Grouting water plugging device and method for water-rich tunnel

By arranging an annular air bag on the grouting water blocking device, filling the gap between the conduit and the borehole and injecting high-pressure slurry, the problem of the entire length of the borehole being blocked during grouting and water blocking in the prior art is solved, and partial sealing is achieved. The convenience of plugging and subsequent detection reduces construction costs.

WO2024198324A1PCT designated stage expired Publication Date: 2024-10-03CHINA RAILWAY NO 5 ENGINEERING GROUP CO LTD

Patent Information

Application Number
PCT/CN2023/126328
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-03-30
Filing Date
2023-10-25
Publication Date
2024-10-03

AI Technical Summary

Technical Problem

With the existing technology, in the construction of deep tunnels, the grouting water blocking device cannot fill the rock mass cracks without sealing the boreholes, resulting in increased workload and cost for advance drilling operations.

Method used

Design a grouting water-blocking device for water-rich tunnels, including a conduit with a closed front end and an annular air bag. The air bag fills the gap between the conduit and the drill hole when inflated. High-pressure grout is injected through the conduit and deflated after initial solidification to avoid The slurry spreads to achieve local sealing.

Benefits of technology

It effectively reduces the workload of advance drilling operations, avoids blocking the entire length of the borehole, reduces construction costs, and simplifies the subsequent detection process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023126328_03102024_PF_FP_ABST
    Figure CN2023126328_03102024_PF_FP_ABST
Patent Text Reader

Abstract

Disclosed in the present invention are a grouting water plugging device and method for a water-rich tunnel. The device comprises a guide pipe having a closed front end; grouting holes are formed on the side wall of the guide pipe; annular air bags are arranged, in a sleeving mode, at the front side and the rear side of the grouting holes; the air bags in an inflated state can fill a gap between the guide pipe and a drill hole. The method comprises: measuring an original water inflow quantity; determining the number and depths of rock fractures; adjusting the positions of the guide pipe and the air bags, to make all the rock fractures be located between the two air bags; inflating the air bags until the gap between the guide pipe and the drill hole is completely filled, and injecting high-pressure grout into the guide pipe; after initial setting of the grout and deflation of the air bags, reversing the guide pipe to brake the initially set grout in the gap between the guide pipe and the drill hole; and pulling the guide pipe out of the drill hole. By arranging the air bags, the gap can be sealed, the drill hole is prevented from being filled with the grout, and during subsequent detection, a drill rod can be directly inserted into an original drill hole to continue drilling forwards, thereby reducing the workload of advanced drilling operation, and effectively reducing the construction cost.
Need to check novelty before this filing date? Find Prior Art

Description

Grouting water blocking device and method for water-rich tunnel Technical Field

[0001] The present invention mainly relates to the technical field of grouting and water blocking, and in particular to a grouting and water blocking device and method for a water-rich tunnel. Background Art

[0002] During deep tunnel construction, the geological conditions along the tunnel route are difficult to accurately assess, leading to a sharp increase in the frequency of geological disasters encountered during construction. Fault fracture zones and water inrush in water-rich tunnels, in particular, often cause project delays. Therefore, advance drilling should be used to predict parameters such as the surrounding rock grade ahead of the tunnel face, water seepage, water pressure, and water temperature. This allows for the optimal selection of grouting materials and timely grouting to mitigate the risk of geological disasters.

[0003] The water gushing that occurs during the advance drilling construction process does not necessarily come from the rock cracks penetrated by the front end of the drill rod during drilling. It may also be caused by the interaction between the middle and rear parts of the drill rod and the rock wall during the drilling process, causing the rock in the corresponding area to be disturbed, thereby generating cracks (for example, when the depth of the borehole has reached 80m, the drill rod collides with the borehole 20m away from the hole mouth, resulting in water gushing cracks). In the prior art, there is no grouting and water blocking device and method for this situation. When grouting and water blocking are performed using the devices and methods in the prior art, it is necessary to first insert and fix the orifice tube in the borehole, and connect the exposed part of the orifice tube to the pipeline of the high-pressure grouting machine. Then, the high-pressure grouting machine is used to fill the borehole with slurry through the orifice tube. Under the action of pressure, the slurry in the borehole diffuses along the cracks, and after solidification, the water flow can be blocked. This construction method not only fills the rock cracks but also seals the borehole (that is, originally only grouting was required to seal the cracks 20m away from the hole mouth, but in fact the entire 80m long borehole was sealed). In order to continue to detect whether there is water seepage at a farther distance, it is necessary to re-drill ahead (that is, reopen the 80m long borehole and continue to drill ahead). It can be seen that construction using the devices and methods in the prior art will increase the workload of the advance drilling operation, thereby increasing construction costs. Therefore, there is an urgent need for a grouting and water blocking device and method that can fill the rock cracks in front without sealing the borehole.

