Method for monitoring the operation of a winch, and in particular the number of layers of cable winding on a winch drum

The method for monitoring winch drum winding layers using linear and rotation speed measurements addresses the lack of reliable layer monitoring, enhancing cable length estimation, load height determination, and damage anticipation, thereby improving safety and efficiency.

FR3142182B1Active Publication Date: 2024-11-01MANITOWOC CRANE GROUP FRANCE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
FR2022012141
Authority / Receiving Office
FR · FR
Patent Type
Patents
Current Assignee / Owner
Filing Date
2022-11-22
Publication Date
2024-11-01
Estimated Expiration
2042-11-22

AI Technical Summary

Technical Problem

Existing winch systems lack reliable methods for monitoring the number of winding layers of a cable on a drum, which is crucial for estimating cable length, load height, and detecting potential cable damage, leading to inefficiencies and potential hazards.

Method used

A method for continuous monitoring of the number of winding layers on a winch drum by measuring linear speed and drum rotation speed, using tachometric systems to calculate the number of layers, and logging cumulative usage times to assess cable stress and generate alarms for potential damage.

Benefits of technology

Enables precise estimation of cable length and load height, enhances load indicator accuracy, and anticipates cable damage, improving operational safety and efficiency by providing real-time monitoring and alert systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000015_0000
    Figure 00000015_0000
  • Figure 00000016_0000
    Figure 00000016_0000
  • Figure 00000016_0001
    Figure 00000016_0001
Patent Text Reader

Abstract

A method for monitoring the operation of a winch (1) comprising a motor (10) driving a drum (12) around which a cable (2) is wound, said cable being able to wind in several layers, the number of which varies according to the winding and unwinding of the cable, said method implementing continuous monitoring of the number of cable winding layers on the drum by ensuring in real time at least the following steps: - measurement of a first parameter (P1) representing a linear speed of the cable as it exits the drum; - measurement of a second parameter (P2; P2') representing a rotational speed of the drum; - determination of the number of cable winding layers as a function of the first and second parameters. This method finds advantageous application in the monitoring of winches for lifting equipment, and in particular for cranes. Abstract figure: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

Title of the invention: Method for monitoring the operation of a winch, and in particular the number of layers of winding of a cable on a winch drum technical field

[0001] The invention relates to a method for monitoring the operation of a winch, implementing continuous monitoring of the number of layers of winding of a cable on a winch drum.

[0002] The invention finds a preferred, but not limiting, application in crane-type lifting devices, and in particular tower cranes, modular cranes, self-erecting cranes, harbor cranes, and mobile cranes. The invention can also be applied to cable transport devices, such as cable cars or chairlifts. Previous technique

[0003] In an application to a lifting device, such as a crane, it is known to use a lifting winch comprising a motor driving a rotating drum around which a cable, called the lifting cable, is wound, to move a load suspended on a hook attached to the cable, raising and lowering it. It is also known to use a distribution winch comprising a motor driving a rotating drum around which a cable, called the distribution cable, is wound, to move a distribution trolley along a boom, the lifting cable passing through this distribution trolley so that the load is suspended below the distribution trolley, which thus moves the load along the boom.

[0004] It is also known, in a luffing jib crane, to use a lifting winch comprising a motor driving in rotation a drum on which is wound a cable, called a lifting cable, which is connected to the jib to raise or lower it in order to tilt it more or less between a lowered horizontal position and several raised positions.

[0005] In a conventional manner, the drum is driven by the motor via a reduction gear.

[0006] Generally the cable can wind on its drum on several layers of winding, the number of which varies according to the winding and unwinding of the cable; this is referred to as a multilayer drum.

[0007] There is a need to monitor the operation of a winch, in order to know, for example, the length of cable unwound or wound, a load indicator, or a level of cable damage in order to anticipate its replacement. Summary of the invention

[0008] To this end, the invention proposes to make this winch monitoring more reliable or to improve it by focusing on a parameter which is the number of layers of cable winding on the drum.

[0009] Thus, the invention proposes a method for monitoring the operation of a winch, this winch comprising a motor driving a drum around which a cable is wound. This cable can wind onto the drum in several layers, the number of which varies according to the winding and unwinding of the cable. This method implements continuous monitoring of the number of layers of cable winding on the drum by ensuring, in real time, at least the following steps: - measurement of a first parameter representative of a linear speed of cable movement at the exit of the drum; - measurement of a second parameter representative of a drum rotation speed; - determination of the number of cable winding layers as a function of the first parameter and the second parameter.

