A beam cross-section reinforcement structure

By combining columns, beams, stirrups, and clamping sleeves, the problem of large workload and scratch risk of manual wrapping of steel wire ties is solved, and efficient and automated reinforcement of beam structures is achieved.

CN224982071UActive Publication Date: 2026-11-17SINOHYRDO ENG BUREAU 3 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522593454.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-05
Publication Date
2026-11-17
Estimated Expiration
2035-12-05

AI Technical Summary

Technical Problem

In existing technologies, steel wire ties require repeated manual wrapping, which is labor-intensive and poses a risk of cutting the operator's hands.

Method used

The beam-variable cross-section reinforcement structure is composed of columns, beams, first stirrups, second stirrups, first reinforcing bars, and second reinforcing bars. The automatic binding and adjustment of the reinforcing bars are achieved by using clamping sleeves and threaded rods, and the reinforcement is achieved by concrete pouring.

Benefits of technology

This reduces the workload of manually wrapping steel wire ties, avoids the risk of hand cuts, and achieves efficient reinforcement of beam structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982071U_ABST
    Figure CN224982071U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of building structure reinforcement technology, specifically to a beam variable cross-section reinforcement structure, including a column. A crossbeam is fixedly connected to the top of the column, and a first stirrup is fixedly connected to the bottom of the crossbeam. A second stirrup is welded to the outside of the first stirrup. The column has two sets, and a first reinforcing bar is fixedly connected inside both sets of the column. The first reinforcing bar extends to the top of the second stirrup. A second reinforcing bar is provided on the side of the two sets of first reinforcing bars that are close to each other. A clamping sleeve is fitted on the outside of both the first and second reinforcing bars. Concrete is poured inside the second stirrup. Compared with existing beam variable cross-section reinforcement structures, this utility model, through the design of the clamping sleeve and threaded rod, can quickly clamp and position reinforcing bars of different thicknesses, and can also connect two sets of reinforcing bars, greatly improving the overall practicality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of building structure reinforcement technology, specifically to a beam variable cross-section reinforcement structure. Background Technology

[0002] In the fields of transportation infrastructure construction and building engineering, beams play a crucial role as key load-bearing components. However, with the increase in service life, many early-built beam structures face severe challenges. Due to long-term exposure to natural environmental erosion, such as rainwater erosion and thermal expansion and contraction caused by temperature changes, as well as the combined effects of increasing traffic loads, higher design standards, and construction quality, beam structures inevitably develop a series of problems, requiring reinforcement.

[0003] The traditional method of increasing the cross-section requires chiseling away the floor slabs on both sides of the top of the beam along the span direction to arrange longitudinal reinforcement. Transverse reinforcement is then laid flat and bound with wire ties. However, the wire ties need to be manually wrapped repeatedly, which increases the workload. In addition, the wire ties are too sharp and may cut the operator's palm. Utility Model Content

[0004] In view of the shortcomings of the existing technology, the purpose of this utility model is to provide a beam variable cross-section reinforcement structure, which aims to solve the problems of the existing technology that require repeated manual winding of steel wire ties, which increases the workload, and the steel wire ties being too sharp, which may cut the operator's palm.

[0005] To achieve the above objectives, this utility model provides the following technical solution:

[0006] A beam variable cross-section reinforcement structure includes a column. A crossbeam is fixedly connected to the top of the column, and a first stirrup is fixedly connected to the bottom of the crossbeam. A second stirrup is welded to the outside of the first stirrup. The column has two sets of first reinforcing bars, and the interior of each set of the column is fixedly connected to a first reinforcing bar. The first reinforcing bar extends to the top of the second stirrup. A second reinforcing bar is provided on the side of the two sets of first reinforcing bars that are close to each other. A clamping sleeve is fitted on the outside of both the first and second reinforcing bars. Concrete is poured inside the second stirrup.

[0007] As a preferred embodiment of this utility model, the clamping sleeve is composed of a first semi-circular sleeve and a second semi-circular sleeve. One end of the first semi-circular sleeve is fixedly connected to a protrusion, and a groove is formed at one end of the second semi-circular sleeve near the first semi-circular sleeve and at a position corresponding to the protrusion.

[0008] As a preferred embodiment of this utility model, a positioning shaft is rotatably connected inside the groove. The positioning shaft passes through the outside of the protrusion and is rotatably connected to the protrusion. Rubber pads are provided on the inner sidewalls of the first semi-circular sleeve and the second semi-circular sleeve.