[0004] Summary of the Invention

[0005] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a grouting water blocking device and method for a water-rich tunnel.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0007] A grouting and water blocking device for a water-rich tunnel comprises a conduit with a closed front end, a grouting hole formed on the side wall of the conduit, and an annular airbag mounted on both the front and rear sides of the grouting hole. The airbag can fill the gap between the conduit and the drill hole when inflated.

[0008] As a further improvement of the above technical solution:

[0009] The airbag is slidably mounted on the catheter, and a wire is pulled by the airbag for controlling the forward and backward movement of the airbag.

[0010] The rear section of the catheter is molded with scale lines for marking the insertion depth of the catheter.

[0011] A three-way valve is installed at the rear end of the conduit, one port of the three-way valve is connected to the grouting pipe, and the other port is installed with a measuring instrument.

[0012] The measuring instrument includes one or more of a flow meter, a thermometer, a pH meter and a conductivity meter.

[0013] The measuring instrument comprises a water pressure gauge, and a two-way valve is connected in series in the downstream direction of the measuring instrument.

[0014] Then, the present invention discloses a grouting water blocking method for a water-rich tunnel, which is applied to the above-mentioned grouting water blocking device and includes the following steps:

[0015] Step S1, measuring the original water inflow.

[0016] Step S2: determining the number and depth of rock mass cracks.

[0017] Step S3: adjusting the positions of the guide tube and the airbag so that each rock fracture is located between the two airbags.

[0018] Step S4: The airbag is inflated until the gap between the catheter and the drill hole is completely filled, and high-pressure slurry is injected into the catheter.

[0019] Step S5: After the slurry is initially solidified, the air bag is deflated, and the initially solidified slurry in the gap between the catheter and the drill hole is broken by twisting the catheter.

[0020] Step S6: pulling out the catheter from the drill hole.

[0021] As a further improvement of the above technical solution:

[0022] The step S2 comprises:

[0023] In step S21 , the front end of the catheter is inserted into the drill hole, and the airbag located at the rear side is inflated to fill the space between the catheter and the drill hole.

[0024] Step S22A: Insert the conduit forward. If the water stops flowing out, it is determined that the rock fracture is single. The insertion depth of the conduit at this time is recorded as L. A .

[0025] Step S22B: Insert the conduit forward. If water flows out of the conduit and the borehole simultaneously, it is determined that there are multiple rock fractures. The insertion depth of the conduit at this time is recorded as L. A .

[0026] Step S23: If there are multiple rock fractures, continue to insert the catheter forward. When no water flows out of the catheter, record the insertion depth of the catheter as L. B .

[0027] If the rock mass fracture is single, step S3 includes:

[0028] Step S31A, move the catheter backward to an insertion depth of (L A -S); where S≥2cm, but not greater than the original distance between the two airbags.

[0029] If there are multiple rock mass fractures, step S3 includes:

[0030] Step S31B, move the catheter backward to an insertion depth of (L A -S); where S≥2cm, but not greater than the original distance between the two airbags.

[0031] Step S32: the airbag located at the front side is inflated until the gap between the catheter and the drill hole is filled.

[0032] Step S33, moving the airbag located at the front side forward by means of the string until the amount of water flowing out of the catheter per unit time is the same as the original water inflow amount.

[0033] Compared with the prior art, the advantages of the present invention are:

[0034] By setting up air bags on the catheter, and the air bags are located on the front and back sides of the grouting hole, when they are in an inflated state, the gap between the catheter and the borehole can be completely blocked, so that the high-pressure slurry cannot spread outside the area clamped by the air bags, thus avoiding the slurry filling the entire borehole. During subsequent detection, the drill rod can be directly inserted into the original borehole, and continue drilling forward from the position where the water gushing occurs, thereby reducing the workload of the advance drilling operation and effectively reducing the construction cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] FIG1 is a schematic structural diagram of a grouting water blocking device for a water-rich tunnel in Example 1.

