Pouring device for highway building construction

By designing a highway construction pouring device that includes angle adjustment support components, sealed feeding components and adjusting pouring components, the problems of unevenness and inefficiency in the prior art are solved, and the uniform pouring of concrete and the improvement of construction efficiency are achieved.

CN222541208UActive Publication Date: 2025-02-28HUBEI IND CONSTR GENERAL CONSTRUCT GRP MECHANIZATION CONSTR CO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421661405.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2025-02-28
Estimated Expiration
2034-07-15

AI Technical Summary

Technical Problem

The existing highway construction pouring devices are mostly hand-held for pouring, resulting in uneven pouring and reducing work efficiency.

Method used

A casting device including an angle adjustment support assembly, a sealing feed assembly and a adjusting casting assembly is designed. The angle adjustment support assembly can adjust the direction of the device according to needs, sealing the feeding assembly to ensure uniform conveying of the concrete, and adjusting the pouring assembly to achieve automatic casting.

Benefits of technology

Through the use of this device, the uniform and stable pouring of concrete can be achieved, labor intensity can be reduced, construction efficiency can be improved, and the quality and safety of the building structure can be ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

The utility model relates to the field of pouring devices, in particular to a pouring device for highway building construction. The technical problem that most pouring devices are manually held by hands for pouring, so that pouring is not uniform, and the working efficiency is reduced is solved. According to the technical scheme, the pouring device for highway building construction comprises a pouring device body. The device can be stably supported by arranging the angle adjusting and supporting assembly, the direction can be adjusted according to the requirement of the pouring direction, concrete can be conveyed to a construction position from stirring equipment through the sealed feeding assembly, and uniform and stable pouring is carried out, so that a foundation and support of a building structure are formed, and the construction efficiency is improved. The adjusting pouring assembly can automatically carry out concrete pouring, the labor intensity of workers is reduced, the construction efficiency is improved, the concrete pouring can be automatically carried out, the labor intensity of workers is reduced, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of casting devices, in particular to a casting device for highway construction. Background Art

[0002] The pouring device for highway construction is a device used for concrete pouring, and its functions and importance are as follows: Function: Concrete pouring: The main function is to transport concrete from the mixing equipment to the construction site, and to pour it evenly and stably to form the foundation and support of the building structure; Improve construction efficiency: The pouring device can automatically pour concrete, reduce manual labor intensity, and improve construction efficiency; Ensure pouring quality: By accurately controlling the flow and distribution of concrete, the pouring device can ensure the pouring quality and avoid quality problems such as hollowing and cracks. Importance: Construction efficiency: The use of the pouring device can greatly improve construction efficiency, shorten construction period, and reduce construction costs; Construction quality: The pouring device can ensure the uniformity and stability of concrete, and ensure the firmness and durability of the building structure; Safety: The automated pouring device can reduce manual operation, reduce safety risks on the construction site, and ensure the safety of construction personnel; However, most of the existing pouring devices are manually handheld for pouring, which leads to uneven pouring and reduces work efficiency. The pouring device of the utility model provides a device that can pour evenly as needed to improve work efficiency. Utility Model Content

[0003] In order to overcome the problem that the pouring device is mostly manually held for pouring during use, resulting in uneven pouring and reduced work efficiency.

[0004] The technical solution of the utility model is: a pouring device for highway construction, including a pouring device body, and also including an angle adjustment support component, a sealing feed component, and an adjustment pouring component; the pouring device body is divided into an angle adjustment support component for stabilizing the support device; the lower end of the angle adjustment support component is fixedly installed with a sealing feed component for feeding; the upper end of the angle adjustment support component is rotatably connected with an adjustment pouring component for pouring in construction.

[0005] Preferably, the angle-adjustable support assembly can provide stable support for the device, and can adjust the direction according to the needs of the pouring direction. The sealed feed assembly can transport concrete from the mixing equipment to the construction location, and pour it evenly and stably to form the foundation and support of the building structure. The adjustable pouring assembly can automatically pour concrete, reduce manual labor intensity, and improve construction efficiency. The concrete pouring can be automatically poured, reduce manual labor intensity, and improve construction efficiency.