[0010] Such a process thus makes it possible to know in real time the number of layers of winding of the cable on the drum, and therefore equivalently the layer of winding in use, which is advantageous and useful information for improving the accuracy in the estimation of many parameters, such as a length of cable unwound or wound, a height under load, a load indicator, a defect in winding the cable on the drum, etc.

[0011] This process is based on the following approach:

[0012] - measurement of the first parameter allowing the linear speed of the scroll to be deduced cable;

[0013] - measurement of the second parameter allowing the rotational speed of the drum to be deduced

[0014] - establishing the number of cable winding layers, which is related to the radius the winding radius of the cable on the drum, this winding radius being itself a function of the linear speed of cable movement and the rotational speed of the drum.

[0015] According to one feature, the measurement of the first parameter consists of measuring the rotational speed of a pulley on which the cable runs at the output of the drum, the linear speed of the cable being deduced as a function of this rotational speed of the pulley and a geometry of the pulley.

[0016] The rotational speed of the pulley carrying the cable can, for example, be measured using a tachometric system (optical, mechanical, inductive, or other).

[0017] According to another feature, the measurement of the second parameter consists of a direct measurement of the rotation speed of the drum or a measurement of an output speed of the motor.

[0018] The rotational speed of the drum or the output speed of the motor can, for example, be measured using a tachometric system (optical, mechanical, inductive, or other).

[0019] According to one possibility, the method implements a calculation of the linear speed of cable scrolling as a function of the first parameter, and a calculation of the rotation speed of the drum as a function of the second parameter, and the number of layers of cable winding is determined as a function of a ratio between the linear speed of cable scrolling and the rotation speed of the drum.

[0020] Indeed, this ratio between the linear speed of cable movement and the rotation speed of the drum is proportional to the radial distance (or winding diameter) of the cable.

[0021] According to another possibility, the method implements a determination of a length of cable unwound or wound as a function of the number of layers of winding of the cable and a reference position.

[0022] Indeed, knowledge of the number of layers of winding of the cable improves the accuracy in estimating such a length.

[0023] According to another possibility, the number of cable winding layers can take different values ​​between 1 and N, N being the maximum number of cable winding layers, and the method implements a history in a database, over a given period of time, of the values ​​of the number of winding layers which are associated with layer numbers, to establish cumulative usage times specific to each layer number.

[0024] In other words, this history recording makes it possible to know how long the cable has accumulated in time occupied zero layers, one layer, two layers, ... up to N layers, which is particularly useful for estimating whether the deepest layers (layers 1 and 2 at a minimum) have been reached and therefore determining a level of stress or use of the termination of the cable attached to the drum; we speak of a dead part of the cable for the terminal part of the cable which is not stressed or used.

[0025] Advantageously, the method implements an estimation of a cable damage index based on the cumulative usage times specific to each layer number.

[0026] Indeed, if the deep layers are under-stressed or under-used, then there is a situation of potential damage to the dead cable section; and therefore such a damage index is particularly advantageous for anticipating and managing a risk related to this damage to the dead cable section.

[0027] In a particular embodiment, the damage index is classified as critical when at least one of the cumulative service times is less than a critical threshold over the given time period.

[0028] According to one possibility, an alarm is generated when the damage index is classified as critical; so as to alert an operator or manager that it is time to audit, or even replace, the cable.

[0029] An intermediate threshold, higher than the critical threshold, may be provided to indicate that the cable must be fully unwound in order to stress the dead part of the cable, and thus prevent critical damage.

[0030] In a particular embodiment, the method implements tracking of an angular position of the drum.

[0031] Such monitoring has two main advantages: - determining the number of turns in the cable based on the number of cable winding layers and the angular position of the drum; and / or - detection of a cable winding fault based on the number of cable winding layers and the angular position of the drum.

[0032] In a favorite, and non-limiting, application, the winch is a lifting winch of a lifting device, such as a crane, in order to raise / lower a load suspended from a hook fixed on the cable, or the winch is a lifting winch of a lifting device such as a luffing jib crane, in order to tilt a jib more or less in order to raise / lower a load suspended from a hook fixed on the jib.

[0033] It should be noted that such a lifting winch can also allow the load to be moved along the boom, on this type of luffing boom crane.

[0034] According to a possibility related to the lifting winch and the hoisting winch, the method implements a determination of a height under the hook, corresponding to a vertical distance between the hook and the ground on which the lifting device rests, said height under the hook being determined continuously as a function of the number of winding layers.