[0036] FIG2 is a flow chart of the grouting water blocking method in Example 2.

[0037] FIG3 is a process diagram of step S21 in Example 2.

[0038] FIG4 is a process diagram of step S22 in Example 2.

[0039] FIG5 is a process diagram of step S23 in Example 2.

[0040] FIG6 is a process diagram of step S31 in Example 2.

[0041] FIG7 is a process diagram of step S32 in Example 2.

[0042] FIG8 is a process diagram of step S33 in Example 2.

[0043] FIG9 is a process diagram of step S4 in Example 2.

[0044] FIG10 is a process diagram of step S5 in Example 2.

[0045] FIG11 is a process diagram of step S6 in Example 2.

[0046] FIG12 is a process diagram of step S22 in Example 3.

[0047] FIG13 is a process diagram of step S31 in Example 3.

[0048] The numbers in the figure represent: 1. catheter; 11. grouting hole; 12. air bag; 13. rope; 14. scale line; 15. air pipe; 16. ring; 2. borehole; 3. three-way valve; 4. grouting pipe; 5. measuring instrument; 6. two-way valve; 7. rock crack. DETAILED DESCRIPTION

[0049] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0050] Example 1

[0051] As shown in Figure 1, the first embodiment of the grouting and water-blocking device for a water-rich tunnel of the present invention comprises a conduit 1 with a closed front end. Grouting holes 11 are formed in the sidewalls of the conduit 1. Annular airbags 12 are mounted on both the front and rear sides of the grouting holes 11. When inflated, the airbags 12 are capable of filling the gap between the conduit 1 and the borehole 2. When using this device for grouting and water-blocking, the position of the conduit 1 and the airbags 12 is first adjusted so that each rock fissure 7 is located between the two airbags 12. The airbags 12 are then inflated to completely fill the gap between the conduit 1 and the borehole 2. High-pressure grout is then injected into the conduit 1. The high-pressure grout is discharged from the grouting holes 11 into the space between the two airbags 12, which is connected to the rock fissure 7. Under the action of pressure, the high-pressure grout enters the rock fissure 7 and diffuses. After the slurry is initially solidified and the airbag 12 is deflated, the catheter 1 is screwed to break the initial solidified slurry in the gap between the catheter 1 and the borehole 2 and release the connection. The catheter 1 is then pulled out of the borehole 2 to complete the grouting and water blocking construction. Compared with the prior art, in the technical solution of the present application, since the airbag 12 is provided on the catheter 1 and is located on the front and rear sides of the grouting hole 11, when it is in an inflated state, the gap between the catheter 1 and the borehole 2 can be completely blocked, so that the high-pressure slurry cannot spread outside the area clamped by the airbag 12, thus avoiding the slurry filling the entire borehole 2. When conducting subsequent detection, the drill rod can be directly inserted into the original borehole and continue drilling forward from the position where the water gushing occurs, thereby reducing the workload of the advance drilling operation and effectively reducing the construction cost.

[0052] Specifically, in order to control the inflation and deflation of the airbag 12 , an air tube 15 is connected to the airbag 12 , and the end of the air tube 15 passes through the drilled hole 2 .

[0053] In this embodiment, the airbag 12 is slidably mounted on the catheter 1. Each airbag 12 pulls a cord 13 that controls its forward and backward movement. Each airbag 12 has cords 13 pulled on both its front and rear sides, with the ends of the cords 13 extending through the drilled holes 2. A corresponding ring 16 for threading the cords 13 is formed on the catheter 1 at the front of each airbag 12. The cords 13 pulled on the front of the airbag 12 pass through the rings 16 and then deflect, thus driving the airbag 12 forward when pulled.

[0054] In this embodiment, the rear section of the catheter 1 is formed with scale lines 14 for marking the insertion depth of the catheter 1. By providing the scale lines 14 on the outer surface of the rear section of the catheter 1, the depth of the catheter 1 inserted into the borehole 2 can be determined by reading the scale at the opening of the borehole 2, thereby further determining the specific location of the rock fracture 7.