[0006] Preferably, the angle adjustment support assembly includes a working frame, a limit mounting groove ring, a suction pump, a feeding pipe, a booster, an auxiliary support plate and a load-bearing arc plate; a limit mounting groove ring is fixedly installed on the upper end of the working frame; a suction pump is arranged inside the limit mounting groove ring, and the suction pump inside the limit mounting groove ring sucks the building materials in the storage tank into the feeding pipe, and pressurizes them through the booster, and the load-bearing arc plate on the upper end of the auxiliary support plate can support the connecting material pipe to improve the stability of the device.

[0007] Preferably, the upper end of the suction pump is fixedly connected to a feeding pipe; a booster is provided at the upper end of the feeding pipe; an auxiliary support plate is provided inside the work frame; a load-bearing arc plate is fixedly installed at the upper end of the auxiliary support plate, and the limit rotation groove ring is placed in the limit installation groove ring, and the direction can be adjusted according to the needs of the casting direction.

[0008] Preferably, the sealed feed assembly includes a storage tank, a feed receiving pipe, a first locking block, a sealing gasket, a second locking block and a feed pipe; the storage tank is fixedly installed at the lower end of the working frame; the side end of the storage tank is fixedly connected to the feed receiving pipe, the working frame is placed in a stable position, the second locking block at the side end of the feed pipe is snap-fitted into the first locking block at the side end of the feed pipe to make a firm connection, and the sealing gasket has sealing properties to prevent concrete from overflowing.

[0009] Preferably, a first locking block is provided at the side end of the material receiving pipe; a sealing gasket is provided at the side end of the first locking block; a second locking block is snap-fitted and installed at the side end of the first locking block; and a feeding pipe is provided at the side end of the second locking block, which can transport concrete from the mixing equipment to the storage tank and pour it evenly and stably to form the foundation and support of the building structure.

[0010] Preferably, the adjusting casting assembly includes a limited position rotating groove ring, a connecting through pipe, a steel rod, a feed trough, a counterweight box, a counterweight block, an electric telescopic rod, a limit arc plate and a limit casting block; the limited position rotating groove ring is rotatably connected inside the limit installation groove ring; the upper end of the limit rotating groove ring is fixedly connected to a connecting through pipe; the upper end of the connecting through pipe is fixedly connected to a steel rod, the counterweight block is placed in the counterweight box, the casting pipe is passed through the feed trough opened in the steel rod, and the limit is placed on the limit arc plate at the upper end of the electric telescopic rod, which can be required according to the casting position.

[0011] Preferably, a material conveying trough is opened inside the steel rod; a counterweight box is fixedly installed on the upper end of the steel rod; a counterweight block is placed inside the counterweight box with a limit position; an electric telescopic rod is fixedly installed on the upper end of the steel rod; a limit arc plate is fixedly installed on the upper end of the electric telescopic rod; a limit casting block is fixedly installed on the movable end of the electric telescopic rod, and the electric telescopic rod is started to extend and retract, and concrete pouring is automatically carried out, which reduces manual labor intensity and improves construction efficiency. Concrete pouring can be automatically carried out, which reduces manual labor intensity and improves construction efficiency.

[0012] Beneficial effects of the utility model:

[0013] 1. During use, the angle adjustment support assembly can provide a stable support for the device, and can adjust the direction according to the needs of the pouring direction. The sealed feeding assembly can transport the concrete from the mixing equipment to the construction location, and pour it evenly and stably to form the foundation and support of the building structure. The pouring assembly can automatically pour concrete, reduce the labor intensity, and improve the construction efficiency. It can automatically pour concrete, reduce the labor intensity, and improve the construction efficiency.

