Prefabricated building with reserved connection structure
By connecting the I-beam structure with the mesh steel frame, the problem of insufficient strength of the reserved connection structure in prefabricated buildings is solved, and the stability and strength of the overall structure are improved.
Patent Information
- Application Number
- CN202522391782.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-11
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-11-11
AI Technical Summary
In existing prefabricated buildings, the connection strength of the reserved connection structure is insufficient, which affects the overall structural strength and stability of the assembly connection.
The connectors, which adopt an I-beam structure, are connected to the mesh steel frame through the assembly grooves on them, forming an integral structure between the precast concrete components and the base. Welding and concrete pouring are used to form a stable frame and improve the connection strength.
It improves the connection strength between prefabricated buildings and the load-bearing surface, enhances the stability of the overall structure, and strengthens the load-bearing capacity of the assembly connection.
Smart Images

Figure CN224982364U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of prefabricated building technology, and in particular relates to a prefabricated building reserved connection structure. Background Technology
[0002] Prefabricated buildings refer to buildings where a large amount of on-site work in traditional construction methods is transferred to factories. Building components and accessories (such as floor slabs, wall panels, stairs, balconies, etc.) are processed and manufactured in factories, transported to the construction site, and assembled and installed on-site using reliable connection methods.
[0003] Prefabricated buildings use a large number of pre-reserved connection structures to assist in the later fixed assembly. In the existing technology, most of the pre-reserved connection structures are built into the building by concrete pouring, which results in insufficient connection strength between the protruding pre-reserved connection structure and the main body of the prefabricated building, affecting the overall structural strength of the connection point in the later assembly. Utility Model Content
[0004] This utility model provides a pre-installed connection structure for prefabricated buildings. The utility model is implemented as follows: A pre-installed connection structure for prefabricated buildings includes: The connector is an I-beam structure, and the flange of the connector is provided with assembly slots for connecting several sets of steel frames; The first and second space frames are mesh steel frames, which are respectively located on both sides of the connector. The connector is engaged with the first and second space frames through an assembly groove.
[0005] Preferably, the assembly slot is arranged at an angle to the ground and the opening of the assembly slot faces the ground.
[0006] Preferably, the first space frame includes several sets of horizontally arranged support longitudinal bars and uprights arranged perpendicular to the support longitudinal bars, the assembly groove is adapted to the diameter of the support longitudinal bars, and the assembly groove engages with the support longitudinal bars.
[0007] Preferably, the first space frame includes connecting longitudinals, supporting longitudinals, and uprights. The connecting longitudinals and supporting longitudinals are arranged horizontally, and the connecting longitudinals are arranged in pairs at intervals to form longitudinal assemblies. The mounting rod assembly is arranged parallel to the supporting longitudinals.
[0008] Preferably, the connector is located in the interval formed by the longitudinal rod assembly, the connecting longitudinal rod passes through the flange of the connector, the end of the connecting longitudinal rod is provided with threads and a nut, and the nut of the connecting longitudinal rod abuts against the flange of the connector.
[0009] Preferably, the first space frame and the second space frame have the same structure.
[0010] Preferably, the outer sides of the first and second space frames are provided with a concrete layer, and one end of the connector extends out of the concrete layer.
[0011] Compared with the prior art, the embodiments of this application have the following main advantages: The prefabricated building pre-connection structure provided by this utility model connects precast concrete components and concrete bases through connectors. The connectors are integrally connected to the first and second space frames, thereby forming an integral structure between the precast concrete components and the concrete base. This improves the connection strength between the prefabricated building and the load-bearing surface, and enhances the stability of the entire structure of the prefabricated building and the load-bearing surface. Attached Figure Description
[0012] Figure 1 This is a schematic diagram of a connector structure for a prefabricated building pre-connection structure provided by this utility model.
[0013] Figure 2 This is a schematic diagram of the first and second space frame structures of a prefabricated building with reserved connection structure provided by this utility model.
[0014] Figure 3 This utility model provides a schematic diagram of a connector for a prefabricated building reserved connection structure, as well as a first space frame and a second space frame structure.
[0015] Figure 4 This is a schematic diagram of the first space frame structure consisting only of supporting longitudinal rods in a prefabricated building reserved connection structure provided by this utility model.
[0016] Figure 5 This utility model provides a schematic diagram of the first space frame structure consisting of connecting longitudinal rods and supporting longitudinal rods for a prefabricated building reserved connection structure.
