A precast concrete assembly for pipe jacking

By using the tenon and mortise joint structure of precast concrete components, combined with the welding of steel mesh, the problems of mold installation errors and reliance on manpower in pipe jacking are solved, achieving efficient and low-cost pipe jacking production.

CN224978883UActive Publication Date: 2026-11-17WUHU XINXING DUCTILE IRON PIPES
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202522699275.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-19
Publication Date
2026-11-17
Estimated Expiration
2035-12-19

AI Technical Summary

Technical Problem

In existing pipe jacking technology, installation errors between the mold and the pipe socket can easily lead to grout leakage and root rot. Furthermore, the mold cleaning and release agent application processes rely on manual labor, resulting in low production efficiency.

Method used

The precast concrete components, including first and second concrete half-shells, are used. The half-shells are connected with high precision through tenon and mortise joints and internal steel mesh welding, eliminating the need for mold cleaning and application of release agent.

Benefits of technology

It improves the installation accuracy of pipe jacking, reduces grout leakage and root rot, increases production efficiency, reduces production costs, and ensures uniform wall thickness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224978883U_ABST
    Figure CN224978883U_ABST
Patent Text Reader

Abstract

This utility model discloses a precast concrete component for pipe jacking, belonging to the field of pipe jacking technology, including a first concrete half-shell (1) and a second concrete half-shell (2); both the first concrete half-shell (1) and the second concrete half-shell (2) are semi-cylindrical structures; one end of the first concrete half-shell (1) is provided with a tenon (4), and one end of the second concrete half-shell (2) is provided with a mortise (5); the tenon (4) and the mortise (5) are adapted to each other, and the installation accuracy is improved by splicing the tenon (4) and the mortise (5), and the problems of grout leakage and pipe root rot caused by installation errors are reduced; by using precast concrete components for splicing, the traditional mold cleaning and release agent application are eliminated, saving time and manpower, improving production efficiency and reducing production costs; the top of the component is provided with a splicing interface (9) for inserting the pouring pipe to inject slurry.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of pipe jacking technology. Specifically, this utility model relates to a precast concrete component for pipe jacking. Background Technology

[0002] Pipe jacking technology is a trenchless pipeline laying construction technique used in municipal construction. The pipe used in the construction process is called a pipe jacking pipe. Pipe jacking pipes have sockets and spigots, and are formed using a casting method. Current pipe jacking casting technology mainly uses integrated mold casting, that is, concrete is poured into an integral mold, and after solidification, the pipe jacking structure is formed.

[0003] For example, the specification of Chinese utility model patent CN 222079627 U, published on November 29, 2024, discloses an integrated jacking pipe casting mold. This mold, with its movable outer shell and pipe body, can quickly complete mold assembly and demolding after jacking pipe formation. The groove structure of the base can fix the pipe body in a designated position, thereby ensuring the accuracy of the jacking pipe dimensions and achieving efficient and precise jacking pipe casting. However, the installation error between the mold and the jacking pipe socket can easily cause grout leakage, leading to problems such as root rot and water lines in the jacking pipe. The mold cleaning and release agent application processes also rely on manual labor, resulting in low production efficiency. Utility Model Content

[0004] The present invention aims to provide a precast concrete component for jacking pipe casting with high installation accuracy with the jacking pipe socket.

[0005] To achieve the above objectives, the technical solution adopted by this utility model is as follows: a precast concrete component for pipe jacking, comprising a first concrete half-shell and a second concrete half-shell; both the first concrete half-shell and the second concrete half-shell are semi-cylindrical structures; the end faces of the first concrete half-shell and the second concrete half-shell are fitted together; a splicing structure is provided at the connection between the first concrete half-shell and the second concrete half-shell.

[0006] Furthermore, the splicing structure includes a tenon and a mortise; the tenon is located at one end of the first concrete half-shell, and the mortise is located at one end of the second concrete half-shell; the tenon is connected to one end of the first concrete half-shell, and the mortise is connected to one end of the second concrete half-shell; the tenon and the mortise are adapted to each other.

[0007] Furthermore, the tenon has an L-shaped structure, and the mortise has a round tube structure; one end of the tenon is connected to the end face of the first concrete half-shell, and the other end of the tenon is located inside the round tube of the mortise.

[0008] Furthermore, the mortise depth is greater than the tenon length.

[0009] Furthermore, the first concrete half-shell is provided with a first steel mesh inside, the first steel mesh extending from one end of the first concrete half-shell to the other end, and the first steel mesh is connected to the upper and lower surfaces of the inner wall of the first concrete half-shell; the second concrete half-shell is provided with a second steel mesh inside, the second steel mesh being connected to the upper and lower surfaces of the inner wall of the second concrete half-shell; the second steel mesh extending from one end of the second concrete half-shell to the other end.

[0010] Furthermore, the tenon end is connected to the end of the first reinforcing mesh, and the mortise is connected to the end of the second reinforcing mesh.