[0014] 2. The suction pump in the limited installation groove ring sucks the building materials in the storage tank into the feeding pipe, and the pressure is increased by the booster. The load-bearing arc plate on the upper end of the auxiliary support plate can support the material pipe to improve the stability of the device. The limited rotation groove ring is placed in the limited installation groove ring, and the direction can be adjusted according to the needs of the casting direction;

[0015] 3. Place the work stand in a stable position, and fit the second locking block at the side end of the feed pipe into the first locking block at the side end of the receiving pipe to make a stable connection. The sealing gasket has sealing properties to prevent concrete from overflowing. The concrete can be transported from the mixing equipment to the storage tank and poured evenly and stably to form the foundation and support of the building structure.

[0016] 4. Place the counterweight block in the counterweight box, pass the pouring pipe through the feed trough opened in the steel rod, and place the limit on the limit arc plate at the upper end of the electric telescopic rod. According to the needs of the pouring position, the electric telescopic rod can be started to extend and retract, and the concrete pouring can be carried out automatically, reducing the labor intensity and improving the construction efficiency. The concrete pouring can be carried out automatically, reducing the labor intensity and improving the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 What is shown is a three-dimensional structural schematic diagram of the pouring device of the utility model;

[0018] Figure 2 Shown is a schematic diagram of the angle adjustment support assembly structure of the pouring device of the utility model;

[0019] Figure 3 Shown is a schematic diagram of a sealed feed assembly of a casting device of the utility model;

[0020] Figure 4 Shown is a schematic diagram of the adjusting pouring component of the pouring device of the utility model.

[0021] Explanation of the reference numerals in the accompanying drawings: 1. Casting device body; 2. Angle adjustment support assembly; 3. Sealing feed assembly; 4. Adjusting casting assembly; 201. Working frame; 202. Limiting installation groove ring; 203. Suction pump; 204. Feeding pipe; 205. Supercharger; 206. Auxiliary support plate; 207. Load-bearing arc plate; 301. Storage tank; 302. Material receiving pipe; 303. First locking block; 304. Sealing pad; 305. Second locking block; 306. Feeding pipe; 401. Limiting rotating groove ring; 402. Connecting through pipe; 403. Steel rod; 404. Feed trough; 405. Counterweight box; 406. Counterweight block; 407. Electric telescopic rod; 408. Limiting arc plate; 409. Limiting casting block. DETAILED DESCRIPTION

[0022] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0023] See also Figure 1 The utility model provides an embodiment: a pouring device for highway construction, comprising a pouring device body 1, and also comprising an angle adjustment support assembly 2, a sealing feed assembly 3, and an adjustment pouring assembly 4; the pouring device body 1 is divided into an angle adjustment support assembly 2 for stabilizing the support device; a sealing feed assembly 3 for feeding is fixedly installed at the lower end of the angle adjustment support assembly 2; an adjustment pouring assembly 4 for pouring in construction is rotatably connected to the upper end of the angle adjustment support assembly 2; the angle adjustment support assembly 2 can stably support the device and can adjust the direction according to the needs of the pouring direction; the sealing feed assembly 3 can transport concrete from the mixing equipment to the construction location and pour it evenly and stably to form the foundation and support of the building structure; the adjustment pouring assembly 4 can automatically pour concrete, reduce the labor intensity of manual labor, and improve the construction efficiency; the angle adjustment support assembly 2 can automatically pour concrete, reduce the labor intensity of manual labor, and improve the construction efficiency.

[0024] See also Figure 2In this embodiment, the angle adjustment support assembly 2 includes a work frame 201, a limit installation groove ring 202, a suction pump 203, a feeding pipe 204, a supercharger 205, an auxiliary support plate 206 and a load-bearing arc plate 207; the upper end of the work frame 201 is fixedly installed with a limit installation groove ring 202; the limit installation groove ring 202 is provided with a suction pump 203, and the upper end of the suction pump 203 is fixedly connected with the feeding pipe 204; the upper end of the feeding pipe 204 is provided with a supercharger 205; the work frame 201 is provided with an auxiliary support plate 206 and a load-bearing arc plate 207; Auxiliary support plate 206; a load-bearing arc plate 207 is fixedly installed on the upper end of the auxiliary support plate 206, and the suction pump 203 in the limit installation groove ring 202 sucks the building materials in the storage tank 301 into the feeding pipe 204, and the pressure is increased by the supercharger 205. The load-bearing arc plate 207 on the upper end of the auxiliary support plate 206 can support the docking pipe 302 to improve the stability of the device, and the limit rotation groove ring 401 is placed in the limit installation groove ring 202, and the direction can be adjusted according to the needs of the casting direction.