[0035] According to another possibility related to the lifting winch and the hoisting winch, the method implements a determination of a load indicator which is representative of a weight of the load, said load indicator being determined continuously as a function of the number of winding layers.

[0036] The invention also relates to a monitoring system for monitoring the operation of a winch, the winch comprising a motor driving a drum around which a cable is wound, said cable being able to wind onto said drum in several layers of winding, the number of which varies according to the winding and unwinding of the cable, this monitoring system implementing continuous monitoring of the number of layers of cable winding onto the drum by means of: - a first measuring device to measure a first parameter representative of a linear speed of cable scrolling at the exit of the drum; - a second measuring device to measure a second parameter representative of a drum rotation speed; - a calculation unit to determine the number of cable winding layers as a function of the first parameter and the second parameter.

[0037] The invention also relates to a lifting device, such as a crane, comprising: - a lifting winch comprising a motor driving a drum around which is wound a lifting cable connected to a hook for raising / lowering a load suspended from this hook, this lifting cable being able to wind around said drum in several layers of winding, the number of which varies according to the winding and unwinding of the lifting cable, or - a lifting winch comprising a motor driving in rotation a drum on which is wound a lifting cable which is connected to a boom to raise or lower the boom in order to raise / lower a load suspended from a hook fixed on the boom; and in which this lifting device includes a monitoring system as described above for monitoring the operation of said lifting winch or said hoisting winch. Brief description of the drawings

[0038] Other features and advantages of the present invention will become apparent from the following detailed description of a non-limiting example of implementation, made with reference to the accompanying figures in which:

[0039] [Fig-1] is a schematic view of a winch and a monitoring system for monitor the operation of the winch;

[0040] [Fig.2] is a schematic view from two distinct angles of a drum for illustrate the winding layers of a cable;

[0041] [Fig.3] is a schematic view of two lifting devices equipped with winches adapted for the implementation of a monitoring method.

[0042] [Detailed description of one or more embodiments of the invention]

[0043] With reference to [Fig. 1], a winch 1 adapted for implementing a monitoring method comprises: - a motor 10 which is a rotary motor equipped with a motor shaft 11 driven in rotation; - a drum 12, of the multilayer drum type, rotatably mounted on a frame around a drum axis 13, said drum 12 being coupled to the motor shaft 11 to be driven in rotation by the motor 10 around its drum axis 13.

[0044] The drum 12 can be coupled to the motor shaft 11 via a reducer 14 to modify the speed ratio and / or the torque between the motor shaft 11 and the drum 12.

[0045] The motor 10 can be controlled by a control system 4 (such as, for example, a system integrating at least one processor and / or one controller and / or one electronic board) via a speed variator 16 (also called a frequency variator) configured to regulate the speed of the motor 10.

[0046] A cable 2 is wound on the drum 12, this cable 2 being able to wind on the drum 12 in several layers of winding the number of which varies according to the winding and unwinding of the cable 2. The number of winding layers of the cable 2 can take different values ​​between 1 and N, N being the maximum number of winding layers of the cable 2. Thus, when the cable 2 is wound to its maximum, the number of winding layers is N.

[0047] The values ​​for the number of winding layers are thus associated with layer numbers. In other words, when the cable 2 is wound to its maximum, it winds into N layers comprising a layer No. 1 (the deepest layer or the one closest to the axis of the drum 13, which is in contact with the drum 12), then a layer No. 2 (in contact with layer No. 1), then a layer No. 3, and so on up to layer No. N (the layer furthest from the axis of the drum 13). Layer No. 1 thus corresponds to the layer visible when the cable 2 is unwound almost to its maximum (the maximum unwound corresponds to the normally unreached case where there are no more layers and only one end of the cable is attached to the drum); and layer No. N thus corresponds to the layer visible when the cable 2 is wound to its maximum.

[0048] On each layer, the number of turns or twists of the cable 2 can be substantially equivalent, which depends on the length of the drum 12 and the diameter of the cable 2.

[0049] Furthermore, each winding layer of cable 2 is associated with a radial distance (or layer radius) measured from the drum axis 13 to the center of cable 2 in the layer; the radial distance therefore increasing with the layer number.

[0050] Fig. 2 illustrates an example of a drum 12 around which five layers of cable 2 are wound, with a layer Cl or layer no. 1 associated with a radial distance RI, a layer C2 or layer no. 2 associated with a radial distance R2, a layer C3 or layer no. 3 associated with a radial distance R3, a layer C4 or layer no. 4 associated with a radial distance R4, and a layer C5 or layer no. 5 associated with a radial distance R5.

