A building pipe packaging device

By designing a building pipe packaging device and utilizing components such as curved plates and support rollers, the automatic supply of steel strips was achieved, solving the problem of low efficiency in manual packaging and enabling rapid and stable packaging of building pipes.

CN224980053UActive Publication Date: 2026-11-17TIANJIN YOUXIN BUILDING MATERIALS MFG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522135238.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-10-10
Publication Date
2026-11-17
Estimated Expiration
2035-10-10

AI Technical Summary

Technical Problem

The current method of packaging building pipes mainly relies on manual winding of iron wire or hemp rope, which is labor-intensive and inefficient, and cannot meet the needs of large-scale production of modern building pipes.

Method used

A building pipe packaging device was designed, including components such as a base, an arc plate, a support roller, a limiting roller, and a guide plate. Through the cooperation of a handwheel and a two-way screw, the automatic supply of steel strips and the rapid packaging of building pipes are realized.

Benefits of technology

It enables rapid and stable packaging of building pipes, reduces labor intensity, and improves packaging efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224980053U_ABST
    Figure CN224980053U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of building pipe processing technology and discloses a building pipe packaging device, which solves the current problem of inconvenience in quickly packaging building pipes. It includes a base, with a packaging mechanism on the top of the base. The packaging mechanism includes two arc-shaped plates symmetrically fixed to the top of the base. Two through-slots are symmetrically arranged on the arc-shaped plates. A limiting roller is rotatably connected to the inner side of each through-slot. Two support rollers are symmetrically rotatably connected between the two arc-shaped plates. Two upright plates are symmetrically arranged between the two arc-shaped plates, each located above the two support rollers. Two through-slots are symmetrically arranged on the upright plates, with a limiting roller rotatably connected to the inner side of each through-slot. This utility model allows for adjustment of the distance between the arc-shaped plates and the upright plates according to requirements, facilitating the placement of steel strip coils between the limiting rollers and the support rollers. It provides a continuous supply of steel strip material for building pipe bundling, thus facilitating rapid packaging of building pipes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of building pipe processing technology, specifically a building pipe packaging device. Background Technology

[0002] As an indispensable basic material in construction projects, the production and demand of building pipes are increasing day by day. After the production of building pipes is completed, in order to facilitate transportation and storage and avoid damage or scattering during handling, effective packaging is required. High-quality and efficient packaging can ensure the integrity of building pipes in the circulation process and improve the logistics efficiency and economic benefits of building pipe manufacturers.

[0003] Currently, the packaging of building pipes mainly relies on manual labor, which involves manually wrapping the pipes with wire or hemp rope. This method is not only labor-intensive, but also results in inconsistent packaging quality and extremely low efficiency, which is far from meeting the needs of modern large-scale production of building pipes. Utility Model Content

[0004] In view of the above situation and to overcome the shortcomings of the existing technology, this utility model provides a building pipe packaging device, which effectively solves the problem of the inconvenience of quickly packaging building pipes.

[0005] To achieve the above objectives, this utility model provides the following technical solution: a building pipe packaging device, including a base, and a packaging mechanism is provided on the top of the base;

[0006] The packaging mechanism includes two arc-shaped plates symmetrically fixed to the top of the base. Two through slots are symmetrically provided on the arc-shaped plates. A limit roller is rotatably connected to the inner side of the through slot. Two support rollers are symmetrically rotatably connected between the two arc-shaped plates. Two upright plates are symmetrically provided between the two arc-shaped plates. Both upright plates are located above the two support rollers. Two through slots are symmetrically provided on the upright plates. A limit roller is rotatably connected to the inner side of the through slot.

[0007] Preferably, a guide post is fixedly connected between the two arc-shaped plates, and two guide plates are symmetrically and movably sleeved on the outer side of the guide post. The two guide plates are fixed to the bottom of the two vertical plates respectively, and both guide plates are located between the two support rollers.