[0025] See also Figure 3-4In this embodiment, the sealed feed assembly 3 includes a storage tank 301, a material receiving pipe 302, a first locking block 303, a sealing gasket 304, a second locking block 305 and a feed pipe 306; the storage tank 301 is fixedly installed at the lower end of the work frame 201; the side end of the storage tank 301 is fixedly connected to the material receiving pipe 302, and the side end of the material receiving pipe 302 is provided with a first locking block 303; the side end of the first locking block 303 is provided with a sealing gasket 304; the side end of the first locking block 303 is clamped and installed with a second locking block 305; the side end of the second locking block 305 is provided with a feed pipe 306 , place the work stand 201 in a stable position, and fit the second locking block 305 at the side end of the feeding pipe 306 into the first locking block 303 at the side end of the receiving pipe 302 for a firm connection. The sealing pad 304 has a sealing property to prevent concrete from overflowing. The concrete can be transported from the mixing equipment to the storage tank 301 and poured evenly and stably to form the foundation and support of the building structure. The pouring assembly 4 includes a limited position rotating groove ring 401, a connecting through pipe 402, a steel rod 403, a feeding trough 404, a counterweight box 405, a counterweight block 406, and an electric The movable telescopic rod 407, the limiting arc plate 408 and the limiting casting block 409; the limiting installation groove ring 202 is internally rotatably connected to the limiting rotation groove ring 401; the upper end of the limiting rotation groove ring 401 is fixedly connected to the connecting pipe 402; the upper end of the connecting pipe 402 is fixedly connected to the steel rod 403, and the steel rod 403 is provided with a feeding trough 404; the upper end of the steel rod 403 is fixedly installed with a counterweight box 405; the counterweight block 406 is placed in the counterweight box 405; the upper end of the steel rod 403 is fixedly installed with an electric telescopic rod 407; the upper end of the electric telescopic rod 407 is fixed A limit arc plate 408 is fixedly installed; a limit casting block 409 is fixedly installed at the movable end of the electric telescopic rod 407, the counterweight block 406 is placed in the counterweight box 405, the casting pipe is passed through the feed trough 404 opened in the steel rod 403, and the limit is placed on the limit arc plate 408 at the upper end of the electric telescopic rod 407. The electric telescopic rod 407 can be started to extend and retract according to the needs of the casting position, and concrete casting can be automatically carried out, reducing manual labor intensity and improving construction efficiency. Concrete casting can be automatically carried out, reducing manual labor intensity and improving construction efficiency.

[0026] When in use, first place the work stand 201 in a stable position, and fit the second locking block 305 at the side end of the feed pipe 306 into the first locking block 303 at the side end of the receiving pipe 302 to achieve a stable connection. The sealing pad 304 has a sealing property to prevent concrete from overflowing. The concrete can be transported from the mixing equipment to the storage tank 301, and poured evenly and stably to form the foundation and support of the building structure.

[0027] Then, the suction pump 203 in the limited installation groove ring 202 sucks the building materials in the storage tank 301 into the feeding pipe 204, and the pressure is increased by the supercharger 205. The load-bearing arc plate 207 on the upper end of the auxiliary support plate 206 can support the connecting material pipe 302 to improve the stability of the device. Finally, the limited rotation groove ring 401 is limitedly placed in the limited installation groove ring 202, and the direction can be adjusted according to the needs of the casting direction. The counterweight block 406 is placed in the counterweight box 405, and the casting pipe is passed through the feed trough 404 opened in the steel rod 403, and is limitedly placed on the limited arc plate 408 on the upper end of the electric telescopic rod 407. The electric telescopic rod 407 can be started to extend and retract according to the needs of the casting position, and concrete pouring can be carried out automatically, reducing manual labor intensity and improving construction efficiency. Concrete pouring can be carried out automatically, reducing manual labor intensity and improving construction efficiency.