[0051] A monitoring system 3 is provided to monitor the operation of the winch 1, and more specifically to implement continuous (or real-time) monitoring of the number of cable winding layers 2 on drum 12.

[0052] This monitoring system 3 comprises: - a first measuring device 31 to measure a first parameter PI representative of a linear speed of cable 2 coming out of the drum 12; - a second measuring device 32 or 32' for measuring a second parameter P2 or P2' representative of a rotational speed of the drum 12 around its drum axis 13; and - a calculation unit 40 to determine the number of cable winding layers 2 as a function of the first parameter PI and the second parameter P2.

[0053] In the illustrated example, the calculation unit 40 is integrated into the control system 4 which controls the motor 10. In other words, the control system 4 includes calculation means adapted to form the calculation unit 40 which determines the number of winding layers of the cable 2. It is of course conceivable that the calculation unit 40 is separate from the control system 4.

[0054] The first measuring device 31 may include: - a pulley 34 over which the cable 2 runs from the drum 12, where the pulley 34 is rotatably mounted on a fixed support 35 so that the pulley 34 rotates around a pulley axis 36 under the effect of the cable 2 running; and - a tachometric system 37 (or tachometer) adapted to measure a rotational speed of the pulley 33.

[0055] Indeed, the rotational speed of the pulley 34 is directly related to the linear speed of the cable 2 as it exits the drum 12, according to a linear law that depends on the diameter of the pulley 34. The tachometric system 37 can, for example, be in the form of an optical tachometer, a mechanical or contact tachometer, an inductive tachometer, or another device for measuring a rotational speed. Thus, with this first measuring device 31, the first parameter PI corresponds to the rotational speed of the pulley 34.

[0056] In a first embodiment, the second measuring device 32 is in the form of a tachometric system (or tachometer) adapted to measure an output speed of the motor 10, in other words a rotational speed of the motor shaft 11. This output speed of the motor 10 corresponds to the rotational speed of the drum 12, either directly or after taking into account the reduction ratio of the reducer 14. Thus, with this second measuring device 32, the second parameter P2 corresponds to the output speed of the motor 10.

[0057] In a second embodiment, the second measuring device 32' is in the form of a tachometric system (or tachometer) adapted to directly measure the rotation speed of drum 12. Thus, with this second measuring device 32', the second parameter P2' corresponds to the rotation speed of drum 12.

[0058] It is of course conceivable to use both the second measuring device 32 and the second measuring device 32' to have redundancy in the measurement.

[0059] Thus, the calculation unit 40 implements: - a calculation of the linear speed of cable 2 as a function of the first parameter PI; - a calculation of the rotational speed of drum 12 as a function of the second parameter P2 or P2', and - a calculation of the number of winding layers of cable 2 as a function of a ratio between the linear speed of cable 2 and the rotation speed of drum 12.

[0060] Indeed, the number of winding layers of the cable 2 (or the number of the layer being wound or unwound) is linked to the winding radius of the cable 2 on the drum 12, which corresponds to the radial distance of the outermost layer (which is the layer being wound or unwound, the furthest from the axis of the drum 13), and this winding radius is itself a function of the linear speed of the cable 2 and the rotational speed of the drum 12. In the example of [Fig.2], the winding radius corresponds to the radial distance R5 of the layer C5 or layer no. 5.

[0061] More precisely, the ratio between the linear speed of cable 2 (expressed in meters per second) and the rotation speed of drum 12 (expressed in radians per second) is equivalent to this winding radius (expressed in meters) of cable 2 on drum 12.

[0062] After calculating the number of cable winding layers 2, the calculation unit 40 can, for example, implement: - a determination of the length of cable unwound or wound based on the number of cable winding layers 2 and a reference position; and / or - detection of a change in the number of winding layers of cable 2, namely the change from layer no. K to layer no. (Kl) when cable 2 is unwound and the change from layer no. K to layer no. (K+l) when cable 2 is wound.

[0063] The calculation unit 40 can implement: - a history in a database 41, over a given period of time, of the values ​​of the number of winding layers which are associated with layer numbers, to establish cumulative usage times specific to each layer number; - an estimate of a cable damage index 2 based on durations cumulative usage specific to each layer number; and - a classification of this damage index as critical when at least one of the cumulative usage times is less than a critical threshold over the given time period.

