Electric furnace flue gas combustion settling chamber

By setting up a heat storage rod with a T-cell structure in the electric furnace flue gas combustion settlement room, the thermal shock damage and dust scaling problems caused by drastic flue gas temperature are solved, and the purpose of improving heat transfer efficiency and dust settlement effect is achieved.

CN222578954UActive Publication Date: 2025-03-07WUXI HONGQI DUST COLLECTOR EQUIP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420407186.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-04
Publication Date
2025-03-07
Estimated Expiration
2034-03-04

AI Technical Summary

Technical Problem

The electric furnace flue gas combustion settlement chamber is prone to thermal shock damage when the flue gas temperature changes periodically, and the dust in the high-temperature flue gas is prone to stick to the surface of the heat storage device, resulting in scaling and reducing heat exchange efficiency.

Method used

A heat storage rod with a T-cell structure in the housing is arranged in a settlement chamber perpendicular to the direction of the flue gas flow. The flue gas flow is accelerated through the pits of the T-cell structure, improving heat transfer efficiency, and enhancing the turbulence of the flue gas and dust settlement effect through the combination of the shock wave soot blower.

Benefits of technology

It effectively solves the problem of thermal shock damage caused by drastic flue temperature, improves the heat transfer efficiency between the flue gas and the heat storage rod, reduces the possibility of dust stickiness, extends the service life of the equipment and improves the heat exchange efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222578954U_ABST
    Figure CN222578954U_ABST
Patent Text Reader

Abstract

The utility model relates to an electric furnace flue gas combustion settling chamber, which comprises a settling chamber, a combustion chamber and a combustion chamber, the heat storage rod is fixed at the upper end in the settling chamber and is vertical to the high-temperature flue gas circulation direction, and the heat storage rod comprises a shell which comprises a dimpled structure which is arranged on the surface of the shell and is a pit; and the shell is filled with the heat storage material. When flue gas flows through the pits of the dimpled structures, due to the separation effect of the boundary layers, flue gas flow is locally separated along the surfaces of the pits to generate vortexes, the flowing turbulence of the gas flow around the dimpled structures is increased, the structures of the boundary layers are damaged, and therefore the heat transfer effect of the flue gas on the heat storage rods is improved. Meanwhile, vortexes in the dimpled structure can also achieve the effect similar to an air cushion, resistance is reduced, the flow speed is increased, and the heat exchange rate is increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of flue gas treatment equipment, in particular to an electric furnace flue gas combustion settling chamber. Background Art

[0002] The flue gas volume and temperature of the electric furnace change periodically during the smelting process, resulting in the flue gas volume and temperature entering the waste heat boiler to change periodically. The electric furnace smelting cycle is about 35 to 45 minutes, and the flue gas temperature fluctuates between 200 and 1200°C.

[0003] The flue gas combustion settling chamber of an electric furnace usually includes a settling chamber and a heat accumulator connected to the outside of the settling chamber. It is difficult for the external heat accumulator to adjust the temperature of the flue gas entering the settling chamber in the first time. The periodic temperature changes of the flue gas can easily cause thermal shock damage to the structure inside the settling chamber, affecting the service life of the equipment.

[0004] In addition, the high-temperature flue gas contains a large amount of high-temperature molten particulate matter, which easily sticks to the surface of the heat accumulator, causing dust and scaling on the surface of the heat accumulator, reducing the heat exchange efficiency.

[0005] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present disclosure, and therefore may include information that does not constitute the prior art known to ordinary technicians in the field. Utility Model Content

[0006] In view of the deficiencies in the prior art, an embodiment of the utility model discloses an electric furnace smoke combustion settling chamber, in which a heat storage rod with an outer shell having a cell structure is arranged perpendicular to the smoke flow direction in the settling chamber to solve the problem of thermal shock damage to the structure in the settling chamber caused by periodic temperature changes of the smoke.