[0055] In this embodiment, a three-way valve 3 is installed at the rear end of the conduit 1. One end of the three-way valve 3 is connected to the grouting pipe 4, and the other end is equipped with a measuring instrument 5. The measuring instrument 5 is a water pressure gauge, and a two-way valve 6 is connected in series downstream. When it is necessary to obtain water pressure information of the gushing water, the port of the three-way valve 3 connected to the water pressure gauge is opened, and the port connected to the grouting pipe 4 is closed. The gushing water in the borehole 2 now flows out through the water pressure gauge and the two-way valve 6. When the two-way valve 6 is closed, the gushing water accumulates in the pipe and increases in pressure, and the water pressure gauge can now obtain the water pressure information of the gushing water. When it is necessary to grout the conduit 1, the port of the three-way valve 3 connected to the water pressure gauge is closed, and the port connected to the grouting pipe 4 is opened. The other end of the grouting pipe 4 is connected to the conduit of an external high-pressure grouting machine. The high-pressure grouting liquid enters the conduit 1 from the grouting pipe 4 through the three-way valve 3. In other embodiments, the measuring instrument 5 can also include one or more of a flow meter, a thermometer, a pH meter, and a conductivity meter.

[0056] Then, the invention also discloses a grouting water blocking method for a water-rich tunnel.

[0057] Example 2

[0058] As shown in FIG2 , the first embodiment of the grouting water blocking method for a water-rich tunnel of the present invention is applied to the above-mentioned grouting water blocking device and includes the following steps: Step S1, measuring the initial water flow; Step S2, determining the number and depth of the rock fissures 7; Step S3, adjusting the positions of the guide tube 1 and the airbag 12 so that each rock fissure 7 is located between the two airbags 12; Step S4, inflating the airbag 12 until it completely fills the gap between the guide tube 1 and the borehole 2, and injecting high-pressure slurry into the guide tube 1; Step S5, after the slurry has initially set, the airbag 12 is deflated, and the initially set slurry in the gap between the guide tube 1 and the borehole 2 is broken by twisting the guide tube 1; Step S6, pulling the guide tube 1 out of the borehole 2. When using this device for grouting water blocking construction, the water flow rate is first measured before the guide tube 1 is inserted into the borehole 2, and then the number and depth of the rock fissures 7 are detected. After the number and depth of the rock fissures 7 are determined, the position of the catheter 1 and the airbag 12 is adjusted so that each rock fissure 7 is located between the two airbags 12. The airbag 12 is inflated to completely fill the gap between the catheter 1 and the borehole 2, and then high-pressure grout is injected into the catheter 1. The high-pressure grout is discharged from the grouting hole 11 into the space between the two airbags 12, which is connected to the rock fissures 7. Under the action of pressure, the high-pressure grout enters the rock fissures 7 and diffuses. After the slurry initially sets and the airbag 12 is deflated, the catheter 1 is twisted to break the initial setting slurry in the gap between the catheter 1 and the borehole 2, releasing the connection. The catheter 1 is then pulled out of the borehole 2, completing the grouting and water blocking operation. Compared with the prior art, in the technical solution of the present application, since an airbag 12 is provided on the catheter 1, and the airbag 12 is located on the front and rear sides of the grouting hole 11, when it is in an inflated state, the gap between the catheter 1 and the borehole 2 can be completely blocked, so that the high-pressure slurry cannot diffuse outside the area clamped by the airbag 12, thereby avoiding the slurry filling the entire borehole 2. When conducting subsequent detection, the drill rod can be directly inserted into the original borehole, and continue to drill forward from the position where the water gushing occurs, thereby reducing the workload of the advance drilling operation and effectively reducing the construction cost.