[0064] In the illustrated example, the database 41 is integrated into the control / command system 4. In other words, the control / command system 4 includes internal memory adapted to form the database 41. It is of course conceivable that the database 41 may be located remotely from the control / command system 4.

[0065] The method can implement the generation of an alarm (or alarm signal) when the damage index is classified as critical. Thus, a warning device 42, which can be visual or audible, is provided, connected to the computing unit 40 and / or the control system 4, to be controlled in order to generate a visual or audible alarm when the damage index is classified as critical.

[0066] The calculation unit 40 can implement: - monitoring of an angular position of the drum 12, for example by means of the second measuring device 32'; - a determination of the number of turns of the cable 2 as a function of the number of layers of winding of the cable and the angular position of the drum 12; - detection of a cable winding fault 2 based on the number of cable winding layers 2 and the angular position of the drum 12.

[0067] Figure 3 illustrates a first lifting apparatus 5 of the tower crane type, comprising a mast 55 at the top of which is mounted a boom 56 which can rotate about a vertical axis, and also comprising: - a lifting winch 51 comprising a motor 50 driving a rotating drum 52 around which is wound a lifting cable 53 connected to a hook 54 for raising / lowering a load suspended from this hook 54; and - a distribution winch 61 comprising a motor 60 driving in rotation a drum 62 on which is wound a distribution cable 63 to move in translation a distribution trolley 64 along the boom 56, the lifting cable 53 passing through this distribution trolley 64 so that the load is suspended below the distribution trolley 64 which thus ensures a movement of the load along the boom 56.

[0068] Figure 3 illustrates a second lifting apparatus 7 of the luffing jib crane type, comprising a mast 75 at the top of which is mounted a jib 76 that can pivot about a horizontal axis so that this jib can be more or less inclined with respect to the horizontal and can thus be raised, and this second lifting apparatus 7 comprises a lifting winch 71 comprising a motor 70 driving in rotation a drum 72 on which is wound a lifting cable 73 which is connected to the jib 76 to raise or lower it in order to tilt it more or less between a lowered horizontal position and several raised positions, and thus to raise / lower a load suspended from a hook 74 fixed on the boom 76. It should be noted that such a lifting winch 71 can also possibly allow (by unwinding / winding the lifting cable 73) to also move the load along the boom 76, on this type of luffing boom crane.

[0069] The monitoring system 3 described above can be implemented to: - monitor the operation of the lifting winch 51, and more specifically to implement continuous (or real-time) monitoring of the number of winding layers of the lifting cable 53 on the drum 52; or - to monitor the operation of the distribution winch 61, and more specifically to implement continuous (or real-time) monitoring of the number of winding layers of the distribution cable 63 on the drum 62; or - monitor the operation of the lifting winch 71, and more specifically to implement continuous (or real-time) monitoring of the number of winding layers of the lifting cable 73 on the drum 72.

[0070] In the case of monitoring the lifting winch 51 or the lifting winch 71, the number of winding layers of the lifting cable 53 or the lifting cable 73 allows the calculation unit 40 to determine a height under the hook H, corresponding to a vertical distance between the hook 54 or 74 and the ground on which the lifting device 5 or 7 rests. In other words, the calculation unit 40 can continuously determine this height under the hook H as a function of the number of winding layers.

[0071] In the case of monitoring the lifting winch 51 or the lifting winch 71, the number of winding layers of the lifting cable 53 or the lifting cable 73 allows the calculation unit 40 to determine a load indicator which is representative of the weight of the load suspended from the hook 54 or 74. In other words, the calculation unit 40 can continuously determine this load indicator as a function of the number of winding layers.

Claims

Claims

1. Method for monitoring the operation of a winch (1), said winch (1) comprising a motor (10) driving a drum (12) on which a cable (2) is wound, said cable (2) being able to be wound on said drum (12) on several winding layers, the number of which varies depending on the winding and unwinding of the cable (2), said number of winding layers of the cable (2) being able to take different values ​​between 1 and N, N being the maximum number of winding layers of the cable, said method implementing continuous monitoring of the number of winding layers of the cable (2) on the drum (12) by ensuring in real time at least the following steps: - measurement of a first parameter (PI) representative of a linear speed of travel of the cable (2) at the outlet of the drum (12); - measurement of a second parameter (P2; P2') representative of a rotation speed of the drum (12);- determining the number of winding layers of the cable (2) as a function of the first parameter (PI) and the second parameter (P2; P2'); - recording in a database (41), over a given period of time, the values ​​of the number of winding layers which are associated with layer numbers, to establish cumulative usage durations specific to each layer number.;

2. Method according to claim 1, in which the measurement of the first parameter (PI) consists of a measurement of a rotation speed of a pulley (34) on which the cable (2) circulates at the outlet of the drum (12), the linear speed of travel of the cable (2) being deduced as a function of this rotation speed of the pulley (34) and a geometry of the pulley (34).