[0011] Furthermore, the tenon is welded to the first steel mesh, and the mortise is welded to the second steel mesh.

[0012] Furthermore, a splicing seam is provided at the joint between the first concrete half-shell and the second concrete half-shell; the splicing seam is provided with splicing holes.

[0013] The technical advantages of this invention are as follows: the first and second concrete half-shells are joined together by tenons and mortises welded with internal steel mesh. Mud reinforcement is added to the interior of both half-shells via a pouring pipe, improving installation accuracy and reducing problems such as grout leakage and pipe root rot caused by installation errors. The use of precast concrete components eliminates the need for traditional mold cleaning and release agent application, saving time and manpower, increasing production efficiency, and reducing production costs. The precast outer shell allows for control over its wall thickness, ensuring uniform wall thickness. Attached Figure Description

[0014] This utility model includes the following figures, which show the contents as follows: Figure 1 This is a schematic diagram of the first concrete half-shell structure of a precast concrete assembly used for pipe jacking. Figure 2 This is a schematic diagram of the second concrete half-shell structure of a precast concrete assembly used for pipe jacking. Figure 3 This is a schematic diagram of the overall structure of a precast concrete assembly used for pipe jacking. Figure 4 This is a schematic diagram of the splicing structure of precast concrete components used for pipe jacking.

[0015] The markings in the diagram are as follows: 1. First concrete half-shell; 2. Second concrete half-shell; 3. Splicing structure; 4. Tenon; 5. Mortise; 6. First steel mesh; 7. Second steel mesh; 8. Splicing joint; 9. Splicing hole. Detailed Implementation

[0016] The specific embodiments of this utility model will be further described in detail below with reference to the accompanying drawings, in order to help those skilled in the art to have a more complete, accurate and in-depth understanding of the inventive concept and technical solution of this utility model, and to facilitate its implementation.

[0017] A precast concrete assembly for pipe jacking, such as Figure 3 and Figure 4 As shown, it includes a first concrete half-shell 1 and a second concrete half-shell 2, both of which are cast from C30 concrete. Both the first concrete half-shell 1 and the second concrete half-shell 2 are semi-cylindrical structures, and the curvature of the inner wall is consistent with the design curvature of the jacking pipe to reduce installation errors. The end faces of the first concrete half-shell 1 and the second concrete half-shell 2 are fitted together. A splicing structure 3 is provided at the connection between the first concrete half-shell 1 and the second concrete half-shell 2, and the first concrete half-shell 1 and the second concrete half-shell 2 are connected by the splicing structure 3.

[0018] Specifically, such as Figure 4 As shown, the splicing structure 3 includes a tenon 4 and a mortise 5; the tenon 4 is located at one end of the first concrete half shell 1, and the mortise 5 is located at one end of the second concrete half shell 2; the tenon 4 is connected to one end of the first concrete half shell 1, and the mortise 5 is connected to one end of the second concrete half shell 2; the tenon 4 and the mortise 5 are adapted to each other, and the connection between the tenon 4 and the mortise 5 facilitates worker installation, simplifies the installation steps, and provides high connection strength.

[0019] Specifically, such as Figure 4 As shown, the tenon 4 has an L-shaped structure, and the mortise 5 has a round tube structure; one end of the tenon 4 is connected to the end face of the first concrete half shell 1, and the other end of the tenon 4 is inserted vertically upward into the round tube of the mortise 5 to ensure the connection strength between the first concrete half shell 1 and the second concrete half shell 2.

[0020] Specifically, such as Figure 4 As shown, the depth of the mortise 5 is greater than the length of the tenon 4, which ensures that the tenon 4 is fully inserted into the mortise 5, and ensures a tight fit when the first concrete half-shell 1 and the second concrete half-shell 2 are spliced.

[0021] Specifically, such as Figure 1 and Figure 2As shown, the first concrete half-shell 1 is provided with a first steel mesh 6 inside, which extends from one end of the first concrete half-shell 1 to the other end, and is connected to the upper and lower surfaces of the inner wall of the first concrete half-shell 1; the second concrete half-shell 2 is provided with a second steel mesh 7 inside, which is connected to the upper and lower surfaces of the inner wall of the second concrete half-shell 2; the second steel mesh 7 extends from one end of the second concrete half-shell 2 to the other end. The function of the first steel mesh 6 and the second steel mesh 7 is to strengthen the structural strength of the precast components and improve the production quality.

[0022] Specifically, such as Figure 1 and Figure 2 As shown, the end of the tenon 4 is connected to the end of the first steel mesh 6, and the mortise 5 is connected to the end of the second steel mesh 7, which facilitates installation by workers while improving structural strength.

[0023] Specifically, such as Figure 1 and Figure 2 As shown, the tenon 4 is welded to the first steel mesh 6, and the mortise 5 is welded to the second steel mesh 7. Welding enhances the connection strength and ensures a stable connection after the first concrete half-shell 1 and the second concrete half-shell 2 are spliced. Multiple sets of tenons 4 and mortises 5 can be set, and each tenon 4 can be inserted into its corresponding mortise 5 to further strengthen the connection strength of the first concrete half-shell 1 and the second concrete half-shell 2.