[0007] The technical solution adopted by the utility model is as follows:

[0008] An electric furnace flue gas combustion settling chamber comprises: a settling chamber with a hollow structure and high-temperature flue gas flowing inside; a heat storage rod fixed at the upper end of the interior of the settling chamber and perpendicular to the flow direction of the high-temperature flue gas, comprising: an outer shell, comprising: a cellular structure, which is a pit arranged on the surface of the outer shell; and a heat storage material filled in the outer shell.

[0009] A further technical solution is that the heat storage rods are staggeredly arranged at the upper end of the sedimentation chamber.

[0010] A further technical solution is that the heat storage rod includes: a screw rod, which is arranged at the upper end of the outer shell and passes through the upper end of the sedimentation chamber; a double nut, which is screwed on the screw rod and located at the upper end of the sedimentation chamber; wherein, tightening the double nut fixes the heat storage rod and the sedimentation chamber together.

[0011] A further technical solution is that the electric furnace flue gas combustion settling chamber includes: a shock wave soot blower, which is arranged at the upper end of the interior of the settling chamber and located on the side of the heat storage rod; wherein the nozzle of the shock wave soot blower faces the surface of the heat storage rod.

[0012] A further technical solution is that the sedimentation chamber adopts a membrane water-cooled wall.

[0013] Its further technical solution is that the electric furnace smoke combustion sedimentation chamber includes: a combustion chamber, which is arranged on one side of the upper end of the sedimentation chamber and is connected to the sedimentation chamber, including: an inlet, which is arranged at the upper end of the combustion chamber; the sedimentation chamber includes: an outlet, which is arranged on the other side of the upper end of the sedimentation chamber.

[0014] A further technical solution is that the combustion chamber includes a temperature increasing burner arranged in the combustion chamber.

[0015] A further technical solution is that the sedimentation chamber includes: a filter screen, which is arranged on the inner wall of the sedimentation chamber and located at the lower end of the combustion chamber; and an inspection door, which is opened on the inner wall of the sedimentation chamber and located at the upper end of the filter screen.

[0016] A further technical solution is that the electric furnace flue gas combustion settling chamber includes: an ash hopper, arranged at the lower end of the settling chamber and connected to the settling chamber; and a pneumatic conveying device, arranged at the lower end of the ash hopper and connected to the ash hopper.

[0017] A method for combustion and settling of electric furnace flue gas, using the above-mentioned electric furnace flue gas combustion and settling chamber, comprises the following steps:

[0018] Heating: The flue gas of the electric furnace enters the combustion chamber through the inlet. When the temperature of the incoming flue gas is lower than 800°C, the temperature-raising burner is turned on to raise the flue gas temperature to above 800°C;

[0019] Decomposition: After the flue gas enters the combustion chamber, it stays in the combustion chamber for more than 2 seconds to ensure that the toxic substances in the flue gas are fully burned and decomposed;

[0020] Temperature control: When the flue gas enters the settling chamber, the flue gas is accelerated when it flows through the cell structure on the surface of the heat storage rod, and the flue gas and the heat storage rod exchange heat quickly;

[0021] Sedimentation: Dust in the flue gas continues to settle in the combustion chamber and the settling chamber. After settling, the flue gas is discharged through the outlet, and the temperature of the discharged flue gas is 800-1000°C.

[0022] The beneficial effects of the embodiments of the utility model are as follows:

[0023] (I) The utility model discloses an electric furnace flue gas combustion settling chamber, wherein a heat storage rod is arranged at the upper end of the settling chamber, a cell structure is arranged on the outer shell of the heat storage rod, and a heat storage material is filled in the outer shell. When the flue gas flows through the pit of the cell structure, due to the separation effect of the boundary layer, the flue gas flow is partially separated along the surface of the pit to generate eddies, which increases the turbulence of the air flow around the cell structure and destroys the boundary layer structure, thereby improving the heat transfer effect of the flue gas to the heat storage rod. At the same time, the eddies in the cell structure can also play an effect similar to an air cushion, reducing resistance, increasing flow velocity, and improving heat exchange rate.