[0017] Explanation of reference numerals in the attached figures: 100. Connector; 101. Assembly slot; 210. First space frame; 211. Connecting longitudinal rod; 212. Supporting longitudinal rod; 213. Upright; 220. Second space frame; 300. Concrete layer. Detailed Implementation
[0018] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs; the terminology used herein in the specification of the application is for the purpose of describing particular embodiments only and is not intended to be limiting of the application; the terms "comprising" and "having," and any variations thereof, in the specification, claims, and foregoing drawings of this application are intended to cover non-exclusive inclusion. The terms "first," "second," etc., in the specification, claims, or foregoing drawings of this application are used to distinguish different objects, not to describe a particular order.
[0019] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment mutually exclusive with other embodiments. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.
[0020] This utility model embodiment provides a pre-installed connection structure for prefabricated buildings, such as... Figures 1-5 As shown, the prefabricated building pre-connection structure includes: The connector 100 is an I-beam structure, and the flange of the connector 100 is provided with assembly slots 101 for connecting several sets of steel frames. The first space frame 210 and the second space frame 220 are mesh steel frames. The first space frame 210 and the second space frame 220 are respectively located on both sides of the connector 100. The connector 100 is engaged with the first space frame 210 and the second space frame 220 through the assembly groove 101.
[0021] The first space frame 210 includes several sets of horizontally arranged support longitudinal rods 212 and uprights 213 arranged perpendicular to the support longitudinal rods 212. The assembly groove 101 is adapted to the diameter of the support longitudinal rods 212. Here, the assembly groove 101 is arranged inclined to the ground and the opening of the assembly groove 101 faces the ground. During the assembly process, the connector 100 moves closer to the ground and is engaged with the support longitudinal rods 212 by using the assembly groove 101. After the engagement is completed, the connector 100 can be welded to the first space frame 210 and the second space frame 220 to form a frame structure. Then, the connector 100, the first space frame 210 and the second space frame 220 are formed into an integral precast concrete component by concrete pouring. In this application, the first space frame 210, the second space frame 220, and the concrete layer 300 constitute a concrete component. The connector 100 is mostly located inside the precast concrete component. The part of the connector 100 extending out of the concrete layer 300 is assembled on a concrete base 400 adapted to prefabricated buildings. The main method here is to cast a groove with a slot for accommodating the connector 100 by cast-in-place means. A connecting bolt tube is preset on the end face of the concrete base 400 that constructs the slot. The connecting bolt tube is only one method. It can also be similar to the method of pre-embedded parts, with corresponding screw holes preset on the pre-embedded parts. The connector 100 is assembled on the concrete base 400 by bolts. The gap between the connector 100 and the slot is sealed by cast-in-place concrete later.
[0022] The precast concrete components and the concrete base 400 are connected by a connector 100, which is integrally connected to the first space frame 210 and the second space frame 220, thereby forming an integral structure between the precast concrete components and the concrete base 400, which improves the connection strength between the prefabricated building and the load-bearing surface, and improves the stability of the entire structure of the prefabricated building and the load-bearing surface.
[0023] As a preferred embodiment of this example, the first space frame 210 adopts two structures. The first structure of the first space frame 210 includes several sets of horizontally arranged support rods 212 and uprights 213 arranged perpendicular to the support rods 212. The assembly groove 101 is adapted to the diameter of the support rods 212 and the assembly groove 101 is engaged with the support rods 212. In the specific assembly process, the support longitudinal rods 212 are first pushed into the assembly slots 101 of the connectors 100 in sequence. After the support longitudinal rods 212 are pushed in, the uprights 213 are welded to the parallel support longitudinal rods 212. At this time, a suitable assembly slot 101 is selected to weld the connectors 100 and the support longitudinal rods 212 to form an integral structure. Finally, concrete is poured on the outside of the connectors 100, the first space frame 210, and the second space frame 220. The second type of first space frame 210 includes connecting longitudinal rods 211, supporting longitudinal rods 212, and uprights 213. The connecting longitudinal rods 211 and supporting longitudinal rods 212 are arranged horizontally. The connecting longitudinal rods 211 are arranged in pairs at intervals to form longitudinal rod combinations. The mounting rod assembly is arranged parallel to the supporting longitudinal rods 212. Here, the connecting longitudinal rods 211 are short rod structures, and the supporting longitudinal rods 212 are long rod structures. The connector 100 is assembled and installed between the first space frame 210 and the second space frame 220. The specific assembly method is as follows: First, push the support longitudinal rod 212 into the assembly groove 101 of the connector 100, then weld the upright rod 213 to the parallel support longitudinal rod 212. Then, place the connecting longitudinal rods 211 on both sides of the connector 100. The end of the connecting longitudinal rod 211 is connected to the connecting longitudinal rod 211 assembly groove 101 by a nut. Here, the upright rod 213 is also welded to the connecting longitudinal rod 211 to form an integral structure. Finally, pour concrete on the outside of the connector 100, the first space frame 210 and the second space frame 220. The bolt structure makes the longitudinal traction force of the upright rod 213 greater than that of welding. The staggered arrangement of the connecting longitudinal rod 211 and the support longitudinal rod 212 is beneficial to the internal stress distribution.