[0009] As a preferred embodiment of this utility model, the height of the first semi-circular sleeve is greater than the height of the second semi-circular sleeve, a first baffle is fixedly connected to the outside of one end of the first semi-circular sleeve, and one end of the second semi-circular sleeve is slidably connected to the inside of the first baffle.

[0010] As a preferred embodiment of this utility model, a fixed column is fixedly connected inside the first baffle, and a threaded rod is threadedly connected inside the fixed column. A second baffle is fixedly connected to one end of the second semi-circular sleeve near the first baffle, and a sleeve is fixedly connected inside the second baffle. A threaded groove is formed inside the sleeve at a position corresponding to the threaded rod.

[0011] As a preferred embodiment of this utility model, the clamping sleeve is provided in two sets, and each set of clamping sleeves is fixedly connected to a mounting ear on the side that is close to each other. A disc is rotatably connected inside the mounting ear, and a connecting rod is fixedly connected to the outside of the disc.

[0012] As a preferred embodiment of this utility model, the connecting rod is provided in two sets, one set of connecting rods is rotatably connected to a lead screw, and the lead screw extends into the interior of the other set of connecting rods and is threadedly connected to the connecting rod.

[0013] Compared with the prior art, the beneficial effects of this utility model are:

[0014] 1. In this utility model, the original layer at the bottom of the crossbeam is chiseled out, and then the top of the second stirrup is welded to the outside of the first stirrup. The second stirrup is designed as a U-shape, with space at its inner bottom end for bearing. The first steel bar is inserted into the column and placed on top of the second stirrup. Then, the second steel bar is placed at the end where the two sets of first steel bars are close to each other, so that the gap at the inner bottom end of the second stirrup is filled. Finally, concrete is poured into it to reinforce the crossbeam.

[0015] 2. In this utility model, by tightening the first and second semi-circular sleeves, and then rotating the threaded rod, it will be directly inserted into the inside of the threaded groove, thus forming a closed space between the first and second semi-circular sleeves. This accommodates steel bars of different thicknesses. By rotating the screw, the screw will move spirally to the inside of another set of connecting rods and generate tension on the mounting ears, so that the distance between the two sets of clamping sleeves is similar, and the distance between the two sets of steel bars can be adjusted. Attached Figure Description

[0016] Figure 1 This is a schematic diagram of the overall structure of this utility model;

[0017] Figure 2 This is a schematic diagram of the overall structure of this utility model;

[0018] Figure 3This is a schematic diagram of the clamping sleeve structure of this utility model;

[0019] Figure 4 This is a schematic diagram of the clamping sleeve separation structure of this utility model.

[0020] In the diagram: 1. Column; 2. Beam; 3. First stirrup; 4. Second stirrup; 5. First reinforcing bar; 6. Second reinforcing bar; 7. Hoop sleeve; 8. Concrete; 9. First semi-circular sleeve; 10. Second semi-circular sleeve; 11. Positioning shaft; 12. First baffle; 13. Fixed column; 14. Threaded rod; 15. Sleeve; 16. Mounting lug; 17. Connecting rod; 18. Lead screw. Detailed Implementation

[0021] The technical solutions of the present utility model will be clearly and completely described below with reference to the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model without creative effort are within the protection scope of the present utility model.

[0022] Example: Please refer to Figures 1-4 This utility model provides a technical solution:

[0023] A beam-variable cross-section reinforcement structure includes a column 1, a crossbeam 2 fixedly connected to the top of the column 1, a first stirrup 3 fixedly connected to the bottom of the crossbeam 2, and a second stirrup 4 welded to the outside of the first stirrup 3. The column 1 has two sets of stirrups, each set containing a first reinforcing bar 5 fixedly connected inside. The first reinforcing bar 5 extends to the top of the second stirrup 4. A second reinforcing bar 6 is provided on the side of the two sets of first reinforcing bars 5 that are close to each other. Both the first and second reinforcing bars 5 and the second reinforcing bars 6 are fitted with clamping sleeves 7. Concrete 8 is poured inside the second stirrup 4. First, the original layer at the bottom of the crossbeam 2 is chipped away, exposing the first stirrup 3. The second stirrup 4 is exposed to the outside, and then the top of the second stirrup 4 is welded to the outside of the first stirrup 3. At this time, the second stirrup 4 will be perpendicular to the bottom of the beam 2, and the second stirrup 4 is designed as a U-shape, with space at the bottom of its inner side for bearing. Then, depending on the reinforcement height, the first steel bar 5 is inserted into the position of the column 1 and placed on top of the second stirrup 4. By fitting the clamping sleeve 7 on the outside of the first steel bar 5 and the second steel bar 6 respectively, a connection is made between them, so that the gap at the bottom of the inner side of the second stirrup 4 is filled. Finally, concrete 8 is poured into it to achieve the reinforcement of the beam 2.

