[0015] 1. The housing of the utility model can significantly enhance the structural strength of the first assembly and improve the structural stability of the road surface. A plurality of reinforcing rib grooves are opened upward from the bottom of the first assembly, and the reinforcing rib grooves can further enhance the structural strength of the first assembly.
[0016] 2. Water channels are opened inward on the side walls around the first assembly. Rainwater that penetrates downward from the road surface can be effectively discharged to both sides of the road through the water channels, thereby effectively avoiding problems such as water accumulation on the road surface.
[0017] 3. The first anchor bar and the first threaded sleeve cooperate to improve the hoisting structural strength and hoisting stability of the first assembly. In addition, the first anchor bar and the first threaded sleeve are pre-embedded in the first assembly, so there is no need to temporarily open a hoisting hole during hoisting, which is more convenient to use and improves construction efficiency.
[0018] 4. Both sides of the opening of the second plate body are provided with tongue-and-groove grooves matched with the rainwater grate. The tongue-and-groove grooves cooperate with the rainwater grate to improve the installation stability of the rainwater grate.
[0019] 5. The second anchor bar cooperates with the second threaded sleeve to improve the lifting structural strength and lifting stability of the second assembly, and the second threaded hole can be directly used for lifting connection without additional drilling, which significantly improves the lifting convenience of the second assembly.
[0020] 6. Matching plastic thread protection covers can be set in the first threaded hole and the second threaded hole, so as to effectively block and protect the unused threaded holes to prevent foreign matter from entering the subsequent use of the film. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a structural diagram of the first assembly in Example 1 of the utility model;
[0022] Figure 2 This is an internal cross-sectional view of the first assembly in Example 1 of the utility model;
[0023] Figure 3This is a structural diagram of the outer shell of the first assembly in Example 1 of the utility model;
[0024] Figure 4 This is a structural diagram of the first anchoring bar in Example 1 of the utility model;
[0025] Figure 5 It is a structural diagram of the first assembly in Example 2 of the utility model;
[0026] Figure 6 This is a diagram showing the internal structure of the first assembly in Embodiment 2 of the present utility model;
[0027] Figure 7 This is a structural diagram of the outer shell of the first assembly in Embodiment 2 of the present utility model;
[0028] Figure 8 This is a structural diagram of the grid structure in Example 2 of the utility model;
[0029] Fig. 9 It is a structural diagram of the second assembly of the utility model;
[0030] Fig.10 This is the internal structure diagram of the second assembly of the utility model;
[0031] Fig.11 This is a structural diagram of the second anchor bar of the utility model. DETAILED DESCRIPTION
[0032] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not intended to limit the scope of use of the present invention.
[0033] Embodiment 1:
[0034] like Figure 1-4 and Figure 9-11 As shown, the utility model proposes an assembled temporary road, including a first assembly 1 spliced to form a road surface and a second assembly 3 spliced to form a drainage ditch base trench, the square first assembly 1 includes an outer shell 101 and a first plate 102 cast by steel fiber concrete, the outer shell 101 is fixed on the bottom and side walls of the first plate 102, and the upper opening edge of the outer shell 101 is provided with a flange 1011 folded horizontally toward the middle, and the edge of the flange 1011 is provided with a downward buckle edge 1012, thereby improving the connection stability between the outer shell 101 and the first plate 102. The outer shell 101 can significantly enhance the structural strength of the first assembly 1 and improve the structural stability of the road surface. In addition, in this embodiment, a plurality of reinforcing rib grooves 13 are opened upward from the bottom of the first assembly 1, and the reinforcing rib grooves 13 can further improve the structural strength of the first assembly 1.
[0035] The first assembly body 1 is provided with water guide grooves 11 on the side walls thereof. Rainwater penetrating downward from the road surface can be effectively discharged to both sides of the road through the water guide grooves 11, thereby effectively avoiding problems such as water accumulation on the road surface.
[0036] During specific implementation, the shell 101 is made of Q355B10mm steel plate to form a cuboid structure, which is 2000mm long, 1500mm wide and 300mm high. The bottom surface is made into a trapezoidal protrusion along the length as a reinforcing rib groove 13, the trapezoid is 150mm wide at the bottom, 50mm wide at the top and 50mm high, the trapezoidal protrusion is set 150mm away from the edge, and the rest is 200mm apart. The sides are made into a trapezoidal groove in the middle position as a water guide groove 11, the trapezoid is 100mm wide at the bottom, 60mm wide at the top and 20mm high. An 80mm flange 1011 is set on each side of the shell 101, and the ends of the flange 1011 are bent downward by 32mm to form a buckle edge 1012.