[0028] Through the above steps, setting the angle adjustment support component 2 can provide a stable support for the device, and can adjust the direction according to the needs of the pouring direction. The sealed feeding component 3 can transport the concrete from the mixing equipment to the construction location, and pour it evenly and stably to form the foundation and support of the building structure. The adjusting pouring component 4 can automatically pour concrete, reduce manual labor intensity, and improve construction efficiency. It can automatically pour concrete, reduce manual labor intensity, and improve construction efficiency.

[0029] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the purpose of the present invention.

Claims

1. A pouring device for highway construction, comprising a pouring device body (1); characterized in that: The invention also comprises an angle adjustment support assembly (2), a sealing material feeding assembly (3), and an adjustment pouring assembly (4); the pouring device body (1) is divided into an angle adjustment support assembly (2) for stabilizing the support device; the lower end of the angle adjustment support assembly (2) is fixedly mounted with a sealing material feeding assembly (3) for feeding; the upper end of the angle adjustment support assembly (2) is rotatably connected with an adjustment pouring assembly (4) for pouring in building construction.

2. A pouring device for highway construction according to claim 1, characterized in that: The angle adjustment support assembly (2) comprises a working frame (201), a limit installation groove ring (202), a suction pump (203), a feeding pipe (204), a booster (205), an auxiliary support plate (206) and a load-bearing arc plate (207); the limit installation groove ring (202) is fixedly mounted on the upper end of the working frame (201); and the suction pump (203) is arranged inside the limit installation groove ring (202).

3. A pouring device for highway construction according to claim 2, characterized in that: The upper end of the suction pump (203) is fixedly connected to a feeding pipe (204); the upper end of the feeding pipe (204) is provided with a booster (205); an auxiliary support plate (206) is provided inside the working frame (201); and a load-bearing arc plate (207) is fixedly installed on the upper end of the auxiliary support plate (206).

4. A pouring device for highway construction according to claim 2, characterized in that: The sealed material feeding assembly (3) comprises a storage tank (301), a material receiving pipe (302), a first locking block (303), a sealing gasket (304), a second locking block (305) and a material feeding pipe (306); the storage tank (301) is fixedly mounted on the lower end of the working frame (201); and the material receiving pipe (302) is fixedly connected to the side end of the storage tank (301).

5. A pouring device for highway construction according to claim 4, characterized in that: A first locking block (303) is provided at the side end of the material receiving pipe (302); a sealing gasket (304) is provided at the side end of the first locking block (303); a second locking block (305) is mounted in engagement with the side end of the first locking block (303); and a material feeding pipe (306) is provided at the side end of the second locking block (305).

6. A pouring device for highway construction according to claim 2, characterized in that: The regulating pouring assembly (4) comprises a limit groove ring (401), a connecting pipe (402), a steel rod (403), a material conveying trough (404), a counterweight box (405), a counterweight block (406), an electric telescopic rod (407), a limit arc plate (408) and a limit pouring block (409); the limit installation groove ring (202) is internally rotatably connected to the limit groove ring (401); the upper end of the limit groove ring (401) is fixedly connected to the connecting pipe (402); and the upper end of the connecting pipe (402) is fixedly connected to the steel rod (403).

7. A pouring device for highway construction according to claim 6, characterized in that: A material conveying trough (404) is provided inside the steel rod (403); a counterweight box (405) is fixedly installed at the upper end of the steel rod (403); a counterweight block (406) is placed inside the counterweight box (405) to limit the position; an electric telescopic rod (407) is fixedly installed at the upper end of the steel rod (403); a limit arc plate (408) is fixedly installed at the upper end of the electric telescopic rod (407); and a limit casting block (409) is fixedly installed at the movable end of the electric telescopic rod (407).