[0024] Furthermore, in this embodiment, the clamping sleeve 7 is composed of a first semi-circular sleeve 9 and a second semi-circular sleeve 10. One end of the first semi-circular sleeve 9 is fixedly connected to a protrusion. The second semi-circular sleeve 10 is provided with a groove at one end near the first semi-circular sleeve 9 and at a position corresponding to the protrusion. A positioning shaft 11 is rotatably connected inside the groove. The positioning shaft 11 passes through the outside of the protrusion and is rotatably connected to the protrusion. Rubber pads are provided on the inner sidewalls of both the first semi-circular sleeve 9 and the second semi-circular sleeve 10. By fitting the first semi-circular sleeve 9 and the second semi-circular sleeve 10 onto one end of the first reinforcing bar 5 and then bringing them together, the protrusion will rotate along the positioning shaft 11, thereby reducing the gap between the first semi-circular sleeve 9 and the second semi-circular sleeve 10. Subsequently, the rubber pads will increase the friction with the surfaces of the first reinforcing bar 5 and the second reinforcing bar 6.

[0025] Furthermore, in this embodiment, the height of the first semi-circular sleeve 9 is greater than the height of the second semi-circular sleeve 10. A first baffle 12 is fixedly connected to the outside of one end of the first semi-circular sleeve 9, and one end of the second semi-circular sleeve 10 is slidably connected to the inside of the first baffle 12. A fixed post 13 is fixedly connected to the inside of the first baffle 12, and a threaded rod 14 is threadedly connected to the inside of the fixed post 13. A second baffle is fixedly connected to the end of the second semi-circular sleeve 10 near the first baffle 12, and a sleeve 15 is fixedly connected to the inside of the second baffle. A threaded groove is opened at the position corresponding to the threaded rod 14 inside the sleeve 15. When the first semi-circular sleeve 9 and the second semi-circular sleeve 10 are tightened, the second baffle will slide between the first baffle 12. Then the threaded rod 14 is rotated. When the threaded rod 14 rotates, it reacts with the fixed post 13, causing it to spiral inside the fixed post 13. Finally, it will directly insert into the inside of the threaded groove, so that the fixed post 13 and the sleeve 15 are connected, and a closed space is formed between the first semi-circular sleeve 9 and the second semi-circular sleeve 10.

[0026] Furthermore, in this embodiment, the clamping sleeve 7 is provided in two sets. The two sets of clamping sleeves 7 are fixedly connected to the side of their close proximity with mounting ears 16. A disc is rotatably connected inside the mounting ear 16, and a connecting rod 17 is fixedly connected to the outside of the disc. There are two sets of connecting rods 17. A lead screw 18 is rotatably connected inside one set of connecting rods 17. The lead screw 18 extends into the interior of the other set of connecting rods 17 and is threadedly connected to the connecting rod 17. When it is necessary to adjust the distance between the first reinforcing bar 5 and the second reinforcing bar 6, the lead screw 18 is rotated, thereby realizing the spiral movement of the lead screw 18 into the interior of the other set of connecting rods 17 and generating a pulling force on the mounting ear 16, so that the distance between the two sets of clamping sleeves 7 is close.

