A concrete pouring formwork for the closure section of bridge piers

By designing a concrete pouring formwork for the closure section of the bridge pier, the problem of a weak layer between the top surface of the closure section and the bottom surface of the upper pier body was solved, achieving rapid and high-quality concrete pouring and improving the appearance quality.

CN224982055UActive Publication Date: 2026-11-17THE THIRD ENG OF CHINA RAILWAY 12TH BUREAU GROUP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522455619.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-19
Publication Date
2026-11-17
Estimated Expiration
2035-11-19

AI Technical Summary

Technical Problem

During the construction of the closure section of bridge piers, existing technology makes it difficult to effectively pour concrete from the side, resulting in a weak layer between the top surface of the closure section and the bottom surface of the upper pier body, which affects the appearance quality and construction speed.

Method used

The concrete pouring formwork for the closure section of the bridge pier is adopted, including the formwork panel, formwork back rib, attached vibrator, pouring port, pouring hopper, slurry discharge and venting port and slurry discharge hopper. The pouring port is designed to be higher than the bottom surface of the upper pier body, and the slurry discharge hopper is lower than the bottom surface of the upper pier body. Combined with the attached vibrator, it is ensured that the concrete fills the mold cavity and removes air bubbles and laitance.

Benefits of technology

It improved construction speed, ensured the appearance quality of concrete, eliminated the weak layer between the top surface of the closure section and the bottom surface of the upper pier, and achieved the construction effect of no misalignment and no need to remove excess concrete later.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982055U_ABST
    Figure CN224982055U_ABST
Patent Text Reader

Abstract

This utility model belongs to the technical field of bridge pier closure section construction. The purpose is to provide a concrete pouring template for bridge pier closure sections, which allows for side pouring and vibration, effectively removing air bubbles and laitance, improving construction speed, resulting in better concrete appearance quality, and eliminating weak concrete layers between the top surface of the closure section and the bottom surface of the upper pier body. The technical solution is as follows: the upper part of the template panel overlaps with the upper pier body, and the lower part overlaps with the lower pier body. Multiple rings of template back ribs are provided on the outside of the template panel, and multiple attached vibrators are installed on the outside of the template panel. At the junction of the template panel and the bottom of the upper pier body, there is a pouring port and multiple slurry discharge and venting ports evenly distributed. A pouring hopper is provided outside the pouring port, and a pouring insert plate is provided above the pouring port. A slurry discharge hopper is provided outside each slurry discharge and venting port, and a slurry discharge and venting insert plate is provided above each slurry discharge and venting port. This utility model is used for concrete pouring construction of bridge pier closure sections.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to a concrete pouring template for the closure section of bridge piers, belonging to the technical field of bridge pier closure section construction. Background Technology

[0002] High-speed railway bridge piers are generally poured from bottom to top. However, with the development of high-speed railway construction technology in my country, bridge structures are becoming increasingly lightweight. This has led to the emergence of integral rigid frame bridges with a post-cast closure section on the piers. In this method, the lower pier body is poured first, followed by the upper pier body, which is poured simultaneously with the beams, with the closure section reserved for final pouring. Because the closure section is located at the bottom of the upper pier body and the top of the lower pier body, it cannot be poured from top to bottom as in the conventional way. Instead, it needs to be poured from the side, which carries risks such as incomplete concrete filling, a weak layer between the top surface of the closure section and the bottom surface of the upper pier body, and poor appearance quality after closure. Utility Model Content

[0003] To address the shortcomings of existing technologies, the purpose of this utility model is to provide a concrete pouring template for the closure section of bridge piers, which allows for side pouring and vibration, effectively removing air bubbles and laitance, improving construction speed, enhancing concrete appearance quality, and eliminating weak concrete layers between the top surface of the closure section and the bottom surface of the upper pier body.

[0004] To achieve the above objectives, the present invention adopts the following technical solution: a concrete pouring template for the closure section of a bridge pier, comprising a template panel, template back ribs, attached vibrators, a pouring port, a pouring hopper, a pouring insert plate, a slurry discharge and venting port, a slurry discharge hopper, and a slurry discharge and venting insert plate. The upper part of the template panel overlaps with the upper pier body, and the lower part overlaps with the lower pier body. Multiple template back ribs are provided on the outside of the template panel, and multiple attached vibrators are installed on the outside of the template panel. The template panel is evenly distributed with multiple openings at the junction with the bottom of the upper pier. Each opening includes a grouting port and multiple grout discharge and venting ports. A grouting hopper is provided outside the grouting port, and a grouting insert plate is provided above the grouting port for opening or closing the grouting port. A grout discharge hopper is provided outside each grout discharge and venting port, and a grout discharge and venting insert plate is provided above each grout discharge and venting port for opening or closing the grout discharge and venting port. The top of the grouting hopper is higher than the bottom surface of the upper pier, and the top of the slurry discharge hopper is lower than the bottom surface of the upper pier.