[0059] In this embodiment, there are three rock fissures 7, and step S2 includes: step S21, the front end of the catheter 1 is inserted into the borehole 2, and the air bag 12 at the rear side is inflated to fill the gap between the catheter 1 and the borehole 2 (as shown in Figure 3, at this time, under the blockage of the air bag 12 at the rear side, all the gushing water enters the catheter 1 from the grouting hole 11 and is discharged from the rear end); step S22, the catheter 1 is inserted forward and deeper, and the gushing water flows out of the catheter 1 and the borehole 2 at the same time, and it is determined that there are multiple rock fissures 7, and the insertion depth of the catheter 1 at this time is recorded as L A(As shown in FIG4 , the air bag 12 at the rear side has just passed the location of the rock fissure 7 at the rearmost side. At this time, the water flowing out of the rock fissure 7 at the rearmost side cannot enter the conduit 1 due to being blocked by the air bag 12, and therefore flows out of the borehole 2; while the water flowing out of the soil fissure 7 at the front side continues to enter the conduit 1 from the grouting hole 11 and flows out from the rear end); Step S23, continue to insert the conduit 1 forward, and when no water flows out of the conduit 1, record the insertion depth of the conduit 1 as L B (As shown in Figure 5, the air bag 12 at the rear side has just passed the location of the rock fissure 7 at the front side. At this time, all the water flowing out of the rock fissure 7 cannot enter the catheter 1 because it is blocked by the air bag 12, so it all flows out from the borehole 2.) The rear section of the catheter 1 is formed with a scale line 14 for marking the insertion depth of the catheter 1. By setting the scale line 14 on the outer surface of the rear section of the catheter 1, by reading the scale at the opening of the borehole 2, the depth of the catheter 1 inserted into the borehole 2 can be known, so that the specific position of the rock fissure 7 can be further determined. By moving the catheter 1 to change the depth of the rear air bag 12 in the borehole 2, and observing the outflow method of the gushing water and the scale of the catheter 1, the value L can be obtained. A and L B , where L A It reflects the depth of the last rock crack 7 from the borehole, L B This reflects the depth of the frontmost rock fissure 7 from the borehole. In other words, the technical solution disclosed in this application can measure the number and depth of rock fissures 7 by simply pushing the conduit 1 and observing the water flow, without the need for external equipment. This reduces construction difficulty and saves construction costs.

[0060] In this embodiment, step S3 includes: step S31, moving the catheter 1 backward to an insertion depth of (L A -S); where S≥2cm, but not greater than the original spacing between the two balloons 12 (as shown in Figure 6, when the insertion depth of the catheter 1 is L AAt step S32, the airbag 12 at the front is inflated to fill the gap between the conduit 1 and the borehole 2 (as shown in FIG7 , at this time, the rock fissure 7 at the front is located before the airbag 12 at the front, so the water gushing out of it cannot enter the conduit 1 through the grouting hole 11 and be discharged. If grouting is performed at this time, the slurry cannot enter the rock fissure 7 at the front). S33, move the airbag 12 located at the front side forward by means of the rope 13 until the amount of water flowing out of the conduit 1 per unit time is the same as the original water gushing amount (as shown in FIG8 , at this time the airbag 12 at the front side is located in front of the frontmost rock fissure 7, that is, the three rock fissures 7 are all located in the area sandwiched by the two airbags 12, so the water gushing out of the three rock fissures 7 enters the conduit 1 through the grouting hole 11 and is discharged. At this time, the amount of water flowing out of the conduit 1 per unit time is the same as the original water gushing amount. If grouting is performed at this time, the slurry can enter the three rock fissures 7). The airbag 12 is slidably mounted on the conduit 1, and the airbag 12 pulls a rope 13 for controlling the forward and backward movement of the airbag 12. The front and rear sides of each airbag 12 are pulled by ropes 13, and the ends of the ropes 13 pass through the borehole 2. A corresponding ring 16 for threading a cord 13 is formed on the conduit 1 in front of each airbag 12. The cord 13, pulled in front of the airbag 12, passes through the ring 16 and then turns, thereby driving the airbag 12 forward when the cord 13 is pulled. In the technical solution disclosed in this application, the depth of the airbag 12 in the borehole 2 can be adjusted simply by pulling the cord 13. Combined with the observation of water flow, each rock fracture 7 can be positioned between two airbags 12, thereby preventing slurry from entering the rock fracture 7. This method is simple to operate and does not require external equipment.

[0061] In this embodiment, after completing step S33, step S4 is executed: the airbag 12 is inflated until it completely fills the space between the conduit 1 and the borehole 2, creating a strong squeeze between the outer wall of the conduit 1 and the inner wall of the borehole 2. This squeeze must be able to effectively resist the slurry's displacement. High-pressure slurry is then injected into the conduit 1 and discharged through the grouting holes 11 into the space between the two airbags 12. This space is connected to the rock fissure 7. Under the action of pressure, the high-pressure slurry enters the rock fissure 7 and diffuses (as shown in Figure 9).