[0027] In this embodiment, the specific implementation scenario is as follows: First, the bottom layer of the crossbeam 2 is chiseled away to expose the first stirrup 3. Then, the top of the second stirrup 4 is welded to the outside of the first stirrup 3. At this time, the second stirrup 4 will be perpendicular to the bottom of the crossbeam 2, and the second stirrup 4 is designed as a U-shape, with space at its inner bottom end for bearing. Then, depending on the reinforcement height, the first reinforcing bar 5 is inserted into the column 1 and placed on top of the second stirrup 4. Then, the second reinforcing bar 6 is placed at the end where the two sets of first reinforcing bars 5 are close to each other. By fitting the first semi-circular sleeve 9 and the second semi-circular sleeve 10 onto one end of the first reinforcing bar 5 and the second reinforcing bar 6, the clamping sleeve 7 is then brought together, and the protrusion will rotate along the positioning axis 11, thereby reducing the gap between the first semi-circular sleeve 9 and the second semi-circular sleeve 10. Then, the rubber pad will increase... When the friction between the first reinforcing bar 5 and the second reinforcing bar 6 is increased, the first semi-circular sleeve 9 and the second semi-circular sleeve 10 are tightened. At this time, the second baffle will slide between the first baffle 12. Then the threaded rod 14 is rotated. When the threaded rod 14 rotates, it reacts with the fixed column 13, causing it to move spirally inside the fixed column 13. Finally, it will directly insert into the inside of the threaded groove, so that the fixed column 13 and the sleeve 15 are connected, and a closed space is formed between the first semi-circular sleeve 9 and the second semi-circular sleeve 10. By rotating the screw rod 18, the screw rod 18 is spirally moved to the inside of another set of connecting rods 17, and a pulling force is generated on the mounting ear 16, so that the distance between the two sets of clamping sleeves 7 is close, so that the gap at the bottom of the inner side of the second stirrup 4 is filled. Finally, concrete 8 is poured into it to strengthen the beam 2.

[0028] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A beam variable cross-section reinforcement structure comprising a column (1), characterized in that: The top of the column (1) is fixedly connected to a crossbeam (2), the bottom of the crossbeam (2) is fixedly connected to a first stirrup (3), and a second stirrup (4) is welded to the outside of the first stirrup (3). The column (1) is provided with two sets, and the interior of the two sets of the column (1) is fixedly connected to a first reinforcing bar (5). The first reinforcing bar (5) extends to the top of the second stirrup (4). A second reinforcing bar (6) is provided on the side of the two sets of first reinforcing bars (5) that are close to each other. A clamping sleeve (7) is fitted on the outside of the first reinforcing bar (5) and the second reinforcing bar (6). Concrete (8) is poured inside the second stirrup (4).

2. A beam variable cross-section reinforcing structure according to claim 1, characterized in that: The clamping sleeve (7) is composed of a first semi-circular sleeve (9) and a second semi-circular sleeve (10). One end of the first semi-circular sleeve (9) is fixedly connected to a protrusion, and the second semi-circular sleeve (10) has a groove at one end close to the first semi-circular sleeve (9) and at a position corresponding to the protrusion.

3. The beam variable cross-section reinforcement structure according to claim 2, characterized in that: The groove is rotatably connected to a positioning shaft (11), which passes through the outside of the protrusion and is rotatably connected to the protrusion. Rubber pads are provided on the inner sidewalls of the first semi-circular sleeve (9) and the second semi-circular sleeve (10).

4. A beam variable cross-section reinforcement structure according to claim 2, characterized in that: The height of the first semi-circular sleeve (9) is greater than the height of the second semi-circular sleeve (10). A first baffle (12) is fixedly connected to the outside of one end of the first semi-circular sleeve (9), and one end of the second semi-circular sleeve (10) is slidably connected to the inside of the first baffle (12).

5. A beam variable cross-section reinforcement structure according to claim 4, characterized in that: The first baffle (12) is fixedly connected to a fixed post (13), and the fixed post (13) is threadedly connected to a threaded rod (14). The second semi-circular sleeve (10) is fixedly connected to a second baffle at one end near the first baffle (12). The second baffle is fixedly connected to a sleeve (15), and the sleeve (15) is threaded at a position corresponding to the threaded rod (14).

6. The beam variable cross-section reinforcement structure according to claim 1, characterized in that: The clamping sleeve (7) is provided in two sets. The two sets of clamping sleeves (7) are fixedly connected to the side of each other with mounting ears (16). The mounting ears (16) are rotatably connected to a disc, and the disc is fixedly connected to a connecting rod (17).

7. A beam variable cross-section reinforcement structure according to claim 6, characterized in that: The connecting rod (17) is provided in two sets. One set of connecting rods (17) is rotatably connected to a lead screw (18). The lead screw (18) extends into the interior of the other set of connecting rods (17) and is threadedly connected to the connecting rod (17).