[0005] Preferably, the bottom of the injection plate is provided with a first inclined surface adapted to the inclined surface of the injection hopper, and the bottom of each slurry discharge and venting plate is provided with a second inclined surface adapted to the inclined surface of the slurry discharge hopper.

[0006] Preferably, an additional template back rib is provided above the injection port and the slurry discharge and venting port on the template panel. The additional template back rib is provided with a plate slot at the position corresponding to the injection port and the slurry discharge and venting port. The plate slot is used to position the injection plate and the slurry discharge and venting plate.

[0007] Preferably, both the template back rib and the additional template back rib are long steel plates, which are vertically welded to the template panel.

[0008] Preferably, the top of the grouting hopper is 20cm higher than the bottom surface of the upper pier.

[0009] Preferably, the top surface of the slurry discharge hopper is 2cm lower than the bottom surface of the upper pier.

[0010] Preferably, the overlap length between the template panel and the upper and lower pier bodies is 30cm.

[0011] Preferably, the number of slurry discharge and venting ports is three.

[0012] Preferably, the number of attached vibrators is two, installed opposite each other.

[0013] Compared with the prior art, the present invention has the following beneficial effects.

[0014] 1. This utility model has a simple structure, is easy to install, and has a fast construction speed.

[0015] 2. In this utility model, the template panel overlaps with both the upper and lower pier bodies by 30cm, and multiple layers of template back ribs are wrapped around the outside of the template panel. After pouring the closure section, the concrete has a good appearance quality, no misalignment, and no need to remove or grind off excess concrete after demolding.

[0016] 3. This utility model is equipped with a grouting port, a grouting hopper, a grouting insert plate, a grout discharge and venting port, a grout discharge hopper, and a grout discharge and venting insert plate. The top of the grouting hopper is higher than the bottom surface of the upper pier body, and the top of the grout discharge hopper is lower than the bottom surface of the upper pier body. In this way, during the pouring process, the floating slurry and air bubbles can be completely discharged, and the height difference pressure of the concrete during pouring is also increased, so that the concrete can fill the mold cavity and there is no weak concrete layer between the top surface of the closure section and the bottom surface of the upper pier body. Attached Figure Description

[0017] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0018] Figure 1This is a schematic diagram of the structure of this utility model.

[0019] Figure 2 for Figure 1 The left view.

[0020] Figure 3 for Figure 1 A magnified view of a portion of point A in the middle.

[0021] Figure 4 for Figure 1 A magnified view of a section at point B.

[0022] Figure 5 for Figure 2 Sectional view at point CC.

[0023] In the diagram: 1 is the template panel, 2 is the template back rib, 3 is the attached vibrator, 4 is the grouting port, 5 is the grouting hopper, 6 is the grouting insert plate, 7 is the grout discharge and venting port, 8 is the grout discharge hopper, 9 is the grout discharge and venting insert plate, 10 is the upper pier body, 11 is the lower pier body, 12 is the first inclined section, 13 is the second inclined section, 14 is the additional template back rib, 15 is the insert plate groove, and 16 is the closing section. Detailed Implementation

[0024] The technical solutions of the present utility model will be clearly and completely described in conjunction with the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other implementation methods obtained by those skilled in the art without creative effort are within the scope of protection of the present utility model.

[0025] It should be noted that the structures, proportions, sizes, etc. shown in the accompanying drawings of this specification are only used to complement the content disclosed in the specification for those skilled in the art to understand and read, and are not intended to limit the conditions under which this utility model can be implemented. Therefore, they have no substantial technical significance. Any modification to the structure, change in the proportional relationship, or adjustment of the size should still fall within the scope of the technical content disclosed in this utility model, provided that it does not affect the effects and purposes that this utility model can produce. It should be noted that in this specification, relational terms such as "first" and "second" are only used to distinguish one entity from several other entities, and do not necessarily require or imply any such actual relationship or order between these entities.

[0026] The present invention provides the following embodiments.