[0024] In addition, due to the high turbulence of the airflow on the shell surface, the shear force of the airflow on the shell surface is large, which reduces the possibility of dust in the flue gas sticking to the shell surface and ensures the heat exchange performance of the heat storage rod.

[0025] (ii) Furthermore, the heat storage rods are staggered at the upper end of the settling chamber. The staggered heat storage rods increase the contact area between the flue gas and the heat storage rods, increase the flow path of the flue gas, and the flue gas continuously impacts the heat storage rods, increasing the turbulence of the flue gas flow and improving the heat transfer efficiency between the flue gas and the heat storage rods.

[0026] (III) Furthermore, the dust in the flue gas continues to settle throughout the combustion chamber and the settling chamber. When the flue gas passes through the heat storage rod area on the front side of the settling chamber for rapid heat transfer, the settling is less, and the dust on the surface of the heat storage rod is blown off by the shock wave soot blower for settling. After entering the back side of the settling chamber, the flue gas slows down and settles more, which can ensure the waste heat recovery and dust settling effects at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a structural schematic diagram of the electric furnace smoke combustion settling chamber of the utility model.

[0028] Figure 2 It is a structural schematic diagram of the heat storage rod in the flue gas combustion settling chamber of the electric furnace of the utility model.

[0029] Figure 3 for Figure 1 Section view at AA.

[0030] Figure 4 The utility model is a flow chart of the electric furnace smoke combustion sedimentation method.

[0031] In the figure:

[0032] 1. Combustion chamber; 11. First inlet; 12. Second inlet; 13. Temperature-raising burner; 14. Air inlet regulating valve; 2. Settling chamber; 21. Outlet; 22. Filter; 23. Inspection door; 3. Heat storage rod; 31. Shell; 311. Cell structure; 32. Heat storage material; 33. Screw; 34. Double nut; 4. Shock wave soot blower; 5. Ash hopper; 51. Waste heat recovery device; 6. Pneumatic conveying device. DETAILED DESCRIPTION

[0033] The specific implementation of the present invention will be described below in conjunction with the accompanying drawings.

[0034] In order to make the purpose, technical scheme and advantages of the present invention clearer, the device proposed by the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. According to the following description, the advantages and features of the present invention will be clearer. It should be noted that the accompanying drawings adopt a very simplified form and use non-precise proportions, which are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention. In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, please refer to the accompanying drawings. It should be noted that the structure, proportion, size, etc. illustrated by the accompanying drawings of this specification are only used to match the content disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no technical substantive significance. Any modification of the structure, change of the proportional relationship or adjustment of the size, without affecting the effect that the present invention can produce and the purpose that can be achieved, should still fall within the scope of the technical content disclosed by the present invention.

[0035] First embodiment:

[0036] The first embodiment discloses an electric furnace smoke combustion settling chamber.

[0037] An electric furnace smoke combustion settling chamber comprises a settling chamber 2 and a heat storage rod 3.

[0038] Figure 1 Schematic diagram of the structure of the electric furnace smoke combustion settling chamber of the present invention. Figure 1 As shown, the settling chamber 2 has a hollow structure, and high-temperature flue gas flows inside. Preferably, the settling chamber 2 adopts a membrane water-cooled wall. The membrane water-cooled wall can ensure that the settling chamber 2 has good sealing performance, while increasing the heating area, and effectively improving the heat recovery efficiency.