[0008] Preferably, a U-shaped plate is fixedly installed on the top of the base, the U-shaped plate is located below the two support rollers, a bidirectional lead screw is rotatably connected to the inner side of the U-shaped plate, one end of the bidirectional lead screw extends to the outer side of the U-shaped plate and is fixedly connected to a handwheel, and two nuts are symmetrically threaded on the outer side of the bidirectional lead screw.

[0009] Preferably, the inner bottom wall of the U-shaped plate is provided with a sliding groove, and both nuts are slidably connected to the sliding groove.

[0010] Preferably, the outer side of the nut is symmetrically rotatably connected to two movable rods, and the ends of the two movable rods away from the nut are respectively rotatably connected to two guide plates.

[0011] Preferably, the bottom of the upright plate is symmetrically fixedly connected to two support plates, and the bottom of each support plate is provided with a support wheel located at the top of the base.

[0012] Compared with the prior art, the beneficial effects of this utility model are:

[0013] 1. Through the cooperation of handwheel, double-acting screw, screw nut, slide groove, movable rod, guide plate and guide column, the distance between the arc plate and the vertical plate can be adjusted according to the needs, which makes it easy to place the steel strip roll between the first limiting roller, the second limiting roller and the support roller, and can continuously supply steel strip raw materials for building pipe bundling, thus facilitating the rapid packaging of building pipes;

[0014] 2. The cooperation between the support plate and the support wheel facilitates stable support of the upright plate. Attached Figure Description

[0015] The accompanying drawings are provided to further understand the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention and do not constitute a limitation thereof.

[0016] In the attached diagram:

[0017] Figure 1 This is a schematic diagram of the structure of the building pipe packaging device of this utility model;

[0018] Figure 2 This is a schematic diagram of the packaging mechanism of this utility model;

[0019] Figure 3 This is a schematic diagram of the U-shaped plate structure of this utility model.

[0020] In the diagram: 1. Base; 2. Packaging mechanism; 201. Arc plate; 202. Through groove one; 203. Limiting roller one; 204. Through groove two; 205. Limiting roller two; 206. Vertical plate; 207. Support roller; 208. Guide plate; 209. U-shaped plate; 2010. Support wheel; 2011. Support plate; 2012. Slide groove; 2013. Nut; 2014. Two-way lead screw; 2015. Movable rod; 2016. Guide column; 2017. Handwheel. Detailed Implementation

[0021] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model without creative effort are within the protection scope of the present utility model.

[0022] Example 1, by Figure 1 The present invention relates to a building pipe packaging device, including a base 1, and a packaging mechanism 2 is provided on the top of the base 1.

[0023] Specifically, by Figure 2-3 The packaging mechanism 2 includes two arc-shaped plates 201 symmetrically fixed to the top of the base 1. Two through slots 202 are symmetrically arranged on the arc-shaped plates 201. A limiting roller 203 is rotatably connected to the inner side of each through slot 202. Two support rollers 207 are symmetrically rotatably connected between the two arc-shaped plates 201. Two upright plates 206 are symmetrically arranged between the two arc-shaped plates 201, each located above the two support rollers 207. Two through slots 204 are symmetrically arranged on the upright plates 206. A limiting roller 205 is rotatably connected to the inner side of each through slot 204. A guide post 2016 is fixedly connected between the two arc-shaped plates 201. Two guide plates 208 are symmetrically and movably sleeved on the outer side of the guide post 2016. The two guide plates 208 are respectively fixed to the two upright plates 206. At the bottom, both guide plates 208 are located between two support rollers 207. A U-shaped plate 209 is fixedly installed on the top of the base 1. The U-shaped plate 209 is located below the two support rollers 207. A bidirectional lead screw 2014 is rotatably connected to the inner side of the U-shaped plate 209. One end of the bidirectional lead screw 2014 extends to the outer side of the U-shaped plate 209 and is fixedly connected to a handwheel 2017. Two screw nuts 2013 are symmetrically threaded on the outer side of the bidirectional lead screw 2014. A sliding groove 2012 is provided on the inner bottom wall of the U-shaped plate 209. Both screw nuts 2013 are slidably connected to the sliding groove 2012. Two movable rods 2015 are symmetrically rotatably connected to the outer side of the screw nuts 2013. The ends of the two movable rods 2015 away from the screw nuts 2013 are rotatably connected to the two guide plates 208 respectively.