[0027] like Figure 1 , Figure 2As shown, this utility model discloses a concrete pouring template for the closure section of a bridge pier, comprising a template panel 1, template back ribs 2, attached vibrators 3, a pouring port 4, a pouring hopper 5, a pouring insert plate 6, a slurry discharge and venting port 7, a slurry discharge hopper 8, and a slurry discharge and venting insert plate 9. The upper part of the template panel 1 overlaps with the upper pier body 10 around the upper pier body 10, and the lower part overlaps with the lower pier body 11 around the lower pier body 11. Multiple template back ribs 2 are provided on the outside of the template panel 1, and multiple attached vibrators 3 are installed on the outside of the template panel 1. The template panel 1 and the bottom of the upper pier body 10 are evenly distributed with a ring of multiple openings. Each of the multiple openings includes a grouting port 4 and multiple grout discharge and venting ports 7. A grouting hopper 5 is provided outside the grouting port 4. A grouting insert plate 6 for opening or closing the grouting port 4 is provided above the grouting port 4. A grout discharge hopper 8 is provided outside each grout discharge and venting port 7. A grout discharge and venting insert plate 9 for opening or closing the grout discharge and venting port 7 is provided above each grout discharge and venting port 7. The top of the grouting hopper 5 is higher than the bottom surface of the upper pier body 10, and the top of the grout discharge hopper 8 is lower than the bottom surface of the upper pier body 10.

[0028] The template panel 1 can be made of 5mm thick steel plate to form a mold with the same external dimensions as the closing section 16, and is fastened with bolts to hug the upper pier 10 and the lower pier 11.

[0029] The grouting port 4 is the concrete grouting port. The top of the grouting hopper 5 is higher than the bottom surface of the upper pier 10, which can increase the pressure difference of the concrete during pouring. The grout discharge and venting port 7 is the channel for the discharge of laitance and air bubbles generated after concrete vibration. The installation of the grout discharge hopper 8 facilitates waste collection. The top of the grout discharge hopper 8 is lower than the bottom surface of the upper pier 10, which allows the laitance to flow out smoothly and avoids the laitance from being obstructed and accumulating in the mold cavity. These structures can ensure that the concrete can fill the mold cavity during pouring, so that there is no weak concrete layer between the top surface of the closure section 16 and the bottom surface of the upper pier 10.

[0030] like Figure 3 , Figure 4 As shown, the bottom of the injection plate 6 is provided with a first inclined surface 12 that is adapted to the inclined surface of the injection hopper 5, and the bottom of each slurry discharge and exhaust plate 9 is provided with a second inclined surface 13 that is adapted to the inclined surface of the slurry discharge hopper 8.

[0031] The injection plate 6 and the discharge plate 9 can be made of 3mm thick steel plate and their shape matches the shape of the closing section 16 at that point. After the plates are inserted, the inclined surfaces at the bottom of the injection hopper 5 and the discharge hopper 8 can abut against the first inclined surface 12 and the second inclined surface 13 to prevent the bottom of the injection plate 6 and the discharge plate 9 from moving outward.

[0032] like Figure 5As shown, an additional template back rib 14 is provided above the injection port 4 and the slurry discharge and venting port 7 on the template panel 1. Insert plate slots 15 are provided on the additional template back ribs 14 at positions corresponding to the injection port 4 and the slurry discharge and venting port 7. The insert plate slots 15 are used to position the injection insert plate 6 and the slurry discharge and venting insert plate 9. The insert plate slots 15 are located close to the template panel 1.

[0033] Both the template back rib 2 and the additional template back rib 14 are long steel plates, which are vertically welded to the template panel 1 to increase the strength of the template panel 1 and prevent the template panel 1 from deforming.

[0034] The top of the grouting hopper 5 is 20cm higher than the bottom surface of the upper pier body 10.

[0035] The top surface of the slurry discharge hopper 8 is 2cm lower than the bottom surface of the upper pier body 10.

[0036] The overlap length between the template panel 1 and the upper pier body 10 and the lower pier body 11 is 30cm.

[0037] The number of slurry discharge and exhaust ports 7 is 3.

[0038] The number of attached vibrators 3 is two, installed opposite each other. In order to overcome the difficulty that the immersion vibrator cannot be removed into the closure section 16, the attached vibrators 3 are installed on the template panel 1 to vibrate during the concrete pouring process and ensure the quality of the concrete.

[0039] The installation and pouring process of this utility model is as follows.