[0039] Figure 2 FIG. 1 is a schematic diagram of the structure of the heat storage rod 3 in the flue gas combustion settling chamber of the electric furnace of the present invention. Figure 1 and Figure 2As shown, the heat storage rod 3 is fixed at the upper end of the interior of the settling chamber 2 and is perpendicular to the flow direction of the high-temperature flue gas, and includes a shell 31 and a heat storage material 32. The shell 31 has a cell structure 311, and the cell structure 311 is arranged on the surface of the shell 31, and the cell structure 311 is a pit. The heat storage material 32 is filled in the shell 31. Exemplarily, the heat storage rod 3 includes a screw 33 and a double nut 34. The screw 33 is arranged at the upper end of the shell 31 and passes through the upper end of the settling chamber 2. The double nut 34 is screwed on the screw 33 and is located at the upper end of the settling chamber 2. Among them, by tightening the double nut 34, the upper end of the shell 31 is against the settling chamber 2, and the heat storage rod 3 is fixed to the settling chamber 2. The screw 33 and the nut fixation facilitate the installation and disassembly of the heat storage rod 3. The cell structure 311 is arranged in an annular shape on the surface of the shell 31. When the flue gas flows through the pits of the cell structure 311, due to the separation effect of the boundary layer, the flue gas flow is partially separated to generate vortices, which increases the turbulence of the air flow around the cell structure 311 and destroys the boundary layer structure, thereby improving the heat transfer effect. At the same time, the vortices in the cell structure 311 can also play a similar effect to an air cushion, which can prevent the increase of resistance even in the case of turbulent flow, thereby achieving control of flow resistance. Preferably, the heat storage material 32 is a composite phase change heat storage material 32, which can stably absorb or release heat.

[0040] Figure 3 for Figure 1 The cross-sectional view at AA. Figure 3 As shown, further, the heat storage rods 3 are staggered at the upper end of the settling chamber 2. The staggered heat storage rods 3 increase the contact area between the flue gas and the heat storage rods 3, increase the flow path of the flue gas, and the flue gas continuously impacts the heat storage rods 3, increasing the turbulence of the flue gas flow and improving the heat transfer efficiency between the flue gas and the heat storage rods 3.

[0041] like Figure 1 As shown, further, the heat storage rod 3 is arranged at the front side of the upper end of the settling chamber 2. After the flue gas passes through the heat storage rod 3 area on the front side of the settling chamber 2 and quickly transfers heat, it enters the back side of the settling chamber 2, and the flue gas decelerates, ensuring the settling effect of the electric furnace ash.

[0042] like Figure 1 As shown, further, the electric furnace flue gas combustion settling chamber includes a shock wave soot blower 4, which is arranged at the upper end of the settling chamber 2 and located on the side of the heat storage rod 3. The nozzle of the shock wave soot blower 4 faces the surface of the heat storage rod 3. The shock wave soot blower 4 sprays shock waves at the nozzle to cause the dust on the surface of the heat storage rod 3 to fall off.

[0043] like Figure 1As shown, further, the electric furnace flue gas combustion settling chamber includes a combustion chamber 1, which is arranged on one side of the upper end of the settling chamber 2 and is connected to the settling chamber 2. The combustion chamber 1 includes an inlet, which is arranged at the upper end of the combustion chamber 1; the settling chamber 2 includes an outlet 21, and the outlet 21 is arranged on the other side of the upper end of the settling chamber 2. Exemplarily, the combustion chamber 1 is vertically arranged on the front side of the upper end of the settling chamber 2. The inlet includes a first inlet 11 and a second inlet 12, and the first inlet 11 is introduced into the high-temperature flue gas of the electric furnace, and the flue gas temperature is about 1200°C, and the second inlet 12 is introduced into the high-temperature flue gas extracted from the top of the electric furnace cover, and the flue gas temperature is ≤800°C. Preferably, the combustion chamber includes an air inlet regulating valve 14, and the air inlet regulating valve 14 is arranged at the inlet to control the mixing ratio of the high-temperature flue gas of the electric furnace and the high-temperature flue gas extracted from the top of the electric furnace cover to control the initial temperature of the flue gas in the combustion chamber 1.