[0024] In operation, firstly, rotate the handwheel 2017 to drive the bidirectional lead screw 2014 to rotate, and drive the lead screw nut 2013 to slide along the slide groove 2012. Then, through the movable rod 2015, drive the guide plate 208 to slide along the guide column 2016. At the same time, the upright plate 206 moves horizontally to adjust the distance between the upright plate 206 and the arc plate 201 as needed. Then, place the steel strip roll between the arc plate 201 and the upright plate 206 so that the steel strip roll is located on the two support rollers 207. At the same time, the first limiting roller 203 and the second limiting roller 205 are in contact with the steel strip roll. During packaging, the steel strip is pulled by the packaging machine or manually. The steel strip roll roll rolls with the first limiting roller 203, the second limiting roller 205 and the support roller 207, and the disc-shaped steel strip is gradually pulled out, continuously supplying steel strip raw materials for building pipe bundling. Finally, the building pipe is quickly packaged.

[0025] Specifically, by Figure 2 As shown, two support plates 2011 are symmetrically fixedly connected to the bottom of the upright plate 206, and the bottom of the two support plates 2011 is provided with support wheels 2010 located at the top of the base 1.

[0026] In use, when the guide plate 208 slides along the guide post 2016, it drives the upright plate 206 to move horizontally. At the same time, the support wheels 2010 on both sides of the bottom of the upright plate 206 roll on the top of the base 1 to support the upright plate 206 and ensure the stability of the upright plate 206.

Claims

1. A building tube packing device comprising a base (1), characterized in that: The base (1) is provided with a packaging mechanism (2) on its top. The packaging mechanism (2) includes two arc-shaped plates (201) symmetrically fixed to the top of the base (1). Two through slots (202) are symmetrically provided on the arc-shaped plates (201). A limiting roller (203) is rotatably connected to the inner side of the through slot (202). Two support rollers (207) are symmetrically rotatably connected between the two arc-shaped plates (201). Two upright plates (206) are symmetrically provided between the two arc-shaped plates (201). The two upright plates (206) are both located above the two support rollers (207). Two through slots (204) are symmetrically provided on the upright plates (206). A limiting roller (205) is rotatably connected to the inner side of the through slot (204). A guide column (205) is fixedly connected between the two arc-shaped plates (201). 016), two guide plates (208) are symmetrically and movably sleeved on the outside of the guide column (2016). The two guide plates (208) are fixed to the bottom of the two upright plates (206) respectively, and the two guide plates (208) are located between the two support rollers (207). A U-shaped plate (209) is fixedly installed on the top of the base (1). The U-shaped plate (209) is located below the two support rollers (207). A two-way screw (2014) is rotatably connected to the inside of the U-shaped plate (209). One end of the two-way screw (2014) extends to the outside of the U-shaped plate (209) and is fixedly connected to a handwheel (2017). Two screw nuts (2013) are symmetrically threaded on the outside of the two-way screw (2014).

2. The building pipe packaging device according to claim 1, characterized in that: The inner bottom wall of the U-shaped plate (209) is provided with a sliding groove (2012), and the two nuts (2013) are slidably connected to the sliding groove (2012).

3. The building pipe packaging device according to claim 1, characterized in that: The outer side of the nut (2013) is symmetrically rotatably connected to two movable rods (2015), and the ends of the two movable rods (2015) away from the nut (2013) are respectively rotatably connected to two guide plates (208).

4. A building pipe packaging device according to claim 1, characterized in that: The bottom of the upright plate (206) is symmetrically fixedly connected to two support plates (2011), and the bottom of the two support plates (2011) is provided with support wheels (2010) located on the top of the base (1).