3. A method according to claim 1 or 2, wherein the measurement of the second parameter consists of a direct measurement of the rotational speed of the drum (12) or a measurement of an output speed of the motor (10).

4. Method according to any one of the preceding claims, in which the method implements a calculation of the linear speed of travel of the cable (2) as a function of the first parameter (PI), and a calculation of the speed of rotation of the drum (12) as a function of the second parameter (P2; P2'), and the number of winding layers of the cable (2) is determined as a function of a ratio between the linear speed of travel of the cable (2) and the speed of rotation of the drum (12).

5. A method according to any preceding claim, wherein the method involves determining a length of unwound or wound cable as a function of the number of winding layers of the cable (2) and a reference position.

6. A method according to any preceding claim, wherein the method involves detecting a change in the number of winding layers of the cable (2).

7. Method according to any one of the preceding claims, in which the method implements an estimation of a damage index of the cable (2) as a function of the cumulative usage durations specific to each layer number.

8. The method of claim 7, wherein the damage index is classified as critical when at least one of the cumulative usage durations is below a critical threshold over the given time period.

9. The method of claim 8, wherein an alarm is generated when the damage index is classified as critical.

10. A method according to any preceding claim, wherein the method involves tracking an angular position of the drum (12).

11. A method according to claim 10, wherein the method implements a determination of a number of turns of the cable (2) as a function of the number of winding layers of the cable (2) and the angular position of the drum (12).

12. Method according to claim 10 or 11, wherein the method implements a detection of a winding fault of the cable (2) as a function of the number of winding layers of the cable (2) and the angular position of the drum (12).

13. A method according to any preceding claim, wherein the winch is a lifting winch (51) of a lifting apparatus (5), such as a crane, for lifting / lowering a load suspended from a hook (54) fixed to the cable, or the winch is a lifting winch (71) of a lifting apparatus (7) of the luffing jib crane type, for tilting a boom (76) more or less in order to lift / lower a load suspended from a hook (74) fixed to the boom (76).

14. Method according to claim 13, in which the method implements a determination of a height under hook (H), corresponding to a vertical distance between the hook (54; 74) and the ground on which it rests the lifting device (5; 7), said height under hook (H) being continuously determined as a function of the number of winding layers.

15. A method according to claim 13 or 14, wherein the method implements a determination of a load indicator which is representative of a weight of the load, said load indicator being continuously determined as a function of the number of winding layers.

16. Monitoring system (3) for monitoring the operation of a winch (1), said winch (1) comprising a motor (10) driving a drum (12) on which a cable (2) is wound, said cable (2) being able to be wound on said drum (12) on several winding layers, the number of which varies depending on the winding and unwinding of the cable (2), said monitoring system (3) implementing continuous monitoring of the number of winding layers of the cable on the drum (12) by means of: - a first measuring device (31) configured to measure a first parameter (PI) representative of a linear speed of travel of the cable (2) at the outlet of the drum (12); - a second measuring device (32; 32') configured to measure a second parameter (P2; P2') representative of a rotation speed of the drum (12);- a calculation unit (40) configured to determine the number of winding layers of the cable (2) as a function of the first parameter (PI) and the second parameter (P2; P2'); and wherein said calculation unit (40) is configured to implement a historization in a database (41), over a given period of time, of the values ​​of the number of winding layers which are associated with layer numbers, to establish cumulative usage durations specific to each layer number.;

17. Lifting apparatus (5; 7), such as for example a crane, comprising: - a lifting winch (51) comprising a motor (50) driving a drum (52) on which is wound a lifting cable (53) connected to a hook (54) for lifting / lowering a load suspended from this hook (54), said lifting cable (53) being able to be wound on said drum (52) on several winding layers, the number of which varies depending on the winding and unwinding of the lifting cable (53), or - a lifting winch (71) comprising a motor (70) rotating a drum (72) on which is wound a lifting cable (73) which is connected to a boom (76) for raising or lowering the latter in order to lift / lower a load suspended from a hook (74) fixed on the boom (76); and wherein said lifting apparatus (5; 7) comprises a monitoring system (3) according to claim 16 for monitoring the operation of said lifting winch (51) or said lifting winch (71).