[0062] In this embodiment, step S5 will be executed after completing step S4: wait for the slurry to initially solidify, and then deflate the airbag 12, and then screw the catheter 1 so that the initially solidified slurry in the gap between the catheter 1 and the borehole 2 is broken, and the connection between the catheter 1 and the borehole 2 is released (as shown in Figure 10).

[0063] In this embodiment, after completing step S5, step S6 is executed: the conduit 1 is pulled out from the borehole 2 to complete the grouting and water blocking construction. The pulled-out conduit 1 only needs to be cleaned of slurry and can be reserved for next use (as shown in FIG11 ).

[0064] Example 3

[0065] The second embodiment of the grouting water blocking method for a water-rich tunnel of the present invention is basically the same as the embodiment 2, except that: there is only one rock fissure 7, and step S2 includes: step S21, the front end of the catheter 1 is inserted into the borehole 2, and the air bag 12 located at the rear side is inflated to fill the gap between the catheter 1 and the borehole 2 (at this time, under the blocking of the air bag 12 located at the rear side, all the gushing water enters the catheter 1 from the grouting hole 11 and is discharged from the rear end); step S22, the catheter 1 is penetrated forward, the gushing water stops flowing out, and it is determined that there is only one rock fissure 7, and the insertion depth of the catheter 1 at this time is recorded as L A (As shown in Figure 12, the air bag 12 at the rear side is located at the position of the rearmost rock fissure 7. At this time, the water gushing out of the rearmost rock fissure 7 is blocked by the air bag 12, so the gushing water stops flowing out.) The rear section of the catheter 1 is formed with a scale line 14 for marking the insertion depth of the catheter 1. By setting the scale line 14 on the outer surface of the rear section of the catheter 1 and reading the scale at the opening of the borehole 2, the depth of the catheter 1 inserted into the borehole 2 can be known, so that the specific position of the rock fissure 7 can be further determined. By moving the catheter 1 to change the depth of the rear air bag 12 in the borehole 2, and observing the outflow method of the gushing water and the scale of the catheter 1, the value L can be obtained. A , which reflects the depth of the rock fissure 7 from the borehole. In other words, in the technical solution disclosed in this application, the number and depth of the rock fissures 7 can be measured without the need for external equipment by simply pushing the conduit 1 and observing the water flow, thereby reducing construction difficulty and saving construction costs.

[0066] In this embodiment, the step S3 includes: step S31, moving the catheter 1 backward to an insertion depth of (L A -S); where S≥2cm, but not greater than the original spacing between the two balloons 12 (as shown in Figure 13, when the insertion depth of the catheter 1 is L A When the airbag 12 is at the rear side, it faces the rock fissure 7 at the rearmost side. In order to prevent the high-pressure slurry from entering the rock fissure 7 at the rearmost side due to the blockage of the airbag 12, it moves a distance S to the rear. At the same time, in order to prevent the airbag 12 at the front side from coming to the rear side of the rock fissure 7 due to excessive movement distance, S should not be greater than the original distance between the two airbags 12).

[0067] Although the present invention has been disclosed above with reference to preferred embodiments, this is not intended to limit the present invention. Any person skilled in the art can, without departing from the scope of the technical solution of the present invention, utilize the technical content disclosed above to make many possible changes and modifications to the technical solution of the present invention, or modify it into an equivalent embodiment with equivalent changes. Therefore, any simple modification, equivalent change, and modification made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention shall fall within the scope of protection of the technical solution of the present invention.

Claims

1. A grouting water blocking device for a water-rich tunnel, characterized in that: The invention comprises a catheter (1) with a closed front end, wherein a grouting hole (11) is formed on the side wall of the catheter (1), and an annular air bag (12) is mounted on both the front and rear sides of the grouting hole (11), wherein the air bag (12) can fill the gap between the catheter (1) and the borehole (2) in an inflated state.

2. The grouting water blocking device for a water-rich tunnel according to claim 1 is characterized in that: The airbag (12) is slidably mounted on the catheter (1), and the airbag (12) pulls a wire (13) for controlling the forward and backward movement of the airbag (12).