[0044] like Figure 1 As shown, further, the combustion chamber 1 includes a temperature increasing burner 13 , and the temperature increasing burner 13 is arranged in the combustion chamber 1 .

[0045] like Figure 1 As shown, further, the settling chamber 2 includes a filter screen 22 and an inspection door 23. The filter screen 22 is arranged on the inner wall of the settling chamber 2 and is located at the lower end of the combustion chamber 1. The inspection door 23 is opened on the inner wall of the settling chamber 2 and is located at the upper end of the filter screen 22. Preferably, the filter screen 22 is a water-cooled grid filter screen 22, which effectively filters large particles or foreign matter in the flue gas of the electric furnace. The large particles and foreign matter are removed by the staff by regularly opening the inspection door 23 to ensure that the electric furnace ash can be pneumatically transported.

[0046] like Figure 1 As shown, further, the electric furnace flue gas combustion settling chamber includes an ash hopper 5 and a pneumatic conveying device 6. The ash hopper 5 is arranged at the lower end of the settling chamber 2 and is communicated with the settling chamber 2. The pneumatic conveying device 6 is arranged at the lower end of the ash hopper 5 and is communicated with the ash hopper 5. Dust in the flue gas settles into the ash hopper 5 and is sent to the ash bin through the pneumatic conveying device 6. Preferably, a fin-type waste heat recovery device 51 is arranged in the ash hopper 5 to improve the heat energy recovery efficiency.

[0047] In this embodiment, the outer shell 31 of the heat storage rod 3 is provided with a cell structure 311, and the outer shell 31 is filled with a heat storage material 32. When the airflow flows through the pit of the cell structure 311, due to the separation effect of the boundary layer, the airflow is partially separated along the surface of the pit to generate eddies, which increases the turbulence of the airflow around the cell structure 311 and destroys the boundary layer structure, thereby improving the heat transfer effect of the flue gas on the heat storage rod 3. At the same time, the eddies in the cell structure 311 can also play an effect similar to an air cushion, reducing resistance, increasing flow velocity, and improving heat exchange rate.

[0048] In addition, since the airflow turbulence on the surface of the shell 31 is high, the shear force of the airflow on the surface of the shell is large, which reduces the possibility of dust in the flue gas adhering to the surface of the shell 31, thereby ensuring the heat exchange performance of the heat storage rod 3.

[0049] Second embodiment:

[0050] The second embodiment discloses a method for combustion and sedimentation of flue gas from an electric furnace.

[0051] Figure 4 The flowchart of the electric furnace flue gas combustion sedimentation method of the present invention is shown in FIG. Figure 4 As shown, the electric furnace flue gas combustion settling method uses the aforementioned electric furnace flue gas combustion settling chamber, and includes the following steps:

[0052] Step S1, heating: the flue gas of the electric furnace enters the combustion chamber 1 through the inlet. When the temperature of the incoming flue gas is lower than 800°C, the temperature increasing burner 13 is turned on to increase the flue gas temperature to above 800°C.

[0053] Exemplarily, the flue gas from the electric furnace enters the combustion chamber 1 through the first inlet 11, and the flue gas above the electric furnace cover enters the combustion chamber 1 through the second inlet 12, and the two groups of flue gas are mixed in the combustion chamber 1. When the temperature sensor in the combustion chamber 1 detects that the flue gas temperature is lower than 800°C, the temperature increasing burner 13 is turned on to directly increase the flue gas temperature to above 800°C.

[0054] Step S2, decomposition: After the flue gas enters the combustion chamber 1, the residence time in the combustion chamber 1 is greater than 2S to ensure that the toxic substances in the flue gas are fully burned and decomposed.

[0055] Exemplarily, the flue gas from the electric furnace stays in the combustion chamber 1 for 2 to 3 seconds to ensure that toxic substances such as dioxins and furans contained in the flue gas from the electric furnace are fully burned and decomposed.