[0024] In this embodiment, the connecting rod 211 passes through the flange of the connector 100, and the end of the connecting rod 211 is provided with threads and nuts. The connecting rod 211 has two sets of nuts, which respectively abut against both sides of the flange of the connector 100.
[0025] It should be noted that, for the sake of simplicity, the foregoing embodiments are all described as a series of actions. However, those skilled in the art should understand that the present invention is not limited to the described order of actions, as some steps may be performed in other orders or simultaneously according to the present invention. Furthermore, those skilled in the art should also understand that the embodiments described in the specification are preferred embodiments, and the actions and modules involved are not necessarily essential to the present invention.
[0026] The above embodiments are only used to illustrate the technical solutions of this utility model, and are not intended to limit the scope of protection of this utility model. Obviously, the described embodiments are only some embodiments of this utility model, not all embodiments. Based on these embodiments, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this utility model. Although this utility model has been described in detail with reference to the above embodiments, those skilled in the art can still combine, add, delete, or otherwise adjust the features of the various embodiments of this utility model according to the circumstances without conflict or creative effort, thereby obtaining different technical solutions that do not fundamentally depart from the concept of this utility model. These technical solutions are also within the scope of protection of this utility model.
Claims
1. A prefabricated building pre-connection structure, characterized in that, include: The connector (100) is an I-beam structure, and the flange of the connector (100) is provided with an assembly groove (101) for connecting several sets of steel frames; The first space frame (210) and the second space frame (220) are mesh steel frames. The first space frame (210) and the second space frame (220) are respectively located on both sides of the connector (100). The connector (100) is engaged with the first space frame (210) and the second space frame (220) through the assembly groove (101).
2. The prefabricated building pre-connection structure as described in claim 1, characterized in that, The assembly slot (101) is arranged at an angle to the ground and the opening of the assembly slot (101) faces the ground.
3. The prefabricated building pre-connection structure as described in claim 2, characterized in that, The first space frame (210) includes several sets of horizontally arranged support rods (212) and uprights (213) arranged perpendicular to the support rods (212). The assembly groove (101) is adapted to the diameter of the support rods (212) and the assembly groove (101) is engaged with the support rods (212).
4. The prefabricated building pre-connection structure as described in claim 2, characterized in that, The first space frame (210) includes connecting longitudinal rods (211), supporting longitudinal rods (212) and uprights (213). The connecting longitudinal rods (211) and supporting longitudinal rods (212) are arranged horizontally. The connecting longitudinal rods (211) are arranged in pairs at intervals to form a longitudinal rod combination. The mounting rod assembly is arranged parallel to the supporting longitudinal rods (212).
5. The prefabricated building reserved connection structure as described in claim 4, characterized in that, The connector (100) is located in the interval formed by the longitudinal rod assembly. The connecting longitudinal rod (211) passes through the flange of the connector (100). The end of the connecting longitudinal rod (211) is provided with a thread and a nut. The nut of the connecting longitudinal rod (211) abuts against the flange of the connector (100).
6. A prefabricated building pre-connection structure as described in claim 3 or 5, characterized in that, The first space frame (210) and the second space frame (220) have the same structure.
7. The prefabricated building pre-connection structure as described in claim 1, characterized in that, The first space frame (210) and the second space frame (220) are provided with a concrete layer (300) on their outer sides, and one end of the connector (100) extends out of the concrete layer (300).