3. The grouting water blocking device for a water-rich tunnel according to claim 1 or 2, characterized in that: The rear section of the catheter (1) is formed with a scale line (14) for marking the insertion depth of the catheter (1).

4. The grouting water blocking device for a water-rich tunnel according to claim 1, characterized in that: A three-way valve (3) is installed at the rear end of the conduit (1); one port of the three-way valve (3) is connected to a grouting pipe (4), and the other port is installed with a measuring instrument (5).

5. The grouting water blocking device for a water-rich tunnel according to claim 4 is characterized in that: The measuring instrument (5) comprises one or more of a flow meter, a thermometer, a pH meter and a conductivity meter.

6. The grouting water blocking device for a water-rich tunnel according to claim 4, characterized in that: The measuring instrument (5) comprises a water pressure gauge, and a two-way valve (6) is connected in series in the downstream direction of the measuring instrument (5).

7. A method for blocking water by grouting in a water-rich tunnel, characterized in that: The grouting and water blocking device used in any one of claims 1 to 6 comprises the following steps: Step S1, measuring the original water inflow; Step S2, determining the number and depth of rock mass fissures (7); Step S3, adjusting the positions of the guide tube (1) and the airbag (12) so that each rock mass fissure (7) is located between the two airbags (12); Step S4, the airbag (12) is inflated until the gap between the catheter (1) and the borehole (2) is completely filled, and high-pressure slurry is injected into the catheter (1); Step S5, when the slurry is initially solidified, the air bag (12) is deflated, and the initially solidified slurry in the gap between the catheter (1) and the drill hole (2) is broken by twisting the catheter (1); Step S6, pulling out the catheter (1) from the drill hole (2).

8. The grouting water blocking method for a water-rich tunnel according to claim 7, characterized in that: The step S2 comprises: Step S21, the front end of the catheter (1) is inserted into the bore hole (2), and the air bag (12) located at the rear side is inflated until it fills the catheter (1). A gap between the borehole (2); Step S22A, insert the conduit (1) forward. If the gushing water stops flowing out, it is determined that the rock mass fissure (7) is a single location, and the insertion depth of the conduit (1) at this time is recorded as L. A ; Step S22B, insert the conduit (1) forward. If water gushes out of the conduit (1) and the borehole (2) at the same time, it is determined that there are multiple rock fractures (7). The insertion depth of the conduit (1) at this time is recorded as L. A ; Step S23: If there are multiple rock cracks (7), continue to insert the catheter (1) forward. When no water flows out of the catheter (1), record the insertion depth of the catheter (1) as L. B .

9. The grouting water blocking method for a water-rich tunnel according to claim 7, characterized in that: If the rock mass fissure (7) is single, step S3 comprises: Step S31A, move the catheter (1) backward to an insertion depth of (L A -S); wherein S≥2cm, but not greater than the original spacing between the two airbags (12).

10. The grouting water blocking method for a water-rich tunnel according to claim 7, characterized in that: If there are multiple rock mass fissures (7), step S3 includes: Step S31B, move the catheter (1) backward to an insertion depth of (L A -S); wherein S≥2cm, but not greater than the original spacing between the two airbags (12); Step S32, the airbag (12) located at the front side is inflated until it fills the gap between the catheter (1) and the drill hole (2); Step S33, moving the air bag (12) located at the front side forward by means of the wire rope (13) until the amount of water per unit time flowing out of the catheter (1) is the same as the original water inflow amount.

Citation Information

Patent Citations

  • Adjustable annular double-layer air bag hole sealing device and method for performing hole sealing

    CN104060965A

  • Targeted domain-control grouting device and grouting process

    CN104314587A

  • Curtain rapid-leakage-plugging device in high-water-head stratum and working method thereof

    CN111733849A

  • Tunnel fractured rock mass grouting and water plugging device and method

    CN113982653A

  • Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method

    CN114135321A

Cited By

  • Repair pretreatment device for weak water-rich stratum tunnel structure

    CN119466884A

  • A pretreatment device for repairing tunnel structure in soft and water-rich strata

    CN119466884B

  • Cabin-separated grouting method for strengthening shield tunnel wall back grouting control

    CN119860238A

  • Method for treating floor heave of soft rock broken floor roadway

    CN119878061A

  • A method for treating floor heave in roadways with fractured rock floor

    CN119878061B