[0037] The first plate body 102 can be a rectangular parallelepiped structure cast using C30 steel fiber concrete, with a length of 2000 mm, a width of 1500 mm, and a height of 300 mm. A reinforcing steel cage 103 is arranged inside the first plate body 102, and the reinforcing steel cage 103 is composed of three-level 18 steel bars in double rows and two directions, and three-level 8@300 as hooks. A U-shaped first anchor bar 22 made of a first-level 20 steel bar is arranged at a position 350 mm away from the frame. The surface layer of the first plate body 102 is finished.
[0038] A plurality of first threaded holes 2 for hoisting are provided on the top surface of the first assembly 1. Specifically, a first anchoring rib 22 is pre-embedded in the first plate body 102, and a first threaded sleeve 21 is fixedly connected to the first anchoring rib 22. The upper port of the first threaded sleeve 21 is arranged flush with the top surface of the first plate body 102 to form the first threaded hole 2. The first anchoring rib 22 can be U-shaped or T-shaped. The cooperation between the first anchoring rib 22 and the first threaded sleeve 21 can improve the hoisting structural strength and hoisting stability of the first assembly 1. In addition, the first anchoring rib 22 and the first threaded sleeve 21 are pre-embedded in the first assembly 1, and there is no need to temporarily open a hoisting hole during hoisting, which is more convenient to use and improves construction efficiency.
[0039] Specifically, when the first anchor bar 22 is U-shaped, a U-shaped structure with a length of 800 mm and a height of 210 mm can be made using a grade 20 steel bar. A nut or a straight threaded sleeve (i.e., the first threaded sleeve 21) with a length of 40 mm and an inner diameter of 20 mm is welded at the top of the U-shaped structure.
[0040] When the first anchor bar 22 is T-shaped, a 20-diameter steel bar of the first grade can be used to make a T-shaped structure, which is 200 mm long and 130 mm high. A nut or a straight threaded sleeve (i.e., the first threaded sleeve 21) with a length of 40 mm and an inner diameter of 20 mm is welded to the top of the T-shaped structure.
[0041] The second assembly 3 includes a second plate body cast by steel fiber concrete and designed in a U shape. The opening of the second plate body is provided with a tongue-and-groove groove 31 matched with the rain grate 5 on both sides. The tongue-and-groove groove 31 cooperates with the rain grate 5 to improve the installation stability of the rain grate 5. A plurality of second threaded holes 4 for hoisting are provided at the upper opening of the second plate body. Specifically, a second anchoring rib 42 is vertically provided in the second plate body, and a second threaded sleeve 41 is fixedly connected to the upper end of the second anchoring rib 42. The upper end of the second threaded sleeve 41 is flush with the bottom surface of the tongue-and-groove groove 31 to form a second threaded hole 4. In this embodiment, the second anchoring rib 42 is U-shaped. The second anchoring rib 42 cooperates with the second threaded sleeve 41 to improve the hoisting structural strength and hoisting stability of the second assembly 3, and the second threaded hole 4 can be directly used for hoisting connection without drilling additional holes, which significantly improves the hoisting convenience of the second assembly 3.
[0042] In specific implementation, the second assembly block can be cast using C30 steel fiber concrete, and its U-shaped groove structure is 1000 mm long and 600 mm high, and an 8@150 steel cage 103 is matched and arranged inside.
[0043] The second anchor bar 42 and the second threaded sleeve 41 can be made of a 16mm diameter steel bar into a U-shaped structure and welded with a nut or a straight threaded sleeve with an inner diameter of 16mm, and placed 200mm away from the end of the U-shaped groove structure.
[0044] The U-shaped groove of the second assembly 3 is provided with a 50*50mm groove 31 at both ends, which is used to place the rainwater grate 5 later. The width and depth of the groove 31 are both 5mm. In addition, in this embodiment, a 100mm diameter round hole 32 is provided at a position 500mm from the end and 250mm from the top of the U-shaped groove structure of the second assembly 3.
[0045] In addition, in this embodiment, matching plastic thread protection covers can be provided in the first threaded hole 2 and the second threaded hole 4, so as to effectively seal and protect the unactivated threaded holes to prevent foreign matter from entering and affecting subsequent use.
[0046] Embodiment 2:
[0047] The difference from Example 1 is that the bottom of the first plate body 102 in this embodiment is a flat design. In this design, the outer shell 101 is made of Q355B steel plate and is formed into a rectangular structure (2000mm long, 1500mm wide, and 250mm high). The bottom steel plate thickness is 20mm, and the thickness of the steel plates in other parts is 10mm. Trapezoidal grooves are made on the sides at a position 50mm away from the bottom as water guide grooves 11. The trapezoid is 100mm wide at the bottom, 60mm wide at the top, and 20mm high. The top steel plate is provided with holes of 200mm in length and 150mm in width at four positions 365mm away from the long side and 295mm away from the short side. In this embodiment, the first anchor bar 22 of the T-shaped structure made of a grade 20 steel bar in diameter can be installed in the first plate body 102 at a position 295mm away from its short side and 365mm away from its long side.