[0056] In step S3, the flue gas enters the settling chamber 2, and is accelerated when flowing through the cell structure 311 on the surface of the heat storage rod 3, so that the flue gas and the heat storage rod 3 perform rapid heat exchange.

[0057] Step S4, sedimentation: dust in the flue gas is continuously sedimented in the combustion chamber 1 and the sedimentation chamber 2, and the flue gas is discharged through the outlet 21 after sedimentation, and the temperature of the discharged flue gas is 800-1000°C.

[0058] For example, the dust in the flue gas continues to settle throughout the combustion chamber 1 and the settling chamber 2. When the flue gas flow passes through the heat storage rod 3 area on the front side of the settling chamber 2 for rapid heat transfer, the settling is less. After entering the back side of the settling chamber 2, the flue gas flow slows down and settles more. The dust settles into the ash hopper 5 and falls into the pneumatic conveying device 6, and is transported to the ash bin for centralized treatment. The flue gas is finally discharged through the outlet 21, and the discharge temperature is 800-1000°C.

[0059] In this embodiment, when the flue gas flow passes through the heat storage rod 3 area on the front side of the settling chamber 2 for rapid heat transfer, there is less sedimentation. After entering the rear side of the settling chamber 2, the flue gas flow slows down and settles more, which can simultaneously ensure the waste heat recovery and dust settling effects.

[0060] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0061] The above-mentioned embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. An electric furnace flue gas combustion settling chamber, characterized in that: include: The settling chamber has a hollow structure, and high-temperature flue gas flows inside; The heat storage rod is fixed at the upper end of the settling chamber and is perpendicular to the flow direction of the high-temperature flue gas, and includes: Housing, comprising: The D-cell structure is arranged on the surface of the shell and is a pit; The heat storage material is filled in the shell.

2. The electric furnace smoke combustion settling chamber according to claim 1, characterized in that: The heat storage rods are staggeredly arranged at the upper end of the interior of the settling chamber.

3. The electric furnace smoke combustion settling chamber according to claim 1, characterized in that: The heat storage rod comprises: A screw rod is disposed at the upper end of the housing and passes through the upper end of the settling chamber; A double nut, screwed on the screw and located at the upper end of the settling chamber; The double nuts are tightened to fix the heat storage rod and the sedimentation chamber together.

4. The electric furnace smoke combustion settling chamber according to claim 1, characterized in that: The electric furnace smoke combustion settling chamber comprises: A shock wave soot blower is arranged at the upper end of the settling chamber and located on the side of the heat storage rod; Wherein, the nozzle of the shock wave soot blower faces the surface of the heat storage rod.

5. The electric furnace smoke combustion settling chamber according to claim 1, characterized in that: The sedimentation chamber adopts a membrane water-cooled wall.

6. The electric furnace smoke combustion settling chamber according to claim 1, characterized in that: The electric furnace smoke combustion settling chamber comprises: The combustion chamber is arranged on one side of the upper end of the settling chamber and communicated with the settling chamber, and comprises: an inlet, disposed at an upper end of the combustion chamber; The settling chamber comprises: The outlet is arranged on the other side of the upper end of the sedimentation chamber.

7. The electric furnace smoke combustion settling chamber according to claim 6, characterized in that: The combustion chamber comprises: A temperature-raising burner is arranged in the combustion chamber.

8. The electric furnace smoke combustion settling chamber according to claim 6, characterized in that: The settling chamber comprises: A filter screen is arranged on the inner wall of the settling chamber and is located at the lower end of the combustion chamber; An inspection door is provided on the inner wall of the settling chamber and is located at the upper end of the filter screen.

9. The electric furnace smoke combustion settling chamber according to claim 7, characterized in that: The electric furnace smoke combustion settling chamber comprises: An ash hopper is arranged at the lower end of the settling chamber and is communicated with the settling chamber; The pneumatic conveying device is arranged at the lower end of the ash hopper and is communicated with the ash hopper.