[0040] After the reinforcement of the pier closure section 16 is installed, the formwork panel 1 is installed on the closure section 16. The top of the formwork panel 1 is tightly wrapped with the upper pier body 10, and the bottom is tightly wrapped with the lower pier body 11, with each overlap reaching a height of 30cm. Then, the grouting plate 6 and the grouting and venting plate 9 at the grouting port 4 and the grouting and venting port 7 are opened, and concrete is poured from the grouting port 4. At the same time, the attached vibrator 3 is turned on to vibrate the concrete. When the concrete is poured to the top edge of the grouting hopper 8, the laitance on the concrete surface will be discharged from several grouting and venting ports 7. As the concrete continues to be poured, the concrete always flows from the grouting port 4 to the grouting and venting ports 7. After the laitance and air bubbles are discharged, the normal concrete of better quality begins to be discharged. After the concrete is completely normal, the grouting and venting plate 9 is inserted. All grouting and venting ports 7 are controlled according to this standard. Finally, the grouting plate 6 is inserted, and the concrete is cured with the formwork in place.

[0041] The above description is merely a preferred embodiment of this utility model, but the protection scope of this utility model is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in this utility model should be included within the protection scope of this utility model. Therefore, the protection scope of this utility model should be determined by the scope of the claims.

Claims

1. A concrete pouring formwork for the closure section of a bridge pier, characterized in that: It includes a template panel (1), template back ribs (2), attached vibrators (3), grouting port (4), grouting hopper (5), grouting insert (6), grout discharge and venting port (7), grout discharge hopper (8) and grout discharge and venting insert (9). The upper part of the template panel (1) overlaps with the upper pier body (10) around the upper pier body (10), and the lower part overlaps with the lower pier body (11) around the lower pier body (11). Multiple template back ribs (2) are provided on the outside of the template panel (1), and multiple attached vibrators (3) are installed on the outside of the template panel (1). The template panel (1) is connected to the bottom of the upper pier body (10) with a ring of multiple openings. Among the multiple openings, there is a grouting port (4) and multiple grout discharge and venting ports (7). A grouting hopper (5) is provided outside the grouting port (4). A grouting insert plate (6) for opening or closing the grouting port (4) is provided above the grouting port (4). A grout discharge hopper (8) is provided outside each grout discharge and venting port (7). A grout discharge and venting insert plate (9) for opening or closing the grout discharge and venting port (7) is provided above each grout discharge and venting port (7). The top of the grouting hopper (5) is higher than the bottom surface of the upper pier (10), and the top of the slurry discharge hopper (8) is lower than the bottom surface of the upper pier (10).

2. The concrete pouring formwork for the closure section of a bridge pier as described in claim 1, characterized in that: The bottom of the injection plate (6) is provided with a first inclined surface (12) adapted to the inclined surface of the injection hopper (5), and the bottom of each slurry discharge and exhaust plate (9) is provided with a second inclined surface (13) adapted to the inclined surface of the slurry discharge hopper (8).

3. A concrete pouring formwork for the closure section of a bridge pier as described in claim 1 or 2, characterized in that: An additional template back rib (14) is provided above the injection port (4) and the slurry discharge and venting port (7) on the template panel (1). An insert plate slot (15) is provided on the additional template back rib (14) at the position corresponding to the injection port (4) and the slurry discharge and venting port (7). The insert plate slot (15) is used to position the injection insert plate (6) and the slurry discharge and venting insert plate (9).

4. The concrete pouring formwork for the closure section of a bridge pier as described in claim 3, characterized in that: The template back rib (2) and the additional template back rib (14) are both long steel plates, which are vertically welded to the template panel (1).

5. A concrete pouring formwork for the closure section of a bridge pier as described in claim 1 or 2, characterized in that: The top of the grouting hopper (5) is 20cm higher than the bottom surface of the upper pier (10).

6. A concrete pouring formwork for the closure section of a bridge pier as described in claim 1 or 2, characterized in that: The top surface of the slurry discharge hopper (8) is 2cm lower than the bottom surface of the upper pier body (10).

7. A concrete pouring formwork for the closure section of a bridge pier as described in claim 1 or 2, characterized in that: The overlap length between the template panel (1) and the upper pier body (10) and the lower pier body (11) is 30cm.

8. A concrete pouring formwork for the closure section of a bridge pier as described in claim 1 or 2, characterized in that: The number of the slurry discharge and exhaust ports (7) is 3.

9. A concrete pouring formwork for the closure section of a bridge pier as described in claim 1 or 2, characterized in that: The number of attached vibrators (3) is two, installed opposite each other.