[0048] In this embodiment, the first plate body 102 can be a rectangular parallelepiped structure (length 2000mm, width 1500mm, height 250mm) cast with C30 steel fiber concrete, in which a grid structure 104 is arranged, and the grid structure 104 includes a plurality of vertically staggered and fixedly connected grid plates. The grid structure 104 can be composed of a grid structure 104 with a length of 1980mm and a width of 1480mm using Q355B steel plates with a thickness of 10mm and a height of 220mm, the net size of the four corner grids is 135*185mm, the net size of the grids adjacent to the long side is 135*190mm, the net size of the grids adjacent to the short side is 140*185mm, and the net size of the remaining grids is 140*190mm, and each grid steel plate is centered with a size of 50*100mm.
[0049] Accordingly, the construction method of the above-mentioned prefabricated temporary road includes the following steps:
[0050] S1. Use soil mixed with curing agent and cement to make solidified soil, and then find the slope from the middle of the road to both sides with a slope of 5%. After rolling and forming, the road base layer is cured;
[0051] S2. While maintaining the soil, use excavation equipment to dig a drainage ditch foundation trench of a certain depth close to the road edge according to the construction situation;
[0052] S3. Use the lifting equipment to lift and install the second assembly 3 in sequence to match the U-shaped drain ditch base groove;
[0053] S4. The second assembly 3 is connected with a 5mm thick special mortar, and after the special mortar solidifies, the weather-resistant sealant is used to seal the tongue-and-groove 31 at the joint position;
[0054] S5. Backfill the gap between the second assembly 3 and the drainage ditch foundation trench; the circular hole 32 with a diameter of 100 mm on one side of the second assembly 3 adjacent to the road is blocked with a geotextile wrapped filter material, and the other side is blocked with a matching size rubber threaded cap;
[0055] S6. Install a rainwater grate 5 of matching size on the gutter assembly to complete the gutter construction;
[0056] S7. Use lifting equipment to lift and install the pavement assembly, and splice and install the pavement assembly in sequence according to different width layout diagrams on the pavement base layer, so that they are combined into a complete temporary road.
[0057] Obviously, the embodiments described above are only some embodiments of the present application, rather than all embodiments. The preferred embodiments of the present application are given in the accompanying drawings, but they do not limit the patent scope of the present application. The present application can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present application more thorough and comprehensive. Although the present application is described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned specific implementation methods, or to perform equivalent replacement of some of the technical features therein. Any equivalent structure made using the contents of the specification and drawings of this application, directly or indirectly used in other related technical fields, is similarly within the scope of patent protection of this application.
Claims
1. A prefabricated temporary road, characterized in that: It includes a first assembly body that is spliced to form a road surface and a second assembly body that is spliced to form a drainage ditch base trench. The first assembly body includes an outer shell and a first plate body that is cast with steel fiber concrete. Water guide grooves are opened inward on the side walls around the first assembly body. A plurality of first threaded holes for hoisting are arranged on the top surface of the first assembly body. The second assembly body includes a second plate body that is cast with steel fiber concrete and has a U-shaped design. A plurality of second threaded holes for hoisting are arranged at the upper opening of the second plate body, and a rainwater grate is also provided at the opening of the second plate body.
2. The assembled temporary road according to claim 1 is characterized in that: A plurality of reinforcing rib grooves are formed upwardly at the bottom of the first assembly body.
3. The assembled temporary road according to claim 1 is characterized in that: The shell is fixed on the bottom and side walls of the first plate body, and the upper opening edge of the shell is provided with a flange horizontally folded toward the middle, and the edge of the flange is provided with a downward buckle edge.
4. The assembled temporary road according to any one of claims 1 to 3, characterized in that: A reinforcing steel cage is arranged inside the first plate body.
5. The assembled temporary road according to any one of claims 1 to 3, characterized in that: A grid structure is disposed in the first plate body, and the grid structure includes a plurality of vertically staggered and fixedly connected grid plates.
6. The assembled temporary road according to claim 1, characterized in that: A first anchoring rib is fixedly disposed in the first plate body, a first threaded sleeve is fixedly connected to the first anchoring rib, and an upper end of the first threaded sleeve is flush with the top surface of the first plate body to form the first threaded hole.
7. The assembled temporary road according to claim 6 is characterized in that: The first anchoring bar is of U-shaped or T-shaped design.
8. The assembled temporary road according to claim 1 is characterized in that: Both sides of the opening of the second plate body are provided with tongue-and-groove grooves matched with the rainwater grate.
9. The assembled temporary road according to claim 8, characterized in that: A second anchoring rib is vertically arranged in the second plate body, a second threaded sleeve is fixedly connected to the upper end of the second anchoring rib, and an upper end of the second threaded sleeve is flush with the bottom surface of the tongue-and-groove groove to form a second threaded hole.
10. The assembled temporary road according to claim 9, characterized in that: The second anchoring bar is of U-shaped design.