[0024] Specifically, such as Figure 1 As shown, a splicing joint 8 is provided at the joint between the first concrete half-shell 1 and the second concrete half-shell 2; a splicing hole 9 is provided on the splicing joint 8. The splicing hole 9 is used to insert a pouring pipe to inject slurry into the first concrete half-shell 1 and the second concrete half-shell 2. The splicing joint 8 is used to observe the slurry injection. When the slurry overflows from the splicing joint 8 on the other side, it indicates that the first concrete half-shell 1 and the second concrete half-shell 2 have been filled with slurry.

[0025] The working process of this precast concrete assembly used for pipe jacking is as follows: Step 1: The first concrete half-shell 1 and the second concrete half-shell 2 are made of C30 concrete, and the first steel mesh 6 and the second steel mesh 7 are pre-embedded inside respectively; the tenon 4 is welded on the first steel mesh 6 and the mortise 5 is welded on the second steel mesh 7.

[0026] Step 2: The workers use hoisting tools to lift the first concrete half-shell 1 and the second concrete half-shell 2 onto the splicing platform, align the tenon 4 on the first concrete half-shell 1 with the mortise 5 on the second concrete half-shell 2, and insert the tenon 4 into the mortise 5; a splicing seam 8 and a splicing interface 9 are set at the splicing point of the first concrete half-shell 1 and the second concrete half-shell 2. The width of the splicing seam 8 is controlled to be 3 to 5 mm, and the overall axis deviation after splicing is checked to ensure that the deviation error is within 3 mm.

[0027] Step 3: Insert the grouting pipe into the splice joint 9, and inject cement slurry into the first concrete half shell 1 and the second concrete half shell 2 until the cement slurry overflows from the splice joint 8 at the other end. Remove the grouting pipe and let it stand for 24 hours to complete the curing.

[0028] The present invention has been described above by way of example with reference to the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-described manner. Any non-substantial improvements made using the inventive concept and technical solution of the present invention; or the direct application of the inventive concept and technical solution to other situations without modification, are all within the protection scope of the present invention.

Claims

1. A precast concrete assembly for pipe jacking, characterized by: It includes a first concrete half-shell (1) and a second concrete half-shell (2); both the first concrete half-shell (1) and the second concrete half-shell (2) are semi-cylindrical structures; the end face of the first concrete half-shell (1) and the end face of the second concrete half-shell (2) are fitted together; a splicing structure (3) is provided at the connection between the first concrete half-shell (1) and the second concrete half-shell (2).

2. A precast concrete assembly for pipe jacking according to claim 1, wherein: The splicing structure (3) includes a tenon (4) and a mortise (5); the tenon (4) is located at one end of the first concrete half shell (1), and the mortise (5) is located at one end of the second concrete half shell (2); the tenon (4) is connected to one end of the first concrete half shell (1), and the mortise (5) is connected to one end of the second concrete half shell (2); the tenon (4) and the mortise (5) are adapted to each other.

3. A precast concrete assembly for pipe jacking according to claim 2, wherein: The tenon (4) is an L-shaped structure, and the mortise (5) is a round tube structure; one end of the tenon (4) is connected to the end face of the first concrete half shell (1), and the other end of the tenon (4) is located inside the round tube of the mortise (5).

4. A precast concrete assembly for pipe jacking according to claim 3, wherein: The mortise (5) is deeper than the tenon (4) in length.

5. A precast concrete assembly for pipe jacking according to claim 4, wherein: The first concrete half-shell (1) is provided with a first steel mesh (6) inside, the first steel mesh (6) extends from one end of the first concrete half-shell (1) to the other end, and the first steel mesh (6) is connected to the upper and lower surfaces of the inner wall of the first concrete half-shell (1); the second concrete half-shell (2) is provided with a second steel mesh (7) inside, the second steel mesh (7) is connected to the upper and lower surfaces of the inner wall of the second concrete half-shell (2); the second steel mesh (7) extends from one end of the second concrete half-shell (2) to the other end.

6. A precast concrete assembly for pipe jacking according to claim 5, wherein: The end of the tenon (4) is connected to the end of the first steel mesh (6), and the mortise (5) is connected to the end of the second steel mesh (7).

7. A precast concrete assembly for pipe jacking according to claim 6, wherein: The tenon (4) is welded to the first steel mesh (6), and the mortise (5) is welded to the second steel mesh (7).

8. A precast concrete assembly for pipe jacking according to any one of claims 1 to 7, wherein: The first concrete half shell (1) and the second concrete half shell (2) are provided with a splicing seam (8); the splicing seam (8) is provided with a splicing hole (9).

Citation Information

Patent Citations

  • Integrated pipe jacking pouring mold

    CN222079627U